CN104062502B - A kind of cross interconnected system phase inspection method of high-tension cable - Google Patents
A kind of cross interconnected system phase inspection method of high-tension cable Download PDFInfo
- Publication number
- CN104062502B CN104062502B CN201410280054.8A CN201410280054A CN104062502B CN 104062502 B CN104062502 B CN 104062502B CN 201410280054 A CN201410280054 A CN 201410280054A CN 104062502 B CN104062502 B CN 104062502B
- Authority
- CN
- China
- Prior art keywords
- phases
- phase
- cross interconnected
- cross
- cable
- Prior art date
- Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
- Active
Links
Landscapes
- Testing Relating To Insulation (AREA)
- Testing Of Short-Circuits, Discontinuities, Leakage, Or Incorrect Line Connections (AREA)
Abstract
本发明公开了一种高压电缆交叉互联系统相位检查方法,该方法包括:检测人员在高压电缆的首段进行接线;检测人员到高压电缆的1号接头箱对交叉互联系统进行相位检查;检测人员到高压电缆的2号接头箱对交叉互联系统进行相位检查;重复以上步骤,直至完成全部交叉互联系统的相位检查工作。本发明方法通过对以往高压电缆交叉互联系统相位检查方法进行改进,即可在对端无人配合的情况下,仅通过一块普通的万用表和简单的接线,快捷、高效地完成相位检查工作。
The invention discloses a phase inspection method of a high-voltage cable cross-interconnection system. The method includes: inspectors perform wiring at the first section of the high-voltage cable; Go to the No. 2 joint box of the high-voltage cable to check the phase of the cross-connection system; repeat the above steps until the phase inspection of all cross-connection systems is completed. The method of the invention improves the phase inspection method of the previous high-voltage cable cross-connection system, and can quickly and efficiently complete the phase inspection work only through an ordinary multimeter and simple wiring under the condition that no one at the opposite end cooperates.
Description
技术领域technical field
本发明涉及一种电压相位测取装置,尤其涉及一种高压电缆交叉互联系统相位检查方法。The invention relates to a voltage phase measuring device, in particular to a phase checking method of a high-voltage cable cross-connection system.
背景技术Background technique
高压交联聚乙烯电缆由于其优秀的电气性能、良好的耐热性能,以及敷设及附件安装方便和不受落差限制等优点,同时考虑市政规划的要求,市区及开发区电网主网架的架空线路逐渐被高压电缆所取代。Due to its excellent electrical properties, good heat resistance, and the advantages of convenient laying and accessories installation and no drop restrictions, high-voltage XLPE cables also consider the requirements of municipal planning and the main network frame of urban and development areas. Overhead lines are gradually being replaced by high voltage cables.
由于电压等级高、通流容量大,高压交联聚乙烯电缆均为单芯电缆。单芯电缆的导体和金属护套的关系,就相当于变压器的一次绕组和二次绕组,当电缆导体流过交流电流时,会在金属护套产生感应电压,因此单芯电缆金属护套的连接方式对高压电缆的载流量和安全稳定运行有着重要影响。Due to the high voltage level and large flow capacity, the high-voltage XLPE cables are all single-core cables. The relationship between the conductor of the single-core cable and the metal sheath is equivalent to the primary winding and the secondary winding of the transformer. When the cable conductor flows through the AC current, an induced voltage will be generated in the metal sheath, so the metal sheath of the single-core cable The connection method has an important influence on the carrying capacity and safe and stable operation of the high-voltage cable.
高压电缆的交叉互联系统,就是将长距离的高压单芯电缆的金属护套按一定规律进行连接而组成的系统,而交叉互联系统的相位检查则是高压电缆现场交接试验项目之一。The cross-connection system of high-voltage cables is a system composed of connecting the metal sheaths of long-distance high-voltage single-core cables according to certain rules, and the phase inspection of the cross-connection system is one of the field handover test items of high-voltage cables.
发明内容Contents of the invention
本发明的目的在于提供一种高压电缆交叉互联系统相位检查方法,旨在解决现有技术在进行相位检查时,必须有技术人员在对端进行配合带来的不便等问题。本发明方法只需分别将三相金属护套按照直接接地、经电阻接地和不接地的方式连接,检测人员即可在另一端完成相位检查工作。The purpose of the present invention is to provide a phase inspection method for a high-voltage cable cross-connection system, which aims to solve the inconvenience caused by the need for technicians to cooperate at the opposite end when performing phase inspection in the prior art. The method of the invention only needs to connect the three-phase metal sheaths in the manners of direct grounding, resistance grounding and non-grounding respectively, and the detection personnel can complete the phase inspection work at the other end.
创新点:本发明仅通过一块普通的万用表和简单的接线,即可对高压电缆的交叉互联系统进行检查,无需任何人员配合Innovation point: the present invention can check the cross-connection system of high-voltage cables only through an ordinary multimeter and simple wiring, without the cooperation of any personnel
本发明是这样实现的,一种高压电缆交叉互联系统相位检查方法包括:步骤1:检测人员在高压电缆的首段进行接线;步骤2:检测人员到高压电缆的1号接头箱对交叉互联系统进行相位检查;步骤3:检测人员到高压电缆的2号接头箱对交叉互联系统进行相位检查;步骤4:重复以上步骤,直至完成全部交叉互联系统的相位检查工作。The present invention is realized in this way. A phase inspection method of a high-voltage cable cross-connection system includes: Step 1: The inspector performs wiring at the first section of the high-voltage cable; Step 2: The inspector goes to the No. 1 joint box of the high-voltage cable to the cross-connection system Conduct phase inspection; Step 3: inspectors go to the No. 2 joint box of the high-voltage cable to perform phase inspection on the cross-connection system; Step 4: Repeat the above steps until the phase inspection of all cross-connection systems is completed.
所述步骤1:首先,检测人员在高压电缆的首段进行接线。将金属护套的a相直接接地,将b相经过100欧姆的电阻接地,c相悬空不接地。Step 1: First, inspectors perform wiring on the first section of the high-voltage cable. Phase a of the metal sheath is directly grounded, phase b is grounded through a 100 ohm resistor, and phase c is suspended without grounding.
所述步骤2:检测人员到高压电缆的1号接头箱对交叉互联系统进行相位检查。1号接头箱处,电缆接头施工时会通过同轴电缆将两段电缆的金属护套分别引出至交叉互联箱,因此会有6相,即同轴电缆内线芯3相和外线芯3相。用万用表的电阻(欧姆)档,分别对地测量同轴电缆的内外线芯,此时电阻为零的则为电缆首端的a相,电阻约为100欧姆的为b相,c相电阻无穷大,其余3相线芯(a1、b1、c1)的电阻亦为无穷大,且该3相线芯指向2号接头箱。再将金属护套的a1相直接接地,将b1相经过100欧姆的电阻接地,c1相悬空不接地,为下一步相位检查工作做准备。Step 2: inspectors go to the No. 1 joint box of the high-voltage cable to check the phase of the cross-connection system. At the joint box No. 1, the metal sheaths of the two sections of cables will be led out to the cross-connection box through the coaxial cable during the construction of the cable joint, so there will be 6 phases, that is, 3 phases of the inner core and 3 phases of the outer core of the coaxial cable. Use the resistance (ohm) file of the multimeter to measure the inner and outer cores of the coaxial cable respectively to the ground. At this time, the resistance of zero is the a phase of the cable head end, the resistance of about 100 ohms is b phase, and the resistance of c phase is infinite. The resistance of the remaining three-phase wire cores (a1, b1, c1) is also infinite, and the three-phase wire cores point to the No. 2 joint box. Then, directly ground the a1 phase of the metal sheath, ground the b1 phase through a 100 ohm resistance, and leave the c1 phase suspended without grounding to prepare for the next step of phase inspection.
所述步骤3:检测人员到高压电缆的2号接头箱对交叉互联系统进行相位检查。重复第二步检测内容,以确定2号接头箱的a1、b1、c1相位正确,并指向1好接头箱。再将a2、b2、c2相金属护套做好相位检查准备,前往3号接头箱进行检查。Step 3: The inspector goes to the No. 2 joint box of the high-voltage cable to check the phase of the cross-connection system. Repeat the second step to check the content to ensure that the phases of a1, b1, and c1 of the No. 2 joint box are correct and point to the No. 1 joint box. Then prepare the metal sheaths of phases a2, b2, and c2 for phase inspection, and go to the No. 3 joint box for inspection.
所述步骤4:重复以上步骤,直至完成全部交叉互联系统的相位检查工作。Step 4: Repeat the above steps until the phase inspection work of all cross-connection systems is completed.
交叉互联系统是将电缆线路分成若干大段,每大段原则上又分成长度相等的三小段,每段之间装设绝缘接头,绝缘接头处金属护套三相之间用同轴电缆进行交叉互联,绝缘接头处装设一组过电压保护器,每一大段的两端金属护套分别互联接地。The cross interconnection system is to divide the cable line into several large sections, and each large section is divided into three small sections of equal length in principle. Insulated joints are installed between each section, and the three phases of the metal sheath at the insulating joints are crossed by coaxial cables. Interconnection, a set of overvoltage protectors are installed at the insulating joints, and the metal sheaths at both ends of each large section are interconnected and grounded respectively.
本发明的一种高压电缆交叉互联系统相位检查方法,本发明通过对以往高压电缆交叉互联系统相位检查方法进行改进,即可在对端无人配合的情况下,仅通过一块普通的万用表和简单的接线,快捷、高效地完成相位检查工作。A phase inspection method of a high-voltage cable cross-connection system according to the present invention. The present invention improves the phase inspection method of a high-voltage cable cross-connection system in the past. In the case of unmanned cooperation at the opposite end, only an ordinary multimeter and a simple Wiring, quickly and efficiently complete the phase inspection work.
附图说明Description of drawings
图1是本发明实施例提供的高压电缆交叉互联系统示意图;Fig. 1 is a schematic diagram of a high-voltage cable cross-connection system provided by an embodiment of the present invention;
图2是本发明实施例提供的同轴电缆引出图;Fig. 2 is a drawing of the coaxial cable provided by the embodiment of the present invention;
图3是本发明实施例提供的交叉互联箱实际接线图;Fig. 3 is the actual wiring diagram of the cross interconnection box provided by the embodiment of the present invention;
图4是本发明实施例提供的一种高压电缆交叉互联系统相位检查方法实施方法流程图。Fig. 4 is a flowchart of an implementation method of a phase inspection method for a high-voltage cable cross-interconnection system provided by an embodiment of the present invention.
具体实施方式detailed description
为了使本发明的目的、技术方案及优点更加清楚明白,以下结合附图及实施例,对本发明进行进一步详细说明。应当理解,此处所描述的具体实施例仅仅用以解释本发明,并不用于限定本发明。In order to make the object, technical solution and advantages of the present invention clearer, the present invention will be further described in detail below in conjunction with the accompanying drawings and embodiments. It should be understood that the specific embodiments described here are only used to explain the present invention, not to limit the present invention.
如图4所示,本发明是这样实现的,一种高压电缆交叉互联系统相位检查方法包括:步骤S401:检测人员在高压电缆的首段进行接线;步骤S402:检测人员到高压电缆的1号接头箱对交叉互联系统进行相位检查;步骤S403:检测人员到高压电缆的2号接头箱对交叉互联系统进行相位检查;步骤S404:重复以上步骤,直至完成全部交叉互联系统的相位检查工作。As shown in Figure 4, the present invention is implemented in this way. A phase inspection method for a high-voltage cable cross-connection system includes: step S401: the inspector performs wiring at the first section of the high-voltage cable; step S402: the inspector goes to No. 1 of the high-voltage cable The joint box checks the phase of the cross-interconnection system; step S403: inspectors go to the No. 2 joint box of the high-voltage cable to check the phase of the cross-interconnection system; step S404: repeat the above steps until the phase inspection of all cross-interconnection systems is completed.
如图1所示,交叉互联系统主要由多个交叉互联箱和导线组成;As shown in Figure 1, the cross-connection system is mainly composed of multiple cross-connection boxes and wires;
所述步骤S401:首先,检测人员在高压电缆的首段进行接线。将金属护套的a相直接接地,将b相经过100欧姆的电阻接地,c相悬空不接地。Said step S401: first, inspectors perform wiring on the first section of the high-voltage cable. Phase a of the metal sheath is directly grounded, phase b is grounded through a 100 ohm resistor, and phase c is suspended without grounding.
所述步骤S402:检测人员到高压电缆的1号接头箱对交叉互联系统进行相位检查。1号接头箱处,电缆接头施工时会通过同轴电缆将两段电缆的金属护套分别引出(见图2)至交叉互联箱(见图3),因此会有6相,即同轴电缆内线芯3相(图3上部)和外线芯3相(图3下部)。用万用表的电阻(欧姆)档,分别对地测量同轴电缆的内外线芯,此时电阻为零的则为电缆首端的a相,电阻约为100欧姆的为b相,c相电阻无穷大,其余3相线芯(a1、b1、c1)的电阻亦为无穷大,且该3相线芯指向2号接头箱。再将金属护套的a1相直接接地,将b1相经过100欧姆的电阻接地,c1相悬空不接地,为下一步相位检查工作做准备。The step S402: inspectors go to the No. 1 joint box of the high-voltage cable to check the phase of the cross-connection system. At the No. 1 joint box, the metal sheaths of the two sections of cables will be respectively led out (see Figure 2) to the cross-connection box (see Figure 3) through the coaxial cable during the construction of the cable joint, so there will be 6 phases, that is, the coaxial cable 3-phase inner core (upper part in Figure 3) and 3-phase outer core (lower part in Figure 3). Use the resistance (ohm) file of the multimeter to measure the inner and outer cores of the coaxial cable respectively to the ground. At this time, the resistance of zero is the a phase of the cable head end, the resistance of about 100 ohms is b phase, and the resistance of c phase is infinite. The resistance of the remaining three-phase wire cores (a1, b1, c1) is also infinite, and the three-phase wire cores point to the No. 2 joint box. Then, directly ground the a1 phase of the metal sheath, ground the b1 phase through a 100 ohm resistance, and leave the c1 phase suspended without grounding to prepare for the next step of phase inspection.
如图3所示,交叉互联箱主要由:接地端子、护层保护器、进线端口、外线芯夹座、内线芯夹座螺母;接地端子安装在交叉互联箱的右上侧,进线端口安装在交叉互联箱的下方,护层保护器安装在接地端子的左侧,内线芯夹座螺母安装在护层保护器上,外线芯夹座安装在进线端口的上方。As shown in Figure 3, the cross interconnection box is mainly composed of: grounding terminal, sheath protector, inlet port, outer core holder, inner wire core holder nut; the ground terminal is installed on the upper right side of the cross interconnection box, and the inlet port is installed Below the cross interconnection box, the sheath protector is installed on the left side of the grounding terminal, the inner wire core holder nut is installed on the sheath protector, and the outer wire core holder is installed above the incoming line port.
所述步骤S403:检测人员到高压电缆的2号接头箱对交叉互联系统进行相位检查。重复第二步检测内容,以确定2号接头箱的a1、b1、c1相位正确,并指向1好接头箱。再将a2、b2、c2相金属护套做好相位检查准备,前往3号接头箱进行检查。The step S403: inspectors go to the No. 2 joint box of the high-voltage cable to check the phase of the cross-connection system. Repeat the second step to check the content to ensure that the phases of a1, b1, and c1 of the No. 2 joint box are correct and point to the No. 1 joint box. Then prepare the metal sheaths of phases a2, b2, and c2 for phase inspection, and go to the No. 3 joint box for inspection.
所述步骤S404:重复以上步骤,直至完成全部交叉互联系统的相位检查工作。The step S404: repeating the above steps until the phase inspection work of all the cross-interconnection systems is completed.
由于电压等级高、通流容量大,高压交联聚乙烯电缆均为单芯电缆。Due to the high voltage level and large flow capacity, the high-voltage XLPE cables are all single-core cables.
单芯电缆的导体和金属护套的关系,就相当于变压器的一次绕组和二次绕组。当电缆导体流过交流电流时,其周围产生的一部分磁力线与金属护套交链,会在金属护套产生感应电压。感应电压的大小不仅与电缆中流过的电流或短路电流有关,同时与电缆的排列方式和电缆线路的长度有关。如果电缆金属护套两端接地使其形成闭合通路,金属护套中将产生环流;电缆正常运行时,金属护套上的环流与导线的负荷电流基本上为同一数量级,将产生很大的环流损耗,使电缆发热,影响电缆的输送容量。因此单芯电缆金属护套的连接方式对高压电缆的载流量和安全稳定运行有着重要影响。The relationship between the conductor and the metal sheath of a single-core cable is equivalent to the primary winding and secondary winding of a transformer. When the cable conductor flows through the AC current, a part of the magnetic field lines generated around it will interlink with the metal sheath, and an induced voltage will be generated in the metal sheath. The magnitude of the induced voltage is not only related to the current flowing in the cable or the short-circuit current, but also related to the arrangement of the cable and the length of the cable line. If both ends of the metal sheath of the cable are grounded to form a closed path, a circulating current will be generated in the metal sheath; when the cable is in normal operation, the circulating current on the metal sheath and the load current of the wire are basically of the same order of magnitude, and a large circulating current will be generated The loss makes the cable heat up and affects the transmission capacity of the cable. Therefore, the connection method of the single-core cable metal sheath has an important impact on the current carrying capacity and safe and stable operation of the high-voltage cable.
为了减少金属护套损耗,提高电缆的输送容量,当高压电缆线路较长时(1km以上)可以采用金属护套交叉互联。如图1所示,交叉互联系统就是将电缆线路分成若干大段,每大段原则上又分成长度相等的三小段,每段之间装设绝缘接头,绝缘接头处金属护套三相之间用同轴电缆进行交叉互联,绝缘接头处装设一组过电压保护器,每一大段的两端金属护套分别互联接地。In order to reduce the loss of the metal sheath and increase the transmission capacity of the cable, the metal sheath cross-connection can be used when the high-voltage cable line is long (more than 1km). As shown in Figure 1, the cross-interconnection system is to divide the cable line into several large sections. Coaxial cables are used for cross interconnection, a set of overvoltage protectors are installed at the insulating joints, and the metal sheaths at both ends of each large section are interconnected and grounded respectively.
高压电缆的交叉互联系统,就是将长距离的高压单芯电缆的金属护套按一定规律进行连接而组成的系统。The cross-connection system of high-voltage cables is a system composed of connecting the metal sheaths of long-distance high-voltage single-core cables according to certain rules.
上述虽然结合附图对本发明的具体实施方式进行了描述,但并非对本发明保护范围的限制,所属领域技术人员应该明白,在本发明的技术方案的基础上,本领域技术人员不需要付出创造性的劳动即可做出的各种修改或变形仍在本发明的保护范围之内。Although the specific implementation of the present invention has been described above in conjunction with the accompanying drawings, it is not a limitation to the protection scope of the present invention. Those skilled in the art should understand that on the basis of the technical solution of the present invention, those skilled in the art do not need to pay any creative effort. Various modifications or deformations that can be made by labor are still within the protection scope of the present invention.
Claims (1)
- A kind of 1. cross interconnected system phase inspection method of high-tension cable, it is characterised in that the cross interconnected system of the high-tension cable Phase shift inspection method includes:Step 1:Testing staff carries out wiring in the head end of high-tension cable;Step 2:Testing staff carries out phase shift inspection to No. 1 joint case of high-tension cable to cross interconnected system;Step 3:Testing staff carries out phase shift inspection to No. 2 joint casees of high-tension cable to cross interconnected system;Step 4:Above step is repeated, until completing the phase shift inspection work of all cross interconnected systems;Wiring is carried out for a phases of protective metal shell are directly grounded to the head end of high-tension cable in step 1, b phases are passed through into 100 Europe The resistance eutral grounding of nurse, c phases are hanging earth-free;The protective metal shell of two sections of cables is led to cross interconnected case by step 2 middle cable connector respectively by coaxial cable, that is, is connect Head case, measure the inside and outside core resistance of coaxial cable over the ground respectively, a phases, b phases and c phases of No. 1 joint case are determined, then by a Phase, the a1 phases of b phases and the corresponding No. 1 joint case of c, the protective metal shell of b1 phases and c1 phases carry out phase shift inspection preparation, are specially: A1 phases are directly grounded, and b1 phases pass through 100 ohm of resistance eutral grounding, and c1 phases are hanging earth-free;Cross interconnected case includes:Ground terminal, sheath protector, inlet wire port, outer core holder, interior core holder nut;Connect Ground terminal is arranged on the upper right side of cross interconnected case, and inlet wire port is arranged on the lower section of cross interconnected case, sheath protector installation In the left side of ground terminal, interior core holder nut is arranged on sheath protector, and outer core holder is arranged on inlet wire port Top;Content in repeat step two in step 3, to ensure to determine that a1, b1, c1 phase of No. 2 joint casees are correct, and point to No. 1 Joint case;A2, b2, c2 phase protective metal shell of No. 2 a1, b1, c1 corresponding joint casees are carried out into phase shift inspection again to prepare, gone to No. 3 joint casees are checked;One~step 3 of above step is repeated in step 4, until completing the phase shift inspection work of all cross interconnected systems;Cross interconnected system is that cable run is divided into some big sections, is divided into three segments of equal length again in principle per big section, Install insulating joint between every section, carried out with coaxial cable cross interconnected at insulating joint between protective metal shell three-phase, insulation connects One group of overvoltage protection device is installed at head, each big section of both ends protective metal shell interconnects ground connection respectively.
Priority Applications (1)
| Application Number | Priority Date | Filing Date | Title |
|---|---|---|---|
| CN201410280054.8A CN104062502B (en) | 2014-06-20 | 2014-06-20 | A kind of cross interconnected system phase inspection method of high-tension cable |
Applications Claiming Priority (1)
| Application Number | Priority Date | Filing Date | Title |
|---|---|---|---|
| CN201410280054.8A CN104062502B (en) | 2014-06-20 | 2014-06-20 | A kind of cross interconnected system phase inspection method of high-tension cable |
Publications (2)
| Publication Number | Publication Date |
|---|---|
| CN104062502A CN104062502A (en) | 2014-09-24 |
| CN104062502B true CN104062502B (en) | 2017-11-17 |
Family
ID=51550306
Family Applications (1)
| Application Number | Title | Priority Date | Filing Date |
|---|---|---|---|
| CN201410280054.8A Active CN104062502B (en) | 2014-06-20 | 2014-06-20 | A kind of cross interconnected system phase inspection method of high-tension cable |
Country Status (1)
| Country | Link |
|---|---|
| CN (1) | CN104062502B (en) |
Families Citing this family (3)
| Publication number | Priority date | Publication date | Assignee | Title |
|---|---|---|---|---|
| CN108629131B (en) * | 2018-05-08 | 2019-12-24 | 广东电网有限责任公司 | Intelligent generation method and device of cross-connection structure diagram |
| CN115021172B (en) * | 2022-05-07 | 2023-10-27 | 国网江苏省电力有限公司常州供电分公司 | Cross interconnection box and cross interconnection system capable of preventing misconnection |
| CN118169606B (en) * | 2024-03-20 | 2024-08-30 | 上海锐测电子科技有限公司 | High-voltage cable grounding system detection device |
Family Cites Families (8)
| Publication number | Priority date | Publication date | Assignee | Title |
|---|---|---|---|---|
| US7764067B2 (en) * | 2007-12-27 | 2010-07-27 | Caterpillar Inc | High voltage cable testing method |
| CN201319045Y (en) * | 2008-11-05 | 2009-09-30 | 山西省电力公司电力科学研究院 | Ground impedance testing cable in large-scale ground grid |
| CN102128983B (en) * | 2011-01-25 | 2012-11-21 | 福建省电力有限公司三明电业局 | Method for measuring phase of power transmission and distribution line |
| CN202034753U (en) * | 2011-03-25 | 2011-11-09 | 长沙电缆附件有限公司 | Cross interconnection box used in single-core power cable |
| CN102928697B (en) * | 2012-10-19 | 2015-03-18 | 广东电网公司电力科学研究院 | Low-frequency-band damping detection method and system of PSS2A (Power System Stabilizer 2A) model of excitation regulator |
| CN102914733A (en) * | 2012-11-16 | 2013-02-06 | 中国电力科学研究院 | In-situ detecting method for partial discharge of damped oscillation wave of large-length ultrahigh voltage crosslinked cable |
| CN203456149U (en) * | 2013-08-28 | 2014-02-26 | 远东电缆有限公司 | Ultra-high-voltage cross-interconnection cable |
| CN103983853B (en) * | 2014-05-09 | 2018-03-20 | 国家电网公司 | A kind of cross interconnected system phase inspection method of high-tension cable |
-
2014
- 2014-06-20 CN CN201410280054.8A patent/CN104062502B/en active Active
Also Published As
| Publication number | Publication date |
|---|---|
| CN104062502A (en) | 2014-09-24 |
Similar Documents
| Publication | Publication Date | Title |
|---|---|---|
| CN103308832B (en) | A kind of high-voltage cable insulating transition joint local discharge test device and using method | |
| CN111157801B (en) | Cable dielectric loss detection method, device, storage medium and processor | |
| CN106771869A (en) | Long range power cable insulation on-line monitoring method based on current in resistance property partition method | |
| CN108509712B (en) | Overvoltage simulation analysis method and system for cable line | |
| CN103323751B (en) | A kind of high pressure stub cable insulation terminal local discharge test device and using method | |
| CN108152662A (en) | A kind of cross interconnected box fault diagnosis method and system based on earth current | |
| CN104502807A (en) | Cable line fault positioning method, device and system | |
| CN110596538B (en) | Method and system for calculating electrical parameters of power cable | |
| CN102128983A (en) | Method for measuring phase of power transmission and distribution line | |
| CN104062502B (en) | A kind of cross interconnected system phase inspection method of high-tension cable | |
| CN105510645A (en) | Wiring method for automatic detection of three-phase integrated-type power transformer | |
| CN112415327B (en) | Identification method of fault section of cable distribution network based on difference of ground wire current direction | |
| CN103983853B (en) | A kind of cross interconnected system phase inspection method of high-tension cable | |
| CN205429680U (en) | Cable cross -bonding case | |
| CN105375438B (en) | Zero sequence current detection device and method for Neutral Point Through Low Resistance system | |
| CN108508327A (en) | A kind of test apparatus and its method of inspection of the cross interconnected service check of cable | |
| CN113109662A (en) | Method and system for determining relative aging degree of cable based on interphase relative dielectric loss | |
| Guo et al. | A method of 20 kV cable line fault location based on sheath grounding current | |
| CN105510768B (en) | A kind of trouble shoot method of service conductor ground connection | |
| Candela et al. | A model for the study of sheath currents in medium voltage cables for industrial application | |
| CN107271775B (en) | A method for phase inspection of power overhead lines | |
| KR101873005B1 (en) | 3 Phase 4 Wires Zero Current Transformer for Detecting Insulation Resistance | |
| CN208283500U (en) | A kind of test apparatus of the cross interconnected service check of cable | |
| Zhang et al. | Experimental and numerical study of division factors of fault current and measuring current due to ground wires of transmission lines | |
| CN113514669A (en) | Wiring method for equipment detection of traction substation |
Legal Events
| Date | Code | Title | Description |
|---|---|---|---|
| C06 | Publication | ||
| PB01 | Publication | ||
| C10 | Entry into substantive examination | ||
| SE01 | Entry into force of request for substantive examination | ||
| GR01 | Patent grant | ||
| GR01 | Patent grant |