CN106368645B - The Construction Method of Pressure Lifting and Lowering of Temperature Measuring Cable in SAGD Well - Google Patents
The Construction Method of Pressure Lifting and Lowering of Temperature Measuring Cable in SAGD Well Download PDFInfo
- Publication number
- CN106368645B CN106368645B CN201610911934.XA CN201610911934A CN106368645B CN 106368645 B CN106368645 B CN 106368645B CN 201610911934 A CN201610911934 A CN 201610911934A CN 106368645 B CN106368645 B CN 106368645B
- Authority
- CN
- China
- Prior art keywords
- pressure
- temperature measuring
- packing
- flange
- measuring cable
- Prior art date
- Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
- Expired - Fee Related
Links
Classifications
-
- E—FIXED CONSTRUCTIONS
- E21—EARTH OR ROCK DRILLING; MINING
- E21B—EARTH OR ROCK DRILLING; OBTAINING OIL, GAS, WATER, SOLUBLE OR MELTABLE MATERIALS OR A SLURRY OF MINERALS FROM WELLS
- E21B33/00—Sealing or packing boreholes or wells
- E21B33/02—Surface sealing or packing
- E21B33/03—Well heads; Setting-up thereof
- E21B33/068—Well heads; Setting-up thereof having provision for introducing objects or fluids into, or removing objects from, wells
- E21B33/072—Well heads; Setting-up thereof having provision for introducing objects or fluids into, or removing objects from, wells for cable-operated tools
Landscapes
- Life Sciences & Earth Sciences (AREA)
- Engineering & Computer Science (AREA)
- Geology (AREA)
- Mining & Mineral Resources (AREA)
- Physics & Mathematics (AREA)
- Environmental & Geological Engineering (AREA)
- Fluid Mechanics (AREA)
- General Life Sciences & Earth Sciences (AREA)
- Geochemistry & Mineralogy (AREA)
- Earth Drilling (AREA)
Abstract
本发明公开了SAGD井测温缆带压提、下的施工方法。包括以下步骤:测温缆带压下井:将工字法兰的扇形一端与井口配合后安装紧固好;将测温缆带压提、下密封装置全部安装并紧固好止;向盘根盒内放入盘根,并用盘根盒压盖压紧盘根,观察盘根是否密封好测温缆,然后打开热采闸阀,通过注入装置将测温缆从测温缆带压提、下密封装置顶部引入直至达到设计测温深度;测温缆下入到设计位置后,通过注脂机向测温缆带压提、下密封装置的注脂密封器的注脂阀注脂,实现测温缆的密封;通过泄压阀放压后,拆除盘根,再通过打吊卡子从测温缆带压提、下密封装置上端开始分别拆除盘根压盖、盘根盒、泄压法兰和液动密封器,最后安装井口静止密封装置将井口与测温缆密封;本发明有效地减少污染,保护了环境。
The invention discloses a construction method for pressure lifting and lowering of a temperature measuring cable in a SAGD well. It includes the following steps: temperature measurement cable is pressed down into the well: install and fasten the fan-shaped end of the I-shaped flange with the wellhead; install and fasten the temperature measurement cable with pressure lift and lower sealing device; Put the packing into the box, and press the packing with the gland of the packing box, observe whether the packing is well sealed with the temperature measuring cable, then open the thermal mining gate valve, and press the temperature measuring cable from the temperature measuring cable belt through the injection device The top of the sealing device is introduced until the design temperature measurement depth is reached; after the temperature measurement cable is lowered to the design position, the temperature measurement cable is pressed and lifted by the grease injection machine, and the grease injection valve of the grease injection sealer of the lower sealing device is injected with grease to realize the measurement Sealing of the temperature cable: After the pressure is released through the pressure relief valve, the packing is removed, and then the packing gland, packing box, and pressure relief flange are respectively removed from the upper end of the temperature measuring cable and the upper end of the lower sealing device by lifting the clamp and a hydraulic sealer, and finally a wellhead static sealing device is installed to seal the wellhead and the temperature measuring cable; the invention effectively reduces pollution and protects the environment.
Description
技术领域technical field
本发明涉及一种施工方法,尤其是涉及一种SAGD井测温缆带压提、下的施工方法。The invention relates to a construction method, in particular to a construction method for a SAGD well temperature measuring cable to be lifted and lowered under pressure.
背景技术Background technique
目前SAGD井在提、下测温装置时,需要先将生产井停抽,停注,等待生产油井的温度与压力下降,再用泵车与水车进行压井作业,待井口无压后,打开井口测试管线进行测温缆的提、下施工。SAGD井下温度测试常规提、下作业会对作业油井采用高密度压井液压井或放喷手段将油井井下压力降低后进行作业。高密度压井液压井不仅成本高、时间长,而且会堵塞地下油水通道,影响采油产量和注汽效果。如果采用放喷降压,不但会大量降低地层能量,给后续生产带来不可估量的损失,同时也会造成环境污染。无压提、下测温装置存在的问题:At present, when lifting and lowering the temperature measuring device in a SAGD well, it is necessary to stop the pumping and injection of the production well first, wait for the temperature and pressure of the production well to drop, and then use the pump truck and water truck to carry out the well killing operation. Open the wellhead test pipeline to carry out the lifting and lowering construction of the temperature measuring cable. SAGD downhole temperature test routine lifting and running operations will use high-density well killing hydraulic wells or blowout means to reduce the downhole pressure of the oil well before operating the oil well. High-density well killing hydraulic wells are not only costly and time-consuming, but also block underground oil and water channels, affecting oil production and steam injection effects. If spraying is used to lower the pressure, it will not only greatly reduce the formation energy, but also bring immeasurable losses to subsequent production, and also cause environmental pollution. Problems existing in the non-pressure lifting and lower temperature measuring device:
1、影响生产油井的正常采油周期,减少产量。1. Affect the normal production cycle of production oil wells and reduce production.
2、压井过程中压井液量一旦过大,会影响采油液面的波动,严重时使采油井无法生产,需重新作业。2. Once the killing fluid volume is too large during the well killing process, it will affect the fluctuation of the oil production liquid level. In severe cases, the oil production well cannot be produced and needs to be re-operated.
3、浪费资源,每次压井至少需要两至三车的水或浓盐水;高温下浓盐水对金属有腐蚀。3. Waste of resources, at least two to three trucks of water or concentrated brine are needed for each kill; concentrated brine corrodes metals at high temperatures.
发明内容Contents of the invention
本发明是针对上述问题提供一种结构合理,不需要停井放压、降温,实现动态密封,缩短施工周期;减少常规作业所需压井液及其地面施工设备及费用,且减少污染,保护环境的SAGD井测温缆带压提、下的施工方法。The present invention aims at the above problems and provides a structure that is reasonable, does not need to shut down the well to release pressure and cool down, realizes dynamic sealing, shortens the construction period; Environmental SAGD well temperature measurement cable belt pressure lift, down construction method.
本发明解决技术问题的技术方案是:SAGD井测温缆带压提、下的施工方法,包括以下步骤:The technical scheme that the present invention solves technical problem is: the construction method of SAGD well temperature-measuring cable belt pressure lifting, lowering, comprises the following steps:
一、测温缆带压下井:1. Temperature measurement cable pressure downhole:
步骤 1)将测温缆带压提、下密封装置中工字法兰的扇形一端与井口配合后安装紧固好; Step 1) Fit the fan-shaped end of the I-shaped flange of the temperature measuring cable with the pressure lifting and lower sealing device with the wellhead, and then install and fasten it;
步骤2)再安装热采闸阀,以及在热采闸阀上顺次安装注脂密封器、液动防喷器、泄压法兰、盘根盒及盘根压盖,直至将测温缆带压提、下密封装置全部安装并紧固好止;Step 2) Install the thermal recovery gate valve again, and install the grease injection sealer, hydraulic blowout preventer, pressure relief flange, packing box and packing gland on the thermal recovery gate valve in sequence until the temperature measuring cable is pressed The lifting and lower sealing devices are all installed and fastened;
步骤3)向盘根盒内放入盘根,并用盘根盒压盖压紧盘根,观察盘根是否密封好测温缆,然后打开热采闸阀2,通过注入装置将测温缆从测温缆带压提、下密封装置顶部引入直至达到设计测温深度;Step 3) Put the packing into the packing box, and press the packing with the gland of the packing box, observe whether the packing is sealed with the temperature measuring cable, then open the thermal recovery gate valve 2, and inject the temperature measuring cable from the measuring cable through the injection device. The temperature cable is lifted by pressure, and the top of the lower sealing device is introduced until the design temperature measurement depth is reached;
步骤4)测温缆下入到设计位置后,通过注脂机向测温缆带压提、下密封装置的注脂密封器的注脂阀注脂,实现测温缆的密封;Step 4) After the temperature measuring cable is lowered to the design position, inject grease into the grease injection valve of the grease injection sealer of the temperature measuring cable belt pressure lifting and lower sealing device through the grease injection machine to realize the sealing of the temperature measuring cable;
步骤5)通过泄压阀放压后,拆除盘根,再通过打吊卡子从测温缆带压提、下密封装置上端开始分别拆除盘根压盖、盘根盒、泄压法兰和液动密封器,最后安装井口静止密封装置将井口与测温缆密封;Step 5) After the pressure is released through the pressure relief valve, remove the packing, and then remove the packing gland, packing box, pressure relief flange and hydraulic pressure from the upper end of the temperature measuring cable and the lower sealing device by using the lifting clamp. Dynamic sealer, and finally install the wellhead static sealing device to seal the wellhead and temperature measuring cable;
二、测温缆带压提出井口:2. The temperature measuring cable brings up the wellhead under pressure:
步骤1)通过注脂机向注脂密封器的注脂阀注脂,实现测温缆的密封;Step 1) Inject grease into the grease injection valve of the grease injection sealer through the grease injection machine to realize the sealing of the temperature measuring cable;
步骤2)通过与吊车配合打吊卡子的方式,拆除井口静止密封装置,并在注脂密封器上顺次安装液动密封器、泄压法兰、盘根盒及盘根压盖,并紧固好;Step 2) Remove the wellhead static sealing device by cooperating with the crane to lift the clamp, and install the hydraulic sealer, pressure relief flange, packing box and packing gland on the grease sealer in sequence, and tighten them tightly. fixed;
步骤3)通过测温缆提出装置将测温缆提出至注脂密封器中,关闭热采闸阀;Step 3) Lift the temperature measuring cable into the grease injection sealer through the temperature measuring cable lifting device, and close the thermal mining gate valve;
步骤4)通过泄压阀放压后,将盘根盒中的盘根取出,将测温缆全部提出;Step 4) After releasing the pressure through the pressure relief valve, take out the packing in the packing box, and lift out all the temperature measuring cables;
步骤5)顺次拆除盘根盒、泄压法兰、液动防喷器及注脂密封器,最后再次安装井口静止密封装置将井口密封。Step 5) Remove the packing box, pressure relief flange, hydraulic blowout preventer and grease sealer in sequence, and finally install the wellhead static sealing device again to seal the wellhead.
所述的步骤1)之前需先确认井口压力不高于5MPa,温度不高于300℃,周围100米内注汽井要求停注,保证施工井的压力温度稳定。Before step 1), it is necessary to confirm that the wellhead pressure is not higher than 5MPa and the temperature is not higher than 300°C. The steam injection wells within 100 meters around are required to stop injection to ensure that the pressure and temperature of the construction wells are stable.
所述的测温缆带压提、下密封装置为其一端法兰与井口相配的工字法兰的另一端法兰与热采闸阀的一端法兰固连,热采闸阀的另一端法兰与注脂密封器的一端法兰固连,注脂密封器的另一端法兰与液动防喷器的一端法兰固连,液动防喷器的另一端法兰与串联的泄压法兰和盘根盒的一端法兰固连,盘根盒的另一端与盘根压盖螺纹连接,工字法兰与热采闸阀、热采闸阀与注脂密封器、注脂密封器与液动防喷器以及液动防喷器与泄压法兰和泄压法兰与盘根盒之间均设有密封钢圈。The pressure-lifting and lower sealing device of the temperature-measuring cable is that one end flange of the I-shaped flange matched with the wellhead, the other end flange of the I-shaped flange is fixedly connected with the one end flange of the thermal recovery gate valve, and the other end flange of the thermal recovery gate valve is It is fixedly connected with one end flange of the grease injection sealer, the other end flange of the grease injection sealer is fixedly connected with the one end flange of the hydraulic blowout preventer, and the other end flange of the hydraulic blowout preventer is connected with the series pressure relief method One end flange of the flange and the packing box is fixedly connected, and the other end of the packing box is threadedly connected with the packing gland. There are sealing steel rings between the dynamic blowout preventer and the hydraulic blowout preventer and the pressure relief flange, and between the pressure relief flange and the packing box.
所述的注脂密封器内的轴向中心处至上而下分别设有管套、注脂压套和注脂定位螺帽,且三者的轴向中心均设有与测温缆直径适配的通孔。The axial center of the grease injection sealer is respectively provided with a pipe sleeve, a grease injection pressure sleeve and a grease injection positioning nut from top to bottom, and the axial center of the three is equipped with a diameter matching temperature measuring cable. through holes.
所述的管套的横向中心线位置至少设有一个注脂阀,且注脂阀固连于注脂密封器上。At least one grease injection valve is provided at the transverse centerline of the pipe sleeve, and the grease injection valve is fixedly connected to the grease injection sealer.
所述的泄压法兰横向中部设有泄压阀。A pressure relief valve is provided in the transverse middle of the pressure relief flange.
所述的盘根盒内的轴向中心处至下而上分别设有扶正器定位螺帽、垫圈、扶正器、塔式的盘根和盘根固定挡块。The axial center of the packing box is respectively provided with a centralizer positioning nut, a washer, a centralizer, a tower-type packing and a packing fixed block from bottom to top.
所述的盘根压盖内的轴向中心处还设有扶正器,且与盘根接触。A centralizer is also provided at the axial center of the packing gland and is in contact with the packing.
所述的扶正器为设有内外层的两个弧形环,该两个弧形环的中部错位搭接成圆形构成。The centralizer is two arc-shaped rings with inner and outer layers, and the middle parts of the two arc-shaped rings are dislocated and overlapped to form a circle.
所述的液动防喷器由相距距离大于10米的液压泵站控制。The hydraulic blowout preventer is controlled by a hydraulic pump station at a distance of more than 10 meters.
本发明与现有技术相比具有下列优点和效果:Compared with the prior art, the present invention has the following advantages and effects:
本发明不需要停井放压降温,可以缩短施工周期;减少常规作业所需压井液及其地面施工设备的费用。采用塔式盘根密封,实现在带压下提、下测温缆时的动态密封。测温缆带压下入油井后,采用注脂方法,实现带压状态下的井口密封施工。在带压提、下测温缆时,一旦动态密封失效,液压泵站与液动防喷器距离15米,在紧急情况下可在远处及时启动液动防喷器对测温装置进行密封,实现井口防喷。The invention does not need to shut down the well to depressurize and cool down, can shorten the construction period, and reduces the cost of well-killing fluid and ground construction equipment required for conventional operations. The tower packing seal is adopted to realize the dynamic sealing when the temperature measuring cable is lifted and lowered under pressure. After the temperature measuring cable is driven into the oil well under pressure, the grease injection method is used to realize the wellhead sealing construction under pressure. When the temperature measuring cable is lifted and lowered under pressure, once the dynamic seal fails, the distance between the hydraulic pump station and the hydraulic blowout preventer is 15 meters. In case of emergency, the hydraulic blowout preventer can be activated in time to seal the temperature measuring device , to achieve wellhead blowout prevention.
另外,本发明没有外来流体入侵,油气层就没有外来固相、液相的气相的伤害,不会产生新的层间矛盾,地层压力系统不会受到破坏,不需要重新建立平衡,有利于油井修复后的稳产、高产;相对于传统的提、下温度测试装置作业,在不放喷、不放溢流的情况下带压作业,对单井而言不需要卸压,压井等操作,降低了成本,有效地减少污染,保护了环境,保持了整个注采网络的地层压力系统不受破坏,不需要再建立压平衡,在保证油井产量,提高注气时效等方面有着巨大的作用。本发明结构简单,通用性强,具有较好经济效益和社会效益。In addition, the present invention does not have external fluid intrusion, and the oil and gas layers will not be damaged by external solid phases, liquid phases, and gas phases, and new interlayer contradictions will not occur, the formation pressure system will not be damaged, and there is no need to re-establish balance, which is beneficial to oil wells Stable and high production after restoration; Compared with the operation of the traditional lifting and lowering temperature testing device, it works under pressure without blowout or overflow, and does not need pressure relief, well killing and other operations for a single well. It reduces costs, effectively reduces pollution, protects the environment, and keeps the formation pressure system of the entire injection-production network undamaged, without the need to establish pressure balance. It plays a huge role in ensuring oil well production and improving gas injection timeliness. The invention has simple structure, strong versatility, and better economic and social benefits.
本发明带压作业能产生如下显著的综合效益:The belt operation of the present invention can produce following remarkable comprehensive benefits:
1、保护产层,提高储量利用率(采收率);1. Protect the production layer and improve the utilization rate of reserves (recovery rate);
2、实现零污染,延长油气井的生产周期;2. Realize zero pollution and prolong the production cycle of oil and gas wells;
3、保护环境,节能减排,实现零排放;3. Protect the environment, save energy and reduce emissions, and achieve zero emissions;
4、节约了产能恢复费用;4. Saving the cost of capacity recovery;
5、节约了压井液成本;5. Save the cost of killing fluid;
6、不停产作业;6. Non-stop production operations;
7、缩短综合作业工期。7. Shorten the comprehensive operation period.
附图说明Description of drawings
图1是本发明的主视结构示意图;Fig. 1 is the front view structure schematic diagram of the present invention;
图2是本发明扶正器的主视结构示意图;Fig. 2 is the schematic diagram of the front view structure of the centralizer of the present invention;
图3是本发明扶正器的俯视结构示意图;Fig. 3 is a top view structural schematic diagram of the centralizer of the present invention;
图中主要零件:工字法兰1,热采闸阀2,注脂定位螺帽3,液动防喷器4,注脂阀5,注脂密封器6、密封钢圈7、液动防喷器8,泄压法兰9,扶正器定位螺帽10,垫圈11,扶正器12,测温缆13,盘根压盖14,盘根15,盘根盒16,泄压阀17,管套18。The main parts in the figure: I-shaped flange 1, thermal recovery gate valve 2, grease injection positioning nut 3, hydraulic blowout preventer 4, grease injection valve 5, grease injection sealer 6, sealing steel ring 7, hydraulic blowout preventer 8, pressure relief flange 9, centralizer positioning nut 10, gasket 11, centralizer 12, temperature measuring cable 13, packing gland 14, packing 15, packing box 16, pressure relief valve 17, sleeve 18.
具体实施方式Detailed ways
下面结合具体实施例对本发明进行进一步详细说明,但本发明的保护范围不受具体的实施例所限制,以权利要求书为准。另外,以不违背本发明技术方案的前提下,对本发明所作的本领域普通技术人员容易实现的任何改动或改变都将落入本发明的权利要求范围之内。The present invention will be further described in detail below in conjunction with specific examples, but the protection scope of the present invention is not limited by the specific examples, and the claims shall prevail. In addition, on the premise of not violating the technical solution of the present invention, any modification or change made to the present invention that can be easily realized by those skilled in the art will fall within the scope of the claims of the present invention.
实施例1:Example 1:
如图1、2、3所示,SAGD井测温缆带压提、下的施工方法,包括以下步骤:As shown in Figures 1, 2, and 3, the construction method of the temperature measuring cable belt pressure lifting and lowering of the SAGD well includes the following steps:
一、测温缆13带压下井:1. The temperature measuring cable 13 goes downhole under pressure:
步骤1)将测温缆带压提、下密封装置中工字法兰1的扇形一端与井口配合后安装紧固好;Step 1) Install and fasten the fan-shaped end of the I-shaped flange 1 in the temperature measuring cable belt pressure lifting and lower sealing device to the wellhead;
步骤2)再安装热采闸阀2,以及在热采闸阀2上顺次安装注脂密封器6、液动防喷器8、泄压法兰9、盘根盒16及盘根压盖14,直至将测温缆带压提、下密封装置全部安装并紧固好止;Step 2) Install the thermal mining gate valve 2 again, and install the grease injection sealer 6, the hydraulic blowout preventer 8, the pressure relief flange 9, the packing box 16 and the packing gland 14 on the thermal mining gate valve 2 in sequence, Until the temperature measuring cable is pressed and lifted, and the lower sealing device is completely installed and fastened;
步骤3)向盘根盒内放入盘根,并用盘根盒压盖压紧盘根,观察盘根是否密封好测温缆,然后打开热采闸阀2,通过注入装置将测温缆13从测温缆带压提、下密封装置顶部引入直至达到设计测温深度,下入过程中控制下放速度,防止遇阻折断,遇阻后先缓慢上提一段距离再下放;Step 3) Put the packing into the packing box, and press the packing with the gland of the packing box, observe whether the packing is sealed with the temperature measuring cable, then open the thermal mining gate valve 2, and inject the temperature measuring cable 13 from the The temperature measurement cable is lifted by pressure, and the top of the lower sealing device is introduced until the design temperature measurement depth is reached. During the lowering process, the lowering speed is controlled to prevent breaking when encountering obstacles. After encountering obstacles, it is slowly lifted up for a certain distance before lowering;
步骤 4)测温缆13下入到设计位置后,通过注脂机向测温缆带压提、下密封装置的注脂密封器6的注脂阀5注脂,实现测温缆13的密封; Step 4) After the temperature measurement cable 13 is lowered to the designed position, inject grease into the grease injection valve 5 of the grease injection sealer 6 of the temperature measurement cable belt pressure lifting and lower sealing device through the grease injection machine to realize the sealing of the temperature measurement cable 13 ;
步骤5)通过泄压阀17放压后,拆除盘根,再通过打吊卡子从测温缆带压提、下密封装置上端开始分别拆除盘根压盖14、盘根盒16、泄压法兰9和液动密封器8,最后安装井口静止密封装置将井口与测温缆13密封;Step 5) After releasing the pressure through the pressure relief valve 17, remove the packing, and then remove the packing gland 14, packing box 16, and pressure relief method respectively from the temperature measurement cable belt pressure lift and the upper end of the lower sealing device by lifting clips. Lan 9 and hydraulic sealer 8, and finally install the wellhead static sealing device to seal the wellhead and temperature measuring cable 13;
二、测温缆带压提出井口:2. The temperature measuring cable brings up the wellhead under pressure:
步骤1)通过注脂机向注脂密封器6的注脂阀5注脂,实现测温缆13的密封;Step 1) inject grease into the grease injection valve 5 of the grease injection sealer 6 through the grease injection machine to realize the sealing of the temperature measuring cable 13;
步骤2)通过与吊车配合打吊卡方式,拆除井口静止密封装置,并在注脂密封器6上顺次安装液动密封器8、泄压法兰9、盘根盒16及盘根压盖14,并紧固好;Step 2) Remove the wellhead static sealing device by cooperating with the crane to play the elevator, and install the hydraulic sealer 8, the pressure relief flange 9, the packing box 16 and the packing gland on the grease injection sealer 6 in sequence 14, and fastened;
步骤3)通过测温缆提出装置将测温缆13提出至注脂密封器6中,关闭热采闸阀2;Step 3) Lift the temperature measuring cable 13 into the grease injection sealer 6 through the temperature measuring cable lifting device, and close the thermal mining gate valve 2;
步骤4)通过泄压阀17放压后,将盘根盒16中的盘根15取出,将测温缆13全部提出;Step 4) After releasing the pressure through the pressure relief valve 17, take out the packing 15 in the packing box 16, and lift out all the temperature measuring cables 13;
步骤5)顺次拆除盘根盒16、泄压法兰9、液动防喷器8及注脂密封器6,最后再次安装井口静止密封装置将井口密封。Step 5) Remove the packing box 16, pressure relief flange 9, hydraulic blowout preventer 8 and grease injection sealer 6 in sequence, and finally install the wellhead static sealing device again to seal the wellhead.
上述的步骤1)之前需先确认井口压力不高于5MPa,温度不高于300℃,周围100米内注汽井要求停注,保证施工井的压力温度稳定。Before the above step 1), it is necessary to confirm that the wellhead pressure is not higher than 5MPa, the temperature is not higher than 300°C, and the steam injection wells within 100 meters around are required to stop injection to ensure that the pressure and temperature of the construction wells are stable.
上述的测温缆带压提、下密封装置为其一端法兰与井口相配的工字法兰1的另一端法兰与热采闸阀2的一端法兰固连,热采闸阀2的另一端法兰与注脂密封器6的一端法兰固连,注脂密封器6的另一端法兰与液动防喷器8的一端法兰固连,液动防喷器8的另一端法兰与串联的泄压法兰9和盘根盒16的一端法兰固连,盘根盒16的另一端与盘根压盖14螺纹连接,工字法兰1与热采闸阀2、热采闸阀2与注脂密封器6、注脂密封器6与液动防喷器8以及液动防喷器4与泄压法兰9和泄压法兰9与盘根盒16之间均设有密封钢圈7。The above-mentioned pressure-lifting and lower sealing device of the temperature-measuring cable is that the flange at one end matches the wellhead. The flange is fixedly connected to one end flange of the grease injection sealer 6, the other end flange of the grease injection sealer 6 is fixedly connected to the one end flange of the hydraulic blowout preventer 8, and the other end flange of the hydraulic blowout preventer 8 It is fixedly connected with the pressure relief flange 9 in series and one end flange of the packing box 16, and the other end of the packing box 16 is threadedly connected with the packing gland 14, and the I-shaped flange 1 is connected with the thermal recovery gate valve 2 and the thermal recovery gate valve 2 and the grease injection sealer 6, the grease injection sealer 6 and the hydraulic blowout preventer 8, and the hydraulic blowout preventer 4 and the pressure relief flange 9, and the pressure relief flange 9 and the packing box 16 are all provided with seals steel ring7.
上述的注脂密封器6内的轴向中心处至上而下分别设有管套18、注脂压套4和注脂定位螺帽3,且三者的轴向中心均设有与测温缆13直径适配的通孔。The axial center of the above-mentioned grease injection sealer 6 is respectively provided with a pipe sleeve 18, a grease injection pressure sleeve 4 and a grease injection positioning nut 3 from top to bottom, and the axial center of the three is provided with a temperature measuring cable. 13 diameter adapted through holes.
上述的管套18的横向中心线位置至少设有一个注脂阀5,且注脂阀5固连于注脂密封器6上。At least one grease injection valve 5 is provided at the transverse centerline position of the above-mentioned pipe sleeve 18 , and the grease injection valve 5 is fixedly connected to the grease injection sealer 6 .
上述的泄压法兰9横向中部设有泄压阀17。A pressure relief valve 17 is provided in the transverse middle of the above pressure relief flange 9 .
上述的盘根盒15内的轴向中心处至下而上分别设有扶正器定位螺帽10、垫圈11、扶正器12、塔式的盘根15和盘根固定挡块。A centralizer positioning nut 10, a washer 11, a centralizer 12, a tower-type packing 15 and a packing fixing block are respectively provided at the axial center of the above-mentioned packing box 15 from bottom to top.
上述的盘根压盖14内的轴向中心处还设有扶正器12,且与盘根15接触。A centralizer 12 is also provided at the axial center of the above-mentioned packing gland 14 and is in contact with the packing 15 .
上述的扶正器12为设有内外层的两个弧形环,该两个弧形环的中部错位搭接成圆形构成。The above-mentioned centralizer 12 is two arc-shaped rings with inner and outer layers, and the middle parts of the two arc-shaped rings are dislocated and overlapped to form a circle.
上述的液动防喷器8由相距距离小于10米的液压泵站控制。The above-mentioned hydraulic blowout preventer 8 is controlled by a hydraulic pump station with a distance of less than 10 meters.
上述的工字法兰1、热采闸阀2、液动防喷器8以及泄压法兰9的轴向中心处均设有35~60mm的通孔。The above-mentioned I-shaped flange 1, thermal recovery gate valve 2, hydraulic blowout preventer 8 and pressure relief flange 9 are all provided with through holes of 35-60mm in the axial center.
上述的盘根压盖14的轴向中心处设有与测温缆13直径适配的通孔。A through hole matching the diameter of the temperature measuring cable 13 is provided at the axial center of the above-mentioned packing gland 14 .
Claims (9)
Priority Applications (1)
| Application Number | Priority Date | Filing Date | Title |
|---|---|---|---|
| CN201610911934.XA CN106368645B (en) | 2016-10-19 | 2016-10-19 | The Construction Method of Pressure Lifting and Lowering of Temperature Measuring Cable in SAGD Well |
Applications Claiming Priority (1)
| Application Number | Priority Date | Filing Date | Title |
|---|---|---|---|
| CN201610911934.XA CN106368645B (en) | 2016-10-19 | 2016-10-19 | The Construction Method of Pressure Lifting and Lowering of Temperature Measuring Cable in SAGD Well |
Publications (2)
| Publication Number | Publication Date |
|---|---|
| CN106368645A CN106368645A (en) | 2017-02-01 |
| CN106368645B true CN106368645B (en) | 2019-09-03 |
Family
ID=57895911
Family Applications (1)
| Application Number | Title | Priority Date | Filing Date |
|---|---|---|---|
| CN201610911934.XA Expired - Fee Related CN106368645B (en) | 2016-10-19 | 2016-10-19 | The Construction Method of Pressure Lifting and Lowering of Temperature Measuring Cable in SAGD Well |
Country Status (1)
| Country | Link |
|---|---|
| CN (1) | CN106368645B (en) |
Families Citing this family (1)
| Publication number | Priority date | Publication date | Assignee | Title |
|---|---|---|---|---|
| CN108086952B (en) * | 2018-01-12 | 2024-06-14 | 科莱斯(天津)电热科技有限公司 | High-pressure wellhead T-cable hanging and releasing integrated device |
Citations (8)
| Publication number | Priority date | Publication date | Assignee | Title |
|---|---|---|---|---|
| CN2135642Y (en) * | 1992-09-01 | 1993-06-09 | 辽河石油勘探局茨榆坨采油厂 | Changeable rod sealing device |
| CN2286239Y (en) * | 1997-04-02 | 1998-07-15 | 中国石油天然气总公司石油勘探开发科学研究院廊坊分院完井工艺研究所 | Low-voltage electric cable test wellhead blowout preventor |
| WO2013163607A1 (en) * | 2012-04-27 | 2013-10-31 | Rohrback Cosasco Systems, Inc. | Magnetic retrieval tool |
| CN204040979U (en) * | 2014-08-11 | 2014-12-24 | 中国石油化工股份有限公司 | Hi-pot test well low frictional resistance logging cable sealer |
| CN104675357A (en) * | 2013-12-02 | 2015-06-03 | 中国石油化工股份有限公司 | Simple wellhead device and application method thereof |
| CN204804750U (en) * | 2015-07-16 | 2015-11-25 | 任丘市博鑫石油机械制造有限公司 | Cable blowout preventer |
| CN204804739U (en) * | 2015-06-01 | 2015-11-25 | 中国石油化工股份有限公司 | Oil pipe prevents gusher mouth pressure relief device |
| CN205172507U (en) * | 2015-12-10 | 2016-04-20 | 盘锦鸿海钻采技术发展有限公司 | Natural gas is annotated, is adopted well cable logging high pressure and prevents system of spouting |
Family Cites Families (1)
| Publication number | Priority date | Publication date | Assignee | Title |
|---|---|---|---|---|
| US8047295B2 (en) * | 2007-04-24 | 2011-11-01 | Fmc Technologies, Inc. | Lightweight device for remote subsea wireline intervention |
-
2016
- 2016-10-19 CN CN201610911934.XA patent/CN106368645B/en not_active Expired - Fee Related
Patent Citations (8)
| Publication number | Priority date | Publication date | Assignee | Title |
|---|---|---|---|---|
| CN2135642Y (en) * | 1992-09-01 | 1993-06-09 | 辽河石油勘探局茨榆坨采油厂 | Changeable rod sealing device |
| CN2286239Y (en) * | 1997-04-02 | 1998-07-15 | 中国石油天然气总公司石油勘探开发科学研究院廊坊分院完井工艺研究所 | Low-voltage electric cable test wellhead blowout preventor |
| WO2013163607A1 (en) * | 2012-04-27 | 2013-10-31 | Rohrback Cosasco Systems, Inc. | Magnetic retrieval tool |
| CN104675357A (en) * | 2013-12-02 | 2015-06-03 | 中国石油化工股份有限公司 | Simple wellhead device and application method thereof |
| CN204040979U (en) * | 2014-08-11 | 2014-12-24 | 中国石油化工股份有限公司 | Hi-pot test well low frictional resistance logging cable sealer |
| CN204804739U (en) * | 2015-06-01 | 2015-11-25 | 中国石油化工股份有限公司 | Oil pipe prevents gusher mouth pressure relief device |
| CN204804750U (en) * | 2015-07-16 | 2015-11-25 | 任丘市博鑫石油机械制造有限公司 | Cable blowout preventer |
| CN205172507U (en) * | 2015-12-10 | 2016-04-20 | 盘锦鸿海钻采技术发展有限公司 | Natural gas is annotated, is adopted well cable logging high pressure and prevents system of spouting |
Also Published As
| Publication number | Publication date |
|---|---|
| CN106368645A (en) | 2017-02-01 |
Similar Documents
| Publication | Publication Date | Title |
|---|---|---|
| CN110630204A (en) | Under-pressure operation equipment for gas drive injection well completion and under-pressure operation method thereof | |
| CN104389544A (en) | Reducing dual tubing oil recovery wellhead casing head | |
| CN103982154A (en) | Well casing recovery method | |
| CN202266242U (en) | Gas well pumping and raining device | |
| CN204944764U (en) | Preventer hermetic seal test unit | |
| CN103806878B (en) | Not kill-job of sea electric pump lifting technology tubing string | |
| CN103711452B (en) | A kind of gel slug packing well control method | |
| CN106368645B (en) | The Construction Method of Pressure Lifting and Lowering of Temperature Measuring Cable in SAGD Well | |
| CN206571459U (en) | Integral type operation device under pressure for oil-water well | |
| CN204646137U (en) | A kind of low-pressure gas well operation device under pressure | |
| CN118622219B (en) | Method and system for realizing completion operation of oil-gas well without well killing | |
| CN103790542A (en) | Coiled tubing suspension sealing device for testing under high-temperature belt pressure and using method | |
| CN204646172U (en) | Pressure sealing casing head can be repaired | |
| CN103939013A (en) | Integrated high-temperature pressure balance workover rig | |
| CN106285547B (en) | For SAGD well temperature measuring cable it is with pressure mention, under sealing device | |
| CN205189811U (en) | Sealed wellhead assembly | |
| CN104165032B (en) | An open coiled tubing injector and method of use thereof | |
| RU2533470C2 (en) | Procedure for recovery of tightness in flow strings | |
| CN103939047B (en) | A kind of annular preventer packing unit more changing device | |
| CN106593340B (en) | High-pressure shallow fully enclosed drilling plug device and its application method | |
| CN205243429U (en) | Edge natural gas well well head protection and mining devices | |
| CN206035436U (en) | Integrated wellhead assembly is adopted to marine notes | |
| CN104775764A (en) | Under-pressure operating device for low-pressure gas well | |
| CN105735945A (en) | Oil pumping device | |
| CN204212732U (en) | A kind of reducing formula dual tubing oil recovery casing head of well head |
Legal Events
| Date | Code | Title | Description |
|---|---|---|---|
| C06 | Publication | ||
| PB01 | Publication | ||
| SE01 | Entry into force of request for substantive examination | ||
| SE01 | Entry into force of request for substantive examination | ||
| GR01 | Patent grant | ||
| GR01 | Patent grant | ||
| CF01 | Termination of patent right due to non-payment of annual fee |
Granted publication date: 20190903 |