CN106284619A - Water storage structure of urban runoff unit - Google Patents

Water storage structure of urban runoff unit Download PDF

Info

Publication number
CN106284619A
CN106284619A CN201610885621.1A CN201610885621A CN106284619A CN 106284619 A CN106284619 A CN 106284619A CN 201610885621 A CN201610885621 A CN 201610885621A CN 106284619 A CN106284619 A CN 106284619A
Authority
CN
China
Prior art keywords
sedimentation tank
cistern
reservoir
water
water storage
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Pending
Application number
CN201610885621.1A
Other languages
Chinese (zh)
Inventor
任良治
任柏橙
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Chongqing Geology And Mineral Exploration And Development Bureau 208 Hydrogeology Engineering Geology Team (chongqing Geological Disaster Prevention Engineering Exploration And Design Institute)
Original Assignee
Chongqing Geology And Mineral Exploration And Development Bureau 208 Hydrogeology Engineering Geology Team (chongqing Geological Disaster Prevention Engineering Exploration And Design Institute)
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Chongqing Geology And Mineral Exploration And Development Bureau 208 Hydrogeology Engineering Geology Team (chongqing Geological Disaster Prevention Engineering Exploration And Design Institute) filed Critical Chongqing Geology And Mineral Exploration And Development Bureau 208 Hydrogeology Engineering Geology Team (chongqing Geological Disaster Prevention Engineering Exploration And Design Institute)
Priority to CN201610885621.1A priority Critical patent/CN106284619A/en
Publication of CN106284619A publication Critical patent/CN106284619A/en
Pending legal-status Critical Current

Links

Classifications

    • EFIXED CONSTRUCTIONS
    • E03WATER SUPPLY; SEWERAGE
    • E03FSEWERS; CESSPOOLS
    • E03F5/00Sewerage structures
    • E03F5/10Collecting-tanks; Equalising-tanks for regulating the run-off; Laying-up basins
    • EFIXED CONSTRUCTIONS
    • E03WATER SUPPLY; SEWERAGE
    • E03FSEWERS; CESSPOOLS
    • E03F5/00Sewerage structures
    • E03F5/14Devices for separating liquid or solid substances from sewage, e.g. sand or sludge traps, rakes or grates
    • YGENERAL TAGGING OF NEW TECHNOLOGICAL DEVELOPMENTS; GENERAL TAGGING OF CROSS-SECTIONAL TECHNOLOGIES SPANNING OVER SEVERAL SECTIONS OF THE IPC; TECHNICAL SUBJECTS COVERED BY FORMER USPC CROSS-REFERENCE ART COLLECTIONS [XRACs] AND DIGESTS
    • Y02TECHNOLOGIES OR APPLICATIONS FOR MITIGATION OR ADAPTATION AGAINST CLIMATE CHANGE
    • Y02ATECHNOLOGIES FOR ADAPTATION TO CLIMATE CHANGE
    • Y02A10/00TECHNOLOGIES FOR ADAPTATION TO CLIMATE CHANGE at coastal zones; at river basins
    • Y02A10/30Flood prevention; Flood or storm water management, e.g. using flood barriers

Landscapes

  • Health & Medical Sciences (AREA)
  • Life Sciences & Earth Sciences (AREA)
  • Engineering & Computer Science (AREA)
  • Hydrology & Water Resources (AREA)
  • Public Health (AREA)
  • Water Supply & Treatment (AREA)
  • Sewage (AREA)

Abstract

The invention discloses a water storage structure of an urban runoff unit, wherein a sedimentation tank and a reservoir are built below an urban highway, a water through hole is arranged at the upper part of a separation wall between the sedimentation tank and the reservoir, a water grate is arranged above the sedimentation tank, the sedimentation tank and the reservoir are provided with air ducts communicated with the outside, the upper ends of the air ducts are placed in a flower bed of a sidewalk for discharging air in the sedimentation tank and the reservoir, the bottom of one side of the sedimentation tank and the reservoir is provided with a dredging groove, the dredging groove is lower than the sedimentation tank and the reservoir, the bottom surfaces of the sedimentation tank and the reservoir gradually incline towards the direction of the dredging groove to form an inclined plane with a gradient alpha, drain outlets are respectively arranged above the sedimentation tank and the reservoir and are sealed by drain outlet cover plates, and pedestrian ladders which are respectively opposite to the corresponding drain outlets are arranged in the sedimentation tank and the reservoir. The urban waterlogging water storage system has the advantages of low cost, strong water storage capacity and high implementability, thoroughly solves the problem of urban waterlogging, and can recycle the accumulated rainwater.

Description

The water storage structure of urban runoff unit
Technical field
The present invention relates to municipal works technical field, be particularly used for solving the runoff unit water-retention knot of urban waterlogging Structure.
Background technology
Present stage does not use the method that water filling solves urban waterlogging problem.Common practice is to utilize existing city Greenery patches and footpath reconstruction " sponge city ", international term is " low impact exploitation storm-water system builds ", and its principle is: under Water suction, water-retention, infiltration, water purification during rain, " discharge the water stored " and be used when needing.
Existing problems:
First, city is " an inch of land is an inch of gold ", it is impossible to scattered, build urban green space in large area, to sponge city Build and cause difficulty;
Second, the old city built up, involve the series of problems such as removal, be not easy to sponge city integrated planning and Implement;
3rd, the area that sponge city is covered, for the entire area in city, proportion is the least, and it is former Reason is to utilize " modular " water suction and water storage, and its water suction and storage capacity are the most weak, seem helpless when in the face of torrential rain;
4th, modular that " sponge city " is utilized water suction water storage mechanism, easily silt up, and be not easily cleaned, running Severe i.e. may be stranded after 1 year to silt up and its water suction water storage function that scatters and disappears;
5th, " sponge city " cost is high, and every square kilometre reaches 1~1.5 hundred million yuan.
Summary of the invention
The present invention is directed to above-mentioned technical problem improve, it is desirable to provide a kind of low cost, water-holding capacity are strong, exploitativeness The water storage structure of high urban runoff unit, thoroughly solve urban waterlogging problem, and the rainwater of savings can be again with.
To this end, the technical solution adopted in the present invention is: the water storage structure of a kind of urban runoff unit, including sedimentation tank and Cistern, described sedimentation tank and cistern build below municipal highway, and one in front and one in back sets along the bearing of trend of municipal highway Putting, build reduction town road above sedimentation tank and cistern, the divider wall top between sedimentation tank and cistern sets Putting water hole, make the rainwater after sedimentation tank precipitates enter cistern, the intensity that is provided above at sedimentation tank enough carries weight The shutter grate of type vehicle, described sedimentation tank, cistern be provided with and the extraneous breather line communicated, and the upper end of breather line is placed in For being discharged by the air in sedimentation tank, cistern in the flower stand of footpath, the side bottom at sedimentation tank, cistern is arranged clearly Silt groove, described desilting groove is lower than sedimentation tank, cistern, and the bottom surface of sedimentation tank, cistern gradually tilts towards the direction of desilting groove Forming the inclined-plane of gradient α, described sedimentation tank, the top of cistern are respectively arranged with sewage draining exit and are sealed by drain cover, The People's Bank of China's ladder just to each self-corresponding sewage draining exit it is provided with in described sedimentation tank, cistern.
Operation principle: when heavy rain makes street hydrops, a part of rainwater from city existing sewer drain, it is impossible to row The part walked, by highway runoff, when flowing through above sedimentation tank, flows into sedimentation tank by shutter grate.Glar in sedimentation tank After sand, by the water hole above divider wall, enter cistern.Cistern size and volume are built after calculating, it is sufficient to hold Nanotesla torrential rain and the city hydrops that causes.So, after the rainwater in Mei Tiao street enters cistern nearby, go up the most not in the street Can there is hydrops again.
Preferred as such scheme, the shutter grate that described sedimentation tank is provided above totally two, time interval ground horizontally set, The water on municipal highway is made to flow in sedimentation tank in time.
Further, described sedimentation tank, the left and right sides of cistern are each provided with a breather line, described breather line in " Z " font, the two ends at breather line is provided with passage filter screen, optimizes the structure of vent line, it is to avoid vent line Blocking, and reduce manufacturing cost, convenient installation.
Further, the water hole on described divider wall top is provided with water hole filter screen, makes the rainwater after precipitation flow into Again filter during cistern.
Beneficial effects of the present invention:
(1), urban waterlogging problem can thoroughly be solved.
(2), do not take up an area, do not remove.
(3), small investment.One-time investment, is benefited forever.Estimate that every square kilometre of investment is less than 30,000,000 yuan, and extra large Continuous every square kilometre of city investment reaches 1 1.5 hundred million yuan, and this scheme ratio " sponge city " saves 5 times of funds.
(4), the rainwater of savings can be again with.At economic development, under the situation that city size is increasing, it is subject to The impact of Global climate change, water resource is the deficientest.The savings of urban rainwater utilizes, and not only can solve urban waterlogging problem, And can effectively alleviate Urban Water Shortage Problem of Cities.
(5), later maintenance simple, maintenance cost is extremely low.
Accompanying drawing explanation
Fig. 1 is the top view of the present invention.
Fig. 2 is the A-A sectional view of Fig. 1.
Fig. 3 is B1-B1, B2-B2 sectional view of Fig. 1.
Fig. 4 is C1-C1, C2-C2 sectional view of Fig. 1.
Fig. 5 is the side view of divider wall in the present invention.
Detailed description of the invention
Below by embodiment and combine accompanying drawing, the invention will be further described:
Shown in Fig. 1 Fig. 5, the water storage structure of a kind of urban runoff unit, by sedimentation tank 1, cistern 2, divider wall 3, water hole 4, shutter grate 5, breather line 6, desilting groove 7, sewage draining exit 8, drain cover 9, People's Bank of China's ladder 10, passage filter screen 11 and Water hole filter screen 12 forms.
Sedimentation tank 1 and cistern 2 are built below municipal highway, and one in front and one in back set along the bearing of trend of municipal highway Putting, sedimentation tank 1 and cistern 2 are almost wide with municipal highway, to improve sedimentation tank 1 and the volume of cistern 2 under same length. Above sedimentation tank 1 and cistern 2, build reduction town road, do not affect the current of existing town road.
Divider wall 3 top between sedimentation tank 1 and cistern 2 arranges water hole 4, makes after sedimentation tank 1 precipitates Rainwater flows into cistern 2 through water hole 4.The intensity that is provided above at sedimentation tank 1 enough carries the shutter grate 5 of heavy vehicle, best It is, at the shutter grate 5 totally two that sedimentation tank 1 is provided above, time interval ground horizontally set.
Sedimentation tank 1, cistern 2 are provided with the breather line 6 communicated with the external world, and the upper end of breather line 6 is placed in People's Bank of China For being discharged by the air in sedimentation tank 1, cistern 2 in the flower stand in road, it is not take up footpath, when rainwater water inlet sedimentation tank 1 He Time in cistern 2, in pond, air can be discharged by respective breather line 6.Preferably, sedimentation tank 1, the left and right two of cistern 2 Side is each provided with a breather line 6, and breather line 6 is provided with passage in " Z " font, the two ends at breather line 6 Filter screen 11.
A side bottom at sedimentation tank 1, cistern 2 arranges desilting groove 7, and desilting groove 7 is lower than sedimentation tank 1, cistern 2, and Sedimentation tank 1, the bottom surface of cistern 2 are gradually formed slopely the inclined-plane of gradient α towards the direction of desilting groove 7, it is simple to be deposited at the bottom of pond Silt particle enters in desilting groove 7.
Sedimentation tank 1, the top of cistern 2 are respectively arranged with sewage draining exit 8 and are sealed by drain cover 9, sedimentation tank 1, The People's Bank of China's ladder 10 just to each self-corresponding sewage draining exit 8 it is provided with, it is simple to artificial enter in pond desilting smoothly or by dirt in cistern 2 Water pump enters for 8 to extract mud and sewage in pond out from sewage draining exit.
It is provided with water hole filter screen 12 on the water hole 4 on divider wall 3 top, divider wall 3 is preferably evenly equipped with several mistakes Water hole 4.
Avenue is divided into several surface runoff unit (so-called surface runoff unit, it is simply that in this region, Its surface water can be substantially to a direction flowing), at the low-lying place of highway of each surface runoff unit, urban runoff unit is set Water storage structure.
It is embodied as step as follows:
The first step: actual measurement Large-scale Urban (such as 1:2000) topography.
Second step: according to hypsographic map, in conjunction with on-the-spot field inspection avenue distribution situation, divide several " surface runoff unit ".
3rd step: collect urban history rainfall data, average rainfall particularly over the years and historic flood level, flooded High water level etc..
4th step: planning and designing.
(I), according to the average rainfall in this urban storm season, the areal rainfall in this city is calculated.Further according to centre plane rain Amount calculates total rainfall of each surface runoff unit.
(II), at the low-lying place of highway of each runoff unit planning sedimentation tank and cistern, can be one, it is also possible to It is multiple.The total measurement (volume) of cistern is greater than total rainfall of calculating.
(III), feasibility study.
Feasibility study stage, should ask and be expounded through peer review and check.In Method for Checking can use anti-inference method, i.e. this runoff unit Cistern total measurement (volume), if more than the water accumulating volume during peak level flooded in this runoff unit.Carry out appropriation budget simultaneously.
Check formula: W >=(S1-S2)h
In formula, cistern total measurement (volume) in W--runoff unit
S1The surface runoff unit gross area
S2Building occupied area in runoff unit
H this unit extreme high water average height
(IV), construction drawing design
On the basis of feasibility study, further prioritization scheme, carry out cistern, sewage draining exit, the construction of highway bridge set Meter.
5th step: construction
Affect traffic less for construction period, in urban district, segmentation is constructed.Close this section of highway about 3 months, strictly According to design and construction.Constructed before flood season arrives complete.
6th step: the later stage uses and safeguards
Very heavy rains when, cistern starts water-retention.After every heavy rain, the water in cistern should be checked immediately Position.As reaching a certain height, it is necessary to water pump, water is evacuated to surface drainage system and discharges, remove mud with sewage pump, it is simple under Water-retention is continued during secondary very heavy rains.
Annual late April to late August is major flood season, in this time stage, it is necessary to keep whole cistern to be in vacant State.August savings water, can retain, clean street, urban afforestation water, fire demand water, industrial for municipal sector Water.When serious water shortage, it is possible to for people and animals' drinking water after disinfecting.

Claims (4)

1. the water storage structure of a urban runoff unit, it is characterised in that: include sedimentation tank (1) and cistern (2), described precipitation Pond (1) and cistern (2) are built below municipal highway, and one in front and one in back arrange along the bearing of trend of municipal highway, in precipitation Reduction town road is built in the top of pond (1) and cistern (2), the divider wall (3) between sedimentation tank (1) and cistern (2) Top arranges water hole (4), makes the rainwater after sedimentation tank (1) precipitates enter cistern (2), in the top of sedimentation tank (1) Arranging intensity and enough carry the shutter grate (5) of heavy vehicle, described sedimentation tank (1), cistern (2) are provided with logical with what the external world communicated Feed channel (6), the flower stand that the upper end of breather line (6) is placed in footpath is interior for by sedimentation tank (1), cistern (2) Air is discharged, and the side bottom at sedimentation tank (1), cistern (2) arranges desilting groove (7), and described desilting groove (7) compares sedimentation tank (1), cistern (2) low, and the bottom surface of sedimentation tank (1), cistern (2) is gradually formed slopely gradient α towards the direction of desilting groove (7) Inclined-plane, described sedimentation tank (1), the top of cistern (2) be respectively arranged with sewage draining exit (8) and by drain cover (9) seal Live, in described sedimentation tank (1), cistern (2), be provided with People's Bank of China's ladder (10) just to each self-corresponding sewage draining exit (8).
2. according to the water storage structure of the urban runoff unit described in claim 1, it is characterised in that: described sedimentation tank (1) top The shutter grate (5) totally two arranged, time interval ground horizontally set.
3. according to the water storage structure of the urban runoff unit described in claim 1, it is characterised in that: described sedimentation tank (1), water-retention The left and right sides in pond (2) is each provided with a breather line (6), and described breather line (6) is in " Z " font, in breather line (6) Two ends be provided with passage filter screen (11).
4. according to the water storage structure of the urban runoff unit described in claim 1, it is characterised in that: described divider wall (3) top Water hole (4) on be provided with water hole filter screen (12).
CN201610885621.1A 2016-10-11 2016-10-11 Water storage structure of urban runoff unit Pending CN106284619A (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201610885621.1A CN106284619A (en) 2016-10-11 2016-10-11 Water storage structure of urban runoff unit

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201610885621.1A CN106284619A (en) 2016-10-11 2016-10-11 Water storage structure of urban runoff unit

Publications (1)

Publication Number Publication Date
CN106284619A true CN106284619A (en) 2017-01-04

Family

ID=57717235

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201610885621.1A Pending CN106284619A (en) 2016-10-11 2016-10-11 Water storage structure of urban runoff unit

Country Status (1)

Country Link
CN (1) CN106284619A (en)

Cited By (3)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN107055798A (en) * 2017-04-24 2017-08-18 浙江中景市政园林建设有限公司 A kind of town road drainage system
CN113455342A (en) * 2021-07-06 2021-10-01 南昌工程学院 Water-saving irrigation system for slope water and soil conservation
CN113502900A (en) * 2021-07-28 2021-10-15 北京市市政工程设计研究总院有限公司 Rainwater recycling system integrating functions of precipitation, filtration and stagnation storage

Citations (4)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
US6277274B1 (en) * 1999-04-16 2001-08-21 Larry Steven Coffman Method and apparatus for treating stormwater runoff
CN203475587U (en) * 2013-08-06 2014-03-12 黄明逸 Road rainwater collecting and utilizing device
CN203795512U (en) * 2014-04-21 2014-08-27 江苏南通二建集团有限公司 Rainwater recycling device
CN205171636U (en) * 2015-11-25 2016-04-20 浙江荣林环境工程有限公司 Urban road rainwater collection utilization system

Patent Citations (4)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
US6277274B1 (en) * 1999-04-16 2001-08-21 Larry Steven Coffman Method and apparatus for treating stormwater runoff
CN203475587U (en) * 2013-08-06 2014-03-12 黄明逸 Road rainwater collecting and utilizing device
CN203795512U (en) * 2014-04-21 2014-08-27 江苏南通二建集团有限公司 Rainwater recycling device
CN205171636U (en) * 2015-11-25 2016-04-20 浙江荣林环境工程有限公司 Urban road rainwater collection utilization system

Non-Patent Citations (1)

* Cited by examiner, † Cited by third party
Title
郑丽娟等: "《雨水利用技术与管理》", 31 January 2015 *

Cited By (5)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN107055798A (en) * 2017-04-24 2017-08-18 浙江中景市政园林建设有限公司 A kind of town road drainage system
CN107055798B (en) * 2017-04-24 2020-10-27 浙江中景市政园林建设有限公司 Town road drainage system
CN113455342A (en) * 2021-07-06 2021-10-01 南昌工程学院 Water-saving irrigation system for slope water and soil conservation
CN113455342B (en) * 2021-07-06 2022-07-08 南昌工程学院 Water-Saving Irrigation System for Slope Soil and Water Conservation
CN113502900A (en) * 2021-07-28 2021-10-15 北京市市政工程设计研究总院有限公司 Rainwater recycling system integrating functions of precipitation, filtration and stagnation storage

Similar Documents

Publication Publication Date Title
CN103088896B (en) Ecological road shock resistance rainwater utilization system
CN105714723B (en) A kind of urban road rainwater-collecting processing and application system
CN102910787A (en) Garden-type rainwater processing and recycling integrated system in residential community
CN104878825B (en) High-capacity impound pipeline rainwater impounding and discharging system and method
CN106351311A (en) Dispersed water storage method for solving urban inland inundation
CN106013386A (en) Serially-connected multi-level-rain-garden permeation system for existing residential areas
CN104032793A (en) Garden type rainwater impact resistance system used for residential area road
CN105064274A (en) Storing and discharging integrated box-type revetment
CN103967105A (en) Housing cluster rainwater ecological drain-off system
CN105804153B (en) A kind of accurate abandoned stream filtering storage integrated tank of rainwater
CN106284619A (en) Water storage structure of urban runoff unit
CN205839923U (en) A kind of novel intelligent grid storm water man-agement system
CN208650225U (en) A kind of infiltration type drainage ditch
CN114991253A (en) Rainwater purification regulation and storage system
Aladesote Cost-benefit analysis of green infrastructure for sustainable stormwater management of the built environment
CN209011283U (en) A kind of sponge novel urban rainwater separate system
CN108547363A (en) The energy-efficient greenery patches rainwater circulatory system
CN206267225U (en) Water storage unit below street and highway
CN107354990A (en) A kind of storage for roadside oozes net row's type rainwater reuse device
CN110670472A (en) Steel construction view overline bridge step
Wałęga et al. The use of bioretention cell to decreasing outflow from parking lot
CN105804201B (en) A kind of novel intelligent grid storm water man- agement system
CN211774469U (en) Rainwater recycling device
CN204849894U (en) Municipal administration rainwater retaining system
CN210916859U (en) Rainwater collecting, utilizing and discharging system for road sponge facilities in collapsible loess areas

Legal Events

Date Code Title Description
C06 Publication
PB01 Publication
SE01 Entry into force of request for substantive examination
SE01 Entry into force of request for substantive examination
RJ01 Rejection of invention patent application after publication

Application publication date: 20170104