CN105178344B - The construction method of the built-in anti-float anchor rod plugging structure of sole plate precipitation of deep well - Google Patents
The construction method of the built-in anti-float anchor rod plugging structure of sole plate precipitation of deep well Download PDFInfo
- Publication number
- CN105178344B CN105178344B CN201510323347.4A CN201510323347A CN105178344B CN 105178344 B CN105178344 B CN 105178344B CN 201510323347 A CN201510323347 A CN 201510323347A CN 105178344 B CN105178344 B CN 105178344B
- Authority
- CN
- China
- Prior art keywords
- steel
- anchor
- steel plate
- floating
- concrete
- Prior art date
- Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
- Expired - Fee Related
Links
Landscapes
- Piles And Underground Anchors (AREA)
- Foundations (AREA)
Abstract
本发明涉及一种基础底板中深井降水井内置抗浮锚杆封堵结构,降水井口设置钢套管,降水井底部通过扩孔形成扩体水泥土端,井内设置囊式抗浮锚杆,锚杆囊袋内设置扩展端板,囊式抗浮锚杆上设有环形定位钢筋,锚杆囊袋插入扩体水泥土后通过高压注浆形成压浆扩体抗浮端,锚杆上端穿过封堵钢板后锚固;封堵钢板顶面焊接连接钢筋,底面设置防水橡胶垫圈,封堵钢板与钢套管连接钢板通过螺栓连接,封堵钢板顶面依次为防水混凝土层及后浇混凝土封闭体。本发明采用内置抗浮锚杆的方式能在保障井口封堵质量的同时减少后期由于地下水上浮给降水井口带来的破坏,具有较好的经济技术效益。
The invention relates to a built-in anti-floating anchor plugging structure in a deep well dewatering well on a foundation floor, a steel casing is arranged at the head of the dewatering well, an expanded cement soil end is formed at the bottom of the dewatering well through reaming, and a capsule type anti-floating anchor is arranged in the well. The expansion end plate is set in the rod bag, and the ring-shaped positioning steel bar is arranged on the bag type anti-floating anchor rod. Anchor after sealing the steel plate; the top surface of the sealing steel plate is welded to connect the steel bars, and the bottom surface is provided with a waterproof rubber gasket, the sealing steel plate and the steel casing are connected by bolts, and the top surface of the sealing steel plate is followed by a waterproof concrete layer and a post-cast concrete closure . The invention adopts the method of built-in anti-floating anchor rod, which can reduce the damage to the dewatering wellhead due to the floating of groundwater in the later stage while ensuring the plugging quality of the wellhead, and has good economic and technical benefits.
Description
技术领域technical field
本发明涉及一种基础底板中深井降水井内置抗浮锚杆封堵结构及施工方法。属于地基处理领域,适用于建筑物地基降水井封堵处理工程。The invention relates to a built-in anti-floating bolt plugging structure and construction method of a deep well dewatering well on a foundation floor. The utility model belongs to the field of foundation treatment and is suitable for the plugging and treatment project of the dewatering well of the building foundation.
背景技术Background technique
随着城市地上开发空间限制,地下空间利用率逐年升高且不断深入,因此大量建筑施工时会开挖深基坑,而深基坑施工中经常会遇到在地下室永久结构底板内设置降水井的情形。多数情况下,为满足施工现场要求,降水井需要在底板施工完成后才能进行封堵,因此降水井穿过垫层就成为必然,与此同时基础底板防水要求又高,降水井部位的封堵必然成为施工中的一个重要问题。With the limitation of above-ground development space in cities, the utilization rate of underground space is increasing year by year and deepening. Therefore, deep foundation pits will be excavated during a large number of building constructions. In the construction of deep foundation pits, it is often encountered that dewatering wells are set in the basement of the permanent structure floor. situation. In most cases, in order to meet the requirements of the construction site, the dewatering well needs to be sealed after the construction of the bottom plate is completed. Therefore, it is inevitable for the dewatering well to pass through the cushion layer. It must become an important issue in construction.
目前传统施工方法是待降水井内地下水抽干后马上回填碎石混凝土等至基础垫层标高,同时采用比基础混凝土高一轻强度等级的膨胀混凝土浇筑至基础顶面,施工方法不足之处在于会在降水井口部位产生施工缝,带来漏水隐患,且无法修补;或采用钢管将降水井接长,穿过基础底板,钢管外侧焊接止水翼板,待施工完毕后在钢管内侧采用钢板焊接封堵,施工方法不足之处在于封堵焊接时间较长,对于出水量大的降水井封堵难度大。At present, the traditional construction method is to backfill gravel concrete to the foundation cushion level immediately after the groundwater in the dewatering well is drained, and at the same time use expansive concrete with a light strength grade higher than the foundation concrete to pour to the top surface of the foundation. The disadvantage of the construction method is that it will Construction joints occur at the head of the dewatering well, which brings hidden dangers of water leakage and cannot be repaired; or use steel pipes to extend the dewatering well, pass through the foundation floor, and weld the water-stop flange on the outside of the steel pipe. The disadvantage of the construction method is that the plugging and welding time is long, and it is difficult to plug the precipitation well with a large water output.
进一步的,为了提高降水井封堵施工的工程质量,已有多种新型降水井封堵技术,例如一种降水井封堵系统(ZL:201120242057.4),其采用钢管将降水井接长,穿过基础底板,钢管外侧焊接止水翼缘的同时在钢管内加焊丝扣承接件,封堵时直接采用丝扣堵板封堵,虽有较快的封堵速度,但钢管与降水井的连接强度不足,在建筑发生不均匀沉降时易产生裂缝,且钢质丝扣易腐蚀,耐久性较差;又如一种深基坑降水井封堵结构(ZL:201320158546.0),其将钢管伸入降水井内,采用固定物固定及法兰盘封口,同时设置防水层及防水卷材,虽与基础底板之间具有较高的密封性,但在地下水位较高、上浮力过大时会造成整体封堵结构抬动等质量隐患。此外,在降水井的封堵施工中,常用到一些辅助的用于封堵施工的封堵装置,但存在结构复杂、成本较高、适用范围窄等缺陷。Furthermore, in order to improve the engineering quality of the dewatering well plugging construction, there are many new types of dewatering well plugging technologies, such as a dewatering well plugging system (ZL: 201120242057.4), which uses steel pipes to extend the dewatering well and pass through For the foundation floor, the outer side of the steel pipe is welded with the water-stop flange, and at the same time, welding threaded fasteners are added to the steel pipe. When sealing, the threaded blocking plate is directly used for sealing. Although the sealing speed is relatively fast, the connection strength between the steel pipe and the dewatering well Insufficient, cracks are easy to occur when the building is unevenly settled, and the steel thread is easy to corrode, and the durability is poor; another example is a deep foundation pit dewatering well sealing structure (ZL: 201320158546.0), which extends the steel pipe into the dewatering well , using fixtures and flange sealing, and setting waterproof layer and waterproof membrane at the same time, although it has high sealing performance with the foundation bottom plate, it will cause overall blockage when the groundwater level is high and the buoyancy is too large Quality risks such as structural lifting. In addition, in the plugging construction of dewatering wells, some auxiliary plugging devices are commonly used for plugging construction, but there are defects such as complex structure, high cost, and narrow application range.
综上所述,已有的降水井封堵结构虽能取得较为理想的封堵效果,但在封堵结构耐久性、施工效率、抗浮性能以及经济效益等方面尚存可改善之处。To sum up, although the existing plugging structures for dewatering wells can achieve relatively ideal plugging effects, there are still room for improvement in terms of the durability of the plugging structure, construction efficiency, anti-floating performance, and economic benefits.
鉴于此,目前亟需发明一种封堵质量可靠、后期抗浮能力高、经济效益优良的深井降水井封堵结构。基础底板中采用深井降水井内置抗浮锚杆封堵结构能大幅提升封堵结构的施工质量以及后期建筑基础的抗浮性能,并具有一定的经济技术效益。In view of this, there is an urgent need to invent a deep well dewatering well plugging structure with reliable plugging quality, high anti-floating ability in the later stage, and excellent economic benefits. The construction quality of the plugging structure and the anti-floating performance of the later building foundation are greatly improved by using the anti-floating bolt plugging structure built in the deep well dewatering well in the foundation floor, and has certain economic and technical benefits.
发明内容Contents of the invention
本发明的目的在于提供一种施工效率高、封堵质量好、抗浮性能强的深井降水井内置抗浮锚杆封堵结构及施工工法。The purpose of the present invention is to provide a deep well dewatering well built-in anti-floating bolt plugging structure and construction method with high construction efficiency, good plugging quality and strong anti-floating performance.
为实现上述技术目的,本发明采用了以下技术方案:For realizing above-mentioned technical purpose, the present invention adopts following technical scheme:
一种基础底板中深井降水井内置抗浮锚杆封堵结构,其特征在于降水井口设置钢套管,降水井底部通过扩孔形成扩体水泥土端,井内设置囊式抗浮锚杆,锚杆囊袋内设置扩展端板,囊式抗浮锚杆上设有环形定位钢筋,锚杆囊袋插入扩体水泥土后通过高压注浆形成压浆扩体抗浮端,锚杆上端穿过封堵钢板后锚固;封堵钢板顶面焊接连接钢筋,底面设置防水橡胶垫圈,封堵钢板与钢套管连接钢板通过螺栓连接,封堵钢板顶面依次为防水混凝土层及后浇混凝土封闭体。A built-in anti-floating bolt plugging structure in the deep well dewatering well on the foundation floor, which is characterized in that a steel casing is arranged at the head of the dewatering well, the bottom of the dewatering well is expanded to form an expanded cement soil end through reaming, and a capsule type anti-floating anchor is arranged in the well. The expansion end plate is set in the rod bag, and the ring-shaped positioning steel bar is arranged on the bag type anti-floating anchor rod. Anchor after sealing the steel plate; the top surface of the sealing steel plate is welded to connect the steel bars, and the bottom surface is provided with a waterproof rubber gasket, the sealing steel plate and the steel casing are connected by bolts, and the top surface of the sealing steel plate is followed by a waterproof concrete layer and a post-cast concrete closure .
所述的钢套管上口设置环形连接钢板,连接钢板上预留螺栓孔;钢套管外壁设有两层环形防水钢板,防水钢板分别嵌于基础垫层及基础底板中。The upper opening of the steel sleeve is provided with an annular connecting steel plate, and bolt holes are reserved on the connecting steel plate; the outer wall of the steel sleeve is provided with two layers of annular waterproof steel plates, and the waterproof steel plates are respectively embedded in the foundation cushion and the foundation bottom plate.
所述的封堵钢板为直径与钢套管连接钢板外径相等的圆钢板,顶面均匀且垂直焊接连接钢筋,中心预留锚杆孔,边缘预留螺栓孔,螺栓孔位与钢套管连接钢板上的螺栓孔相对应。The plugging steel plate is a round steel plate with a diameter equal to the outer diameter of the steel casing connecting steel plate, the top surface is even and vertically welded to the connecting steel bars, the anchor rod hole is reserved in the center, and the bolt hole is reserved at the edge, and the bolt hole position is consistent with the steel casing Corresponds to the bolt holes on the connecting steel plate.
所述的囊式抗浮锚杆为中空钢管,杆身等间距设置环形定位钢筋,定位钢筋直径与降水井内径相等,囊袋内杆体均匀设有注浆孔。The bladder type anti-floating anchor rod is a hollow steel pipe, the rod body is equidistantly provided with annular positioning steel bars, the diameter of the positioning steel bars is equal to the inner diameter of the dewatering well, and the rod body in the bag is uniformly provided with grouting holes.
所述的扩展端板由两块对称设置的铰接式钢板组成,每块铰接式钢板可上下对称折叠,钢板两端铰接连接有上连接环和下连接环,上连接环与杆体焊接固定,下连接环为可活动式并设置钢丝绳,钢丝绳内置于囊式抗浮锚杆的杆体内。The extended end plate is composed of two symmetrically arranged hinged steel plates, each hinged steel plate can be folded symmetrically up and down, the two ends of the steel plate are hingedly connected with an upper connecting ring and a lower connecting ring, the upper connecting ring is welded and fixed to the rod body, the lower The connecting ring is movable and a steel wire rope is set, and the steel wire rope is built in the rod body of the bladder type anti-floating anchor rod.
所述的锚杆囊袋采用不透水耐磨材料制成,锚杆囊袋两端采用钢环与锚杆连接,钢环通过限位板固定,限位板与锚杆焊接连接。The anchor bag is made of impermeable and wear-resistant material, the two ends of the anchor bag are connected with the anchor rod by steel rings, the steel ring is fixed by a limit plate, and the limit plate is welded with the anchor rod.
本发明还提供了所述深井降水井内置抗浮锚杆封堵结构的施工方法,其主要施工步骤如下:The present invention also provides a construction method for the built-in anti-floating bolt plugging structure of the deep well dewatering well, the main construction steps of which are as follows:
1)施工前准备:根据设计图纸,处理施工现场,绘制施工轮廓线,制作钢套管及相关钢构件,施工材料、机械、人员就位;1) Pre-construction preparation: according to the design drawings, process the construction site, draw the construction outline, make steel casings and related steel components, and put construction materials, machinery and personnel in place;
2)临时固定套管位置:在降水井口埋设钢套管,居中对位,并采用钢筋作为支撑架,临时固定钢套管;2) Temporarily fix the position of the casing: bury the steel casing at the head of the dewatering well, align it in the center, and use steel bars as the support frame to temporarily fix the steel casing;
3)浇筑垫层混凝土:按照施工要求浇筑混凝土基础垫层,基础垫层厚度应完全覆盖钢套管外壁下层环形防水钢板,基础垫层浇完后,及时进行木模支撑并对钢套管上口覆盖保护;3) Pouring cushion concrete: according to the construction requirements, pour the concrete foundation cushion. The thickness of the foundation cushion should completely cover the lower ring-shaped waterproof steel plate on the outer wall of the steel casing. mouth covering protection;
4)浇筑套管外侧底板混凝土:按设计要求浇筑混凝土基础底板,基础底板下口与钢套管连接钢板相平或稍低;4) Concrete pouring of the outer bottom plate of the casing: pour the concrete foundation bottom plate according to the design requirements, and the lower opening of the foundation bottom plate is equal to or slightly lower than the steel casing connecting steel plate;
5)取出水泵、降水井底扩孔:底板混凝土养护完成后取出水泵,采用机械扩孔机具旋喷扩孔,形成压浆扩体抗浮端;5) Taking out the water pump and reaming at the bottom of the dewatering well: After the floor concrete is cured, take out the water pump, and use mechanical reaming equipment to expand the holes by rotary spraying to form the anti-floating end of the grout expansion body;
6)安放囊式抗浮锚杆:将囊式抗浮锚杆缓慢导入降水井中,直至锚杆端达到设计标高,锚杆囊袋体完全插入扩体水泥土中,锚杆顶部采用钢筋架临时固定;6) Place the bladder-type anti-floating anchor: Slowly introduce the bladder-type anti-floating anchor into the dewatering well until the end of the anchor reaches the design elevation, the anchor bladder is completely inserted into the expanded cement soil, and the top of the anchor is temporarily reinforced fixed;
7)锚杆囊袋注浆、打开扩展端板:根据设计压力与注浆量,压灌水泥砂浆,使锚杆囊袋膨胀成设计形态与大小,待压浆扩体抗浮端达到一定强度后,提拉钢丝绳打开扩展端板;7) Grouting of the anchor bag and opening the expansion end plate: According to the design pressure and grouting volume, press and pour cement mortar to expand the anchor bag to the designed shape and size, and wait until the grouting expansion body anti-floating end reaches a certain strength Finally, pull the wire rope to open the extended end plate;
8)降水井回填细石混凝土:注浆完成后采用砂浆及细石混凝土填满降水井;8) Backfill fine stone concrete in the dewatering well: fill the dewatering well with mortar and fine stone concrete after grouting;
9)安装封堵钢板:拆除抗浮锚杆临时固定装置,采用螺栓及螺帽分别将封堵钢板与钢套管连接钢板、抗浮锚杆与封堵钢板锚固;9) Install the blocking steel plate: remove the temporary fixing device of the anti-floating anchor rod, and use bolts and nuts to respectively anchor the sealing steel plate and the steel casing connecting steel plate, the anti-floating anchor rod and the blocking steel plate;
10)浇筑盖板上部混凝土:当上述封堵施工全部完成后,在封堵钢板上先浇筑一层防水混凝土,防水混凝土层完全覆盖竖向连接钢筋,再浇筑膨胀混凝土,填塞密实,初凝后蓄水养护。10) Pouring concrete on the top of the cover plate: After the above-mentioned sealing construction is completed, a layer of waterproof concrete is first poured on the sealing steel plate. Water conservation.
本发明具有以下的特点和有益效果:The present invention has following characteristics and beneficial effect:
(1)降水井口的钢套管外壁设置两层环形止水钢板,依次嵌于基础垫层及基础底板中,增加钢套管稳定性的同时有效延长地下水的渗水路径,提高封堵结构的防水效果。(1) The outer wall of the steel casing of the dewatering wellhead is provided with two layers of annular water-stop steel plates, which are embedded in the foundation cushion and the foundation floor in turn to increase the stability of the steel casing while effectively extending the seepage path of groundwater and improving the waterproofing of the sealing structure Effect.
(2)降水井口的钢套管顶部安装带有防水橡胶垫圈的封堵钢板,封堵钢板上设置连接钢筋,并依次浇筑防水混凝土及混凝土封闭体,切断地下水的渗水路径,同时操作简便,施工成本低,防水效果好。(2) A sealing steel plate with a waterproof rubber gasket is installed on the top of the steel casing of the dewatering wellhead. Connecting steel bars are set on the sealing steel plate, and waterproof concrete and concrete closures are poured in sequence to cut off the seepage path of groundwater. At the same time, the operation is simple and the construction Low cost and good waterproof effect.
(3)降水井底部通过机具进行扩孔,并设置囊式抗浮锚杆,通过锚杆作为注浆管进行高压注浆形成压浆扩体抗浮端,且囊袋内的锚杆上设置有扩展端板,可有效提高基础在降水井封堵后的抗浮性能,保证工后封堵结构的质量。(3) The bottom of the dewatering well is reamed by means of tools, and a bladder anti-floating anchor is installed. The anchor is used as a grouting pipe for high-pressure grouting to form a grouting expansion anti-floating end, and the anchor in the bladder is set There are extended end plates, which can effectively improve the anti-floating performance of the foundation after the dewatering well is blocked, and ensure the quality of the plugged structure after construction.
附图说明Description of drawings
图1是本发明基础底板中深井降水井内置抗浮锚杆封堵结构示意图;Fig. 1 is a schematic diagram of the built-in anti-floating bolt plugging structure of the deep well dewatering well in the foundation floor of the present invention;
图2是本发明中钢套管与封堵钢板连接示意图;Fig. 2 is a schematic diagram of the connection between the steel casing and the plugging steel plate in the present invention;
图3是本发明中囊式抗浮锚杆中囊袋、扩展端板与杆体连接示意图。Fig. 3 is a schematic diagram of the connection between the capsule bag, the expanded end plate and the rod body of the capsule type anti-floating anchor rod of the present invention.
图中:1-基础底板,2-基础垫层,3-后浇混凝土封闭体,4-螺栓,5-防水混凝土层,6-连接钢筋,7-封堵钢板,8-防水橡胶垫圈,9-防水钢板,10-钢套管,11-原降水井,12-抗浮锚杆,13-环形定位钢筋,14-扩展端板,15-后注浆水泥土承载抗浮体,16-压浆扩体抗浮端,17-锚杆囊袋,18-扩体水泥土,19-螺帽,20-防水垫片,21-钢环,22-限位钢板,23-上连接环,24-下连接环,25-钢丝绳。In the figure: 1-foundation floor, 2-foundation cushion, 3-post-cast concrete closure, 4-bolt, 5-waterproof concrete layer, 6-connecting steel bar, 7-blocking steel plate, 8-waterproof rubber gasket, 9 -Waterproof steel plate, 10-Steel casing, 11-Original dewatering well, 12-Anti-floating anchor rod, 13-Annular positioning steel bar, 14-Extended end plate, 15-Post-grouting cement-soil bearing anti-floating body, 16-Grouting Expanded anti-floating end, 17-bolt pocket, 18-expanded cement soil, 19-nut, 20-waterproof gasket, 21-steel ring, 22-limiting steel plate, 23-upper connecting ring, 24- Lower connecting ring, 25-steel wire rope.
具体实施方式detailed description
本实施方式中基础底板及垫层的施工技术要求,焊接施工技术要求,囊袋高压注浆配比等不再赘述,重点阐述本发明的涉及的深井降水井内置抗浮锚杆封堵结构施工的实施方式。In this embodiment, the technical requirements for the construction of the base plate and the cushion, the technical requirements for welding construction, the ratio of the high-pressure grouting of the bladder, etc. will not be described in detail, and the construction of the anti-floating anchor plugging structure built in the deep well dewatering well involved in the present invention will be focused on implementation.
图1是本发明基础底板中深井降水井内置抗浮锚杆封堵结构示意图,图2是本发明中钢套管与封堵钢板连接示意图,图3是本发明中囊式抗浮锚杆中囊袋与杆体连接示意图。参照图1所示的深井降水井内置抗浮锚杆封堵结构,主要由钢套管10、封堵钢板7、抗浮锚杆12、囊袋17等组成,实施例以D=500mm的原降水井11为例进行说明:Fig. 1 is a schematic diagram of the built-in anti-floating bolt plugging structure of the deep well dewatering well in the foundation floor of the present invention; Fig. 2 is a schematic diagram of the connection between the medium steel casing and the plugging steel plate of the present invention; Schematic diagram of the connection between the pouch and the rod. Referring to Figure 1, the built-in anti-floating anchor plugging structure of the deep well dewatering well is mainly composed of steel casing 10, plugging steel plate 7, anti-floating anchor 12, and bag 17. The precipitation well 11 is taken as an example for illustration:
钢套管10采用直径500mm,长600mm,厚5mm的无缝钢管或螺旋焊接钢管,上口连接钢板宽度为60mm,在距钢套管10顶部连接钢板60mm左右、240mm左右的外壁水平焊接两块厚4mm、宽100mm的环形防水钢板9,连接钢板表面距边缘20mm处预留直径为8mm的螺栓孔。在原降水井11上口居中对位,竖直埋设钢套管10,埋入深度为250mm左右,并采用钢筋作为支撑架,临时固定住钢套管10。The steel casing 10 is made of a seamless steel pipe or a spiral welded steel pipe with a diameter of 500mm, a length of 600mm, and a thickness of 5mm. The annular waterproof steel plate 9 with a thickness of 4mm and a width of 100mm, a bolt hole with a diameter of 8mm is reserved at the place where the connecting steel plate surface is 20mm away from the edge. At the center of the upper mouth of the original dewatering well 11, a steel casing 10 is vertically buried with a depth of about 250 mm, and steel bars are used as a support frame to temporarily fix the steel casing 10.
钢套管10临时固定后按照施工要求采用C15混凝土浇筑厚100mm的基础垫层2,基础垫层2上面采用C30混凝土浇筑厚350mm~400mm的基础底板1,浇筑底板1前在钢套管10周围吊模留设800mm×800mm×300mm的方洞,钢套管10顶部的标高距基础底板1标高不小于100mm,以保证封堵钢板7的螺栓施工方便。After the steel casing 10 is temporarily fixed, according to the construction requirements, use C15 concrete to pour a foundation cushion 2 with a thickness of 100mm. On the foundation cushion 2, use C30 concrete to pour a foundation floor 1 with a thickness of 350mm~400mm. A square hole of 800 mm × 800 mm × 300 mm is left in the hanging form, and the elevation of the top of the steel casing 10 is not less than 100 mm from the elevation of the base plate 1, so as to ensure the convenient construction of the bolts for sealing the steel plate 7.
基础底板1混凝土养护完成后取出水泵,采用机械扩孔机具旋喷扩孔,形成直径1200mm左右扩体水泥土18,然后将内径25mm、壁厚6mm的囊式抗浮锚杆12缓慢导入降水井中,直至抗浮锚杆12下端达到设计标高,囊袋17完全插入扩体水泥土18中,并将抗浮锚杆12顶部采用钢筋架临时固定。其中囊袋17采用聚酯长纤维复合材料制作,通过钢环21与抗浮锚杆12连接,钢环21由焊接在锚杆表面的限位钢板22固定。After the foundation floor 1 concrete curing is completed, the water pump is taken out, and the holes are expanded by rotary spraying with a mechanical reaming machine to form an expanded cement soil 18 with a diameter of about 1200mm, and then the bladder-type anti-floating anchor rod 12 with an inner diameter of 25mm and a wall thickness of 6mm is slowly introduced into the dewatering well Until the lower end of the anti-floating anchor 12 reaches the design elevation, the bladder 17 is fully inserted into the expanded cement soil 18, and the top of the anti-floating anchor 12 is temporarily fixed with a steel frame. Wherein the bladder 17 is made of polyester long fiber composite material, and is connected with the anti-floating anchor rod 12 through a steel ring 21, and the steel ring 21 is fixed by a limiting steel plate 22 welded on the surface of the anchor rod.
根据设计压力与注浆量,压灌水泥砂浆,使囊袋17膨胀成直径800mm左右的压浆扩体抗浮端16,待囊袋17内的水泥砂浆达到一定强度后,提拉钢丝绳25打开扩展端板14,其中扩展端板14的单块铰接式钢板由两块规格为600mm×400mm的小钢板铰接而成。According to the design pressure and the amount of grouting, pressurize the cement mortar to expand the bladder 17 into a grouting expanded anti-floating end 16 with a diameter of about 800mm. After the cement mortar in the bladder 17 reaches a certain strength, pull the steel wire rope 25 to open it. The extended end plate 14, wherein the single hinged steel plate of the extended end plate 14 is hinged by two small steel plates with a specification of 600mm×400mm.
注浆完成后采用水泥砂浆回填原降水井11,形成后注浆水泥土承载抗浮体15,回填至基础垫层2标高以下300mm时,改换C30混凝土浇筑,浇筑至钢套管10顶部以下50mm左右,完成后拆除抗浮锚杆12的临时固定装置,采用螺栓4及防水橡胶垫圈8将封堵钢板与钢套管连接钢板锚固,采用螺帽19将抗浮锚杆12与封堵钢板7锚固,螺帽19锚固前安装防水垫片20。其中封堵钢板7中心预留直径25mm的锚杆孔,四周预留与钢套管10相对应的直径8mm螺栓孔,顶面均匀且垂直焊接长80mm的螺纹连接钢筋6。After the grouting is completed, use cement mortar to backfill the original dewatering well 11 to form the post-grouting cement-soil bearing anti-floating body 15. When backfilling to 300mm below the level of the foundation cushion 2, replace C30 concrete pouring, pouring to about 50mm below the top of the steel casing 10 After the completion, the temporary fixing device of the anti-floating anchor 12 is removed, and the bolt 4 and the waterproof rubber washer 8 are used to anchor the sealing steel plate and the steel casing connecting steel plate, and the anti-floating anchor 12 is anchored to the sealing steel plate 7 by using the nut 19 , Install the waterproof gasket 20 before the nut 19 is anchored. A bolt hole with a diameter of 25mm is reserved in the center of the plugging steel plate 7, bolt holes with a diameter of 8mm corresponding to the steel casing 10 are reserved around, and the top surface is uniform and vertically welded with a threaded steel bar 6 with a length of 80mm.
当上述封堵施工全部完成后,在封堵钢板上先浇筑一层厚100mm的防水混凝土层5,再采用膨胀混凝土进行二次浇筑形成后浇混凝土封闭体3,最后上方覆盖湿麻袋或草袋,进行不少于14天的湿养护。After the above-mentioned sealing construction is completed, a waterproof concrete layer 5 with a thickness of 100mm is first poured on the sealing steel plate, and then the expanded concrete is used for secondary pouring to form a post-cast concrete closure 3, and finally the top is covered with wet sacks or straw bags , for no less than 14 days of wet curing.
深井降水井内置抗浮锚杆封堵结构的施工主要步骤如下:The main construction steps of the anti-floating bolt plugging structure built in the deep well dewatering well are as follows:
1)施工前准备:根据设计图纸,处理施工现场,绘制施工轮廓线,制作钢套管10及相关钢构件,施工材料、机械、人员就位;1) Preparation before construction: According to the design drawings, process the construction site, draw the construction outline, make steel casing 10 and related steel components, and place construction materials, machinery and personnel in place;
2)临时固定钢套管位置:在降水井口埋设钢套管10,居中对位,并采用钢筋作为支撑架,临时固定钢套管10;2) Temporarily fix the position of the steel casing: bury the steel casing 10 at the head of the dewatering well, align it in the center, and use steel bars as a support frame to temporarily fix the steel casing 10;
3)浇筑垫层混凝土:按照施工要求浇筑混凝土基础垫层2,基础垫层2厚度应完全覆盖钢套管10外壁下层环形防水钢板9,基础垫层2浇完后,及时进行木模支撑并对钢套管10上口覆盖保护;3) Pouring cushion concrete: pour concrete foundation cushion 2 according to the construction requirements. The thickness of the foundation cushion 2 should completely cover the outer wall of the steel casing 10 and the lower circular waterproof steel plate 9. Covering and protecting the upper opening of the steel casing 10;
4)浇筑套管外侧底板混凝土:按设计要求浇筑混凝土基础底板1,基础底板1下口与钢套管10连接钢板相平或稍低一些,允许偏差±10mm;4) Concrete pouring for the outer bottom plate of casing: pour concrete foundation bottom plate 1 according to the design requirements, the lower opening of foundation bottom plate 1 is equal to or slightly lower than the connecting steel plate of steel casing pipe 10, and the allowable deviation is ±10mm;
5)取出水泵、降水井底扩孔:基础底板1混凝土养护完成后取出水泵,采用机械扩孔机具旋喷扩孔,形成压浆扩体抗浮端16;5) Taking out the water pump and reaming at the bottom of the dewatering well: After the concrete curing of the foundation floor 1 is completed, take out the water pump, and use mechanical reaming equipment to expand the holes by rotary spraying to form the anti-floating end 16 of the grouting expansion body;
6)安放囊式抗浮锚杆:将囊式抗浮锚杆12缓慢导入原降水井11中,直至抗浮锚杆12端达到设计标高,锚杆囊袋17完全插入扩体水泥土18中,抗浮锚杆12顶部采用钢筋架临时固定;6) Place the bladder-type anti-floating anchor: Slowly introduce the bladder-type anti-floating anchor 12 into the original dewatering well 11 until the end of the anti-floating anchor 12 reaches the design elevation, and the anchor bag 17 is completely inserted into the expanded cement soil 18 , the top of the anti-floating anchor rod 12 is temporarily fixed with a reinforcement frame;
7)锚杆囊袋注浆、打开扩展端板:根据设计压力与注浆量,压灌水泥砂浆,使锚杆囊袋17膨胀成设计形态与大小,待压浆扩体抗浮16端达到一定强度后,提拉钢丝绳25打开扩展端板14;7) Grouting of the anchor bag and opening of the extended end plate: according to the design pressure and grouting volume, the cement mortar is press-filled to expand the anchor bag 17 to the designed shape and size. After a certain strength, pull the wire rope 25 to open the extended end plate 14;
8)降水井回填细石混凝土:注浆完成后采用水泥砂浆及细石混凝土填满原降水井11;8) Backfill fine stone concrete in the dewatering well: after the grouting is completed, fill the original dewatering well 11 with cement mortar and fine stone concrete;
9)安装封堵钢板:拆除抗浮锚杆12临时固定装置,采用螺栓4及螺帽19分别将封堵钢板7与钢套管10连接钢板、抗浮锚杆12与封堵钢板7锚固;9) Install the blocking steel plate: remove the temporary fixing device of the anti-floating anchor rod 12, and use bolts 4 and nuts 19 to respectively anchor the sealing steel plate 7 and the steel casing 10 connecting steel plate, the anti-floating anchor rod 12 and the blocking steel plate 7;
10)浇筑盖板上部混凝土:当上述封堵施工全部完成后,在封堵钢板7上先浇筑一层防水混凝土,防水混凝土层5完全覆盖竖向连接钢筋6,再浇筑膨胀混凝土,填塞密实,初凝后蓄水养护。10) Pouring concrete on the upper part of the cover plate: After the above-mentioned sealing construction is completed, a layer of waterproof concrete is first poured on the sealing steel plate 7, and the waterproof concrete layer 5 completely covers the vertical connecting steel bars 6, and then pours expansive concrete to fill it tightly. Water storage and maintenance after initial setting.
Claims (1)
Priority Applications (1)
| Application Number | Priority Date | Filing Date | Title |
|---|---|---|---|
| CN201510323347.4A CN105178344B (en) | 2015-06-12 | 2015-06-12 | The construction method of the built-in anti-float anchor rod plugging structure of sole plate precipitation of deep well |
Applications Claiming Priority (1)
| Application Number | Priority Date | Filing Date | Title |
|---|---|---|---|
| CN201510323347.4A CN105178344B (en) | 2015-06-12 | 2015-06-12 | The construction method of the built-in anti-float anchor rod plugging structure of sole plate precipitation of deep well |
Publications (2)
| Publication Number | Publication Date |
|---|---|
| CN105178344A CN105178344A (en) | 2015-12-23 |
| CN105178344B true CN105178344B (en) | 2017-06-20 |
Family
ID=54900733
Family Applications (1)
| Application Number | Title | Priority Date | Filing Date |
|---|---|---|---|
| CN201510323347.4A Expired - Fee Related CN105178344B (en) | 2015-06-12 | 2015-06-12 | The construction method of the built-in anti-float anchor rod plugging structure of sole plate precipitation of deep well |
Country Status (1)
| Country | Link |
|---|---|
| CN (1) | CN105178344B (en) |
Families Citing this family (22)
| Publication number | Priority date | Publication date | Assignee | Title |
|---|---|---|---|---|
| CN106087992B (en) * | 2016-06-30 | 2017-11-07 | 青岛蓝天创先科技服务有限公司 | Will not collapse hole water jetting at high pressure drilling and reaming anchor pile |
| CN106761533B (en) * | 2017-01-16 | 2023-05-05 | 上海摩帝尔金属结构科技有限公司 | Composite integrated plugging device and method |
| CN106958243B (en) * | 2017-04-28 | 2019-04-02 | 河海大学 | Anchor formula anti-float anchor rod and its construction method after a kind of |
| CN107268646B (en) * | 2017-08-04 | 2023-03-21 | 北京建工土木工程有限公司 | High-water-pressure-drop well sealing device and construction method thereof |
| CN109339042A (en) * | 2018-11-20 | 2019-02-15 | 曾庆义 | A cage core bladder bag for anchor rod and bladder anchor rod |
| CN109440832A (en) * | 2018-11-27 | 2019-03-08 | 福建卓越建设工程开发有限公司 | Anchor cable can be recycled pressure dispersing type pouch and expand body anti-floating pile and construction method |
| CN110005377B (en) * | 2019-04-02 | 2021-04-06 | 中国地质科学院勘探技术研究所 | Method for building vertical well bottom chamber |
| CN110185030A (en) * | 2019-05-13 | 2019-08-30 | 深圳钜联锚杆技术有限公司 | A kind of cage core assembly, pouch component, bag type paste anchor pole and its assemble method |
| CN110453707B (en) * | 2019-08-18 | 2021-03-23 | 杨树东 | Self-sealing waterproof structure of high-pressure dewatering well and construction method of self-sealing waterproof structure |
| CN110925018B (en) * | 2019-12-02 | 2021-06-25 | 河南科技大学 | Construction method and precipitation system of pump house in tunnel communication channel |
| CN111663549B (en) * | 2020-06-01 | 2024-10-18 | 广东金辉华集团有限公司 | A basement dewatering well blocking device and anti-blocking method |
| CN112663604A (en) * | 2020-10-19 | 2021-04-16 | 中建八局发展建设有限公司 | Novel bag type expanded anti-pulling anchor rod and construction method thereof |
| CN113106870A (en) * | 2021-03-29 | 2021-07-13 | 泉州市中原盛辉地产代理有限公司 | Construction method of assembled integral hollow slab bridge |
| CN113137273B (en) * | 2021-04-08 | 2022-05-06 | 苏州中车建设工程有限公司 | Large-diameter shield tunnel deformation control structure and construction method thereof |
| CN113585361B (en) * | 2021-09-06 | 2023-04-07 | 青岛理工大学 | Horizontal sliding support, anti-floating anchor rod and construction method |
| CN114032862B (en) * | 2021-11-03 | 2022-12-13 | 中铁二局集团建筑有限公司 | A water surface garbage collection device using water flow traction force |
| CN114411723A (en) * | 2021-12-13 | 2022-04-29 | 江苏积庆源科技有限公司 | Assembled bearing platform, pressure-bearing type bag type uplift anchor rod and anchoring method |
| CN114875906B (en) * | 2022-05-23 | 2023-09-08 | 中国十七冶集团有限公司 | Grouting body-expanding reinforced anchor rod application method |
| CN116220083A (en) * | 2022-09-09 | 2023-06-06 | 中航天建设工程集团有限公司 | Pressure-reducing anti-floating water stop device system |
| CN115369870B (en) * | 2022-09-22 | 2023-08-01 | 中国五冶集团有限公司 | Post-cast anti-floating anchor rod |
| CN115977164B (en) * | 2023-02-07 | 2025-10-03 | 长江勘测规划设计研究有限责任公司 | Method and device for sealing core sampling holes in ground-connected wall joints under high water pressure conditions |
| CN118516986A (en) * | 2024-05-27 | 2024-08-20 | 中建八局浙江建设有限公司 | Anti-floating anchor structure and construction method thereof |
Citations (6)
| Publication number | Priority date | Publication date | Assignee | Title |
|---|---|---|---|---|
| CN201411692Y (en) * | 2009-05-07 | 2010-02-24 | 中国京冶工程技术有限公司 | Multi-corrosion controllable expansion extruded soil bolt |
| CN202323943U (en) * | 2011-12-01 | 2012-07-11 | 湖南科技大学 | Branch-shaped inflatable anti-floating anchor rod of soft-soil foundation region |
| CN202509532U (en) * | 2011-12-22 | 2012-10-31 | 深圳市市政工程总公司 | Multi-rib tension type anti-floating anchor |
| CN202559345U (en) * | 2012-02-23 | 2012-11-28 | 山东同圆设计集团有限公司 | Bottom-expanded pre-stress anti-floating anchor rod |
| CN204080836U (en) * | 2014-09-10 | 2015-01-07 | 中国建筑第六工程局有限公司 | The fast plugging device of dewatering well in a kind of building basement |
| CN204780962U (en) * | 2015-06-12 | 2015-11-18 | 杭州江润科技有限公司 | Built -in anti sea anchor pole block structure of deep well precipitation well in soleplate |
Family Cites Families (1)
| Publication number | Priority date | Publication date | Assignee | Title |
|---|---|---|---|---|
| US7699111B2 (en) * | 2008-01-29 | 2010-04-20 | Tam International, Inc. | Float collar and method |
-
2015
- 2015-06-12 CN CN201510323347.4A patent/CN105178344B/en not_active Expired - Fee Related
Patent Citations (6)
| Publication number | Priority date | Publication date | Assignee | Title |
|---|---|---|---|---|
| CN201411692Y (en) * | 2009-05-07 | 2010-02-24 | 中国京冶工程技术有限公司 | Multi-corrosion controllable expansion extruded soil bolt |
| CN202323943U (en) * | 2011-12-01 | 2012-07-11 | 湖南科技大学 | Branch-shaped inflatable anti-floating anchor rod of soft-soil foundation region |
| CN202509532U (en) * | 2011-12-22 | 2012-10-31 | 深圳市市政工程总公司 | Multi-rib tension type anti-floating anchor |
| CN202559345U (en) * | 2012-02-23 | 2012-11-28 | 山东同圆设计集团有限公司 | Bottom-expanded pre-stress anti-floating anchor rod |
| CN204080836U (en) * | 2014-09-10 | 2015-01-07 | 中国建筑第六工程局有限公司 | The fast plugging device of dewatering well in a kind of building basement |
| CN204780962U (en) * | 2015-06-12 | 2015-11-18 | 杭州江润科技有限公司 | Built -in anti sea anchor pole block structure of deep well precipitation well in soleplate |
Also Published As
| Publication number | Publication date |
|---|---|
| CN105178344A (en) | 2015-12-23 |
Similar Documents
| Publication | Publication Date | Title |
|---|---|---|
| CN105178344B (en) | The construction method of the built-in anti-float anchor rod plugging structure of sole plate precipitation of deep well | |
| CN202124865U (en) | Quick plugging device for dewatering wellhead of sand-free cement pipe deep well | |
| CN101768976B (en) | Base pit dewatering and water saving device and construction method thereof | |
| CN103993615B (en) | Large-drawdown pipe well plugging structure and construction method thereof | |
| CN101691756B (en) | Construction method of emergency dewatering well for pressurized water inrush in foundation pit | |
| CN207727600U (en) | Plugging dewatering well device | |
| CN204530733U (en) | Underground construction deep-well precipitation well head plugging structure | |
| CN102839691B (en) | Quick sealing method and device for sandless cement pipe deep well dewatering wellhead | |
| CN104947700B (en) | A kind of sealing method of precipitation well | |
| CN104988915B (en) | A kind of prefabricated installation method of detachable steel casing and under water connection beam | |
| CN103321246B (en) | Construction Method of Foundation Pit Using Underground Diaphragm Wall | |
| CN109736340B (en) | Dewatering device and method for guaranteeing integrity of cushion layer by reserving dewatering well on foundation slab | |
| CN104099946B (en) | Inspection-pit between a kind of Novel top pipeline section | |
| CN101748742B (en) | Dual-plugging construction method of concrete and flange for depressurization well | |
| CN203145029U (en) | Plugging structure for deep foundation pit dewatering well | |
| CN204491645U (en) | A kind of deep foundation pit precipitation well-sealing device | |
| CN105484277A (en) | Component for tubular well precipitation construction in elevator foundation pit or sump and construction method | |
| CN201567582U (en) | A water-saving device for foundation pit dewatering | |
| CN109025899B (en) | Well sealing device | |
| CN203855990U (en) | Big pipe shaft block structure that falls | |
| CN109723071B (en) | Construction method of double-layer steel drum drainage system built in basement floor post-cast strip | |
| CN204780962U (en) | Built -in anti sea anchor pole block structure of deep well precipitation well in soleplate | |
| CN205205844U (en) | Member is used in construction of tubular well precipitation in elevator foundation ditch or sump pit | |
| CN206599776U (en) | Junction block for buried waterproof steel plate in diaphram wall | |
| CN212641468U (en) | Pit-in-pit rapid construction structure |
Legal Events
| Date | Code | Title | Description |
|---|---|---|---|
| C06 | Publication | ||
| PB01 | Publication | ||
| C10 | Entry into substantive examination | ||
| SE01 | Entry into force of request for substantive examination | ||
| GR01 | Patent grant | ||
| GR01 | Patent grant | ||
| CB03 | Change of inventor or designer information |
Inventor after: Zhang Xuehua Inventor after: Jing Jun Inventor after: Wang Jun Inventor after: Luo Bin Inventor before: Wang Xinquan |
|
| CB03 | Change of inventor or designer information | ||
| TR01 | Transfer of patent right |
Effective date of registration: 20180330 Address after: 610046 Sichuan city of Chengdu province Wuhou District grass Golden Road No. 9 Patentee after: CITIC GUOAN CONSTRUCTION GROUP Co.,Ltd. Address before: Gongshu District Shi Xiang Road Hangzhou city Zhejiang province 310015 and Hangzhou Road intersection C Wanda Plaza office building room 1901 Patentee before: HANGZHOU JIANGRUN TECHNOLOGY Ltd. |
|
| TR01 | Transfer of patent right | ||
| CF01 | Termination of patent right due to non-payment of annual fee |
Granted publication date: 20170620 |
|
| CF01 | Termination of patent right due to non-payment of annual fee |