[go: up one dir, main page]

CN101691840B - Water level observation well and construction method thereof - Google Patents

Water level observation well and construction method thereof Download PDF

Info

Publication number
CN101691840B
CN101691840B CN2009103073959A CN200910307395A CN101691840B CN 101691840 B CN101691840 B CN 101691840B CN 2009103073959 A CN2009103073959 A CN 2009103073959A CN 200910307395 A CN200910307395 A CN 200910307395A CN 101691840 B CN101691840 B CN 101691840B
Authority
CN
China
Prior art keywords
pipe
well
layer
cement mortar
water level
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Expired - Fee Related
Application number
CN2009103073959A
Other languages
Chinese (zh)
Other versions
CN101691840A (en
Inventor
杨建民
郑刚
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Tianjin University
Original Assignee
Tianjin University
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Tianjin University filed Critical Tianjin University
Priority to CN2009103073959A priority Critical patent/CN101691840B/en
Publication of CN101691840A publication Critical patent/CN101691840A/en
Application granted granted Critical
Publication of CN101691840B publication Critical patent/CN101691840B/en
Expired - Fee Related legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Images

Landscapes

  • Rigid Pipes And Flexible Pipes (AREA)

Abstract

本发明公开了一种水位观测井,该井的井管采用PVC管,所述PVC管的各管段之间通过螺纹套管连接,所述井管的滤水部位设有出水孔,所述PVC管的外壁上固接有粗糙布料层,所述粗糙布料层上满沾有水泥砂浆层,所述出水孔贯穿所述粗糙布料层和所述水泥砂浆层以及所述PVC管。本发明还公开了一种水位观测井的施工方法,该井井管管段制作方法为:a、在所述PVC管段和螺纹套管的外壁上分别固接粗糙布料层;b、在所述粗糙布料层上满粘水泥砂浆层,形成所述井管的管段;c、在所述水泥砂浆层终凝前,在对应滤水部位的井管管段上钻出水孔,所述出水孔贯穿所述粗糙布料层和所述水泥砂浆层以及所述PVC管。本发明观测结果准确,施工成本低。

Figure 200910307395

The invention discloses a water level observation well. The well pipe of the well adopts a PVC pipe, and the pipe sections of the PVC pipe are connected by threaded casings. The water filtering part of the well pipe is provided with a water outlet hole. A rough cloth layer is fixed on the outer wall of the pipe, and the rough cloth layer is covered with a cement mortar layer, and the water outlet hole runs through the rough cloth layer, the cement mortar layer and the PVC pipe. The invention also discloses a construction method of a water level observation well. The manufacturing method of the pipe section of the well includes: a. fixing a rough cloth layer on the outer wall of the PVC pipe section and the threaded casing; b. The cloth layer is covered with a cement mortar layer to form the pipe section of the well pipe; c, before the final setting of the cement mortar layer, a water hole is drilled on the pipe section of the well pipe corresponding to the water filtering part, and the water outlet hole runs through the The coarse cloth layer and the cement mortar layer and the PVC pipe. The invention has accurate observation results and low construction cost.

Figure 200910307395

Description

一种水位观测井及其施工方法A water level observation well and its construction method

技术领域 technical field

本发明涉及工程监测领域,特别涉及一种水位观测井及其施工方法。The invention relates to the field of engineering monitoring, in particular to a water level observation well and a construction method thereof.

背景技术 Background technique

土木和水利工程的工程监测中常需要进行地下水位监测,现行的水位观测井常用钢管或混凝土砂石滤管。Groundwater level monitoring is often required in engineering monitoring of civil and water conservancy projects, and steel pipes or concrete sandstone filter pipes are commonly used in current water level observation wells.

应用钢管或混凝土砂石滤管制作水位观测井的施工工艺包括以下步骤:测放井位、埋设护口管、安装钻机、钻进成孔、清孔换浆、下井管、填砾料、填粘土球、在井管外围填粘性土、井口封闭、洗井、安泵试抽、排水、回填或封井。以上步骤中填砾料的目的在于在井管的滤管段形成良好的渗水通道,填粘土球和在井管外围填粘性土的目的在于在滤水管以上部分封堵渗水以避免各土层水力串通。填粘土球和在井管外围填粘性土两步骤是水位观测井管埋置成功的关键。The construction process of using steel pipe or concrete sandstone filter pipe to make a water level observation well includes the following steps: measuring and releasing the well position, burying the mouth protection pipe, installing the drilling rig, drilling into the hole, clearing the hole and changing the slurry, running the well pipe, filling gravel, filling Clay balls, filling clay around the well pipe, sealing the wellhead, washing the well, installing the pump and testing, draining, backfilling or sealing the well. The purpose of gravel filling in the above steps is to form a good water seepage channel in the filter pipe section of the well pipe, and the purpose of filling clay balls and filling clay around the well pipe is to block water seepage above the water filter pipe to avoid hydraulic collusion of various soil layers . The two steps of filling clay balls and filling clay around the well pipe are the key to the successful embedding of the water level observation well pipe.

以上应用钢管或混凝土砂石滤管制作水位观测井主要存在造价高的不足,尤其是应用钢管制作水位观测井。应用PVC管所制井管可以极大的节省造价。Above-mentioned application of steel pipes or concrete sandstone filter pipes to make water level observation wells mainly has the disadvantage of high cost, especially the use of steel pipes to make water level observation wells. The use of PVC pipes to make well pipes can greatly save the cost.

PVC管材是一种生产成本低、强度高,耐腐蚀的良好塑料制品。PVC管材有很好的力学性能,且具备极好的耐腐蚀性,使用过程中重量轻,安装方便,易实现密封连接,不易断裂,不需维护,加工良好的PVC管道,一般来讲使用寿命可长达50年,被广泛应用于建筑、排污、废水、通风管道和农业灌溉等方面。PVC pipe is a good plastic product with low production cost, high strength and corrosion resistance. PVC pipe has good mechanical properties, and has excellent corrosion resistance, light weight during use, easy installation, easy to achieve sealed connection, not easy to break, no maintenance, well-processed PVC pipe, generally speaking, the service life It can last up to 50 years and is widely used in construction, sewage, waste water, ventilation pipes and agricultural irrigation.

部分工程中有采用PVC管作为水位观测井井管的实例,但是应用PVC管作为水位观测井最大的缺点在于其外壁光滑、易于渗漏而导致井管穿过的各含水层串通,使得PVC管水位观测井为混合水位,而非滤管段含水层的水位值,导致观测结果失真。In some projects, there are examples of using PVC pipes as well pipes for water level observation wells, but the biggest disadvantage of using PVC pipes as water level observation wells is that their outer walls are smooth and easy to leak, which leads to the collusion of various aquifers that the well pipes pass through, making PVC pipes The water level observation well is a mixed water level instead of the water level value of the aquifer in the filter pipe section, resulting in distortion of the observation results.

发明内容 Contents of the invention

本发明为解决公知技术中存在的技术问题而提供一种观测结果准确,施工成本低的水位观测井及其施工方法。The invention provides a water level observation well with accurate observation results and low construction cost and a construction method thereof to solve the technical problems existing in the known technology.

本发明为解决公知技术中存在的技术问题所采取的一个技术方案是:一种水位观测井,该井的井管采用PVC管,所述PVC管的各管段之间通过螺纹套管连接,所述井管的滤水部位设有出水孔,所述PVC管的外壁上固接有粗糙布料层,所述粗糙布料层上满沾有水泥砂浆层,所述出水孔贯穿所述粗糙布料层和所述水泥砂浆层以及所述PVC管。A technical solution adopted by the present invention to solve the technical problems existing in the known technology is: a water level observation well, the well pipe of the well adopts PVC pipes, and the pipe sections of the PVC pipes are connected by threaded sleeves. The water filtering part of the well pipe is provided with a water outlet hole, and a rough cloth layer is fixed on the outer wall of the PVC pipe, and the rough cloth layer is covered with a cement mortar layer, and the water outlet hole runs through the rough cloth layer and the The cement mortar layer and the PVC pipe.

所述PVC管的管段公称外径为50mm~200mm,厚度为2.0mm~3.9mm。The pipe section of the PVC pipe has a nominal outer diameter of 50 mm to 200 mm and a thickness of 2.0 mm to 3.9 mm.

本发明为解决公知技术中存在的技术问题所采取的另一个技术方案是:一种水位观测井的施工方法,包括以下步骤:测放井位、埋设护口管、安装钻机、钻进成孔、清孔换浆、下井管、填砾料、填粘土球、在井管外围填粘性土、井口封闭、洗井、安泵试抽、排水、回填或封井,所述井管采用PVC管,所述PVC管的管段之间通过螺纹套管连接,所述井管的管段制作方法为:Another technical solution adopted by the present invention to solve the technical problems existing in the known technology is: a construction method of a water level observation well, comprising the following steps: measuring and releasing the well position, burying the mouth protection pipe, installing a drilling rig, drilling and forming a hole , hole cleaning and slurry replacement, well pipe running, gravel filling, clay ball filling, clay filling around the well pipe, well head sealing, well flushing, pump installation and test pumping, drainage, backfilling or well sealing, the well pipe is made of PVC pipe , the pipe sections of the PVC pipe are connected by threaded sleeves, and the pipe section of the well pipe is made in the following steps:

a、在所述PVC管段和螺纹套管的外壁上分别固接粗糙布料层;a. Fix the rough cloth layer on the outer wall of the PVC pipe section and the threaded sleeve respectively;

b、在所述粗糙布料层上满粘水泥砂浆层,形成所述井管的管段;b. A cement mortar layer is covered on the rough cloth layer to form the pipe section of the well pipe;

c、在所述水泥砂浆层终凝前,在对应滤水部位的井管管段上钻出水孔,所述出水孔贯穿所述粗糙布料层和所述水泥砂浆层以及所述PVC管。c. Before the final setting of the cement mortar layer, a water hole is drilled on the well pipe section corresponding to the water filtering part, and the water outlet hole runs through the coarse cloth layer, the cement mortar layer and the PVC pipe.

所述步骤a为:先在所述PVC管段和所述螺纹套管的外壁上涂抹粘结剂后粘贴3~5层粗糙布料,形成所述粗糙布料层。The step a is: first apply adhesive on the PVC pipe section and the outer wall of the threaded casing, and then paste 3-5 layers of rough cloth to form the rough cloth layer.

所述步骤b为:将固接有粗糙布料层的所述PVC管段和所述螺纹套管的外壁在水泥砂浆中旋转蘸浆,形成所述水泥砂浆层。The step b is: dipping the PVC pipe segment fixedly connected with the rough fabric layer and the outer wall of the threaded sleeve in cement mortar to form the cement mortar layer.

本发明具有的优点和积极效果是:通过采用在PVC管和螺纹套管外壁固接粗糙布料层,粗糙布料层上满沾水泥砂浆层的井管,有效解决了PVC管外壁光滑、易于渗漏而导致井管穿过的各含水层串通的问题,使得该水位观测井为滤管段含水层的水位值,观测结果准确;较好地利用了PVC管材的优点,如很好的力学性能如耐压性能、极好的耐腐蚀性、重量轻、安装方便、易实现密封连接、不易断裂、不需维护、寿命长等;相对于钢管和混凝土砂石滤管,该水位观测井造价低廉、在满足工程目的的同时可以多点布置。The advantages and positive effects of the present invention are: by adopting a well pipe with a rough cloth layer fixed on the outer wall of the PVC pipe and the threaded casing, and the rough cloth layer is covered with a cement mortar layer, the smooth outer wall of the PVC pipe and easy leakage are effectively solved. The problem of collusion between the various aquifers that the well pipe passes through makes the water level observation well the water level value of the aquifer in the filter pipe section, and the observation results are accurate; the advantages of PVC pipes are better utilized, such as good mechanical properties such as resistance Pressure performance, excellent corrosion resistance, light weight, easy installation, easy to achieve sealed connection, not easy to break, no maintenance, long life, etc.; It can be arranged in multiple points while meeting the engineering purpose.

附图说明 Description of drawings

图1是本发明潜水层水位观测井示意图;Fig. 1 is the schematic diagram of the submerged layer water level observation well of the present invention;

图2是本发明承压含水层水位观测井示意图;Fig. 2 is a schematic diagram of a water level observation well in a confined aquifer of the present invention;

图3是图1和图2的A-A(无钻孔段)截面图;Fig. 3 is A-A (no drilling section) sectional view of Fig. 1 and Fig. 2;

图4是图1和图2的B-B(钻孔段)截面图。Fig. 4 is a B-B (drilling section) sectional view of Fig. 1 and Fig. 2 .

图中:1、PVC管,2、布料层,3、水泥砂浆层,4、出水孔。In the figure: 1. PVC pipe, 2. fabric layer, 3. cement mortar layer, 4. water outlet hole.

具体实施方式 Detailed ways

为能进一步了解本发明的发明内容、特点及功效,兹例举以下实施例,并配合附图详细说明如下:In order to further understand the invention content, characteristics and effects of the present invention, the following examples are given, and detailed descriptions are as follows in conjunction with the accompanying drawings:

请参阅图1~图4,本发明一种水位观测井,该井的井管采用PVC管1,上述PVC管1的各管段之间通过螺纹套管连接,由上述PVC管段和螺纹套管连接形成的PVC管1的外壁上固接有粗糙布料层2,上述粗糙布料层2上满沾有水泥砂浆层4,对应滤水部位,钻出水孔4,出水孔4贯穿粗糙布料层2和水泥砂浆层3以及PVC管1。Please refer to Fig. 1~Fig. 4, a kind of water level observation well of the present invention, the well pipe of this well adopts PVC pipe 1, and each pipe section of above-mentioned PVC pipe 1 is connected by threaded casing, is connected by above-mentioned PVC pipe section and threaded casing A rough cloth layer 2 is fixed on the outer wall of the formed PVC pipe 1, and the above rough cloth layer 2 is covered with a cement mortar layer 4, corresponding to the water filtering part, and a water hole 4 is drilled, and the water outlet hole 4 runs through the rough cloth layer 2 and the cement mortar layer. Mortar layer 3 and PVC pipe 1.

上述PVC管的管段公称外径可以为50mm~200mm,厚度可以为2.0mm~3.9mm。The nominal outer diameter of the above-mentioned PVC pipe section may be 50mm-200mm, and the thickness may be 2.0mm-3.9mm.

上述水位观测井的施工方法,以下步骤:测放井位、埋设护口管、安装钻机、钻进成孔、清孔换浆、下井管、填砾料、填粘土球、在井管外围填粘性土、井口封闭、洗井、安泵试抽、排水、回填或封井,井管采用PVC管1,PVC管1的管段之间通过螺纹套管连接,为防止PVC管1外壁光滑渗水,本发明采用如下方法制作井管的管段:The construction method of the above-mentioned water level observation well includes the following steps: measuring and releasing the well position, burying the mouth protection pipe, installing the drilling rig, drilling into the hole, clearing the hole and changing the slurry, running the well pipe, filling gravel, filling clay balls, filling the periphery of the well pipe Cohesive soil, wellhead sealing, well cleaning, pump installation and testing, drainage, backfilling or well sealing, the well pipe is made of PVC pipe 1, and the pipe sections of PVC pipe 1 are connected by threaded sleeves. In order to prevent the outer wall of PVC pipe 1 from being smooth and seepage The present invention adopts following method to make the pipe section of well pipe:

a、在所述PVC管段和螺纹套管的外壁上分别固接粗糙布料层;a. Fix the rough cloth layer on the outer wall of the PVC pipe section and the threaded sleeve respectively;

b、在所述粗糙布料层上满粘水泥砂浆层,形成所述井管的管段;b. A cement mortar layer is covered on the rough cloth layer to form the pipe section of the well pipe;

c、在所述水泥砂浆层终凝前,在对应滤水部位的井管管段上钻出水孔,所述出水孔贯穿所述粗糙布料层和所述水泥砂浆层以及所述PVC管。c. Before the final setting of the cement mortar layer, a water hole is drilled on the well pipe section corresponding to the water filtering part, and the water outlet hole runs through the coarse cloth layer, the cement mortar layer and the PVC pipe.

在所述PVC管段和螺纹套管的外壁上分别固接粗糙布料层的方法有:在上述管件的外壁上涂抹粘结剂后粘贴3~5层粗糙布料;也可以在上述管件的外壁上用钢丝绑固多层粗糙布料。The method of respectively fixing the rough cloth layer on the outer wall of the PVC pipe section and the threaded casing includes: applying adhesive on the outer wall of the above-mentioned pipe fitting and pasting 3 to 5 layers of rough cloth; it can also be used on the outer wall of the above-mentioned pipe fitting. Steel wire binds multiple layers of coarse cloth.

上述步骤b中在粗糙布料层上满粘水泥砂浆层的方法有:将固接有粗糙布料层的PVC管段和螺纹套管的外壁在水泥砂浆中旋转蘸浆;也可以在上述粗糙布料层上涂刷水泥砂浆。The method of sticking the cement mortar layer on the rough cloth layer in the above step b includes: rotating the PVC pipe section and the outer wall of the threaded sleeve fixed to the rough cloth layer in the cement mortar; Apply cement mortar.

实施例1:Example 1:

某高层住宅楼基坑工程开挖面积1.23万m2,基坑挖深15.130m。基坑周边采用地下连续墙,地连墙深34米,墙厚1.0米。基坑周边布置潜水层水位观测井,该水位观测井的结构如图1、图3和图4所示。The excavation area of a high-rise residential building foundation pit project is 12,300 m 2 , and the depth of the foundation pit is 15.130m. The surrounding of the foundation pit adopts an underground diaphragm wall, the depth of which is 34 meters, and the thickness of the wall is 1.0 meters. Water level observation wells in the aquifer layer are arranged around the foundation pit, and the structure of the water level observation wells is shown in Figure 1, Figure 3 and Figure 4.

在基坑开挖深度范围内的地层自上而下垂直分布为:The top-to-bottom vertical distribution of strata within the excavation depth range of the foundation pit is:

①人工填土和杂填土,厚度2.3m①Artificial fill and miscellaneous fill, with a thickness of 2.3m ;

②粉质粘土,厚度5.1m;② Silty clay, thickness 5.1m;

③淤泥,厚度11.4m③ Silt, thickness 11.4m ;

④粉质粘土,厚度5.7m④ Silty clay, thickness 5.7m ;

⑤粉土,厚度9.80m⑤silt, thickness 9.80m ;

⑥粉砂,厚度8.10m⑥silt, thickness 8.10m ;

⑦粉质粘土,厚度14.5m⑦silty clay, thickness 14.5m ;

⑧粉土,厚度16.30m⑧ Silt, thickness 16.30m .

上述潜水层水位观测井采用PVC管,PVC管的管段公称外径为50mm,厚度为2.0mm,总管长9m,第一管段6m,第二管段3m,PVC管的两管段之间采用螺纹套管连接。在PVC管段和螺纹套管的外壁涂抹粘结剂后粘贴3层棉纺布料,之后将上述管件的外壁在水泥砂浆中旋转蘸浆,待井管外壁上水泥砂浆快凝固时在滤水部位钻孔,形成井管滤管段。The above-mentioned aquifer water level observation well adopts PVC pipe. The nominal outer diameter of the pipe section of the PVC pipe is 50mm, the thickness is 2.0mm, the total pipe length is 9m, the first pipe section is 6m, and the second pipe section is 3m. The threaded casing is used between the two pipe sections of the PVC pipe connect. Apply adhesive on the outer wall of the PVC pipe section and the threaded casing, and paste 3 layers of cotton fabric, and then dip the outer wall of the above-mentioned pipe fittings in the cement mortar, and drill holes in the water filtration part when the cement mortar on the outer wall of the well pipe is quickly solidified. A well pipe screen section is formed.

采用PVC管制作水位观测井的施工方法包括以下步骤:测放井位、埋设护口管、安装钻机、钻进成孔、清孔换浆、下井管、填砾料、填粘土球、在井管外围填粘性土、井口封闭、洗井、安泵试抽、排水、回填或封井。The construction method of using PVC pipes to make water level observation wells includes the following steps: measuring and releasing the well position, burying the mouth protection pipe, installing the drilling rig, drilling into the hole, clearing the hole and changing the slurry, running the well pipe, filling gravel, filling clay balls, in the well Filling with cohesive soil around the pipe, sealing the wellhead, flushing the well, installing the pump for pumping test, draining, backfilling or sealing the well.

采用PVC管制作的潜水层水位观测井埋置成功后,应用101型水位计进行水位观测,井管外壁未发生水力串通,测试结果符合要求。After the aquifer water level observation well made of PVC pipe was successfully buried, the 101-type water level gauge was used to observe the water level. No hydraulic collusion occurred on the outer wall of the well pipe, and the test results met the requirements.

实施例2:Example 2:

某段地铁隧道基坑工程长260m,宽20.5m,基坑挖深15.420m。基坑周边采用地下连续墙,地连墙深35米,墙厚1.2米。基坑周边布置潜水层和承压含水层水位观测井,请参见图1~图4。The excavation project of a subway tunnel is 260m long, 20.5m wide, and the excavation depth is 15.420m. An underground continuous wall is adopted around the foundation pit, the ground connection wall is 35 meters deep and the wall thickness is 1.2 meters. Water level observation wells in the aquifer and confined aquifer are arranged around the foundation pit, see Figures 1 to 4.

在基坑开挖深度范围内的地层自上而下垂直分布为:The top-to-bottom vertical distribution of strata within the excavation depth range of the foundation pit is:

①人工填土和杂填土,厚度3.4m①Artificial fill and miscellaneous fill, thickness 3.4m ;

②淤泥,厚度12.1m② Silt, thickness 12.1m ;

③粉质粘土,厚度3.6m;③ Silty clay, thickness 3.6m;

④粉土,厚度2.5m;④ Silt, thickness 2.5m;

⑤粉砂,厚度10.0m⑤ Silt, thickness 10.0m ;

⑥粉质粘土,厚度12.5m⑥silty clay, thickness 12.5m ;

⑦粉土,厚度10.3m⑦silt, thickness 10.3m ;

⑧粉砂,厚度5.4m⑧silt, thickness 5.4m .

潜水层水位观测井采用PVC管,PVC管的管段公称外径为90mm,厚度为3.0mm,总管长10m,第一管段6m,第二管段4m,PVC管的两管段之间采用螺纹套管连接。The water level observation well in the aquifer uses PVC pipes. The nominal outer diameter of the PVC pipe section is 90mm, the thickness is 3.0mm, the total pipe length is 10m, the first pipe section is 6m, and the second pipe section is 4m. The two pipe sections of the PVC pipe are connected by threaded sleeves .

承压含水层水位观测井采用PVC管,PVC管的管段公称外径为90mm,厚度为3.0mm,总管长24m,共4管段,每管段6m,PVC管的4个管段之间采用螺纹套管连接。The water level observation well in the confined aquifer uses PVC pipes. The nominal outer diameter of the PVC pipe section is 90mm, the thickness is 3.0mm, and the total pipe length is 24m. connect.

在PVC管段和螺纹套管的外壁涂抹粘结剂后粘贴4层棉纺布料,之后将上述管件的外壁在水泥砂浆中旋转蘸浆,待外壁上水泥砂浆快凝固时在滤水部位钻孔,形成井管滤管段。After smearing adhesive on the outer wall of the PVC pipe section and the threaded casing, paste 4 layers of cotton cloth, and then dip the outer wall of the above-mentioned pipe fittings in the cement mortar, and when the cement mortar on the outer wall is quickly solidified, drill holes in the water filter part to form Well pipe filter pipe section.

采用PVC管制作水位观测井的施工方法包括以下步骤:测放井位、埋设护口管、安装钻机、钻进成孔、清孔换浆、下井管、填砾料、填粘土球、在井管外围填粘性土、井口封闭、洗井、安泵试抽、排水、回填或封井。The construction method of using PVC pipes to make water level observation wells includes the following steps: measuring and releasing the well position, burying the mouth protection pipe, installing the drilling rig, drilling into the hole, clearing the hole and changing the slurry, running the well pipe, filling gravel, filling clay balls, in the well Filling with cohesive soil around the pipe, sealing the wellhead, flushing the well, installing the pump for pumping test, draining, backfilling or sealing the well.

采用PVC管制作的潜水层水位观测井和承压含水层水位观测井埋置成功后,应用101型水位计进行水位观测,井管外壁未发生水力串通,测试结果符合要求。After the aquifer water level observation wells and confined aquifer water level observation wells made of PVC pipes were successfully buried, the water level was observed with a 101-type water level gauge. No hydraulic collusion occurred on the outer wall of the well pipes, and the test results met the requirements.

实施例3:Example 3:

某地铁车站基坑工程长463m,宽19.35m,基坑挖深18.590m。基坑周边采用地下连续墙,地连墙深38米,墙厚1.2米。基坑周边布置潜水层和承压含水层水位观测井,请参见图1~图4。The foundation pit project of a subway station is 463m long, 19.35m wide, and 18.590m deep. An underground continuous wall is adopted around the foundation pit, the ground connection wall is 38 meters deep and the wall thickness is 1.2 meters. Water level observation wells in the aquifer and confined aquifer are arranged around the foundation pit, see Figures 1 to 4.

在基坑开挖深度范围内的地层自上而下垂直分布为:The top-to-bottom vertical distribution of strata within the excavation depth range of the foundation pit is:

①人工填土和杂填土,厚度4.50m;①Artificial fill and miscellaneous fill, thickness 4.50m;

②淤泥,厚度13.00m;② Silt, thickness 13.00m;

③粉质粘土,厚度4.0m;③ Silty clay, thickness 4.0m;

④粉土,厚度2.80m;④ Silt, thickness 2.80m;

⑤粉砂,厚度13.10m;⑤silt, thickness 13.10m;

⑥粉质粘土,厚度21.5m。⑥Silly clay with a thickness of 21.5m.

潜水层水位观测井采用PVC管,PVC管的管段公称外径为200mm,厚度为3.9mm,总管长10m,第一管段6m,第二管段4m,PVC管的两管段之间采用螺纹套管连接。The water level observation well in the aquifer uses PVC pipes. The nominal outer diameter of the PVC pipe section is 200mm, the thickness is 3.9mm, the total pipe length is 10m, the first pipe section is 6m, and the second pipe section is 4m. The two pipe sections of the PVC pipe are connected by threaded sleeves .

承压含水层水位观测井采用PVC管,PVC管的管段公称外径为200mm,厚度为3.9mm,总管长30m,共5管段,每管段6m,PVC管的管段之间采用螺纹套管连接。The water level observation well in the confined aquifer uses PVC pipes. The nominal outer diameter of the PVC pipe section is 200mm, the thickness is 3.9mm, and the total pipe length is 30m.

在PVC管段和螺纹套管的外壁涂抹粘结剂后粘贴4层棉纺布料,之后将上述管件的外壁在水泥砂浆中旋转蘸浆,待上述管件的外壁上水泥砂浆快凝固时在滤水部位钻孔,形成井管滤管段。After smearing adhesive on the outer wall of the PVC pipe section and the threaded casing, paste 4 layers of cotton fabric, and then dip the outer wall of the above-mentioned pipe fitting in the cement mortar, and drill the water filter part when the cement mortar on the outer wall of the above-mentioned pipe fitting is fast solidified. holes to form the well pipe filter pipe section.

采用PVC管制作水位观测井的施工方法包括以下步骤:测放井位、埋设护口管、安装钻机、钻进成孔、清孔换浆、下井管、填砾料、填粘土球、在井管外围填粘性土、井口封闭、洗井、安泵试抽、排水、回填或封井。The construction method of using PVC pipes to make water level observation wells includes the following steps: measuring and releasing the well position, burying the mouth protection pipe, installing the drilling rig, drilling into the hole, clearing the hole and changing the slurry, running the well pipe, filling gravel, filling clay balls, in the well Filling with cohesive soil around the pipe, sealing the wellhead, flushing the well, installing the pump for pumping test, draining, backfilling or sealing the well.

采用PVC管制作的潜水层水位观测井和承压含水层水位观测井埋置成功后,应用101型水位计进行水位观测,井管外壁未发生水力串通,测试结果符合要求。After the aquifer water level observation wells and confined aquifer water level observation wells made of PVC pipes were successfully buried, the water level was observed with a 101-type water level gauge. No hydraulic collusion occurred on the outer wall of the well pipes, and the test results met the requirements.

本发明的基本原理是:采用PVC管制作水位观测井管,PVC管的管段之间的连接方式采用螺纹套管,PVC管外粘布料并涂刷水泥砂浆的防渗处理方法。该井管制作方法利用了PVC管材的优点如很好的力学性能如耐压性能、极好的耐腐蚀性、重量轻、安装方便、易连接且密封、不易断裂、不需维护、寿命长等。在PVC管外粘布料并涂刷水泥砂浆的防渗处理方法克服了应用中存在的管壁光滑容易造成水力串通的缺点。相对于钢管和混凝土砂石滤管,PVC管水位观测井造价低廉、在满足工程目的的同时可以多点布置。The basic principle of the present invention is: adopt PVC pipe to make water level observation well pipe, the connection mode between the pipe sections of PVC pipe adopts threaded bushing, the anti-seepage treatment method of sticking cloth outside PVC pipe and brushing cement mortar. The well pipe production method utilizes the advantages of PVC pipes such as good mechanical properties such as pressure resistance, excellent corrosion resistance, light weight, easy installation, easy connection and sealing, not easy to break, no maintenance, long life, etc. . The anti-seepage treatment method of sticking cloth on the outside of the PVC pipe and painting cement mortar overcomes the disadvantage that the smooth pipe wall is easy to cause hydraulic collusion in the application. Compared with steel pipes and concrete sandstone filter pipes, PVC pipe water level observation wells are inexpensive and can be arranged in multiple points while meeting the engineering purpose.

尽管上面结合附图对本发明的优选实施例进行了描述,但是本发明并不局限于上述的具体实施方式,上述的具体实施方式仅仅是示意性的,并不是限制性的,本领域的普通技术人员在本发明的启示下,在不脱离本发明宗旨和权利要求所保护的范围情况下,还可以作出很多形式,这些均属于本发明的保护范围之内。Although the preferred embodiments of the present invention have been described above in conjunction with the accompanying drawings, the present invention is not limited to the above-mentioned specific embodiments. The above-mentioned specific embodiments are only illustrative and not restrictive. Those of ordinary skill in the art Under the enlightenment of the present invention, people can also make many forms without departing from the purpose of the present invention and the scope of protection of the claims, and these all belong to the protection scope of the present invention.

Claims (5)

1.一种水位观测井,该井的井管采用PVC管,所述PVC管的各管段之间通过螺纹套管连接,所述井管的滤水部位设有出水孔,其特征在于,所述PVC管的外壁上固接有粗糙布料层,所述粗糙布料层上满沾有水泥砂浆层,所述出水孔贯穿所述粗糙布料层和所述水泥砂浆层以及所述PVC管。1. a kind of water level observation well, the well pipe of this well adopts PVC pipe, is connected by threaded casing between each pipe section of described PVC pipe, and the water filtering position of described well pipe is provided with water outlet, it is characterized in that, all A rough cloth layer is fixed on the outer wall of the PVC pipe, and the rough cloth layer is covered with a cement mortar layer, and the water outlet hole runs through the rough cloth layer, the cement mortar layer and the PVC pipe. 2.根据权利要求1所述的水位观测井,其特征在于,所述PVC管的管段公称外径为50mm~200mm,厚度为2.0mm~3.9mm。2 . The water level observation well according to claim 1 , characterized in that, the pipe section of the PVC pipe has a nominal outer diameter of 50 mm to 200 mm and a thickness of 2.0 mm to 3.9 mm. 3.一种水位观测井的施工方法,包括以下步骤:测放井位、埋设护口管、安装钻机、钻进成孔、清孔换浆、下井管、填砾料、填粘土球、在井管外围填粘性土、井口封闭、洗井、安泵试抽、排水、回填或封井,所述井管采用PVC管,所述PVC管的管段之间通过螺纹套管连接,其特征在于,所述井管的管段制作方法为:3. A construction method of a water level observation well, comprising the following steps: measuring and releasing the well position, burying the mouth protection pipe, installing a drilling rig, drilling into a hole, clearing the hole and changing slurry, lowering the well pipe, filling gravel, filling clay balls, Fill the well pipe with cohesive soil, seal the wellhead, wash the well, install the pump for test pumping, drain, backfill or seal the well. The well pipe is made of PVC pipe, and the pipe sections of the PVC pipe are connected by threaded casings. It is characterized in that , the method for making the pipe section of the well pipe is: a、在所述PVC管段和螺纹套管的外壁上分别固接粗糙布料层;a. Fix the rough cloth layer on the outer wall of the PVC pipe section and the threaded sleeve respectively; b、在所述粗糙布料层上满粘水泥砂浆层,形成所述井管的管段;b. A cement mortar layer is covered on the rough cloth layer to form the pipe section of the well pipe; c、在所述水泥砂浆层终凝前,在对应滤水部位的井管管段上钻出水孔,所述出水孔贯穿所述粗糙布料层和所述水泥砂浆层以及所述PVC管。c. Before the final setting of the cement mortar layer, a water hole is drilled on the well pipe section corresponding to the water filtering part, and the water outlet hole runs through the coarse cloth layer, the cement mortar layer and the PVC pipe. 4.根据权利要求3所述的水位观测井的施工方法,其特征在于,所述步骤a为:先在所述PVC管段和所述螺纹套管的外壁上涂抹粘结剂后粘贴3~5层粗糙布料,形成所述粗糙布料层。4. The construction method of the water level observation well according to claim 3, characterized in that, the step a is: first apply adhesive on the outer wall of the PVC pipe section and the threaded casing, and then paste 3 to 5 A layer of coarse cloth, forming the layer of coarse cloth. 5.根据权利要求3所述的水位观测井的施工方法,其特征在于,所述步骤b为:将分别固接有粗糙布料层的所述PVC管段和所述螺纹套管在水泥砂浆中旋转蘸浆,以在所述粗糙布料层上形成所述水泥砂浆层。5. The construction method of the water level observation well according to claim 3, characterized in that, the step b is: rotating the PVC pipe section and the threaded casing respectively fixed with a rough cloth layer in cement mortar dipping in slurry to form the cement mortar layer on the coarse cloth layer.
CN2009103073959A 2009-09-21 2009-09-21 Water level observation well and construction method thereof Expired - Fee Related CN101691840B (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN2009103073959A CN101691840B (en) 2009-09-21 2009-09-21 Water level observation well and construction method thereof

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN2009103073959A CN101691840B (en) 2009-09-21 2009-09-21 Water level observation well and construction method thereof

Publications (2)

Publication Number Publication Date
CN101691840A CN101691840A (en) 2010-04-07
CN101691840B true CN101691840B (en) 2012-07-25

Family

ID=42080550

Family Applications (1)

Application Number Title Priority Date Filing Date
CN2009103073959A Expired - Fee Related CN101691840B (en) 2009-09-21 2009-09-21 Water level observation well and construction method thereof

Country Status (1)

Country Link
CN (1) CN101691840B (en)

Families Citing this family (6)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN102808583B (en) * 2012-07-23 2015-01-07 中国神华能源股份有限公司 Hydrological exploration drilling well pipe, coal mining pipe descending method and hydrological exploration method
CN103147467A (en) * 2013-03-13 2013-06-12 中国建筑第八工程局有限公司 Leak detection device for underground diaphragm wall and construction method of leak detection device
CN106596176B (en) * 2016-12-23 2020-05-26 上海勘察设计研究院(集团)有限公司 Water and soil integrated sampling method
CN106894821B (en) * 2017-03-03 2019-05-10 中铁建大桥工程局集团第五工程有限公司 It is a kind of originate, the monitoring method of received well and jacking construction
CN109138841A (en) * 2018-08-24 2019-01-04 沈阳建筑大学 A kind of groundwater monitoring well construction device and its application method with reinforcing well casing and suspension type auxiliary frame
CN109098259A (en) * 2018-09-27 2018-12-28 江苏省江都水利工程管理处 A kind of water level logging system of simple to install easy to maintain

Citations (4)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN1151783A (en) * 1994-07-06 1997-06-11 Lwt仪器设备公司 Logging or measurement while tripping
CN2464934Y (en) * 2000-11-17 2001-12-12 核工业第六研究所 Filter for underground extracting liquid
CN2634115Y (en) * 2003-09-01 2004-08-18 中油勘探监理涿州有限责任公司 Remote sensing type well deep monitor
CN2668852Y (en) * 2003-12-24 2005-01-05 中国石化胜利油田有限公司井下作业公司 Mechanical well-depth positioner

Patent Citations (4)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN1151783A (en) * 1994-07-06 1997-06-11 Lwt仪器设备公司 Logging or measurement while tripping
CN2464934Y (en) * 2000-11-17 2001-12-12 核工业第六研究所 Filter for underground extracting liquid
CN2634115Y (en) * 2003-09-01 2004-08-18 中油勘探监理涿州有限责任公司 Remote sensing type well deep monitor
CN2668852Y (en) * 2003-12-24 2005-01-05 中国石化胜利油田有限公司井下作业公司 Mechanical well-depth positioner

Non-Patent Citations (1)

* Cited by examiner, † Cited by third party
Title
杜鸿坚.聚氯乙烯(PVC-U)管材在给水排水工程中的应用.《广东建材》.2005,(第11期), *

Also Published As

Publication number Publication date
CN101691840A (en) 2010-04-07

Similar Documents

Publication Publication Date Title
CN109629566B (en) Vacuum drainage anchor rod and construction method thereof
CN100480475C (en) Controllable one-well lamina precipitation construction method
CN101691840B (en) Water level observation well and construction method thereof
CN205152968U (en) Precipitation tubular well structure
CN114718101B (en) A seepage cut-off structure of a tailings pond with a seepage cut-off wall and a precipitation well and a construction method thereof
CN109736340B (en) Dewatering device and method for guaranteeing integrity of cushion layer by reserving dewatering well on foundation slab
CN111827328A (en) Subway deep foundation pit well point dewatering system and construction method thereof
CN202227357U (en) Water-reducing tube well structure
CN102995647B (en) A Groundwater Control Method for Pile Hole Grouting and Seepage Isolation
CN106836253A (en) A kind of well-points dewatering device for building engineering construction
CN104878771A (en) Construction method for vacuum tube well dewatering system
CN204715426U (en) A kind of water burst drainage system for closed deep foundation ditch exploratory hole
CN106837411A (en) The arrangement and method of a kind of buried shield tunnel filling and injecting slurry
CN103939669A (en) Anti-seepage underground pipeline structure in soft soil matrix and construction technology of anti-seepage underground pipeline structure
CN104534216A (en) Drainage pipeline and inspection well connection water stop structure
CN107100206A (en) A kind of prevention and controls of basement leakage
CN106958240B (en) Air cushion type layered vacuum pipe well and soft foundation drainage method using same
CN207003415U (en) Air-cushion type batch vacuum pipe well
CN206581281U (en) A kind of well-points dewatering device for building engineering construction
CN212561582U (en) Precipitation inclined shaft in deep foundation pit
CN110965487B (en) Down-pass passage high-flow reverse-suction siphon sewage pipe and encapsulation treatment construction method
CN214363571U (en) An underground cavern precipitation system that is not affected by obstacles
CN111851548A (en) Dewatering inclined shaft in deep foundation pit and construction method thereof
CN114045850A (en) Construction method for replacing waterproof curtain by combination of light well point and pneumatic dewatering
CN204551507U (en) A kind of rock foundation ductule local dewatering device

Legal Events

Date Code Title Description
C06 Publication
PB01 Publication
C10 Entry into substantive examination
SE01 Entry into force of request for substantive examination
C14 Grant of patent or utility model
GR01 Patent grant
CF01 Termination of patent right due to non-payment of annual fee
CF01 Termination of patent right due to non-payment of annual fee

Granted publication date: 20120725

Termination date: 20210921