CN104734352B - A kind of distribution line Loop Closing Operation control method - Google Patents
A kind of distribution line Loop Closing Operation control method Download PDFInfo
- Publication number
- CN104734352B CN104734352B CN201510105282.6A CN201510105282A CN104734352B CN 104734352 B CN104734352 B CN 104734352B CN 201510105282 A CN201510105282 A CN 201510105282A CN 104734352 B CN104734352 B CN 104734352B
- Authority
- CN
- China
- Prior art keywords
- switch
- loop
- line
- tie
- closing operation
- Prior art date
- Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
- Active
Links
Landscapes
- Remote Monitoring And Control Of Power-Distribution Networks (AREA)
Abstract
本发明公开了一种配电线路合环操作控制方法,主站系统判定需要进行合环操作后,由主站向联络开关发送合环指令;联络开关对应的馈线终端接收到主站发送的合环指令后,首先确认开关为联络开关;然后联络开关FTU与相邻两开关的FTU对等通信,获取相邻两个开关处的电压信息,结合自身可采集的两个线电压信息进行计算,得到联络开关处另外两个线电压;将得到的联络开关两侧电压信息与合环定值进行比较,判断当前系统是否符合合环操作条件进行相关操作。此方法在联络开关合闸前对合环条件进行确认,能够保证配电网合环操作的正确性,防止在不具备合环条件时发生合环误操作。终端间采用点对点对等通信方式,通信延时小,可保证信息传输的时效性。
The invention discloses a control method for loop closing operation of a power distribution line. After the main station system judges that the loop closing operation is required, the main station sends a loop closing command to a tie switch; the feeder terminal corresponding to the tie switch receives the closing command sent by the master station After the ring command, first confirm that the switch is a tie switch; then the tie switch FTU communicates with the FTUs of the two adjacent switches peer-to-peer to obtain the voltage information at the two adjacent switches, and calculate it by combining the two line voltage information that can be collected by itself. Obtain the other two line voltages at the tie switch; compare the obtained voltage information on both sides of the tie switch with the loop closing value to determine whether the current system meets the loop closing operation conditions and perform related operations. This method confirms the loop-closing conditions before the contact switch is closed, which can ensure the correctness of the loop-closing operation of the distribution network and prevent loop-closing misoperations when the loop-closing conditions are not met. The point-to-point peer-to-peer communication method is adopted between terminals, and the communication delay is small, which can ensure the timeliness of information transmission.
Description
技术领域technical field
本发明涉及一种配电线路合环操作控制方法。The invention relates to a control method for loop closing operation of a power distribution line.
背景技术Background technique
随着配电网建设的迅猛发展,我国配电网已基本形成了“闭环设计、开环运行”的网架结构,即线路可以由多个电源供电,正常运行时联络开关处于分位,联络开关两侧系统分列运行。在需要倒负荷或线路检修时,先闭合联络开关使线路合环,然后再断开合适的分段开关,可避免部分线路短时停电,提高供电可靠性。现有的合环技术主要是主站根据配电终端上传的电网参数进行计算分析,判断系统是否符合合环条件,若符合则向联络开关对应的馈线终端(FTU)发送遥控合指令,馈线终端收到指令后控制联络开关合闸。然而,主站与终端之间存在通信延时,而配电网运行状况变化较快,当终端接收到主站发送的合闸指令时,系统的运行状况可能已经发生了变化而不具备合环条件,如果根据指令执行合环操作,则有可能引起难以控制的网络循环功率,导致保护动作、设备损坏等严重后果。因此有必要在控制联络开关合闸前,由FTU检测当前系统运行参数,对能否进行合环操作进行判断确认。With the rapid development of distribution network construction, my country's distribution network has basically formed a grid structure of "closed-loop design, open-loop operation", that is, the line can be powered by multiple power sources, and the contact switch is in the position during normal operation. The systems on both sides of the switch operate separately. When load reversal or line maintenance is required, first close the contact switch to close the line, and then open the appropriate section switch, which can avoid short-term power failure of some lines and improve the reliability of power supply. The existing loop closing technology is mainly that the master station performs calculation and analysis based on the grid parameters uploaded by the power distribution terminal, and judges whether the system meets the loop closing conditions. If so, it sends a remote closing command to the feeder terminal (FTU) corresponding to the contact switch. After receiving the instruction, control the contact switch to close. However, there is a communication delay between the master station and the terminal, and the operating status of the distribution network changes rapidly. When the terminal receives the closing command sent by the master station, the operating status of the system may have changed without the ability to close the loop. Conditions, if the loop closing operation is performed according to the instructions, it may cause uncontrollable network circulation power, resulting in serious consequences such as protection actions and equipment damage. Therefore, it is necessary to check the current system operating parameters by the FTU before the control tie switch is closed, so as to judge and confirm whether the loop closing operation can be performed.
在配电线路建设时,馈线开关一般在两侧各配置一个单相电压互感器(PT),分别检测AB相间电压和BC相间电压,PT同时为FTU供电,其二次侧额定电压为220V。于是FTU只能采集到开关两侧各一个线电压信号,且一个为AB相间电压、另一个为BC相间电压,难以通过这两个电压判断是否具备合环条件。在实际运行中,任何一个馈线开关都可能成为联络开关,无法通过对某个开关增加PT的方法解决电压信号不足的问题。During the construction of distribution lines, the feeder switch is generally equipped with a single-phase voltage transformer (PT) on both sides to detect the AB phase voltage and BC phase voltage respectively. The PT supplies power to the FTU at the same time, and its secondary side rated voltage is 220V. Therefore, the FTU can only collect one line voltage signal on each side of the switch, and one is the AB phase voltage, and the other is the BC phase voltage. In actual operation, any feeder switch may become a tie switch, and the problem of insufficient voltage signal cannot be solved by adding PT to a certain switch.
联络开关对应的FTU需要获得其他开关处的电压信息,才能判断系统是否具备合环条件。传统配电自动化主要采用一点对多点通信方式,即主站与所有配电终端进行通信,FTU之间需要经过主站中转才能交换信息,这种方式速度慢、延时大,难以保证信息的时效性。新型通信方式为点对点对等通信,即将馈线终端接入同一个以太网,任意两个终端之间可以直接交换信息,该方式不需要通过主站中转,避免了主站集中控制带来的通信与数据处理延时长的问题。对等通信网可采用光纤以太网络,已有研究结果表明,采用无连接的传输层用户数据报协议(UDP)传输数据,在适当的网络流量下,其实际的传输延迟不会超过10ms。The FTU corresponding to the tie switch needs to obtain the voltage information at other switches in order to judge whether the system meets the conditions for loop closure. Traditional power distribution automation mainly adopts point-to-multipoint communication, that is, the master station communicates with all distribution terminals, and FTUs need to be transferred through the master station to exchange information. Timeliness. The new communication method is point-to-point peer-to-peer communication, that is, the feeder terminals are connected to the same Ethernet, and information can be exchanged directly between any two terminals. The problem of long data processing delay. The peer-to-peer communication network can use optical fiber Ethernet. Existing research results have shown that the actual transmission delay will not exceed 10 ms under appropriate network traffic when using the connectionless transport layer User Datagram Protocol (UDP) to transmit data.
中国专利ZL201210257852.X公开了一种配电网合环运行控制方法,馈线终端采集开关的电压信号计算判断能否合环,并将判断结果上传至配网主站,主站在需要合环时根据终端上传结果决定是否执行合闸操作。该方法未提及合闸前由馈线终端进行合环条件确认的环节,并且其实现的前提是终端可以采集到计算所需的所有电压信号,不能适应馈线开关两侧各仅配置一个电压互感器、可采集电压信号不足的实际情况。Chinese patent ZL201210257852.X discloses a control method for loop closing operation of the distribution network. The feeder terminal collects the voltage signal of the switch to calculate whether the loop can be closed, and uploads the judgment result to the master station of the distribution network. When the master station needs to close the loop According to the upload result of the terminal, it is decided whether to execute the closing operation. This method does not mention the link of confirming the loop closing conditions by the feeder terminal before closing, and the premise of its realization is that the terminal can collect all the voltage signals required for calculation, and it cannot adapt to only one voltage transformer on each side of the feeder switch. , It can collect the actual situation of insufficient voltage signal.
中国专利201310156849.3公开了一种配电网合环换电方法、装置及配电终端,在合环前由站所终端(DTU)进行合环条件判断,该方法针对开闭所(开关站)内的母线合环操作进行控制,不能用于终端可采集电压信号不足的配电线路。Chinese patent 201310156849.3 discloses a method, device and power distribution terminal for power distribution network closing and switching. It can not be used for power distribution lines where the terminal can collect insufficient voltage signals.
发明内容Contents of the invention
本发明为了解决上述问题,提出了一种配电线路合环操作控制方法,该方法由馈线终端在合环操作前确认联络开关两侧系统处于同期状态,避免发生合环误操作。In order to solve the above problems, the present invention proposes a control method for loop closing operation of distribution lines. In this method, the feeder terminal confirms that the systems on both sides of the tie switch are in the same state before the loop closing operation, so as to avoid loop closing misoperation.
为了实现上述目的,本发明采用如下技术方案:In order to achieve the above object, the present invention adopts the following technical solutions:
馈线上各终端(包括站内终端RTU)通过光纤以太网实现点对点通信,对等交换信息;主站通过通信处理机接入对等网络,与各终端通信。Each terminal on the feeder (including the terminal RTU in the station) realizes point-to-point communication through optical fiber Ethernet, and exchanges information on a peer-to-peer basis; the master station accesses the peer-to-peer network through a communication processor, and communicates with each terminal.
一种配电线路合环操作控制方法,包括以下步骤:A control method for loop closing operation of a distribution line, comprising the following steps:
(1)主站向联络开关发送合环指令;(1) The master station sends a ring closing command to the contact switch;
(2)联络开关对应的FTU接收到主站发送的合环指令后,首先判断开关是否为联络开关;如果是联络开关,则继续执行步骤(3),否则闭锁合环并上报主站;(2) After the FTU corresponding to the tie switch receives the loop closing instruction sent by the master station, it first judges whether the switch is a tie switch; if it is a tie switch, then proceed to step (3), otherwise it blocks the loop closure and reports to the master station;
(3)联络开关的FTU与相邻两个分段开关的FTU对等通信,获取相邻两个开关处的线电压信息,结合自身可采集的两个线电压信息进行计算,得到联络开关处的另外两个线电压;(3) The FTU of the tie switch communicates peer-to-peer with the FTUs of the two adjacent segment switches to obtain the line voltage information at the two adjacent switches, and calculate the two line voltage information that can be collected by itself, and obtain the line voltage information at the tie switch. The other two line voltages;
(4)将采集与计算得到的联络开关两侧电压信息与合环定值进行比较,判断当前系统是否符合合环操作条件;(4) Comparing the collected and calculated voltage information on both sides of the contact switch with the loop closing value to determine whether the current system meets the loop closing operation conditions;
(5)如果符合合环条件则执行所述合环指令控制联络开关合闸,并上报主站已执行合闸;否则闭锁合环操作,并将结果上报主站。(5) If the loop closing condition is met, execute the loop closing command to control the contact switch to close, and report to the master station that the switch has been closed; otherwise, block the loop closing operation, and report the result to the master station.
所述步骤(3)中,将联络开关记为n,前后两相邻开关分别记为n-1和n+1,且开关n-1位于联络开关M侧,开关n+1位于联络开关N侧,假定开关M侧PT接入AB相、N侧PT接入CB相。In the step (3), the tie switch is marked as n, and the front and rear adjacent switches are respectively marked as n-1 and n+1, and the switch n-1 is located at the tie switch M side, and the switch n+1 is located at the tie switch N Assume that the PT on the M side of the switch is connected to the AB phase, and the PT on the N side of the switch is connected to the CB phase.
所述步骤(2)中,确认联络开关的条件是该开关处于分位,且开关两侧采集到的电压均大于有压定值,即满足:In the step (2), the condition for confirming the contact switch is that the switch is in the sub-position, and the voltage collected on both sides of the switch is greater than the voltage setting value, that is to say:
其中UM·AB、UN·CB分别为联络开关M侧AB相间线电压幅值和N侧CB相间线电压幅值,UT为有压定值。Among them, U M·AB and U N·CB are the line-to-line voltage amplitudes between AB phases on the M side of the tie switch and the line-to-line voltage amplitudes between the CB phases on the N side of the tie switch, and U T is the constant voltage value.
所述步骤(3)中,利用相邻开关线电压信息计算联络开关处另外两个线电压,计算公式为:In described step (3), utilize adjacent switch line voltage information to calculate other two line voltages at tie switch place, calculation formula is:
其中UM·CB、UN·AB分别为联络开关M侧CB相间和N侧AB相间的线电压幅值,Un-1·AB和Un-1·CB是开关n-1处的线电压,Un+1·AB和Un+1·CB是开关n+1处的线电压。Among them, U M·CB and U N·AB are the line-to-line voltage amplitudes between the CB phases on the M side and the AB phases on the N side of the tie switch, and U n-1·AB and U n-1·CB are the line voltages at the switch n-1. The voltages, U n+1·AB and U n+1·CB are the line voltages at switch n+1.
所述步骤(4)中联络开关两侧线电压信息与合环定值进行比较,判断是否具备合环条件,具体内容包括:In the step (4), the line voltage information on both sides of the contact switch is compared with the ring closing value to determine whether the ring closing condition is met, and the specific contents include:
a)联络开关两侧线电压幅值均满足设定值,即满足:a) The line voltage amplitudes on both sides of the tie switch meet the set value, that is:
Umin<UL<Umax U min < U L < U max
其中UL表示联络开关处的各个线电压,Umin为幅值下限定值,Umax为幅值上限定值;Among them, U L represents each line voltage at the contact switch, U min is the lower limit value of the amplitude, and U max is the upper limit value of the amplitude;
b)开关两侧相对应的线电压幅值差均小于设定值,即满足:b) The corresponding line voltage amplitude difference on both sides of the switch is less than the set value, that is to say:
其中Uth为幅值差设定值、一般可设定为10V;Among them, U th is the setting value of the amplitude difference, which can generally be set to 10V;
c)联络开关采集的两个线电压相位之差满足设定值,即满足:c) The phase difference between the two line voltages collected by the tie switch satisfies the set value, that is:
其中,表示两个线电压的相位角,两侧系统完全同期运行时,CB相间线电压与AB相间线电压相位之差为60度;为相位角差下限定值;为相位角差上限定值。in, Indicates the phase angle of the two line voltages. When the systems on both sides are running at the same time, the phase difference between the line voltage between CB phase and the line voltage between AB phase is 60 degrees; is the lower limit value of the phase angle difference; is the upper limit of the phase angle difference.
所述步骤(4)中,当合环条件的三个条件均满足时,认为两侧系统处于同期状态,允许联络开关合闸,执行合环操作;否则,禁止联络开关合闸,取消合环操作。In the step (4), when the three conditions of the ring closing condition are all satisfied, it is considered that the systems on both sides are in the same state, and the contact switch is allowed to be closed, and the ring closing operation is performed; otherwise, the contact switch is prohibited from closing, and the ring closing is cancelled. operate.
所述步骤(4)中,在线路进行检修或转移负荷时,需要倒闸操作,采用先合上联络开关使系统合环,然后断开分段开关的方法。In the step (4), when the line is overhauled or the load is transferred, switching operation is required, and the method of first closing the tie switch to close the system and then disconnecting the section switch is adopted.
本发明的有益效果为:The beneficial effects of the present invention are:
(1)采用先合上联络开关使系统合环,然后断开分段开关的方法,可以避免开关倒闸引起的部分用户短时停电问题,从而提高供电可靠性;(1) The method of first closing the contact switch to make the system close, and then disconnecting the section switch can avoid the short-term power outage problem of some users caused by switch switching, thereby improving the reliability of power supply;
(2)本发明提出的合环操作控制方法,在合环前判断两侧系统是否同期,确定同期再进行合环操作,可有效避免发生合环误操作;(2) The loop closing operation control method proposed by the present invention judges whether the systems on both sides are in the same period before closing the loop, and then performs the loop closing operation after confirming the synchronization, which can effectively avoid loop closing misoperations;
(3)馈线终端接入对等通信网络,各终端之间可通过对等通信网实现点对点通信,不需通过主站中转,通信延时小,保证了信息传输的时效性。(3) The feeder terminal is connected to the peer-to-peer communication network, and each terminal can realize point-to-point communication through the peer-to-peer communication network without relaying through the main station, and the communication delay is small, which ensures the timeliness of information transmission.
附图说明Description of drawings
图1为本发明配电网合环控制方法的流程图;Fig. 1 is the flow chart of the control method for loop closing of distribution network of the present invention;
图2为典型的“手拉手”环状架空线路结构示意图;Figure 2 is a schematic structural diagram of a typical "hand in hand" ring overhead line;
图3为馈线终端测量电压信号示意图。Figure 3 is a schematic diagram of the voltage signal measured at the feeder terminal.
其中,PT为单相电压互感器,FTU为馈线开关对应的终端,CB1、CB2为出线开关,S1—S7是馈线开关、其中S4为联络开关,FTU1—FTU7分别为各馈线开关对应的馈线终端,RTU1、RTU2为出线开关对应的站内终端,各FTU、RTU接入对等通信网络。Among them, PT is a single-phase voltage transformer, FTU is the terminal corresponding to the feeder switch, CB1 and CB2 are outlet switches, S1-S7 is the feeder switch, among which S4 is the tie switch, FTU1-FTU7 are the feeder terminals corresponding to each feeder switch , RTU1 and RTU2 are the in-station terminals corresponding to the outlet switches, and each FTU and RTU are connected to the peer-to-peer communication network.
具体实施方式:detailed description:
下面结合附图与实施例对本发明作进一步说明。The present invention will be further described below in conjunction with the accompanying drawings and embodiments.
如图2所示,馈线终端呈分布式设置,且各馈线终端分别用于各自开关的测量与控制,各馈线终端(包括站内终端RTU)接入对等通信网络,点对点交换实时信息;主站通过通信处理机接入对等网络,可以与任一终端通信。配电网架构为“闭环设计、开环运行”,以双端电源供电的“手拉手”环网为例,根据运行情况不同,任一馈线开关都可作为联络开关使用。在图2中FTU4对应的S4开关为联络开关,正常运行时S4处于分位,系统开环运行。As shown in Figure 2, the feeder terminals are arranged in a distributed manner, and each feeder terminal is used for the measurement and control of its own switch, and each feeder terminal (including the terminal RTU in the station) is connected to the peer-to-peer communication network for point-to-point exchange of real-time information; the main station Access to the peer-to-peer network through the communication processor can communicate with any terminal. The structure of the distribution network is "closed-loop design, open-loop operation". Taking the "hand in hand" ring network powered by double-ended power supply as an example, any feeder switch can be used as a tie switch according to different operating conditions. In Figure 2, the S4 switch corresponding to FTU4 is a contact switch, and S4 is in the sub-position during normal operation, and the system operates in an open loop.
在线路检修或转移负荷需要倒闸操作时,采用先合上联络开关再断开分段开关的方法,可以避免开关倒闸引起的部分用户短时停电。例如变电站M的变压器发生过载,计划将开关S2下游负荷由变电站N转供。如果先断开开关S2再合上联络开关S4,则会导致S2与S4之间的用户短时停电;应该先合上联络开关S4使线路合环,再断开S2实现转供,在此过程中不会有用户发生停电,提高了供电可靠性。When switching operations are required for line maintenance or load transfer, the method of closing the contact switch first and then disconnecting the section switch can avoid short-term power outages for some users caused by switch switching. For example, if the transformer of substation M is overloaded, it is planned to transfer the downstream load of switch S2 from substation N. If the switch S2 is turned off first and then the tie switch S4 is turned on, it will cause a short-term power outage for users between S2 and S4; the tie switch S4 should be turned on first to close the line, and then turn off S2 to achieve power transfer. There will be no power outages for users, which improves the reliability of power supply.
配电网运行状况变化较快,由于主站与终端之间存在通信延时,当终端接收到合闸指令时,系统的运行状况可能已经发生了变化而不具备合环条件,甚至一侧线路可能已因故障跳闸,如果执行合环操作则有可能引起严重后果。本发明提出在执行合环操作前,由联络开关对应终端对两侧系统运行状态进行判断,确认系统是否具备合环条件。The operating status of the distribution network changes rapidly. Due to the communication delay between the master station and the terminal, when the terminal receives the closing command, the operating status of the system may have changed and does not meet the conditions for closing the loop. Even one side of the line It may have been tripped due to a fault, and there may be serious consequences if the ring closing operation is performed. The present invention proposes that before performing the loop closing operation, the terminal corresponding to the contact switch judges the operating status of the systems on both sides to confirm whether the system meets the loop closing conditions.
如图3中所示,现场一般在开关两侧各配置一个单相电压互感器(PT),分别检测AB相间电压和BC相间电压。于是图2中终端FTU4只能获得变电站M侧AB相间的线电压UM·AB和变电站N侧BC相间的线电压UN·BC,难以通过这两个电压信息判断是否具备合环条件。本发明提出,联络开关对应的终端通过对等通信网络,与前后两相邻开关的馈线终端通信,获取两侧相邻开关处的电压信息,结合自身电压信息进行判断。如图2中所示,FTU4通过对等网络与FTU3、FTU5通信,获取开关S3、S5处的电压信息,其中S3处电压信息为变电站M侧线电压UM·AB和UM·BC,S5处电压信息为变电站N侧线电压UN·AB和UN·BC。As shown in Figure 3, a single-phase potential transformer (PT) is generally installed on both sides of the switch on site to detect the AB phase voltage and BC phase voltage respectively. Therefore, the terminal FTU4 in Figure 2 can only obtain the line-to-line voltage U M·AB between the AB phases on the M side of the substation and the line-to-line voltage U N·BC between the BC phases on the N side of the substation. The invention proposes that the terminal corresponding to the tie switch communicates with the feeder terminals of the two adjacent switches at the front and rear through the peer-to-peer communication network, obtains the voltage information at the adjacent switches on both sides, and makes a judgment in combination with its own voltage information. As shown in Figure 2, FTU4 communicates with FTU3 and FTU5 through a peer-to-peer network to obtain the voltage information at switches S3 and S5, where the voltage information at S3 is the line voltage U M·AB and U M·BC on the M side of the substation, and the voltage information at S5 The voltage information is the N-side line voltage U N·AB and U N·BC of the substation.
如图1所示,是本发明提出的配电网合环控制方法所包含的主要步骤,结合图2对主要步骤说明如下:As shown in Figure 1, it is the main steps included in the distribution network loop closing control method proposed by the present invention, and the main steps are explained as follows in conjunction with Figure 2:
调度员或主站系统判定需要进行合环操作后,由主站向联络开关S4对应的馈线终端FTU4发送合环指令,该合环指令为含有合环标志的遥控合指令;After the dispatcher or the main station system determines that the loop closing operation is required, the main station sends a loop closing command to the feeder terminal FTU4 corresponding to the tie switch S4, and the loop closing command is a remote closing command containing a loop closing sign;
FTU4接收接收到合环指令后,首先确认对应开关是否为联络开关;如果是联络开关则继续执行步骤(3),否则闭锁合环并上报主站;确认联络开关的条件是开关处于分位,且开关两侧采集到的电压均大于有压定值,即满足After FTU4 receives and receives the ring closing command, first confirm whether the corresponding switch is a tie switch; if it is a tie switch, continue to perform step (3), otherwise block the ring and report to the master station; the condition for confirming the tie switch is that the switch is in the position, And the voltage collected on both sides of the switch is greater than the voltage setting value, that is, the
其中UM·AB、UN·CB分别为联络开关M侧AB相间线电压幅值和N侧CB相间线电压幅值,UT为有压定值,一般可设为额定电压的0.7倍;Among them, U M·AB and U N·CB are the line-to-line voltage amplitudes between AB phases on the M side of the tie switch and the phase-to-line voltage amplitudes between CB phases on the N side of the tie switch, and U T is a fixed voltage value, which can generally be set to 0.7 times the rated voltage;
FTU4直接与FTU3和FTU5点对点通信,获取相邻两个开关S3、S5处的电压信息,结合自身可采集的两个线电压信息进行计算,得到联络开关S4处另外两个线电压;计算公式为:FTU4 directly communicates point-to-point with FTU3 and FTU5, obtains the voltage information at the two adjacent switches S3 and S5, and calculates the two line voltage information that can be collected by itself, and obtains the other two line voltages at the tie switch S4; the calculation formula is :
其中UM·CB、UN·AB分别为联络开关M侧CB相间和N侧AB相间的线电压幅值,US3·AB和US3·CB是开关S3处的线电压,US5·AB和US5·CB是开关S5处的线电压。Among them, U M·CB and U N·AB are the line-to-line voltage amplitudes between the CB phases on the M side and the AB phases on the N side of the tie switch respectively, U S3·AB and U S3·CB are the line-to-line voltages at the switch S3, and U S5·AB and U S5·CB is the line voltage at switch S5.
将联络开关S4两侧的电压信息与合环定值进行比较,判断当前系统是否具备合环操作条件;判据包括:S4两侧线电压幅值均满足设定值、S4两侧相对应的线电压幅值差均小于设定值、S4采集的两个线电压相位之差满足设定值;当上述三个条件均满足时,认为系统处于同期状态,符合合环条件;Compare the voltage information on both sides of the contact switch S4 with the loop closing value to determine whether the current system has the conditions for loop closing operation; the criteria include: the line voltage amplitudes on both sides of S4 meet the set value, and the corresponding line on both sides of S4 The voltage amplitude difference is less than the set value, and the phase difference between the two line voltages collected by S4 satisfies the set value; when the above three conditions are met, the system is considered to be in the same state and meets the loop closure conditions;
三个条件具体内容包括:The specific contents of the three conditions include:
1)联络开关两侧线电压幅值均满足设定值,即满足:1) The line voltage amplitudes on both sides of the tie switch meet the set value, that is:
Umin<UL<Umax U min < U L < U max
其中UL表示联络开关处的各个线电压,Umin为幅值下限定值、一般可设为额定电压的0.9倍,Umax为幅值上限定值、一般可设为额定电压的1.1倍;Among them, U L represents each line voltage at the contact switch, U min is the lower limit value of the amplitude, which can generally be set to 0.9 times the rated voltage, and U max is the upper limit value of the amplitude, which can generally be set to 1.1 times the rated voltage;
2)开关两侧相对应的线电压幅值差均小于设定值,即满足:2) The corresponding line voltage amplitude difference on both sides of the switch is less than the set value, that is to say:
其中Uth为幅值差设定值、一般可设定为10V;Among them, U th is the setting value of the amplitude difference, which can generally be set to 10V;
3)联络开关采集的两个线电压相位之差满足设定值,即满足:3) The phase difference between the two line voltages collected by the tie switch satisfies the set value, that is:
其中,表示两个线电压的相位角,两侧系统完全同期运行时,CB相间线电压与AB相间线电压相位之差为60度;为相位角差下限定值,一般可设为50度;为相位角差上限定值,一般可设为70度。in, Indicates the phase angle of the two line voltages. When the systems on both sides are running at the same time, the phase difference between the line voltage between CB phase and the line voltage between AB phase is 60 degrees; It is the lower limit value of the phase angle difference, which can generally be set to 50 degrees; It is the upper limit value of the phase angle difference, which can generally be set to 70 degrees.
如果符合合环条件则执行所述合环指令控制联络开关合闸,并上报主站已执行合闸;否则闭锁合环操作,并将结果上报主站。If the loop-closing condition is met, execute the loop-closing instruction to control the tie switch to close, and report to the master station that the switch has been closed; otherwise, block the loop-closing operation, and report the result to the master station.
当其他馈线开关作为联络开关运行时,与S4是联络开关的情况类似,在此不再一一赘述。同样的道理,本发明提出的方法也适用于其他环网形式,包括但不限于多分段多联络网、单环电缆网、双环电缆网、多供一备等网架结构。When other feeder switches operate as a tie switch, it is similar to the case where S4 is a tie switch, and details will not be repeated here. For the same reason, the method proposed by the present invention is also applicable to other forms of ring network, including but not limited to multi-segment multi-connection network, single-ring cable network, double-ring cable network, multi-supply and one-backup and other grid structures.
上述虽然结合附图对本发明的具体实施方式进行了描述,但并非对本发明保护范围的限制,所属领域技术人员应该明白,在本发明的技术方案的基础上,本领域技术人员不需要付出创造性劳动即可做出的各种修改或变形仍在本发明的保护范围以内。Although the specific implementation of the present invention has been described above in conjunction with the accompanying drawings, it does not limit the protection scope of the present invention. Those skilled in the art should understand that on the basis of the technical solution of the present invention, those skilled in the art do not need to pay creative work Various modifications or variations that can be made are still within the protection scope of the present invention.
Claims (6)
Priority Applications (1)
| Application Number | Priority Date | Filing Date | Title |
|---|---|---|---|
| CN201510105282.6A CN104734352B (en) | 2015-03-10 | 2015-03-10 | A kind of distribution line Loop Closing Operation control method |
Applications Claiming Priority (1)
| Application Number | Priority Date | Filing Date | Title |
|---|---|---|---|
| CN201510105282.6A CN104734352B (en) | 2015-03-10 | 2015-03-10 | A kind of distribution line Loop Closing Operation control method |
Publications (2)
| Publication Number | Publication Date |
|---|---|
| CN104734352A CN104734352A (en) | 2015-06-24 |
| CN104734352B true CN104734352B (en) | 2017-06-20 |
Family
ID=53457930
Family Applications (1)
| Application Number | Title | Priority Date | Filing Date |
|---|---|---|---|
| CN201510105282.6A Active CN104734352B (en) | 2015-03-10 | 2015-03-10 | A kind of distribution line Loop Closing Operation control method |
Country Status (1)
| Country | Link |
|---|---|
| CN (1) | CN104734352B (en) |
Families Citing this family (8)
| Publication number | Priority date | Publication date | Assignee | Title |
|---|---|---|---|---|
| CN105720606B (en) * | 2016-04-12 | 2018-02-16 | 贵州黔燎原电气科技有限公司 | A kind of control method of active power distribution network unperturbed cyclization for active power distribution network |
| CN106787201A (en) * | 2016-12-30 | 2017-05-31 | 国网天津市电力公司 | A kind of closed loop network method that phase is determined based on remote online |
| CN109066985A (en) * | 2018-08-28 | 2018-12-21 | 云南电网有限责任公司电力科学研究院 | A kind of quick cyclization tune electric system and method |
| CN109444790B (en) * | 2018-10-29 | 2021-05-04 | 广西电网有限责任公司电力科学研究院 | Method suitable for feeder terminal to identify working state of power supply voltage transformer |
| CN111914377B (en) * | 2020-08-14 | 2024-05-03 | 南方电网数字电网研究院股份有限公司 | Method and system for repairing feeder line loss model, computer equipment and readable storage medium |
| CN112636471B (en) * | 2020-12-11 | 2022-08-02 | 国网安徽省电力有限公司黄山供电公司 | A method for judging abnormal de-looping during loop-closing process of 10KV distribution network |
| CN116093903B (en) * | 2023-03-17 | 2025-02-11 | 中铁工程设计咨询集团有限公司 | A substation incoming line protection method, device, equipment and readable storage medium |
| CN117439033B (en) * | 2023-12-19 | 2024-05-14 | 成都天合一成科技服务有限公司 | A system to prevent loop closing misoperation based on real-time data of substation |
Citations (5)
| Publication number | Priority date | Publication date | Assignee | Title |
|---|---|---|---|---|
| CN101908763A (en) * | 2010-07-23 | 2010-12-08 | 广东电网公司中山供电局 | Distribution network loop closing control method |
| CN102611107A (en) * | 2012-04-09 | 2012-07-25 | 凯里供电局 | Urban medium-voltage power distribution network closed-loop power supply system based on annular net rack |
| CN102769338A (en) * | 2012-07-20 | 2012-11-07 | 冀北电力有限公司张家口供电公司 | Control method for closed-loop operation of distribution network |
| CN103236695A (en) * | 2013-04-28 | 2013-08-07 | 国家电网公司 | Power distribution network loop closing current switching method and device, and power distribution terminal |
| CN203164336U (en) * | 2013-03-28 | 2013-08-28 | 重庆市电力公司永川供电局 | Overhead distribution line closed-loop monitoring device |
Family Cites Families (1)
| Publication number | Priority date | Publication date | Assignee | Title |
|---|---|---|---|---|
| US9088160B2 (en) * | 2007-12-12 | 2015-07-21 | Abb Research Ltd. | Load restoration for feeder automation in electric power distribution systems |
-
2015
- 2015-03-10 CN CN201510105282.6A patent/CN104734352B/en active Active
Patent Citations (5)
| Publication number | Priority date | Publication date | Assignee | Title |
|---|---|---|---|---|
| CN101908763A (en) * | 2010-07-23 | 2010-12-08 | 广东电网公司中山供电局 | Distribution network loop closing control method |
| CN102611107A (en) * | 2012-04-09 | 2012-07-25 | 凯里供电局 | Urban medium-voltage power distribution network closed-loop power supply system based on annular net rack |
| CN102769338A (en) * | 2012-07-20 | 2012-11-07 | 冀北电力有限公司张家口供电公司 | Control method for closed-loop operation of distribution network |
| CN203164336U (en) * | 2013-03-28 | 2013-08-28 | 重庆市电力公司永川供电局 | Overhead distribution line closed-loop monitoring device |
| CN103236695A (en) * | 2013-04-28 | 2013-08-07 | 国家电网公司 | Power distribution network loop closing current switching method and device, and power distribution terminal |
Non-Patent Citations (1)
| Title |
|---|
| 煤矿配电网合环监测系统的研究与设计;李建修等;《中国煤炭科技》;20140131;第40卷(第1期);第79-81页 * |
Also Published As
| Publication number | Publication date |
|---|---|
| CN104734352A (en) | 2015-06-24 |
Similar Documents
| Publication | Publication Date | Title |
|---|---|---|
| CN104734352B (en) | A kind of distribution line Loop Closing Operation control method | |
| CN102769338B (en) | Closed-loop operational control method for power distribution network | |
| CN105140894B (en) | A kind of power distribution network differential protecting method based on Phase Difference Principle | |
| WO2017166735A1 (en) | Power-grid self-healing system and self-healing logic thereof in 110kv chain power-supply mode | |
| CN103490392B (en) | Fault handling method of power distribution network comprising distributed power supplies and microgrids | |
| CN202309201U (en) | Communication power system | |
| CN204481571U (en) | A kind of Loop Closing Operation in Distribution Network control system based on terminal peer-to-peer communications | |
| CN112134293A (en) | A station terminal public unit and its wide area autonomy method based on edge computing | |
| CN107332217B (en) | The co-architecture and Synergistic method of the power distribution protection of the device containing flexible interconnection | |
| CN104979894A (en) | RMU uninterrupted power supply load transfer method | |
| CN101741137A (en) | The method of automatic input of network centralized backup power supply | |
| CN105790442A (en) | Distributed intelligent feeder automation system capable of achieving quick self-healing | |
| CN106655168A (en) | Method and device for building loop closing model of power distribution network | |
| CN106451373A (en) | Bidirectional allowable protection method employing master station to identify dynamic topology for power distribution circuit | |
| CN104701825A (en) | Quick protection method applicable to intelligent distribution network | |
| CN204103598U (en) | A kind of redundancy protection systems of transformer station | |
| CN105871063A (en) | Interstation protection fault recognition system and method based on information fusion | |
| CN103236695A (en) | Power distribution network loop closing current switching method and device, and power distribution terminal | |
| CN104201657A (en) | Power direction judgment based bidirectional blocking protection method for distributing line | |
| CN104578065B (en) | The cyclization control method of distribution intelligent acquisition switching device | |
| CN204497849U (en) | A kind ofly take into account measure and control device that is centralized, formula feeder automation on the spot | |
| CN107016490A (en) | Power networks risk takes precautions against pre-control practical application method, apparatus and system | |
| CN201805272U (en) | Intelligent incoming line standby self-injection device suitable for areas rich in small hydropower | |
| CN107069964A (en) | A kind of intelligent distributed FA and master station-centralized FA Synergistic methods | |
| CN106385013A (en) | A fault location and isolation system for adaptive distribution network operation mode and its working method |
Legal Events
| Date | Code | Title | Description |
|---|---|---|---|
| C06 | Publication | ||
| PB01 | Publication | ||
| C10 | Entry into substantive examination | ||
| SE01 | Entry into force of request for substantive examination | ||
| GR01 | Patent grant | ||
| GR01 | Patent grant |