CN109873409A - A fault-recovery reconstruction method for distribution network - Google Patents

A fault-recovery reconstruction method for distribution network Download PDF

Info

Publication number
CN109873409A
CN109873409A CN201910278987.6A CN201910278987A CN109873409A CN 109873409 A CN109873409 A CN 109873409A CN 201910278987 A CN201910278987 A CN 201910278987A CN 109873409 A CN109873409 A CN 109873409A
Authority
CN
China
Prior art keywords
fault
load
line
network
value
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Pending
Application number
CN201910278987.6A
Other languages
Chinese (zh)
Inventor
施加腾
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
China Jiliang University
Original Assignee
China Jiliang University
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by China Jiliang University filed Critical China Jiliang University
Priority to CN201910278987.6A priority Critical patent/CN109873409A/en
Publication of CN109873409A publication Critical patent/CN109873409A/en
Pending legal-status Critical Current

Links

Landscapes

  • Data Exchanges In Wide-Area Networks (AREA)

Abstract

本发明公开了一种配电网故障恢复性重构方法,包括以下步骤:A、读取电网故障信息,定位故障点;B、根据整数型环网编码策略对非故障区网络进行编码,获取非故障区网络编码;C、故障隔离,对非故障区恢复供电;D、对故障区的网络编码进行初始化的编码分别对所述整数编码型量子负荷值群中的每个负荷值的解进行有效性判断,以对解有效的负荷值进行优化更新;E、获取故障恢复性重构开关组合,恢复电网数据,该系统设计合理,可以快速的找到系统的故障所在,将故障进行隔离,并且可以快速的优化以及恢复电网系统。

The invention discloses a fault-recovery reconstruction method for a distribution network, comprising the following steps: A. reading power grid fault information, and locating the fault point; B. coding a non-fault area network according to an integer ring network coding strategy, and obtaining Network coding for non-faulty areas; C. Fault isolation, restoring power supply to non-faulty areas; D. Coding for initializing the network coding of faulty areas Perform the solution of each load value in the integer-encoded quantum load value group respectively. Validity judgment to optimize and update the effective load value of the solution; E. Obtain fault recovery reconfiguration switch combination and restore power grid data. The system design is reasonable, can quickly find the fault of the system, isolate the fault, and The grid system can be optimized and restored quickly.

Description

A kind of restorative reconstructing method of distribution network failure
Technical field
The present invention relates to distribution network failure recovery technology field, specially a kind of restorative reconstructing method of distribution network failure.
Background technique
Power distribution network reconfiguration is to pass through interconnection switch and block switch in change system in the case where meeting power distribution network operation constraint Opening and closing assembled state network topology structure is switched over, the transfer load between different feeder lines, to influence network trend Distribution achievees the purpose that the network optimization is run.By emphasis difference, it is divided into static network optimal reconfiguration and fault recovery substantially Reconstruct.Static optimization reconstruct by optimization network structure, reaches system active loss minimum, improves the mesh of power supply reliability 's.
And fault recovery reconstruct be after power distribution network breaks down and quickly isolates failure, in the case where meeting certain condition, In order to reduce power failure area to the network structure regulation of customer power supply as far as possible, weight restores electricity after a failure, and emphasis is not Together.Power distribution network is usually open loop operation, and looped network design structure has the characteristics that radial feeder line, and permanent fault occurs and is isolated Afterwards, power distribution network is forced to be divided into service area and power loss area two parts, and fault recovery reconstruct is main to consider operation interconnection switch to mistake Electric area's network carries out restorative power supply.
Distribution network restoration reconstruct is an integer type combinatorial optimization problem, and solve the problems, such as this at present mainly has method: Mathematical programming approach, heuristic search method and intelligent algorithm.Mathematical programming approach has Global Optimality, but ties up in power distribution network After number increases, often solve difficult.Heuristic search algorithm.After Complicated Distribution Network breaks down, the interrelated spy in region Property will lead to heuristic rule and be difficult to be formed.Intelligent algorithm is good at solving hyperspace optimization problem, is widely used in Network optimization problem.A large amount of invalid infeasible solutions can be generated using simple binary coded form, in searching process, reduced Fault recovery efficiency.
Searching efficiency will be greatly improved by seeking better optimizing algorithm in the restorative reconstruct of distribution network failure, for improving It is particularly important to reconstruct efficiency.Load value group algorithm has obtained widely answering as completely new Swarm Intelligence Algorithm, in many fields With compared with traditional evolution algorithm such as genetic algorithm, load value group algorithm uses biocenose shared information strategy, convergence speed The characteristics of degree is fast, and especially at the initial stage of evolution, adjustable parameter is few, simple and easy, easily reaches global optimum.Binary system load Value group algorithm generates a large amount of infeasible solutions in reconstruct, causes to reconstruct low efficiency, and traditional load value group algorithm is after evolution Phase easily falls into locally optimal solution or falls into dead state.The restorative reconstruction and optimization model of traditional distribution network failure is to switch behaviour Make the minimum simple target of number, but often have ignored the smallest index of network active loss, not can guarantee and economically obtain To optimal restorative reconfiguration scheme.
Summary of the invention
The purpose of the present invention is to provide a kind of restorative reconstructing methods of distribution network failure, to solve in above-mentioned background technique The problem of proposition.
To achieve the above object, the invention provides the following technical scheme: A, reading electric network fault information, fault point;
B, non-faulting area network is encoded according to integer type looped network coding strategy, obtains non-faulting area network code;
C, Fault Isolation restores electricity to non-faulting area;
D, the coding initialized to the network code of faulty section is respectively to the integer coding type quantum load value group In the solution of each load value carry out Effective judgement, to optimize update to solving effective load value;
E, it obtains fault recovery and reconstructs switch combination, restore electric network data.
Preferably, whether the redundancy capacity value for detecting route according to step B is greater than line load, when the redundancy of route Capability value is not more than line load, the inadequate route of computer redundancy capacity its therewith needed for load difference, select extended link superfluous Covolume amount minimum value maximum route finds out the load section for being greater than required load on route, calculates its load value, select this section of load Bar is closed with what this extended link was associated, selects the maximum route of redundancy capacity minimum value, when route is not required maximum Load will be made whether that being greater than extended link of the redundancy capacity greater than zero detects, and when route is required peak load, will open Selected data calculates selected data value.
Preferably, the interconnection switch of non-faulting area network is numbered with natural number according to step B, and to each interconnection switch Corresponding looped network is individually numbered, and the number of the interconnection switch indicates the dimension of load value, is disconnected in each looped network The number of switch is every one-dimensional element of load value.
Preferably, the local optimum position for solving invalid load value is set as by constant according to step D, by local optimum position It is updated to the current location of the load value, according to the adaptive value of the effective load value of seismic responses calculated solution, according to adaptive value New location updating is the position of the coding by the new position that the coding is calculated separately according to integer coding algorithm.
Preferably, according to step E by new location updating be the coding position after restore power grid coded data again, and Coded data is optimized.
Compared with prior art, the beneficial effects of the present invention are:
System design rationally, can quickly find the guilty culprit of system, failure is isolated, and can be fast The optimization and recovery network system of speed.
Detailed description of the invention
Fig. 1 is the restorative reconstruct flow chart of distribution network failure of the present invention;
Fig. 2 is the restorative reconfigurable circuit overhaul flow chart of distribution network failure of the present invention.
Specific embodiment
Following will be combined with the drawings in the embodiments of the present invention, and technical solution in the embodiment of the present invention carries out clear, complete Site preparation description, it is clear that described embodiments are only a part of the embodiments of the present invention, instead of all the embodiments.It is based on Embodiment in the present invention, it is obtained by those of ordinary skill in the art without making creative efforts every other Embodiment shall fall within the protection scope of the present invention.
The present invention provides a kind of technical solution referring to FIG. 1-2: a kind of restorative reconstructing method of distribution network failure, special Sign is: the following steps are included:
A, electric network fault information, fault point are read;
B, non-faulting area network is encoded according to integer type looped network coding strategy, obtains non-faulting area network code;
C, Fault Isolation restores electricity to non-faulting area;
D, the coding initialized to the network code of faulty section is respectively to the integer coding type quantum load value group In the solution of each load value carry out Effective judgement, to optimize update to solving effective load value;
E, it obtains fault recovery and reconstructs switch combination, restore electric network data.
Whether the redundancy capacity value of detection route is greater than line load, when the redundancy capacity value of route is negative no more than route Lotus, the inadequate route of computer redundancy capacity its therewith needed for load difference, select extended link redundancy capacity minimum value max line Road finds out the load section for being greater than required load on route, calculates its load value, select this section of load and be associated with this extended link Close bar, select the maximum route of redundancy capacity minimum value, when route is not required peak load, will be made whether to be greater than Extended link of the redundancy capacity greater than zero detects, and when route is required peak load, will open selected data, calculates selected Data value.
The interconnection switch of non-faulting area network is numbered with natural number, and looped network corresponding to each interconnection switch is carried out Individually number, the number of the interconnection switch indicate the dimension of load value, and the number of the switch disconnected in each looped network is load Every one-dimensional element of value.
The local optimum position for solving invalid load value is set as constant, is the load value by local optimum location updating Current location, according to the adaptive value of the effective load value of seismic responses calculated solution, according to adaptive value according to integer coding algorithm New location updating is the position of the coding by the new position for calculating separately the coding.
By new location updating to restore power grid coded data behind the position of the coding again, and coded data is carried out excellent Change, system design rationally, can quickly find the guilty culprit of system, failure is isolated, and can be quick Optimization and recovery network system.
The beneficial effects of the present invention are: system design is rationally, the guilty culprit of system can be quickly found, by failure It is isolated, and quickly can optimizes and restore network system.
It although an embodiment of the present invention has been shown and described, for the ordinary skill in the art, can be with A variety of variations, modification, replacement can be carried out to these embodiments without departing from the principles and spirit of the present invention by understanding And modification, the scope of the present invention is defined by the appended.

Claims (5)

1.一种配电网故障恢复性重构方法,其特征在于:包括以下步骤:1. A fault recovery reconstruction method for distribution network, characterized in that: comprising the following steps: A、读取电网故障信息,定位故障点;A. Read the grid fault information and locate the fault point; B、根据整数型环网编码策略对非故障区网络进行编码,获取非故障区网络编码;B. Encode the non-faulty area network according to the integer ring network coding strategy, and obtain the non-faulty area network code; C、故障隔离,对非故障区恢复供电;C. Fault isolation, restore power to non-fault areas; D、对故障区的网络编码进行初始化的编码分别对所述整数编码型量子负荷值群中的每个负荷值的解进行有效性判断,以对解有效的负荷值进行优化更新;D. The coding for initializing the network coding of the fault area respectively judges the validity of the solution of each load value in the integer-coded quantum load value group, so as to optimize and update the valid load value of the solution; E、获取故障恢复性重构开关组合,恢复电网数据。E. Obtain fault-recovery reconfiguration switch combinations to restore power grid data. 2.根据权利要求1所述的一种配电网故障恢复性重构方法,其特征在于:所述根据步骤B检测线路的冗余容量值是否大于线路负荷,当线路的冗余容量值不大于线路负荷,计算机冗余容量不够线路其与之所需负荷差值,选择延伸线路冗余容量最小值最大线路,找出线路上大于所需负荷的负荷段,计算其负荷值,选出这段负荷与此延伸线路相联系的合上杆,选出冗余容量最小值最大的线路,当线路不是所需的最大负荷,将进行是否大于冗余容量大于零的延伸线路检测,当线路是所需的最大负荷,将打开所选数据,计算所选的数据值。2 . The method for reconfiguring power distribution network fault recovery according to claim 1 , wherein: according to step B, it is detected whether the redundant capacity value of the line is greater than the line load, and when the redundant capacity value of the line is not equal to the line load. 3 . If the line load is larger than the line load, the computer redundancy capacity is not enough, and the difference between the line and the required load, select the minimum and maximum line of the redundant capacity of the extended line, find out the load section on the line that is larger than the required load, calculate its load value, and select this line. Section load is connected to the closing rod of this extended line, and selects the line with the largest minimum redundant capacity. When the line is not the required maximum load, it will check whether the extended line is greater than the redundant capacity and greater than zero. When the line is The maximum load required, the selected data will be opened, and the selected data value will be calculated. 3.根据权利要求1所述的一种配电网故障恢复性重构方法,其特征在于:根据步骤B将非故障区网络的联络开关以自然数编号,并对每个联络开关所对应的环网进行单独编号,所述联络开关的个数表示负荷值的维数,每个环网中断开的开关的编号为负荷值的每一维元素。3 . The method for reconfiguring a distribution network fault recovery according to claim 1 , wherein: according to step B, the tie switches of the network in the non-fault area are numbered with natural numbers, and the ring corresponding to each tie switch is numbered. 4 . The network is individually numbered, the number of the tie switches represents the dimension of the load value, and the number of the switches disconnected in each ring network is the element of each dimension of the load value. 4.根据权利要求1所述的一种配电网故障恢复性重构方法,其特征在于:根据步骤D将解无效的负荷值的局部最优位置设为常数,将局部最优位置更新为所述负荷值的当前位置,根据优化模型计算解有效的负荷值的适应值,根据适应值依据整数编码算法分别计算所述编码的新位置,将新位置更新为所述编码的位置。4. A method for reconfiguration of power distribution network fault recovery according to claim 1, characterized in that: according to step D, the local optimal position of the load value for which the solution is invalid is set as a constant, and the local optimal position is updated as For the current position of the load value, the adaptation value of the effective load value is calculated according to the optimization model, and the new position of the code is calculated according to the adaptation value according to the integer coding algorithm, and the new position is updated to the position of the code. 5.根据权利要求1所述的一种配电网故障恢复性重构方法,其特征在于:根据步骤E将新位置更新为所述编码的位置后重新恢复电网编码数据,并对编码数据进行优化。5 . The method for reconfiguring power distribution network fault recovery according to claim 1 , wherein: after updating the new position to the coded position according to step E, restore the power grid coded data, and perform the coding on the coded data. 6 . optimization.
CN201910278987.6A 2019-04-09 2019-04-09 A fault-recovery reconstruction method for distribution network Pending CN109873409A (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201910278987.6A CN109873409A (en) 2019-04-09 2019-04-09 A fault-recovery reconstruction method for distribution network

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201910278987.6A CN109873409A (en) 2019-04-09 2019-04-09 A fault-recovery reconstruction method for distribution network

Publications (1)

Publication Number Publication Date
CN109873409A true CN109873409A (en) 2019-06-11

Family

ID=66922190

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201910278987.6A Pending CN109873409A (en) 2019-04-09 2019-04-09 A fault-recovery reconstruction method for distribution network

Country Status (1)

Country Link
CN (1) CN109873409A (en)

Citations (9)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
US8373569B2 (en) * 2010-05-27 2013-02-12 Briggs & Stratton Corporation Power line carrier (PLC) communication of standby generator status
CN104298876A (en) * 2014-10-14 2015-01-21 安徽科盟电子科技有限公司 Partition recovery method for fault of large-scale power distribution network
CN104332995A (en) * 2014-11-14 2015-02-04 南京工程学院 Improved particle swarm optimization based power distribution reconstruction optimization method
CN105305442A (en) * 2015-11-30 2016-02-03 河海大学常州校区 Multi-target intelligent power distribution network self-healing recovery method based on quantum genetic algorithm
CN106532720A (en) * 2016-12-20 2017-03-22 国网辽宁省电力有限公司沈阳供电公司 Dynamic partition fault recovery method of power distribution network containing distributed power supply
CN107579517A (en) * 2017-09-13 2018-01-12 国网黑龙江省电力有限公司电力科学研究院 Judgment method of whether the solution obtained in quantum particle swarm optimization reconstruction of complex distribution network is feasible
CN108182498A (en) * 2018-01-15 2018-06-19 国网黑龙江省电力有限公司电力科学研究院 Restorative Reconfiguration Method for Distribution Network Faults
CN108429257A (en) * 2018-03-26 2018-08-21 东北电力大学 The distribution network structure planing method of subregion and meter and geographic factor is clustered based on load point
CN109617083A (en) * 2018-12-26 2019-04-12 贵州电网有限责任公司 Distribution network failure restorative procedure based on particle swarm algorithm

Patent Citations (9)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
US8373569B2 (en) * 2010-05-27 2013-02-12 Briggs & Stratton Corporation Power line carrier (PLC) communication of standby generator status
CN104298876A (en) * 2014-10-14 2015-01-21 安徽科盟电子科技有限公司 Partition recovery method for fault of large-scale power distribution network
CN104332995A (en) * 2014-11-14 2015-02-04 南京工程学院 Improved particle swarm optimization based power distribution reconstruction optimization method
CN105305442A (en) * 2015-11-30 2016-02-03 河海大学常州校区 Multi-target intelligent power distribution network self-healing recovery method based on quantum genetic algorithm
CN106532720A (en) * 2016-12-20 2017-03-22 国网辽宁省电力有限公司沈阳供电公司 Dynamic partition fault recovery method of power distribution network containing distributed power supply
CN107579517A (en) * 2017-09-13 2018-01-12 国网黑龙江省电力有限公司电力科学研究院 Judgment method of whether the solution obtained in quantum particle swarm optimization reconstruction of complex distribution network is feasible
CN108182498A (en) * 2018-01-15 2018-06-19 国网黑龙江省电力有限公司电力科学研究院 Restorative Reconfiguration Method for Distribution Network Faults
CN108429257A (en) * 2018-03-26 2018-08-21 东北电力大学 The distribution network structure planing method of subregion and meter and geographic factor is clustered based on load point
CN109617083A (en) * 2018-12-26 2019-04-12 贵州电网有限责任公司 Distribution network failure restorative procedure based on particle swarm algorithm

Non-Patent Citations (1)

* Cited by examiner, † Cited by third party
Title
张卫红: "一种新的配电网故障恢复算法及其改进", 《上海交通大学学报》 *

Similar Documents

Publication Publication Date Title
Chen et al. Optimal placement of line switches for distribution automation systems using immune algorithm
Celli et al. Optimal distributed generation allocation in MV distribution networks
CN104578427B (en) Fault self-healing method for power distribution network containing microgrid power source
Botea et al. Optimal reconfiguration for supply restoration with informed A $^{\ast} $ Search
Huang et al. Three-phase balancing of distribution feeders using immune algorithm
CN110994612A (en) Power distribution network fault rapid recovery method based on network topology partition layering
CN103746376A (en) Power distribution network dynamic power restoration method based on load curve
CN108182498A (en) Restorative Reconfiguration Method for Distribution Network Faults
CN111682525A (en) Load Transfer Method Based on Optimal Flow Method and Mayeda Spanning Tree Method
CN106451439B (en) A Two-Stage Reconfiguration Method for Distribution Network of Ship Integrated Electric Propulsion System
CN105738765A (en) Power distribution network fault positioning method based on feeder line terminals and genetic algorithm
CN104899689B (en) Based on the distribution network failure restoration methods that DBCC optimized algorithms and entropy weight are theoretical
CN108270216B (en) A complex distribution network fault recovery system and method considering multiple objectives
CN117335384A (en) A distribution network fault recovery and reconstruction method based on ant colony algorithm
CN119965864B (en) Power distribution network fault recovery method and system based on reconstruction and island collaborative optimization
Hong et al. Genetic algorithm based network reconfiguration for loss minimization in distribution systems
CN107294086B (en) The service restoration method realized based on network equivalent and parallelization
CN119273336A (en) Distribution network fault maintenance optimization method, system, terminal and medium based on information physical system
CN117878926B (en) Monitoring, early warning and emergency treatment method and system for flexible power grid
Ganesan et al. Regular paper distribution system reconfiguration for loss reduction using genetic algorithm
CN109873409A (en) A fault-recovery reconstruction method for distribution network
Jiang et al. Research on load transfer strategy optimisation with considering the operation of distributed generations and secondary dispatch
CN117335401A (en) SOP-based double-ring network wiring power distribution network fault recovery method and device
Huang et al. Multi‐period service restoration of distribution systems incorporating interruptible load
CN110334850A (en) A design and optimization method for valve layout of water supply network

Legal Events

Date Code Title Description
PB01 Publication
PB01 Publication
SE01 Entry into force of request for substantive examination
SE01 Entry into force of request for substantive examination
WD01 Invention patent application deemed withdrawn after publication
WD01 Invention patent application deemed withdrawn after publication

Application publication date: 20190611