CN108963875A - The method of on-load migration 10KV overhead transmission line - Google Patents
The method of on-load migration 10KV overhead transmission line Download PDFInfo
- Publication number
- CN108963875A CN108963875A CN201810793550.1A CN201810793550A CN108963875A CN 108963875 A CN108963875 A CN 108963875A CN 201810793550 A CN201810793550 A CN 201810793550A CN 108963875 A CN108963875 A CN 108963875A
- Authority
- CN
- China
- Prior art keywords
- phase
- insulation
- electrician
- route
- bucket
- Prior art date
- Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
- Pending
Links
- 238000000034 method Methods 0.000 title claims abstract description 29
- 238000013508 migration Methods 0.000 title claims description 5
- 230000005012 migration Effects 0.000 title claims description 5
- 230000005540 biological transmission Effects 0.000 title claims 2
- 229910052573 porcelain Inorganic materials 0.000 claims abstract description 10
- 238000009413 insulation Methods 0.000 claims description 42
- 238000010276 construction Methods 0.000 claims description 14
- 239000012212 insulator Substances 0.000 claims description 8
- 239000004020 conductor Substances 0.000 claims description 4
- 230000000873 masking effect Effects 0.000 claims 10
- 238000009434 installation Methods 0.000 claims 4
- 238000012790 confirmation Methods 0.000 claims 3
- 210000000080 chela (arthropods) Anatomy 0.000 claims 2
- 238000009422 external insulation Methods 0.000 claims 1
- 238000012546 transfer Methods 0.000 abstract description 7
- WABPQHHGFIMREM-UHFFFAOYSA-N lead(0) Chemical compound [Pb] WABPQHHGFIMREM-UHFFFAOYSA-N 0.000 description 9
- 238000013461 design Methods 0.000 description 3
- 230000007547 defect Effects 0.000 description 2
- 230000003796 beauty Effects 0.000 description 1
- 230000009286 beneficial effect Effects 0.000 description 1
- 238000010586 diagram Methods 0.000 description 1
- 230000001681 protective effect Effects 0.000 description 1
- 230000000630 rising effect Effects 0.000 description 1
- 238000012360 testing method Methods 0.000 description 1
Classifications
-
- H—ELECTRICITY
- H02—GENERATION; CONVERSION OR DISTRIBUTION OF ELECTRIC POWER
- H02G—INSTALLATION OF ELECTRIC CABLES OR LINES, OR OF COMBINED OPTICAL AND ELECTRIC CABLES OR LINES
- H02G1/00—Methods or apparatus specially adapted for installing, maintaining, repairing or dismantling electric cables or lines
- H02G1/02—Methods or apparatus specially adapted for installing, maintaining, repairing or dismantling electric cables or lines for overhead lines or cables
- H02G1/04—Methods or apparatus specially adapted for installing, maintaining, repairing or dismantling electric cables or lines for overhead lines or cables for mounting or stretching
Landscapes
- Electric Cable Installation (AREA)
Abstract
本发明涉及一种带负荷迁移10KV架空线路的方法,该方法包括以下步骤:(1)、对作业范围内的带电体和接体进行绝缘遮蔽,(2)、安装临时负荷开关和引流电缆,(3)、对三相导线、横担、瓷瓶、杆顶支架及连接构件进行绝缘遮蔽,(4)、在疲迁移的线路两端的配电线路三相导线与临时引流电缆连接并绝缘遮蔽,(5)、将需要转移的三相引线两端钳断,(6)、迁移线路,(7)、分别连接好迁移线路与带电线路的三相引线,并绝缘遮蔽,(8)、拆除临时负荷开关和引流电缆。带负荷迁移10KV架空线路的方法,保证用户用电不间断,提高供电可靠性,提高供电企业经济效益。
The invention relates to a method for transferring a 10KV overhead line with load. The method comprises the following steps: (1), insulating and shielding the electrified body and the connecting body within the working range, (2), installing a temporary load switch and a drainage cable, (3) Insulate and shield the three-phase wires, cross arms, porcelain bottles, pole top brackets and connecting components. (4) Connect the three-phase wires of the distribution lines at both ends of the fatigued line to the temporary drainage cables and insulate and shield them. (5) Clamp off the two ends of the three-phase leads that need to be transferred, (6), transfer the lines, (7), connect the three-phase leads of the transfer lines and live lines, and insulate and shield them, (8), remove the temporary Load switch and drain cable. The method of transferring 10KV overhead lines with load ensures uninterrupted power consumption of users, improves the reliability of power supply, and improves the economic benefits of power supply enterprises.
Description
技术领域technical field
本发明涉及配电网中线路迁移的方法,具体地说是一种带负荷迁移10KV架空线路的方法。The invention relates to a method for transferring lines in a distribution network, in particular to a method for transferring 10KV overhead lines with load.
背景技术Background technique
配电网是直接面向用户的供电系统,为电力用户提供安全、可靠、经济、高效、洁净、可持续的电能。架空配电网络遍及城乡各个角落,且线路布置密集复杂,走廊狭窄。由于城乡规划的逐渐完善,良好的市容市貌越来越被人们所重视,政府不断加大棚户区等老旧建筑物的改造力度。正是由于建筑物的动迁以及市容市貌的美好,导致我们的架空配电网地理位置的早期规划设计在很多程度上影响城市规划的整体推进,这就需要我们重新规划设计架空配电网10KV线路的路径和线路走向。规划设计完成后的10KV架空线路路径走向,在迁移施工的过程中都采取停电作业的方式进行,运行人员需将10KV架空线路分支乃至整条10KV架空线路停电,然后在10KV架空线路无电的状态下将10KV架空线路迁移,由于大面积停电给广大居民的日常生活带来很多影响,同时也给机关单位及厂矿造成巨大的经济损失,给供电企业造成不必要的经济损失,影响供电可靠性,降低供电企业经济效益。The distribution network is a power supply system directly facing users, providing safe, reliable, economical, efficient, clean and sustainable electric energy for power users. The overhead power distribution network covers every corner of urban and rural areas, and the wiring layout is dense and complex, and the corridors are narrow. Due to the gradual improvement of urban and rural planning, people pay more and more attention to a good city appearance, and the government continues to increase efforts to transform old buildings such as shantytowns. It is precisely because of the relocation of buildings and the beauty of the city that the early planning and design of the geographic location of our overhead distribution network affects the overall advancement of urban planning to a large extent, which requires us to re-plan and design the overhead distribution network 10KV The path of the line and the direction of the line. After the completion of planning and design, the route of the 10KV overhead line will be carried out in the form of power outage during the relocation and construction. The operator needs to cut off the power of the branch of the 10KV overhead line or even the entire 10KV overhead line, and then in the state of no power on the 10KV overhead line The relocation of the 10KV overhead line will cause a lot of impacts on the daily life of the residents due to large-scale power outages. At the same time, it will also cause huge economic losses to government agencies, factories and mines, cause unnecessary economic losses to power supply companies, and affect the reliability of power supply. Reduce the economic benefits of power supply enterprises.
现在急需一种针对上述缺陷的带负荷迁移10KV架空线路的方法。There is an urgent need for a method for migrating 10KV overhead lines with load aimed at the above-mentioned defects.
发明内容Contents of the invention
本发明的目的是要提供一种带负荷迁移10KV架空线路的方法,该方法可以实现在用户不停电的情况下完成10KV架空线路的迁移施工,解决大面积停电给居民带来的不便及给厂矿和供电公司带来的经济损失。The purpose of the present invention is to provide a method for migrating 10KV overhead lines with load. This method can realize the migration construction of 10KV overhead lines without power failure for users, and solve the inconvenience caused by large-scale power outages to residents and to factories and mines. and the economic loss caused by the power supply company.
本发明的技术方案是:Technical scheme of the present invention is:
带负荷迁移10KV架空线路的方法,包括以下步骤:The method for transferring 10KV overhead lines with load includes the following steps:
(1)、将两台临时负荷开关由载重车分别运至被迁移线路两端现场,在被迁移整个线路的下方,每隔一定的距离安放一个绝缘滑轮支架,作为临时引流电缆的支架;(1) Two temporary load switches are transported to the site at both ends of the relocated line by trucks, and an insulating pulley bracket is placed at a certain distance under the entire relocated line as a bracket for temporary drainage cables;
(2)、将临时引流电缆运至施工现场,敷设在两台临时负荷开关之间,敷设电缆时,应注意防止临时引流电缆从支架上滑落而磨损电缆外绝缘,由地面作业人员登杆在电杆适当位置安装临时绝缘横担;(2) Transport the temporary drainage cable to the construction site and lay it between two temporary load switches. When laying the cable, care should be taken to prevent the temporary drainage cable from slipping off the bracket and wear the outer insulation of the cable. Temporary insulating cross-arms are installed at appropriate positions on the poles;
(3)、将三相临时引流电缆两端分别接至两台临时负荷开关上,连接完好后,分别在两连接处安装绝缘遮蔽罩,并检查两台临时负荷开关均在断开位置;(3) Connect the two ends of the three-phase temporary drainage cable to the two temporary load switches respectively. After the connection is complete, install insulating shields at the two connections, and check that the two temporary load switches are in the disconnected position;
(4)、斗内电工携带绝缘作业工具和遮蔽用具进入工作斗,并系好安全带,操作绝缘斗臂车进入带电作业区域,斗内电工按照由近至远、从带电体到接地体、从低到高的原则,分别对三相导线、横担、瓷瓶、杆顶支架及连接构件进行绝缘遮蔽;(4) The electrician in the bucket enters the work bucket with insulated work tools and shielding tools, fastens the safety belt, and operates the insulated bucket arm truck to enter the live working area. Insulate and shield the three-phase wires, cross-arms, porcelain bottles, pole-top brackets and connecting components from low to high;
(5)、地面电工利用绝缘绳和绝缘滑车分别将负荷开关三相引线传递给斗内电工,将三相引线固定在临时绝缘横担上,斗内电工按照由近及远的顺序安装好三相引线,三相引线分别安装在被迁移线路前段的配电线路三相导线上,应注意每安装好一相,就要对引线和导线的连接处恢复绝缘遮蔽;(5) The ground electrician transfers the three-phase lead wires of the load switch to the electrician in the bucket by using the insulating rope and the insulating pulley, and fixes the three-phase lead wires on the temporary insulating cross-arm, and the electrician in the bucket installs the three phases in order from near to far. The phase leads and the three-phase leads are respectively installed on the three-phase conductors of the distribution line in the front section of the relocated line. It should be noted that after each phase is installed, the insulation and shielding of the connection between the lead wires and the wires must be restored;
(6)、按照步骤⑤的方法,安装线路另一端的临时负荷开关的三相引线;(6) According to the method of step ⑤, install the three-phase leads of the temporary load switch at the other end of the line;
(7)、将两台临时负荷开关合上,用钳形电流表测量三相引线上的电流,确认负荷已转移到临时引流电缆上;(7) Close the two temporary load switches, measure the current on the three-phase leads with a clamp ammeter, and confirm that the load has been transferred to the temporary drainage cable;
(8)、斗内电工按照由远及近的顺序分别钳断被迁移线路的三相引线,钳断时,应采取措施防止引线断头搭接到别的带电部件或接地构件上,钳断后,对带电部分应迅速进行绝缘遮蔽,按照此方法,断开被迁移线路另一端的引线;(8) The electrician in the bucket clamps off the three-phase lead wires of the transferred line in order from far to near. , the live parts should be quickly insulated and shielded. According to this method, disconnect the lead wire at the other end of the transferred line;
(9)、地面电工进行迁移线路的施工(包括立线路电杆、安装横担、安装绝缘子、敷设三相导线等) ;(9) Ground electricians carry out the construction of the relocated lines (including erecting line poles, installing cross-arms, installing insulators, laying three-phase wires, etc.);
(10)、绝缘斗臂车转移至已经迁移后的线路一端电杆处的合适位置固定好,斗内电工控制绝缘斗至合适位置,按照由近至远、从带电体到接地体、从低到高的原则,分别对三相导线、横担、瓷瓶、杆顶支架及连接构件进行绝缘遮蔽;(10) The insulated bucket arm truck is transferred to a suitable position at the pole at one end of the line after it has been moved and fixed, and the electrician in the bucket controls the insulating bucket to a suitable position, according to the order from near to far, from the electrified body to the grounding body, from the low Insulate and shield the three-phase conductors, cross-arms, porcelain bottles, pole-top brackets and connecting components, respectively;
按照由近至远的顺序,分别连接好迁移后线路与带电线路的三相引线,应注意每连接一相时,只拆除该相的绝缘遮蔽用具,确认连接完好后,迅速对该相的导线、引线、瓷瓶等恢复绝缘遮蔽;According to the order from near to far, respectively connect the three-phase lead wires of the relocated line and the live line. It should be noted that when connecting a phase, only remove the insulation and shielding equipment of this phase. , lead wires, porcelain bottles, etc. to restore insulation shielding;
三相引线连接完毕后,按照由远及近、由上到下的顺序,拆除这一端线杆上的所有绝缘遮蔽用具;After the three-phase leads are connected, remove all insulation and shielding appliances on the pole at this end in the order from far to near and from top to bottom;
(11)、按照步骤(10)的方法,完成已经迁移后的线路另一端的引线连接工作,检查确认连接完好、通流正常后,拆除该端线杆上的所有绝缘遮蔽用具;(11) According to the method of step (10), complete the lead wire connection work at the other end of the migrated line. After checking and confirming that the connection is intact and the flow is normal, remove all insulation and shielding appliances on the pole at this end;
(12)、地面电工分别断开两台临时负荷开关,解开临时负荷开关与临时引流电缆的连接,回收临时引流电缆;(12) The ground electrician disconnects the two temporary load switches respectively, loosens the connection between the temporary load switch and the temporary drainage cable, and recovers the temporary drainage cable;
(13)、绝缘斗臂车转移至带电线路与临时负荷开关的引线连接处,斗内电工转移绝缘斗至合适位置,按照由远至近的顺序分别拆除临时负荷开关的三相引线,同时,按照由远及近、由上到下的顺序,拆除这一端线杆上的所有绝缘遮蔽用具及临时绝缘横担按照上述方法,绝缘斗臂车转移至带电线路另一端固定好,拆除该端的临时负荷开关的三相引线,同时拆除这一端线杆上的所有绝缘遮蔽用具及临时绝缘横担,完工后斗内电工回到地面,收起绝缘斗臂车,工作结束,工作班撤离作业现场。(13) The insulated bucket arm truck is transferred to the connection between the live line and the lead wire of the temporary load switch. The electrician in the bucket moves the insulating bucket to a suitable position, and removes the three-phase lead wires of the temporary load switch in order from far to near. At the same time, according to From far to near, from top to bottom, remove all insulation shielding appliances and temporary insulation cross-arms on the pole at this end. According to the above method, transfer the insulating arm truck to the other end of the live line and fix it, and remove the temporary load at this end. The three-phase leads of the switch should be removed at the same time from all insulation shielding appliances and temporary insulation cross-arms on the pole at this end. After the completion of the work, the electrician in the bucket returned to the ground, put away the insulation bucket truck, and the work was completed, and the work team was evacuated from the work site.
本发明的有益效果:Beneficial effects of the present invention:
本发明带负荷迁移10KV架空线路的方法不受供电可靠性局限,不影响对用户正常供电,可以实现带负荷且不停电的情况下迁移10KV架空线路。如遇供电可靠性要求较高的用户无法停电迁移10KV架空线路时,依然可以实现10KV架空线路迁移的施工作业,增加经济效益,提高供电可靠性。The method for transferring 10KV overhead lines with load in the present invention is not limited by the reliability of power supply, does not affect the normal power supply to users, and can realize the transfer of 10KV overhead lines with load and without power failure. If users with high power supply reliability requirements cannot relocate 10KV overhead lines due to power outage, the construction work of 10KV overhead line relocation can still be realized, increasing economic benefits and improving power supply reliability.
附图说明Description of drawings
图1为本发明所示加装分段开关的10KV线路的结构示意图。Fig. 1 is a structural schematic diagram of a 10KV line equipped with a section switch as shown in the present invention.
具体实施方式Detailed ways
为了解决现有技术中存在的缺陷,发明人设计了利用绝缘手套作业法的一种带负荷迁移10KV架空线路的方法。这样可以不停电迁移10KV架空线路,不会给电力用户造成损失,也不会给供电企业造成经济损失,提高供电可靠性,提高经济效益。In order to solve the defects in the prior art, the inventor has designed a method for transferring 10KV overhead lines under load using the insulating glove method. In this way, the 10KV overhead line can be migrated without power failure, without causing losses to power users or power supply companies, improving power supply reliability and economic benefits.
下面结合附图对本发明作进一步详述:Below in conjunction with accompanying drawing, the present invention is described in further detail:
如图所示,带负荷迁移10KV架空线路的方法包括以下步骤:As shown in the figure, the method for migrating 10KV overhead lines with load includes the following steps:
(1)、开工前,进行现场实地勘察,制定详细的施工方案,并通过学习,使参加施工的人员明确具体的施工步骤、具体分工和安全注意事项。(1) Before starting construction, conduct on-site surveys, formulate detailed construction plans, and through learning, make the personnel participating in the construction clear about the specific construction steps, specific division of labor and safety precautions.
(2)、全体工作人员到达工作现场,布置安全护栏和作业标志,绝缘斗臂车1进入被迁移线路的一端,定位于最佳工作位置(三相导线9接引点2下方)并装好接地线,选定工作斗的升降方向,注意避开附近高低压线及障碍物。(2) All staff arrive at the work site, arrange safety guardrails and work signs, insulated bucket arm truck 1 enters one end of the moved line, locates at the best working position (below the connection point 2 of the three-phase wire 9) and installs it Grounding wire, select the lifting direction of the working bucket, and pay attention to avoid nearby high and low voltage lines and obstacles.
(3)、将两台临时负荷开关3由载重车分别运至被迁移线路两端现场。在被迁移整个线路的下方,每隔一定的距离安放一个绝缘支架4,作为临时引流电缆5的支架。(3) Transport the two temporary load switches 3 to the site at both ends of the relocated line respectively by the truck. Below the entire circuit being moved, an insulating support 4 is placed at regular intervals as a support for the temporary drainage cable 5 .
(4)、临时引流电缆5运至施工现场,敷设在两台临时负荷开关之间。敷设电缆时,应注意防止临时引流电缆从绝缘支架上滑落而磨损电缆外绝缘。由地面作业人员登杆在电杆6适当位置安装临时绝缘横担7。(4) The temporary drainage cable 5 is transported to the construction site and laid between two temporary load switches. When laying the cables, care should be taken to prevent the temporary drainage cables from slipping off the insulating support and wearing out the outer insulation of the cables. Temporary insulating cross-arm 7 is installed at the appropriate position of electric pole 6 by the ground operator boarding the pole.
(5)、将三相临时引流电缆两端分别接至两台临时负荷开关上。连接完好后,分别在两连接处安装绝缘遮蔽罩,并检查两台临时负荷开关均在断开位置。(5) Connect the two ends of the three-phase temporary drainage cable to two temporary load switches respectively. After the connection is complete, install insulating shields at the two connections, and check that the two temporary load switches are in the disconnected position.
(6)、工作斗中电工操作前检查绝缘防护用具、绝缘工具、安全用具及辅助器具,对绝缘工具使用兆欧表或绝缘测试仪进行分段检测,绝缘阻值不低于 700 兆欧 ;斗中电工,穿戴上绝缘靴、绝缘服(披肩)、绝缘安全帽和绝缘手套等全套绝缘防护用具。斗内电工携带绝缘作业工具和遮蔽用具进入工作斗,工具和遮蔽用具应分类放在斗中和工具袋中,并系好安全带。两名斗内电工经工作负责人许可后,分别操作绝缘斗臂车,进入带电作业区域 ;绝缘斗移动应平稳匀速,在进入带电作业区域时应无大幅晃动现象,绝缘斗下降、上升的速度不应超过 0.5m/s,绝缘斗边沿的最大线速度不应超过0.5m/s ;在工作斗上升过程中,对可能触及范围内的高低压带电部件需进行绝缘遮蔽。(6) The electrician in the work bucket shall check the insulation protection equipment, insulation tools, safety equipment and auxiliary equipment before operation, and use a megohmmeter or insulation tester to conduct segmental testing on the insulation tools, and the insulation resistance shall not be less than 700 megohms; Douzhong electricians should wear a full set of insulating protective equipment such as insulating boots, insulating clothing (shawl), insulating helmets and insulating gloves. The electrician in the bucket enters the working bucket with insulated work tools and shielding appliances. The tools and shielding appliances should be placed in the bucket and tool bag by category, and the safety belt should be fastened. After being approved by the person in charge of the work, two electricians in the bucket respectively operate the insulated bucket arm truck and enter the live working area; the movement of the insulating bucket should be stable and uniform, and there should be no large shaking when entering the live working area. It should not exceed 0.5m/s, and the maximum linear speed at the edge of the insulating bucket should not exceed 0.5m/s; during the rising process of the working bucket, the high and low voltage live parts within the possible reach should be insulated and shielded.
(7)、工作斗定位在合适的工作位置后,首先对离身体最近的边相导线安装导线遮蔽罩,套入的导线遮蔽罩的开口要向下方,并拉到靠近绝缘子的边缘处,用绝缘夹夹紧防止脱落。绝缘遮蔽组合的重叠距离不得小于 15cm。按照由近至远、从带电体到接地体、从低到高的原则,采用以上同样遮蔽方式,分别对三相导线、横担、瓷瓶、杆顶支架及连接构件进行绝缘遮蔽。(7) After the working bucket is positioned at a suitable working position, first install a wire shielding cover on the side phase wire closest to the body. The opening of the inserted wire shielding cover should face downward and be pulled to the edge of the insulator. Insulation clips clamp to prevent falling off. The overlapping distance of insulation shielding combination shall not be less than 15cm. According to the principle of from near to far, from electrified body to grounding body, from low to high, use the same shielding method as above to insulate and shield the three-phase wires, cross arms, porcelain bottles, pole top brackets and connecting components respectively.
(8)、地面电工利用绝缘绳和绝缘滑车分别将负荷开关三相引线8传递给斗内电工,将三相引线固定在临时绝缘横担上,斗内电工按照由近及远的顺序安装好三相引线,三相引线分别安装在被迁移线路前段的配电线路三相导线9上。应注意每安装好一相,就要对引线和导线的连接处恢复绝缘遮蔽。(8) The electrician on the ground transfers the three-phase leads 8 of the load switch to the electrician in the bucket respectively by using insulating ropes and insulating pulleys, and fixes the three-phase leads on the temporary insulating cross-arm, and the electrician in the bucket installs them in order from near to far The three-phase leads are respectively installed on the three-phase conductors 9 of the distribution line at the front section of the moved line. It should be noted that every time a phase is installed, the insulation and shielding of the connection between the lead wire and the wire must be restored.
(9)、按照步骤⑧的方法,安装线路另一端的临时负荷开关的三相引线。(9) According to the method of step ⑧, install the three-phase leads of the temporary load switch at the other end of the line.
(10)、合上两台临时负荷开关,用钳形电流表测量三相引线上的电流,确认负荷已转移到临时引流电缆上。(10) Close the two temporary load switches, measure the current on the three-phase leads with a clamp ammeter, and confirm that the load has been transferred to the temporary drainage cable.
斗内电工按照由远及近的顺序分别钳断被迁移线路的三相引线。钳断时,应采取措施防止引线断头搭接到别的带电部件或接地构件上。钳断后,对带电部分应迅速进行绝缘遮蔽。The electrician in Dounei respectively clamps off the three-phase leads of the transferred line in order from far to near. When the clamp is broken, measures should be taken to prevent the broken end of the lead wire from lapping to other live parts or grounding components. After the clamp is broken, the live parts should be quickly insulated and shielded.
(11)、按照步骤⑩的方法,断开被迁移线路另一端的引线。地面电工进行迁移线路的施工(包括立线路直杆、安装横担、安装绝缘子、敷设三相导线等)。(11) According to the method of step ⑩, disconnect the lead wire at the other end of the transferred line. The ground electrician will carry out the construction of the relocated line (including erecting the straight pole of the line, installing the cross arm, installing insulators, laying three-phase wires, etc.).
(12)、绝缘斗臂车转移至已经迁移后的线路一端电杆处的合适位置固定好,斗内电工控制绝缘斗至合适位置,按照由近至远、从带电体到接地体、从低到高的原则,分别对三相导线、横担、瓷瓶、杆顶支架及连接构件进行绝缘遮蔽。(12) Transfer the insulated bucket arm truck to a suitable position at the electric pole at one end of the line after it has been moved and fix it. The electrician in the bucket controls the insulating bucket to a suitable position. Insulation and shielding of the three-phase wires, cross arms, porcelain bottles, pole top brackets and connecting components are carried out in accordance with the high principle.
按照由近至远的顺序,分别连接好迁移后线路与带电线路的三相引线。应注意每连接一相时,只拆除该相的绝缘遮蔽用具,确认连接完好后,迅速对该相的导线、引线、瓷瓶等恢复绝缘遮蔽。In the order from near to far, respectively connect the three-phase leads of the migrated line and the live line. It should be noted that every time a phase is connected, only the insulation shielding equipment of that phase is removed, and after confirming that the connection is intact, the insulation shielding of the wires, lead wires, porcelain bottles, etc. of the phase is quickly restored.
三相引线连接完毕后,按照由远及近、由上到下的顺序,拆除这一端线杆上的所有绝缘遮蔽用具。After the three-phase leads are connected, remove all insulation and shielding appliances on the pole at this end in the order from far to near and from top to bottom.
(13)、按照(12)步骤的方法,完成已经迁移后的线路另一端的引线连接工作,检查确认连接完好、通流正常后,拆除该端线杆上的所有绝缘遮蔽用具及临时绝缘横担。(13) According to the method in (12), complete the lead wire connection at the other end of the relocated line. After checking and confirming that the connection is intact and the flow is normal, remove all insulation shielding appliances and temporary insulation cross-arms on the pole at this end .
地面电工分别断开两台临时负荷开关,解开临时负荷开关与临时引流电缆的连接,回收临时引流电缆。The ground electrician disconnected the two temporary load switches respectively, untied the connection between the temporary load switch and the temporary drainage cable, and recovered the temporary drainage cable.
绝缘斗臂车转移至带电线路与临时负荷开关的引线连接处,斗内电工转移绝缘斗至合适位置,按照由远至近的顺序分别拆除临时负荷开关的三相引线,同时,按照由远及近、由上到下的顺序,拆除这一端线杆上的所有绝缘遮蔽用具。The insulated bucket arm truck is transferred to the connection between the live line and the lead wire of the temporary load switch. 1. From top to bottom, remove all insulation and shielding appliances on the pole at this end.
(14)、按照步骤(13)的方法,绝缘斗臂车转移至带电线路另一端固定好,拆除该端的临时负荷开关的三相引线,同时拆除这一端线杆上的所有绝缘遮蔽用具及临时绝缘横担。完工后斗内电工回到地面,收起绝缘斗臂车。(14) According to the method of step (13), the insulated bucket arm truck is transferred to the other end of the live line and fixed, and the three-phase lead wire of the temporary load switch at this end is removed, and all insulation shielding appliances and temporary wires on the pole at this end are removed at the same time Insulated cross arm. After the completion of the work, the electrician in the bucket returned to the ground and put away the insulated bucket truck.
(15)、清理施工现场,工作负责人全面检查工作完成情况。(15) Clean up the construction site, and the person in charge of the work will comprehensively check the completion of the work.
Claims (1)
Priority Applications (1)
| Application Number | Priority Date | Filing Date | Title |
|---|---|---|---|
| CN201810793550.1A CN108963875A (en) | 2018-07-19 | 2018-07-19 | The method of on-load migration 10KV overhead transmission line |
Applications Claiming Priority (1)
| Application Number | Priority Date | Filing Date | Title |
|---|---|---|---|
| CN201810793550.1A CN108963875A (en) | 2018-07-19 | 2018-07-19 | The method of on-load migration 10KV overhead transmission line |
Publications (1)
| Publication Number | Publication Date |
|---|---|
| CN108963875A true CN108963875A (en) | 2018-12-07 |
Family
ID=64481716
Family Applications (1)
| Application Number | Title | Priority Date | Filing Date |
|---|---|---|---|
| CN201810793550.1A Pending CN108963875A (en) | 2018-07-19 | 2018-07-19 | The method of on-load migration 10KV overhead transmission line |
Country Status (1)
| Country | Link |
|---|---|
| CN (1) | CN108963875A (en) |
Cited By (4)
| Publication number | Priority date | Publication date | Assignee | Title |
|---|---|---|---|---|
| CN111817203A (en) * | 2020-07-08 | 2020-10-23 | 国网福建省电力有限公司宁德供电公司 | Distribution network high voltage emergency interface and its working method |
| CN113889900A (en) * | 2021-08-30 | 2022-01-04 | 国网浙江省电力有限公司嘉兴供电公司 | Construction method for live migration strain tower and wire of distribution network |
| CN114301003A (en) * | 2021-11-24 | 2022-04-08 | 国网浙江省电力有限公司舟山供电公司 | A load transfer method for flexible cables between adjacent tension towers |
| CN115085080A (en) * | 2022-04-22 | 2022-09-20 | 广东德睿电气科技发展有限公司 | Operation method for replacing 10kv disconnecting switch under load |
Citations (3)
| Publication number | Priority date | Publication date | Assignee | Title |
|---|---|---|---|---|
| JP2002010418A (en) * | 2000-06-23 | 2002-01-11 | Fujikura Ltd | Power supply vehicles and low-voltage customers uninterrupted high-voltage distribution line construction method |
| CN101471548A (en) * | 2007-12-28 | 2009-07-01 | 大原电机株式会社 | Uninterrupted replacement method of concrete utility pole for distribution line using pole clamp and pole crusher |
| CN102122805A (en) * | 2010-12-28 | 2011-07-13 | 徐州海伦哲专用车辆股份有限公司 | Vehicular carrying and working system special for bypass live working device |
-
2018
- 2018-07-19 CN CN201810793550.1A patent/CN108963875A/en active Pending
Patent Citations (3)
| Publication number | Priority date | Publication date | Assignee | Title |
|---|---|---|---|---|
| JP2002010418A (en) * | 2000-06-23 | 2002-01-11 | Fujikura Ltd | Power supply vehicles and low-voltage customers uninterrupted high-voltage distribution line construction method |
| CN101471548A (en) * | 2007-12-28 | 2009-07-01 | 大原电机株式会社 | Uninterrupted replacement method of concrete utility pole for distribution line using pole clamp and pole crusher |
| CN102122805A (en) * | 2010-12-28 | 2011-07-13 | 徐州海伦哲专用车辆股份有限公司 | Vehicular carrying and working system special for bypass live working device |
Cited By (4)
| Publication number | Priority date | Publication date | Assignee | Title |
|---|---|---|---|---|
| CN111817203A (en) * | 2020-07-08 | 2020-10-23 | 国网福建省电力有限公司宁德供电公司 | Distribution network high voltage emergency interface and its working method |
| CN113889900A (en) * | 2021-08-30 | 2022-01-04 | 国网浙江省电力有限公司嘉兴供电公司 | Construction method for live migration strain tower and wire of distribution network |
| CN114301003A (en) * | 2021-11-24 | 2022-04-08 | 国网浙江省电力有限公司舟山供电公司 | A load transfer method for flexible cables between adjacent tension towers |
| CN115085080A (en) * | 2022-04-22 | 2022-09-20 | 广东德睿电气科技发展有限公司 | Operation method for replacing 10kv disconnecting switch under load |
Similar Documents
| Publication | Publication Date | Title |
|---|---|---|
| CN108963875A (en) | The method of on-load migration 10KV overhead transmission line | |
| EP2849296B1 (en) | Live conductor stringing and splicing method and apparatus | |
| KR101103553B1 (en) | Uninterrupted Bypass Method for Distribution Lines Using Insulating Guiders for Space Maintenance | |
| CN203734209U (en) | Live working device for cable bypass | |
| CN108808556A (en) | A kind of electrical verification for power distribution line maintenance is grounded integrated apparatus | |
| CN109217151A (en) | Electric substation's installation engineering method | |
| CN102931609B (en) | On-load changes the operational method of 10kV fuse switch | |
| CA2864485C (en) | Apparatus and method for harvesting power from an overhead transmission conductor | |
| CN101277002B (en) | Method for construction of charged assembling 10kV bi-gyrus distribution line concrete lever | |
| CN102664358B (en) | Live replacement method for static contact of 220 kV flexible busbar | |
| CN107482535A (en) | The Method of Installing Segment Switch on Straight Rod of 10KV Line with Load Breaking | |
| US12388244B2 (en) | Method for replacing sections of electrically conductive phases in a DC two phase power system | |
| CN114725827A (en) | 10kV line live-line breaker live-line voltage transformer disconnection and connection operation method | |
| Benato et al. | Sequence impedances of insulated cables: Measurements versus computations | |
| CN110380340B (en) | Substation power distribution device | |
| CN106410674A (en) | Hot-line work method for 10-kV distribution line and equipment | |
| Christoforidis et al. | Interference analysis from medium-voltage cables of photovoltaic plants to metallic pipelines | |
| CN204886167U (en) | The grounding unit of the lightning protection grounding system of the outdoor optical handover equipment of the TD-LTE network | |
| CN115377862A (en) | A bypass cable fixing operation method | |
| CN102496899A (en) | 10 KV dropping fuse cable electricity testing ground wire | |
| CN103354325A (en) | Method for changing load switch in on-load manner | |
| Charalambous et al. | Modelling and assessment of short-term electromagnetic interference on a railway system from pole-to-ground faults on HVDC cable networks | |
| CN203387140U (en) | Equipotential direct-current-loaded electrified ice melting device | |
| CN208092173U (en) | A kind of singlephase earth fault positioning auxiliary device | |
| Ma et al. | Safety analysis of fence installation on a large power station concerning inductive and conductive coupling from nearby transmission lines |
Legal Events
| Date | Code | Title | Description |
|---|---|---|---|
| PB01 | Publication | ||
| PB01 | Publication | ||
| SE01 | Entry into force of request for substantive examination | ||
| SE01 | Entry into force of request for substantive examination | ||
| WD01 | Invention patent application deemed withdrawn after publication |
Application publication date: 20181207 |
|
| WD01 | Invention patent application deemed withdrawn after publication |