CN105019678B - A kind of energy-saving environment-protecting type waterproof construction method for having roofing - Google Patents

A kind of energy-saving environment-protecting type waterproof construction method for having roofing Download PDF

Info

Publication number
CN105019678B
CN105019678B CN201510452845.9A CN201510452845A CN105019678B CN 105019678 B CN105019678 B CN 105019678B CN 201510452845 A CN201510452845 A CN 201510452845A CN 105019678 B CN105019678 B CN 105019678B
Authority
CN
China
Prior art keywords
spraying
waterproof
construction
coiled material
roofing
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Active
Application number
CN201510452845.9A
Other languages
Chinese (zh)
Other versions
CN105019678A (en
Inventor
王天星
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Nantong Shuimu Qinghua Decoration Design Engineering Co ltd
Original Assignee
BEIJING ZHONGLIAN TIANSHENG BUILDING MATERIALS Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by BEIJING ZHONGLIAN TIANSHENG BUILDING MATERIALS Co Ltd filed Critical BEIJING ZHONGLIAN TIANSHENG BUILDING MATERIALS Co Ltd
Priority to CN201510452845.9A priority Critical patent/CN105019678B/en
Publication of CN105019678A publication Critical patent/CN105019678A/en
Application granted granted Critical
Publication of CN105019678B publication Critical patent/CN105019678B/en
Active legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Landscapes

  • Roof Covering Using Slabs Or Stiff Sheets (AREA)
  • Working Measures On Existing Buildindgs (AREA)

Abstract

The invention discloses a kind of energy-saving environment-protecting type waterproof construction method for having roofing, including spraying anti-cracking and waterproofing mortar, exposed waterproof layer coat substrate interface agent, the construction compound with elastomer modified asphalt waterproof roll of butyl rubber and plastic water-repellent paint, first time self-test are with examination, spraying uvioresistant water-repellent paint overcoat, second of self-test with checking and accepting.Beneficial effects of the present invention:Waterproof construction of the present invention, which does not have to remove, has roofing, system construction can directly be carried out, coating carries out the compound construction technology of heat with coiled material in construction surface, seamless waterproof layer is formed after ensuring seamed coiled material construction, the non-uniform phenomenon that uniformly and effectively compensate for coating of coiled material, whole surface layer is set to form integral seamless waterproof system, energy-conserving and environment-protective;Construction cost is low, construction safety, good water-proof effect and the load-bearing quality for not influenceing Building Design.

Description

A kind of energy-saving environment-protecting type waterproof construction method for having roofing
Technical field
The present invention relates to waterproof construction field, it particularly relates to a kind of energy-saving environment-protecting type waterproof construction for having roofing Method.
Background technology
With the development of China, high buildings and large mansions in all parts of the country are rised sheer from level ground, and high building stands in great numbers, the crowded and energy-conservation in city Environmental protection into everyone all concern the problem of.Water-proof heat-insulating roof is a kind of to integrate waterproof and heat-insulated waterproof room Face, waterproof are basic functions, while take into account heat-insulated, are the important component of water-proof heat-insulating roof engineering again with waterproof.
The roof waterproof layer of traditional architecture industry mainly uses discrete material, precious for example with clinker, expanded vermiculite, expansion The problem of material dry-laid such as Zhu Yan forms, and it is present is that difficulty of construction is big, waterproof effect is again undesirable.The existing room implemented at present Room transformation roofing construction in, it is necessary to which the original waterproof layer of roofing is rooted out after, re-lay new waterproof layer, so, coating apply Smear uneven, not only waterproof effect is not ideal enough, long construction period, and construction is cumbersome, and comprehensive cost is high, construction it is dangerous but also The wasting of resources, environmental pollution are caused, does not meet energy-saving and emission-reduction requirement of the country to building trade.
Therefore, in the market needs one kind badly has roofing, direct carry out system construction, energy-conserving and environment-protective, construction peace without removing Entirely, construction cost is low, the construction method of good water-proof effect and the load-bearing quality for not influenceing Building Design.
The content of the invention
It is existing at present to overcome it is an object of the invention to provide a kind of energy-saving environment-protecting type waterproof construction method for having roofing Technology above shortcomings.
To realize above-mentioned technical purpose, the technical proposal of the invention is realized in this way:
A kind of energy-saving environment-protecting type waterproof construction method for having roofing, is comprised the following specific steps that:
1)Spray anti-cracking and waterproofing mortar:The basic unit for having roofing is cleared up, after base cleaning is clean, by predetermined ratio Example carries out anti-cracking waterproof sand oar and fed intake, and is stirred after feeding intake using hand blender, spray is proceeded by after material stirs Construction is applied, and after construction three hours, checks whether uniform ground, if non-uniform phenomenon, is repaired;Wherein, right When having the basic unit of roofing to be cleared up, the existing waterproof layer on water Luo Kou peripheries is subjected to removal procedure, also, in spraying application When, spraying application is constructed using spraying method while stirring, while smooth using special wiper progress wiper, spraying application Using near after first remote, the order retreated in spraying is constructed;
2)Exposed waterproof layer coat substrate interface agent:To cracking resistance Waterproof sand oar, basic unit is cleared up, and debugging, hot spraying are set The standby and input basic unit interface agent into spraying equipment, carries out spraying application, glass fibers is laid after the completion of spraying application after to be melted Wei Bu;Wherein, spraying application is closely sequentially constructed using first far rear, and all connection details carry out even application, while not There must be grinning effect, glass fabric, which must not lay, tilting phenomenon;
3)Butyl rubber and plastic water-repellent paint, the compound construction of elastomer modified asphalt waterproof roll:Glass fabric laying is completed Afterwards, coiled material is cut by preliminary dimension, meanwhile, debugging, hot spraying equipment simultaneously put into butyl rubber and plastic into spraying equipment Water-repellent paint, spraying application is proceeded by after to be melted, pasted in spraying, be compacted coiled material, be stacked between adjacent web And butyl rubber and plastic water-repellent paint is sprayed at stacking, coiled material, which is received, carries out encapsulation process at head, in the elastomer-modified drip pasted By predetermined thickness spraying butyl rubber and plastic water-repellent paint outside blue or green waterproof roll, wherein, water fall mouthful at sprayed according to from inside to edge The principle of painting is sprayed, and coating spraying is carried out in the range of the 50cm that stretches out at Shui Luokou edges and pastes coiled material, coiled material After the completion of stickup, butyl rubber and plastic water-repellent paint is sprayed in the range of stretching out at Shui Luokou edges more than 500cm again;Its In, paint thickness is more than or equal to 1.5mm on the outside of coiled material, and coiled material is more than or equal to 2.4mm with coating gross thickness, and spraying application is using first High after low, first far rear closely, in spraying reverse order is constructed, also, coiled material pastes the preceding predetermined stacking position on coiled material Datum line is installed, the dope width sprayed at stacking is more than predetermined stacking width;
4)First time self-test is with checking and accepting:To being sealed and being repaired at hollowing, breakage and tilting, under entering after passed examination One procedure is constructed;
7)Spray uvioresistant water-repellent paint overcoat:Uvioresistant waterproofing protection construction is carried out after layer acceptance(check), is pressed Predetermined ratio carries out cracking resistance uvioresistant Waterproof sand oar and fed intake, and is stirred after feeding intake using hand blender, treats that material stirring is equal Spraying application is proceeded by after even, water falls to be smeared into smooth at mouth using cracking resistance uvioresistant waterproof mortar;Wherein, spraying application Constructed using spraying method while stirring, at the same it is smooth using special wiper progress wiper, there must not be drain spray phenomenon, spray Using near after first remote, the order retreated in spraying is constructed for construction;
8)Second of self-test is with checking and accepting:Uvioresistant water-repellent paint overcoat spraying application checks whether after three hours It is even smooth, if non-uniform phenomenon, repaired;
Further, carrying out cleaning to the basic unit for having roofing includes:
1)Clear up existing roofing:The pollutant of existing waterproof layer surface is removed using steel brush, side cleaning is just returned with dust catcher Receive pollutant;
2)Trimming has surface layer:After surface contaminant complete liquidation, hollowing and damage location are scratched using instrument And internal contamination thing is cleared up, carry out spraying repairing using butyl rubber and plastic water-repellent paint after the completion of cleaning;
3)Connection detail is cleared up:Hollowing at detail treatment and damage location are scratched and clear up internal contamination thing, is cleared up After the completion of using butyl rubber and plastic water-repellent paint carry out spraying repairing;Wherein, the detail treatment includes seam, negative and positive angle, daughter Wall, gutter, eaves gutter, cornice, wall feed-through pipeline, the intersection of depths roof pipeline and roof plan, at roof edge.
Further, step 2)Described in glass fabric size include 8 × 8-10 × 8.
Further, step 3)Middle coiled material sticking construction is carried out according to from plane to facade order, wherein, at detail treatment Additional waterproof course is set, and the additional waterproof course is the butyl rubber and plastic waterproof coating layer that thickness is more than or equal to 3.0mm.
Beneficial effects of the present invention:Waterproof construction of the present invention, which does not have to remove, has roofing, can directly carry out system construction, applies Material carries out the compound construction technology of heat with coiled material in construction surface, it is ensured that forms seamless waterproof layer, coiled material after seamed coiled material construction The non-uniform phenomenon that uniformly and effectively compensate for coating, whole surface layer is formed integral seamless waterproof system, energy-conserving and environment-protective; Construction cost is low, construction safety, good water-proof effect and the load-bearing quality for not influenceing Building Design.
Embodiment
Obviously, described embodiment is only part of the embodiment of the present invention, rather than whole embodiments.Based on this Embodiment in invention, the every other embodiment that those of ordinary skill in the art are obtained, belong to the model that the present invention protects Enclose.
Described a kind of energy-saving environment-protecting type waterproof construction method for having roofing according to an embodiment of the invention, including it is as follows Specific steps:
1)Spray anti-cracking and waterproofing mortar:After base cleaning is clean, anti-cracking waterproof sand oar is fed intake in proportion, fed intake It is stirred afterwards using hand blender, proceeds by spraying application after material stirs, should side stirring during spraying application Side spraying application, it is smooth that wiper carried out using special wiper during spraying, should be noted that during spraying application it is first remote after it is near, in spraying after The principle moved back, should be noted that underfooting when stepping back, to prevent the generation of danger, can go up people in about three hours after the completion of spraying, inspection is No uniform ground, if non-uniform phenomenon, repaired;
2)Exposed waterproof layer coat substrate interface agent:After base cleaning is clean, first spraying equipment is debugged, heated, Basic unit's interface agent is put into, interface spraying is proceeded by after to be melted, protective garment should have been dressed before spraying, with anti-scald, spraying is situated between It is first remote rear near as spraying anti-cracking waterproof sand oar during the agent of face, take care, prevent from scalding, Striping operators are it is noted that spraying It is uniform, there must not be grinning effect, after the completion of spraying interface, to carry out paving glass fabric(What it is with 8 × 8-10 × 8 is Preferably), to flatten compacting during laying, not there is a tilting phenomenon, all connection details will even application, must not have grinning effect, The glass fabric will be laid smooth;According to place where troops were originally stationed water layer whether it is exposed or lugless brick during practice of construction, it is determined that using anti- Waterproof mortar is split as interface agent or other raw materials as interface agent;
3)Butyl rubber and plastic water-repellent paint, the compound construction of elastomer modified asphalt waterproof roll:Treat that any of the above project is finished Afterwards, the coiled material cut out needed for each thin portion position should be carried out before spraying application, spraying equipment is debugged, is heated, puts into butyl Rubber and plastic water-repellent paint, waterproof layer spraying application is proceeded by after to be melted, should be noted that its minimum thickness is not small in waterproof construction In 1.5mm, gross thickness is not less than 2.4mm, is first constructed since all drain gullies and the surface layer bottom position, high behind first bottom, first Near after remote, spraying wants thin and thick uniform, retreats and is constructed in spraying, pays attention to underfooting and surrounding safety and prevent from scalding;
4)First time self-test is with checking and accepting:As should be in time sealed, repair phenomena such as finding unreal sealing, tilting during self-check, Any hidden danger must not be stayed, site operation person, Quality Inspector must be joined a regular shift or class inspection, and next process of being allowed for access after passed examination is applied Work;
5)Spray uvioresistant water-repellent paint overcoat:Uvioresistant waterproofing protection is carried out after waterproof construction acceptance(check) to apply Work, uvioresistant water-repellent paint is fed intake in proportion, is stirred after feeding intake with hand blender, after material stirs Proceed by protection spraying application, to keep spraying uniform during spraying, not have drain spray phenomenon, to reduce service life;
6)Second of self-test is with checking and accepting:People can be gone up in about three hours after the completion of spraying uvioresistant water-repellent paint, is checked Whether uniformly, if non-uniform phenomenon, repaired, examination is submitted a report asking for after repairing is qualified, all delivered at once after acceptance(check) Use.
In addition, in a specific embodiment, there is the preparation before roof waterproof construction to prepare including material shortly, Instrument prepares, basic unit prepares and security against fire prepares.
In addition, in a specific embodiment, the material prepares to include waterproof main material and waterproof auxiliary material, the waterproof Main material includes butyl rubber and plastic water-repellent paint;The waterproof auxiliary material includes uvioresistant water-repellent paint, anti-cracking and waterproofing mortar and glass Fiber cloth.
In addition, in a specific embodiment, the instrument preparation includes small grafter, dust catcher, pocket knife, wood, steel and smeared Son, steel brush, broom, coating applicators, protection flush coater, scraper plate, rolling brush, hairbrush, palm, pliers, protective gloves, protection Clothes and Protection helmet.
In addition, in a specific embodiment, the basic unit prepares to comprise the following specific steps that:
1)Cleaning repairing roofing:According to there is the situation of roofing, first there is the removing of waterproof layer steel brush whole bristle Pollutant, the pollutant brushed off is exhausted with dust catcher while during brush in brush(The energy can be saved compared to using water punching, It can be reduced environmental pollution compared to using hair-dryer, it is more environmentally-friendly using dust catcher);
2)Trimming has surface layer:After pollutant complete liquidation, then the processing of hollowing, breakage is carried out, handled Method is that hollowing and breakage are scratched with knife, and then the dirt of cleaning the inside, is applied after the completion of cleaning using butyl rubber and plastic waterproof Material carries out spraying repairing;
3)Connection detail is cleared up:General drain gully is all smaller, and easily blocks, so must be drain gully before repairerment Original waterproof layer cutting on periphery is removed totally, and being cut and disassembled first at negative and positive angle, pipe root detail treatment has surface layer At damaged and hollowing, dust suction cleaning can carry out waterproof construction after repairing basic unit.
The lifting that scaffold carries out material should be set up if necessary(Depending on engineering practice).
In addition, in a specific embodiment, step 3)Butyl rubber and plastic water-repellent paint, elastomer modified asphalt waterproof volume The compound construction of material comprises the following specific steps that:
3.1)Drain gully is constructed:To use spray gun surrounding in drain gully to spray, paste in spraying and cut out by O. gracilipes Good waterproof roll, steel shovel compacting is borrowed if necessary, drain gully should be noted that from drain gully edge when constructing, to around in 50cm Carry out spraying cohesive coiled material, and want to be compacted between thin and thick uniform coating and coiled material, turn into an entirety, to prevent producing herein Life is ftractureed again;
3.2)Gutter, eaves gutter construction:The construction processing of gutter, eaves gutter should be first carried out before large area waterproof construction, is constructed Shi Yingcong ditches, the lowest part of eaves paste waterproof roll to highest point in spraying, and side adhesive rim compacting is answered when pasting coiled material, waits to roll up After the completion of material laying, then spray one layer and be more than the thick butyl rubber and plastic water-repellent paints of 1.5mm;
3.3)Parapet is constructed:The situation according to the roofing is should be noted that during these position waterproof constructions, should be first inner corner trim portion Point spraying application is carried out, Striping operators want thin and thick uniformly to be sprayed along inner corner trim when should be noted that spraying, should elder generation during spraying Height is constructed behind bottom, to prevent causing phenomenon of turning one's coat, should be pressed when parapet is constructed first coiled material than good, after compression in spraying It is real to be pasted from plane to facade, when affixing to inner corner trim, it is compacted using trowel along inner corner trim, there must not be hollowing phenomenon;
3.4)The setting of extra play:Waterproof should be set to add in portions such as flat facade junction, turning point, negative and positive angle, pipe roots Enhancement layer, using with requiring that the butyl rubber and plastic water-repellent paint of one times of thickness carries out spraying application, it must not be done using coiled material additional Layer;
3.5)Big surface construction:After any of the above project is finished, first spraying equipment is debugged, puts into butyl rubber and plastic waterproof Coating is heated, while gets out elastomer modified asphalt waterproof roll, then finishes reference line work before being constructed, fusion Proceed by spraying application after change, during waterproof construction, coiled material is pasted one end along the datum line finished than good coiled material, spraying first Afterwards, tighten up from the coiled material other end coiled material, then sprayed along the datum line finished, pay attention to spraying more than benchmark during spraying Line, answers the stickup for carrying out coiled material in spraying during spraying application, answers during stickup and is pasted in compacting, and first volume coiled material is constructed completion Afterwards, carry out with the construction of volume Two coiled material, volume Two coiled material, during than volume, first volume coiled material should be pushed down(Coiled material lapping pressure head is not small It is wide in 10cm), after coiled material is spooled, first the spraying of overlap joint termination is pasted, then start to paste coiled material, basal plane is arrived in construction by that analogy The end, carry out spraying pressure head after being at the end, sealing, after benchmark coiled material pastes carrying out side connects construction, while connecing construction When, should along the benchmark releasing coil laid, such as, winding(Its side meets place should be wide not less than 10cm), first end after winding Head spraying firm pasting, then start to paste coiled material, while connecing when pasting coiled material, it should be noted that during spraying to benchmark coiled material side and spray not more The coating wide less than 10cm, preferably to paste, the end of construction to basal plane, carries out receiving head densification after being at the end by that analogy Envelope, while connecing sealing;
3.6)Connection detail construction in waterproof construction:Detail treatment(Flat facade junction, wall pipe etc.)All it is waterproof The weak link of engineering, it is necessary to reasonable, safety, the design of science and the constructing operation for requiring high quality are targetedly carried out, It just can guarantee that the globality of roof waterproof system and closed impermeability.
In addition, in a specific embodiment, all site operation personnel must dress protective articles, and must not have it His personnel stop scene.
In addition, in a specific embodiment, before construction of waterproof layer is done, step 1)It is middle according to place where troops were originally stationed water layer whether be It is exposed or lugless brick to choose whether to be used as interface agent by the use of anti-cracking and waterproofing mortar.3~8 kilograms every square metre of weight, The load-bearing quality of Building Design should not be rung
In summary, by means of the above-mentioned technical proposal of the present invention, waterproof construction of the present invention, which does not have to remove, has roofing, can System construction is directly carried out, coating carries out the compound construction technology of heat with coiled material in construction surface, it is ensured that shape after seamed coiled material construction Into seamless waterproof layer, the non-uniform phenomenon that uniformly and effectively compensate for coating of coiled material, whole surface layer is set to form integral nothing Stitch waterproof system, energy-conserving and environment-protective;Construction cost is low, construction safety, good water-proof effect and the load-bearing matter for not influenceing Building Design Amount.
The foregoing is merely illustrative of the preferred embodiments of the present invention, is not intended to limit the invention, all essences in the present invention God any modification, equivalent substitution and improvements made etc., should be included in the scope of the protection with principle.

Claims (3)

1. a kind of energy-saving environment-protecting type waterproof construction method for having roofing, it is characterised in that comprise the following specific steps that:
1)Spray anti-cracking and waterproofing mortar:The basic unit for having roofing is cleared up, after base cleaning is clean, entered by predetermined ratio Row anti-cracking waterproof sand oar feeds intake, and is stirred after feeding intake using hand blender, and proceeding by spraying after material stirs applies Work, and after construction three hours, check whether uniform ground, if non-uniform phenomenon, repaired;Wherein, to having When the basic unit of roofing is cleared up, the existing waterproof layer on water Luo Kou peripheries is subjected to removal procedure, also, in spraying application, Spraying application is constructed using spraying method while stirring, while smooth using special wiper progress wiper, and spraying application is adopted With near after first remote, the order retreated in spraying is constructed;
2)Exposed waterproof layer coat substrate interface agent:To cracking resistance Waterproof sand oar, basic unit clears up, and debugging, hot spraying equipment are simultaneously Basic unit's interface agent is put into spraying equipment, spraying application is carried out after to be melted, glass fabric is laid after the completion of spraying application; Wherein, spraying application is closely sequentially constructed using first far rear, and all connection details carry out even application, while must not have dew Bottom phenomenon, glass fabric, which must not lay, tilting phenomenon;
3)The compound construction of butyl rubber water-repellent paint, elastomer modified asphalt waterproof roll:After the completion of glass fabric laying, press Preliminary dimension is cut to coiled material, meanwhile, debugging, hot spraying equipment simultaneously put into the painting of butyl rubber waterproof into spraying equipment Material, spraying application is proceeded by after to be melted, is pasted in spraying, is compacted coiled material, is stacked between adjacent web and in layer Folded place's spraying butyl rubber water-repellent paint, coiled material, which is received, carries out encapsulation process at head, in the elastomer modified asphalt waterproof pasted By predetermined thickness spraying butyl rubber water-repellent paint outside coiled material, wherein, water fall mouthful at according to the original sprayed from inside to edge Then sprayed, coating spraying is carried out in the range of the 50cm that stretches out at Shui Luokou edges and pastes coiled material, coiled material has been pasted Cheng Hou, butyl rubber water-repellent paint is sprayed again in the range of stretching out at Shui Luokou edges more than 500cm;Wherein, coiled material Outside paint thickness is more than or equal to 1.5mm, and coiled material and coating gross thickness are more than or equal to 2.4mm, spraying application using height after first low, First far rear closely, in spraying reverse order is constructed, also, coiled material pastes the preceding predetermined stratification position setting base on coiled material Directrix, the dope width sprayed at stacking are more than predetermined stacking width;
4)First time self-test is with checking and accepting:To being sealed and being repaired at hollowing, breakage and tilting, next road is entered after passed examination Process is constructed;
5)Spray uvioresistant water-repellent paint overcoat:Uvioresistant waterproofing protection construction is carried out after waterproof construction acceptance(check), Cracking resistance uvioresistant Waterproof sand oar is carried out by predetermined ratio to feed intake, is stirred after feeding intake using hand blender, treats material stirring Spraying application is proceeded by after uniformly, water falls to be smeared into smooth at mouth using cracking resistance uvioresistant waterproof mortar;Wherein, spraying is applied Work is constructed using spraying method while stirring, while smooth using special wiper progress wiper, must not be had drain spray phenomenon, be sprayed Construction is applied using near after first remote, the order retreated in spraying is constructed;
6)Second of self-test is with checking and accepting:Uvioresistant water-repellent paint overcoat spraying application checks whether uniformly flat after three hours It is whole, if non-uniform phenomenon, repaired.
2. the energy-saving environment-protecting type waterproof construction method according to claim 1 for having roofing, it is characterised in that to having room The basic unit in face, which carries out cleaning, to be included:
1)Clear up existing roofing:The pollutant of existing waterproof layer surface is removed using steel brush, side cleaning is just reclaimed dirty with dust catcher Contaminate thing;
2)Trimming has surface layer:After surface contaminant complete liquidation, hollowing and damage location are scratched simultaneously clearly using instrument Internal contamination thing is managed, spraying repairing is carried out using butyl rubber water-repellent paint after the completion of cleaning;
3)Connection detail is cleared up:Hollowing at detail treatment and damage location are scratched and clear up internal contamination thing, cleaning is completed Afterwards spraying repairing is carried out using butyl rubber water-repellent paint;Wherein, the detail treatment includes seam, negative and positive angle, parapet, day Ditch, eaves gutter, cornice, wall feed-through pipeline, the intersection of depths roof pipeline and roof plan, at roof edge.
3. the energy-saving environment-protecting type waterproof construction method according to claim 2 for having roofing, it is characterised in that step 3)In Coiled material sticking construction is carried out according to from plane to facade order, wherein, setting additional waterproof course, the waterproof are attached at detail treatment The butyl rubber waterproof coating layer for adding layer to be more than or equal to 3.0mm for thickness.
CN201510452845.9A 2015-07-29 2015-07-29 A kind of energy-saving environment-protecting type waterproof construction method for having roofing Active CN105019678B (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201510452845.9A CN105019678B (en) 2015-07-29 2015-07-29 A kind of energy-saving environment-protecting type waterproof construction method for having roofing

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201510452845.9A CN105019678B (en) 2015-07-29 2015-07-29 A kind of energy-saving environment-protecting type waterproof construction method for having roofing

Publications (2)

Publication Number Publication Date
CN105019678A CN105019678A (en) 2015-11-04
CN105019678B true CN105019678B (en) 2018-03-13

Family

ID=54409944

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201510452845.9A Active CN105019678B (en) 2015-07-29 2015-07-29 A kind of energy-saving environment-protecting type waterproof construction method for having roofing

Country Status (1)

Country Link
CN (1) CN105019678B (en)

Citations (4)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN102312582A (en) * 2011-07-12 2012-01-11 江苏天誉建材检验有限公司 Construction method for applying polyurea to old flexible waterproof roof for renovation transformation
CN104251042A (en) * 2013-06-27 2014-12-31 张玲玲 Roof waterproof construction method
CN104328767A (en) * 2014-10-25 2015-02-04 重庆市旭星化工有限公司 Seepage-proofing coating construction method
CN105672664A (en) * 2015-10-28 2016-06-15 张领然 Integral heat insulation wallboard building system

Family Cites Families (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
EP1144773B1 (en) * 1999-05-26 2006-09-13 Basf Corporation Metal roofing shingle stock and method for making it

Patent Citations (4)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN102312582A (en) * 2011-07-12 2012-01-11 江苏天誉建材检验有限公司 Construction method for applying polyurea to old flexible waterproof roof for renovation transformation
CN104251042A (en) * 2013-06-27 2014-12-31 张玲玲 Roof waterproof construction method
CN104328767A (en) * 2014-10-25 2015-02-04 重庆市旭星化工有限公司 Seepage-proofing coating construction method
CN105672664A (en) * 2015-10-28 2016-06-15 张领然 Integral heat insulation wallboard building system

Non-Patent Citations (3)

* Cited by examiner, † Cited by third party
Title
喷涂硬泡聚氨酯在屋面防水工程中的应用;王亮;《施工技术》;20020218;第39卷(第2期);正文第86页第2段至第88页倒数第1段 *
屋面卷材防水层施工工艺标准;guhx1970;《百度文库》;20120224;正文第1-11页 *
浅谈屋面防水工程的设计与施工;余洪;《房材与应用》;20050822;第33卷(第182期);正文第21页第1段至第23页倒数第1段 *

Also Published As

Publication number Publication date
CN105019678A (en) 2015-11-04

Similar Documents

Publication Publication Date Title
CN101914927B (en) Waterproof system for basement bottom plate and wall surface and construction method thereof
CN106436777B (en) A kind of subway station skin-type waterproof construction and its construction method
CN108755983B (en) Waterproof process
CN104763111B (en) A kind of construction technology of waterproof and insulation integrated system
CN105604198B (en) A kind of construction method of rigid flexible system waterproof
CN201695411U (en) Waterproof system for basement bottom plate and wall surface
CN113047459A (en) Construction process for laying HDPE (high-density polyethylene) high-molecular self-adhesive film waterproof coiled material
CN109372026A (en) A kind of the combination waterproof layer structure and its construction method of greenbelt underground engineering top plate
CN111535368A (en) Basement waterproof construction process
CN106193485A (en) A kind of building wall exempts from cracking resistance technique of plastering
CN105133855A (en) Energy-saving and environment-friendly waterproof warming construction method for existing roof surface
CN111441391A (en) CBF reaction bonding macromolecule waterproof coiled material construction method
CN105089213A (en) Water-proof construction method with advantages of energy conservation and environment protection for conventional roof
CN106351256A (en) Pipe rack bottom waterproof construction method
CN106121061A (en) The waterproof construction of outer wall of basement and construction method thereof
CN205976015U (en) Waterproof construction of basement outer wall
CN105019678B (en) A kind of energy-saving environment-protecting type waterproof construction method for having roofing
CN109723475B (en) Waterproof single-layer lining spraying waterproof construction process for hard rock tunnel and application of waterproof single-layer lining spraying waterproof construction process
CN105178518A (en) Energy-saving environment-friendly waterproof heat-insulating construction method for existing roof
CN107299728A (en) A kind of construction method of waterproof and insulation integrated plate
CN115012590B (en) Positive roof construction method
CN105089215A (en) Energy-conservation and environment-protection waterproof construction method for existing roof
CN105133797A (en) Energy-saving and environment-friendly waterproof warming construction method for existing roof surface
CN207863199U (en) A kind of waterproof and insulation integrated plate
CN105019676A (en) Energy-saving and environment-friendly type waterproof construction method of existing roof

Legal Events

Date Code Title Description
C06 Publication
PB01 Publication
C10 Entry into substantive examination
SE01 Entry into force of request for substantive examination
GR01 Patent grant
GR01 Patent grant
CP01 Change in the name or title of a patent holder

Address after: 101100 Beijing city town Huoxian Tau Village in southern Tongzhou District

Patentee after: Zoomlion Tiansheng Building Materials Group Co.,Ltd.

Address before: 101100 Beijing city town Huoxian Tau Village in southern Tongzhou District

Patentee before: BEIJING ZHONGLIAN TIANSHENG BUILDING MATERIALS Co.,Ltd.

CP01 Change in the name or title of a patent holder
TR01 Transfer of patent right

Effective date of registration: 20200421

Address after: 221000 Qianlou Village, Huangji Town, Tongshan District, Xuzhou City, Jiangsu Province, Team 121

Patentee after: Chen Huanhuan

Address before: 101100 Beijing city town Huoxian Tau Village in southern Tongzhou District

Patentee before: Zoomlion Tiansheng Building Materials Group Co.,Ltd.

TR01 Transfer of patent right
TR01 Transfer of patent right

Effective date of registration: 20200519

Address after: Room 17b-1208, xingguangyao Plaza, 128 Gongnong Road, Chongchuan District, Nantong City, Jiangsu Province

Patentee after: Nantong Shuimu Qinghua decoration design Engineering Co.,Ltd.

Address before: 221000 Qianlou Village, Huangji Town, Tongshan District, Xuzhou City, Jiangsu Province, Team 121

Patentee before: Chen Huanhuan

TR01 Transfer of patent right