CN102069160B - Combined manufacturing device and method for ultra-large rectangular ingot blank inclined casting - Google Patents
Combined manufacturing device and method for ultra-large rectangular ingot blank inclined casting Download PDFInfo
- Publication number
- CN102069160B CN102069160B CN201110034212A CN201110034212A CN102069160B CN 102069160 B CN102069160 B CN 102069160B CN 201110034212 A CN201110034212 A CN 201110034212A CN 201110034212 A CN201110034212 A CN 201110034212A CN 102069160 B CN102069160 B CN 102069160B
- Authority
- CN
- China
- Prior art keywords
- casting
- mold
- ingot blank
- ultra
- rectangle
- Prior art date
- Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
- Active
Links
Images
Landscapes
- Molds, Cores, And Manufacturing Methods Thereof (AREA)
- Continuous Casting (AREA)
Abstract
Description
技术领域 technical field
本发明是关于冶金领域中的锭坯制造装置,尤其涉及一种超大型矩形锭坯倾斜铸造的组合式制造装置及方法。The invention relates to an ingot manufacturing device in the field of metallurgy, in particular to a combined manufacturing device and method for obliquely casting a super-large rectangular ingot.
背景技术 Background technique
连铸法作为公知技术已被广泛用于板坯制造,特别对于单一材质的薄板坯、中板坯以及坯厚在400mm以下的中厚板坯的批量生产,其特点是效率高、质量好、金属有效利用率高。然而,对于超大型船舶用板、核反应设备用板、化工领域中化学反应容器用板、水力发电用板以及海洋结构用板等,其钢坯的单批次生产批量小、规格大(超宽、超厚)、材质要求特殊,若采用连铸方法,其一无法发挥连铸高效率的优势,其二要求的连铸机械非常庞大、造价极高,其三在技术方面上连铸法还不能很好解决超大型钢坯的内部质量问题。As a well-known technology, the continuous casting method has been widely used in the manufacture of slabs, especially for the batch production of thin slabs, medium slabs and medium-thick slabs with a thickness of less than 400mm. It is characterized by high efficiency, good quality, The effective utilization rate of metal is high. However, for plates for super large ships, plates for nuclear reaction equipment, plates for chemical reaction vessels in the chemical industry, plates for hydroelectric power generation, plates for marine structures, etc., the billets are produced in a single batch with small batches and large specifications (ultra-wide, super thick), special material requirements, if the continuous casting method is used, firstly, the advantages of high efficiency of continuous casting cannot be used, secondly, the continuous casting machinery required is very large and the cost is extremely high, and thirdly, the continuous casting method cannot be technically It is very good to solve the internal quality problem of super large steel billet.
为此,现有生产超大型特厚板仍多采用钢锭模式铸造及轧制的制造方法,或经锻造及轧制的制造方法,其锭型包括:方形铸锭、多棱圆形和扁钢铸锭等,锭型均为带锥度锭型,冷却方法多为大气自然冷却;这种生产方式存在的主要缺点是冒口相对切头量大,成材率低,限制了钢锭吨位,目前只能生产60吨以下,厚度小于1000mm,宽度小于2500mm的锭坯。For this reason, the existing production of ultra-large extra-thick plates still mostly adopts the manufacturing method of steel ingot mode casting and rolling, or the manufacturing method of forging and rolling. The ingot types include: square ingot, polygonal round and flat steel Ingot casting, etc., the ingot type is tapered ingot type, and the cooling method is mostly atmospheric natural cooling; the main disadvantage of this production method is that the riser has a large amount of cutting head relative to the head, and the yield is low, which limits the tonnage of the steel ingot. At present, only Produce ingots below 60 tons, with a thickness of less than 1000mm and a width of less than 2500mm.
再者,现有技术中通常是采用竖直锭模铸造或水平锭模铸造方式。其中竖直锭模铸造方式增加了钢液对铸型的静压力和冲击力,由此对铸型的结构强度要求较高,使铸型不易实现组合式结构,大大增加了铸型结构的制作费用;而现有水平锭模铸造方式则是采用完全水平放置的铸型进行锭坯制造,使大型钢锭在浇铸、凝固的同时,杂质、气体等有害物质漂浮于钢液的上表面并聚集一定深度,无法排除,由此影响了锭坯的质量;在进行锭坯加工时,还需要用机械加工的方式将钢锭的上表面刨削一定深度,无形增加了加工成本。Furthermore, in the prior art, vertical ingot casting or horizontal ingot casting is usually adopted. Among them, the vertical ingot mold casting method increases the static pressure and impact force of the molten steel on the mold, which requires higher structural strength of the mold, making it difficult for the mold to realize a combined structure, which greatly increases the production of the mold structure cost; while the existing horizontal ingot casting method is to use a completely horizontal casting mold to manufacture ingots, so that large-scale steel ingots are cast and solidified, and harmful substances such as impurities and gases float on the upper surface of molten steel and accumulate to a certain extent. The depth cannot be ruled out, which affects the quality of the ingot; when processing the ingot, it is necessary to plan the upper surface of the steel ingot to a certain depth by machining, which invisibly increases the processing cost.
有鉴于此,本发明人凭借多年的相关设计和制造经验,提出一种超大型矩形锭坯倾斜铸造的组合式制造装置及方法,以克服现有技术的缺陷。In view of this, the present inventor proposes a combined manufacturing device and method for oblique casting of a super-large rectangular ingot by virtue of years of related design and manufacturing experience, so as to overcome the defects of the prior art.
发明内容 Contents of the invention
本发明的目的在于提供一种超大型矩形锭坯倾斜铸造的组合式制造装置及方法,该制造装置基于传统的水平铸造装置,结合超大型矩形锭坯特点,将铸型与水平面呈5°~15°倾斜放置,大型钢锭在浇铸、凝固的同时,使杂质、气体等有害物质向斜上方的冒口内聚集并排除;铸型底面制作成水冷金属型,可实现锭坯厚度方向的定向凝固,以提高锭坯质量;铸型采用组合式结构,能够根据制造的锭坯规格组装出相应的铸型,以节省制作铸型的费用,并且容易开箱。The object of the present invention is to provide a combined manufacturing device and method for oblique casting of a super-large rectangular ingot. Placed at an angle of 15°, large-scale steel ingots are cast and solidified, allowing harmful substances such as impurities and gases to accumulate and be removed in the riser at the top of the slope; the bottom of the mold is made into a water-cooled metal mold, which can realize directional solidification in the thickness direction of the ingot. In order to improve the quality of the billet; the casting mold adopts a combined structure, and the corresponding casting mold can be assembled according to the specifications of the manufactured billet, so as to save the cost of making the casting mold, and it is easy to open the box.
本发明的目的是这样实现的,一种超大型矩形锭坯倾斜铸造的组合式制造方法,将组合式矩形铸模沿其长度方向固定放置在与水平面呈5°~15°的倾斜面上,该矩形铸模是由强制冷却金属底板与上侧板、下侧板、左侧板、右侧板、盖板构成的能拆卸的组合结构;在组装后的矩形铸模的最高位置处设有冒口,矩形铸模上设置钢液浇注装置;所述强制冷却金属底板内设置有一组金属管架或沿底板长度方向并列设置的多组金属管架;钢液注入矩形铸模后,向金属管架内通入冷却介质使倾斜的矩形锭坯由下向上顺序冷却以实现定向凝固;待矩形锭坯整体温度达到工艺起模温度后,停止通入冷却介质;拆卸组合式矩形铸模的盖板及各侧板;调运该矩形锭坯至下一工序。The purpose of the present invention is achieved in this way, a combined manufacturing method for oblique casting of a super-large rectangular billet, the combined rectangular casting mold is fixedly placed on an inclined surface of 5° to 15° from the horizontal plane along its length direction, the The rectangular casting mold is a detachable combined structure composed of a forced cooling metal base plate, an upper side plate, a lower side plate, a left side plate, a right side plate and a cover plate; a riser is provided at the highest position of the assembled rectangular casting mold, The molten steel pouring device is arranged on the rectangular casting mold; a group of metal pipe racks or multiple sets of metal pipe racks arranged side by side along the length direction of the bottom plate are arranged in the forced cooling metal bottom plate; after the molten steel is injected into the rectangular casting mold, it is passed into the metal pipe rack The cooling medium cools the inclined rectangular ingot sequentially from bottom to top to achieve directional solidification; when the overall temperature of the rectangular ingot reaches the process mold opening temperature, stop feeding the cooling medium; disassemble the cover plate and each side plate of the combined rectangular casting mold; Transfer the rectangular ingot to the next process.
该方法适用于60吨~150吨锭型规格厚度800~1500mm、宽度2100~5000mm、长度4000~10000mm的超大型矩形锭坯的铸造。The method is suitable for casting a super large rectangular ingot with a thickness of 800-1500 mm, a width of 2100-5000 mm and a length of 4000-10000 mm in a 60-150-ton ingot shape.
一种超大型矩形锭坯倾斜铸造的组合式制造装置,该制造装置包括一矩形铸模,该矩形铸模沿长度方向与水平面呈5°~15°倾斜放置,所述矩形铸模由强制冷却金属底板与上侧板、下侧板、左侧板、右侧板、盖板构成能拆卸的组合结构;所述强制冷却金属底板由矩形金属底板本体和包覆于金属底板本体内的金属管架构成;为了提高铸模寿命,所述强制冷却金属底板、盖板以及各侧板的内侧面挂设有一层面砂层;在所述组装后的矩形铸模的最高位置处设有冒口,矩形铸模上还设有注入钢液的浇注装置。A combined manufacturing device for oblique casting of super-large rectangular ingots. The manufacturing device includes a rectangular casting mold, which is placed at an angle of 5° to 15° along the length direction and the horizontal plane. The rectangular casting mold is composed of a forced cooling metal base plate and The upper side plate, the lower side plate, the left side plate, the right side plate and the cover plate form a detachable combined structure; the forced cooling metal base plate is composed of a rectangular metal base plate body and a metal pipe frame covered in the metal base plate body; In order to improve the life of the mold, a layer of sand layer is hung on the inner surface of the forced cooling metal base plate, cover plate and each side plate; a riser is provided at the highest position of the assembled rectangular mold, and a There is a pouring device for injecting molten steel.
在本发明的一较佳实施方式中,所述强制冷却金属底板内的金属管架是由沿金属底板本体横向呈上下间隔设置的上主管、下主管以及垂直于上主管和下主管并与两根主管导通的多个纵向支管构成;位于金属底板本体一侧的下主管管口设为冷却介质进口,位于金属底板本体另一侧的上主管管口设为冷却介质出口。In a preferred embodiment of the present invention, the metal pipe frame in the forced cooling metal bottom plate is composed of an upper main pipe, a lower main pipe, and an upper main pipe and a lower main pipe perpendicular to the upper main pipe and the lower main pipe and connected to the two main pipes. The root main pipe is composed of a plurality of longitudinal branch pipes; the lower main pipe opening on one side of the metal base plate body is set as the cooling medium inlet, and the upper main main pipe opening on the other side of the metal base plate main body is set as the cooling medium outlet.
在本发明的一较佳实施方式中,所述金属管架沿金属底板本体长度方向并列设置有多组。In a preferred embodiment of the present invention, multiple sets of metal pipe frames are arranged side by side along the length direction of the metal bottom plate body.
在本发明的一较佳实施方式中,所述纵向支管在金属底板本体宽度方向中的排列方式为中间密两侧疏。In a preferred embodiment of the present invention, the arrangement of the longitudinal branch pipes in the width direction of the metal bottom plate body is dense in the middle and sparse on both sides.
在本发明的一较佳实施方式中,所述金属管架沿金属底板本体长度方向并列设置有多组;每组金属管架是由沿金属底板本体横向布置的多个横向支管和位于多个横向支管两端并与多个横向支管导通的两个纵向主管构成;一纵向主管上设有冷却介质进口,另一纵向主管上设有冷却介质出口。In a preferred embodiment of the present invention, multiple sets of metal pipe frames are arranged side by side along the length direction of the metal bottom plate body; Two longitudinal main pipes are formed at both ends of the horizontal branch pipe and connected with multiple horizontal branch pipes; one longitudinal main pipe is provided with a cooling medium inlet, and the other longitudinal main pipe is provided with a cooling medium outlet.
在本发明的一较佳实施方式中,所述强制冷却金属底板和各侧板的内侧面均为金属平面;所述强制冷却金属底板和各侧板上与内侧面相反的背侧面制成网格型凹坑结构。In a preferred embodiment of the present invention, the inner surfaces of the forced cooling metal bottom plate and each side plate are metal planes; Lattice pit structure.
在本发明的一较佳实施方式中,所述各侧板上与相邻板件邻近的凹坑侧面几何中心位置设有用于连接固定相邻板的螺栓透孔。In a preferred embodiment of the present invention, each side plate is provided with a bolt through hole for connecting and fixing the adjacent plate at the geometric center of the side surface of the pit adjacent to the adjacent plate.
在本发明的一较佳实施方式中,在所述强制冷却金属底板上表面靠近四个边的位置设有燕尾槽,或间隔设有多个放置螺栓的透孔。In a preferred embodiment of the present invention, dovetail grooves are provided on the upper surface of the forced cooling metal bottom plate close to the four sides, or a plurality of through holes for placing bolts are arranged at intervals.
在本发明的一较佳实施方式中,所述盖板的板面上设有由多个对应的凹坑和透孔组成的矩形网格状透孔结构;在所述网格状透孔结构内填充有造型型砂;所述盖板的四周侧面凹设有多个凹槽,凹槽的下壁面向下设有螺栓透孔用以连接各侧板。In a preferred embodiment of the present invention, the surface of the cover plate is provided with a rectangular grid-like through-hole structure composed of a plurality of corresponding pits and through-holes; in the grid-like through-hole structure The inside is filled with molding sand; the surrounding sides of the cover plate are concavely provided with a plurality of grooves, and the lower wall of the groove is provided with bolt through holes to connect the side plates.
在本发明的一较佳实施方式中,所述各侧板和盖板分别由两块或多块相应板件组装构成。In a preferred embodiment of the present invention, each of the side plates and the cover plate is formed by assembling two or more corresponding plates.
在本发明的一较佳实施方式中,所述钢液浇注装置由浇注漏斗、直浇道、横浇道、内浇道组成;该钢液浇注装置贯通开设在上侧板、左侧板或右侧板上。In a preferred embodiment of the present invention, the molten steel pouring device is composed of a pouring funnel, a sprue, a runner, and an inner runner; on the right side panel.
在本发明的一较佳实施方式中,所述下侧板内设有冷却金属管架,该冷却金属管架由进水主管、出水主管及导通设置在两主管之间的多个支管构成。In a preferred embodiment of the present invention, the lower side plate is provided with a cooling metal pipe frame, which is composed of a water inlet main pipe, a water outlet main pipe and a plurality of branch pipes connected between the two main pipes. .
在本发明的一较佳实施方式中,所述钢液浇注装置由浇注漏斗、直浇道、横浇道、内浇道组成;该钢液浇注装置贯通开设在下侧板上。In a preferred embodiment of the present invention, the molten steel pouring device is composed of a pouring funnel, a sprue, a runner, and an inner runner; the molten steel pouring device is opened through the lower side plate.
在本发明的一较佳实施方式中,所述冒口安装在矩形铸模的最高位置处,冒口水平断面形状为沿矩形铸模宽度方向的矩形结构,冒口根据铸件宽度设置为一个或多个,冒口上平面与钢液浇注装置的浇注漏斗下端面平齐。In a preferred embodiment of the present invention, the riser is installed at the highest position of the rectangular casting mold, the horizontal section shape of the riser is a rectangular structure along the width direction of the rectangular casting mold, and the riser is set as one or more according to the width of the casting , the upper plane of the riser is flush with the lower end surface of the pouring funnel of the molten steel pouring device.
在本发明的一较佳实施方式中,所述冒口安装在倾斜放置的盖板最高位置处,冒口呈竖直状结构,冒口内腔穿过盖板与矩形铸模锭型内腔相通。In a preferred embodiment of the present invention, the riser is installed at the highest position of the obliquely placed cover plate, the riser is in a vertical structure, and the cavity of the riser passes through the cover plate and communicates with the cavity of the rectangular casting ingot.
在本发明的一较佳实施方式中,所述冒口安装在倾斜放置的上侧板最高位置处,冒口呈L形结构,L形的短边为横向连通上侧板的冒口通道,L形的长边为冒口的补缩部分,横向冒口通道的上沿与矩形铸模锭型内腔的最高点平齐,以利于钢锭浇注过程中杂质上浮到冒口内。In a preferred embodiment of the present invention, the riser is installed at the highest position of the obliquely placed upper side plate, the riser is in an L-shaped structure, and the short side of the L shape is a riser channel connected to the upper side plate in a transverse direction, The long side of the L shape is the feeding part of the riser, and the upper edge of the transverse riser channel is flush with the highest point of the inner cavity of the rectangular casting mold ingot, so as to facilitate the floating of impurities into the riser during the casting process of the steel ingot.
由上所述,本发明的制造装置及方法是根据超大型矩形锭坯的特点,将铸型与水平面呈5°~15°倾斜放置,在大型钢锭浇铸时,可大大降低钢液对铸型的静压力和冲击力,降低了对铸型结合部件间结构强度的要求,使采用组合式铸型结构成为可能;由于铸型采用组合式结构,能够根据制造的锭坯规格组装成相应的铸型,降低了制作铸型的费用,并且使铸型的造型、组装、拆卸更简单灵活,使热开箱成为可能;由于铸型倾斜放置,大型钢锭在浇铸、凝固的同时,可使杂质、气体等有害物质向斜上方的冒口内聚集并排除;铸型底面制作成水冷金属型,可实现锭坯厚度方向的定向凝固,可消除铸件内缩孔、消弱铸件疏松,以提高锭坯质量。From the above, the manufacturing device and method of the present invention are based on the characteristics of the super-large rectangular ingot, and the casting mold is placed at an angle of 5° to 15° from the horizontal plane, which can greatly reduce the impact of molten steel on the mold when casting large steel ingots. The static pressure and impact force reduce the requirements for the structural strength of the joint parts of the mold, making it possible to adopt a combined mold structure; because the mold adopts a combined structure, it can be assembled into a corresponding casting mold according to the specifications of the manufactured ingot. type, which reduces the cost of making molds, and makes the molding, assembly, and disassembly of molds easier and more flexible, making it possible to open the box; Harmful substances such as gas are accumulated and removed in the riser at the upper slope; the bottom surface of the mold is made into a water-cooled metal mold, which can realize directional solidification in the thickness direction of the ingot, eliminate shrinkage holes in the casting, weaken the looseness of the casting, and improve the quality of the ingot .
附图说明 Description of drawings
以下附图仅旨在于对本发明做示意性说明和解释,并不限定本发明的范围。其中:The following drawings are only intended to illustrate and explain the present invention schematically, and do not limit the scope of the present invention. in:
图1:为本发明超大型矩形锭坯倾斜铸造工艺方案一示意图。Fig. 1: It is a schematic diagram of the super-large rectangular ingot inclined
图2:为本发明超大型矩形锭坯倾斜铸造工艺方案二示意图。Fig. 2: It is a schematic diagram of the super-large rectangular billet inclined
图3:为本发明超大型矩形锭坯倾斜铸造工艺方案三示意图。Fig. 3: It is a schematic diagram of the third scheme of the super-large rectangular ingot inclined casting process of the present invention.
图4A:为本发明中强制冷却金属底板及金属管架布置结构一示意图。Fig. 4A: a schematic diagram of the arrangement structure of the forced cooling metal bottom plate and metal pipe frame in the present invention.
图4B:为图4A的侧视示意图。Fig. 4B: is a schematic side view of Fig. 4A.
图4C:为图4A的仰视示意图。Fig. 4C: is a schematic bottom view of Fig. 4A.
图5A:为本发明中强制冷却金属底板及金属管架布置结构二示意图。Fig. 5A: It is a schematic diagram of the second arrangement structure of the forced cooling metal bottom plate and metal pipe frame in the present invention.
图5B:为图5A的侧视示意图。Fig. 5B: is a schematic side view of Fig. 5A.
图5C:为图5A的仰视示意图。Fig. 5C: is a schematic bottom view of Fig. 5A.
图6A:为本发明中强制冷却金属底板及金属管架布置结构三示意图。Fig. 6A: It is a schematic diagram of the third arrangement structure of the forced cooling metal bottom plate and metal pipe frame in the present invention.
图6B:为图6A的侧视示意图。Fig. 6B: is a schematic side view of Fig. 6A.
图6C:为图6A的仰视示意图。Fig. 6C: is a schematic bottom view of Fig. 6A.
图7A:为本发明中上侧板结构示意图。Fig. 7A: It is a schematic diagram of the structure of the upper side plate in the present invention.
图7B:为图7A的侧视示意图。Fig. 7B: is a schematic side view of Fig. 7A.
图8A:为本发明中左、右侧板结构示意图。Fig. 8A: It is a schematic diagram of the structure of the left and right panels in the present invention.
图8B:为图8A的侧视示意图。Fig. 8B: is a schematic side view of Fig. 8A.
图9A:为本发明中下侧板结构一示意图。FIG. 9A is a schematic diagram of the structure of the middle and lower side plates of the present invention.
图9B:为图9A的侧视示意图。Fig. 9B: is a schematic side view of Fig. 9A.
图9C:为图9A的俯视示意图。FIG. 9C : is a schematic top view of FIG. 9A .
图10A:为本发明中下侧板结构二示意图。Fig. 10A is a schematic diagram of the structure of the middle and lower side plates of the present invention.
图10B:为图10A的侧视示意图。Fig. 10B: is a schematic side view of Fig. 10A.
图11A:为本发明中盖板结构示意图。Fig. 11A is a schematic diagram of the structure of the cover plate in the present invention.
图11B:为图11A的侧视示意图。Fig. 11B: is a schematic side view of Fig. 11A.
图11C:为图11A的仰视示意图。Fig. 11C: is a schematic bottom view of Fig. 11A.
图12A:为本发明中侧板和盖板组合构成的结构示意图一。Fig. 12A: Schematic diagram 1 of the combination of side panels and cover panels in the present invention.
图12B:为本发明中侧板和盖板组合构成的结构示意图二。Fig. 12B: Structural schematic diagram II of the combination of side panels and cover panels in the present invention.
图13:为本发明中倾斜放置的强制冷却金属底板挂砂厚度示意图。Fig. 13 is a schematic diagram of the thickness of sand hanging on the obliquely placed forced cooling metal bottom plate in the present invention.
图14A:为本发明中强制冷却金属底板挂砂操作示意图。Fig. 14A: It is a schematic diagram of the sand-hanging operation of the forced cooling metal bottom plate in the present invention.
图14B:为图14A的侧视示意图。Fig. 14B: is a schematic side view of Fig. 14A.
图14C:为图14A的仰视示意图。Fig. 14C: is a schematic bottom view of Fig. 14A.
图15A:为本发明中下侧板挂砂操作示意图。Fig. 15A is a schematic diagram of the operation of hanging sand on the middle and lower side plates of the present invention.
图15B:为图15A的仰视示意图。Fig. 15B: is a schematic bottom view of Fig. 15A.
图16A~图16F:为本发明中组合式制造装置合箱过程示意图。16A to 16F are schematic diagrams of the box closing process of the combined manufacturing device in the present invention.
图17A~图17D:为本发明浇铸过程中聚渣示意图。17A to 17D are schematic diagrams of slag accumulation in the casting process of the present invention.
图18A:为本发明倾斜铸造底面顺序水冷法缺陷仿真结果。Fig. 18A: It is the simulation result of defects of the sequential water cooling method on the inclined casting bottom of the present invention.
图18B:为传统铸造自然冷却方法的缺陷仿真结果。Fig. 18B: The defect simulation result of the traditional casting natural cooling method.
图18C:为现有技术底面整体水冷的定向凝固法缺陷仿真结果。Fig. 18C: It is the defect simulation result of the directional solidification method for the overall water cooling of the bottom surface in the prior art.
具体实施方式 Detailed ways
为了对本发明的技术特征、目的和效果有更加清楚的理解,现对照附图说明本发明的具体实施方式。In order to have a clearer understanding of the technical features, purposes and effects of the present invention, the specific implementation manners of the present invention will now be described with reference to the accompanying drawings.
如图1、图2和图3所示,本发明提出一种超大型矩形锭坯倾斜铸造的组合式制造装置100,该制造装置100包括一矩形铸模1,该矩形铸模1沿其长度方向与水平面呈5°~15°倾斜放置,所述矩形铸模1由强制冷却金属底板11、上侧板12、下侧板13、左侧板14、右侧板15(如图8A、图8B所示)和盖板16构成能拆卸的组合结构;所述强制冷却金属底板11(如图4A~图4C、图5A~图5C和图6A~图6C所示)是由矩形金属底板本体111和包覆于金属底板本体111内的金属管架112构成(金属管架112外包覆浇注的钢水凝固后形成所述矩形金属底板本体111);所述强制冷却金属底板11、盖板16以及各侧板的内侧面挂设有面砂层6;所用的面砂优选树脂砂材料,面砂层6外表面涂轧2~4mm耐高温涂料(优选醇基氧化锆涂料);所述强制冷却金属底板11、上侧板12、下侧板13、左侧板14和右侧板15的内侧面挂设的面砂层6的厚度为5~20mm,所述盖板的内侧面挂设的面砂层6的厚度为50~200mm,其中,强制冷却金属底板11与铸件面间的挂砂厚度,可根据不同部位要求的冷却强度不同而变化,可以通过挂砂厚度调整强制冷却金属底板11与铸件间的传热能力(如图13所示,靠近下侧板13部位可以取5mm,向上逐渐增厚至上侧板12部位取20mm);在所述组装后的矩形铸模1的最高位置处设有冒口2,矩形铸模1上还设有注入钢液的钢液浇注装置3。As shown in Fig. 1, Fig. 2 and Fig. 3, the present invention proposes a combined
如图1~图3所示,采用该组合式制造装置100制造超大型矩形锭坯的方法是,将组合式矩形铸模1沿其长度方向固定放置在与水平面呈5°~15°的倾斜面上,在本实施方式中,首先将地坑4底平面用干砂5铺成所需的倾斜坡度面(5°~15°),再将强制冷却金属底板11固定放置在该倾斜面上(所述强制冷却金属底板11的下表面设有网格型凹坑结构,依靠强制冷却金属底板11自重将下方的干砂5挤满格子内的凹坑以固定该强制冷却金属底板),然后在强制冷却金属底板11上方顺序组装下侧板13、左、右侧板14、15和盖板16,冒口2安装在矩形铸模1的最高位置处,在矩形铸模1上安装钢液浇注装置3,之后,在组装好的矩形铸模1与浇铸地坑4的内壁间填满用做背砂的干砂5,连接进、出冷却管路并准备浇铸;钢液注入矩形铸模1后,向金属管架112内通入冷却介质使倾斜的矩形锭坯由下向上顺序冷却以实现定向凝固;所述冷却介质可以采用水、空气、水-气混合物或其他冷却介质;在所述强制冷却金属底板11内可以设置一组金属管架112,也可沿底板长度方向并列设置多组金属管架112。当金属底板11内设置一组金属管架112时,冷却介质是由下向上流动以保证矩形锭坯由下向上顺序冷却。当金属底板11内设置多组金属管架112时,可根据矩形锭坯凝固的工艺要求,使由下向上排列的多组金属管架112内顺序通入冷却介质,以保证矩形锭坯由下向上顺序冷却,实现定向凝固;在冷却时根据使用要求,通水顺序先下第一组,逐步向上第二组、第三组……,形成独特的顺序冷却方式;待矩形锭坯整体温度达到工艺起模温度后,停止通入冷却介质;拆卸组合式矩形铸模1的盖板16及各侧板;调运该矩形锭坯至下一工序。本发明的制造方法适用于60吨~150吨锭型规格厚度800~1500mm、宽度2100~5000mm、长度4000~10000mm的超大型矩形锭坯的铸造。As shown in Figures 1 to 3, the method of using the combined
由上所述,本发明的制造装置及方法是根据超大型矩形锭坯的特点,将铸型与水平面呈5°~15°倾斜放置,在大型钢锭浇铸时,可大大降低钢液对铸型的静压力和冲击力,降低了对铸型结合部件间结构强度的要求,使采用组合式铸型结构成为可能;由于铸型采用组合式结构,能够根据制造的锭坯规格组装成相应的铸型,降低了制作铸型的费用,并且使铸型的造型、组装、拆卸更简单灵活,使热开箱成为可能;由于铸型倾斜放置,大型钢锭在浇铸、凝固的同时,可使杂质、气体等有害物质向斜上方的冒口内聚集并排除;铸型底面制作成水冷金属型,可实现锭坯厚度方向的定向凝固,消除缩孔、消弱铸件内疏松,以提高锭坯质量。From the above, the manufacturing device and method of the present invention are based on the characteristics of the super-large rectangular ingot, and the casting mold is placed at an angle of 5° to 15° from the horizontal plane, which can greatly reduce the impact of molten steel on the mold when casting large steel ingots. The static pressure and impact force reduce the requirements for the structural strength of the joint parts of the mold, making it possible to adopt a combined mold structure; because the mold adopts a combined structure, it can be assembled into a corresponding casting mold according to the specifications of the manufactured ingot. type, which reduces the cost of making molds, and makes the molding, assembly, and disassembly of molds easier and more flexible, making it possible to open the box; Harmful substances such as gas are accumulated and removed in the riser at the upper slope; the bottom surface of the mold is made into a water-cooled metal mold, which can realize directional solidification in the thickness direction of the ingot, eliminate shrinkage cavities, and weaken the porosity in the casting to improve the quality of the ingot.
进一步,如图4A~图4C所示,在本实施方式中,所述强制冷却金属底板11内的金属管架112是由沿金属底板本体111横向呈上下间隔设置的上主管1121、下主管1122以及垂直于上主管和下主管并与两根主管导通的多个纵向支管1123构成;所述金属管架112布置在金属底板本体111厚度方向邻近其上表面的位置(即:金属管架112靠近铸件一侧的表面布设);位于金属底板本体111一侧的下主管1122管口设为冷却介质进口(该下主管1122另一管口用螺丝堵堵住),位于金属底板本体111另一侧的上主管1121管口设为冷却介质出口(该上主管1121另一管口也用螺丝堵堵住),从而确保冷却介质是由下向上流动以保证矩形锭坯由下向上顺序冷却,实现定向凝固。为加大锭坯中部冷却能力,所述多个纵向支管1123在金属底板本体111宽度方向中的排列方式为中间密两侧疏(如图4A所示)。Further, as shown in FIGS. 4A to 4C , in this embodiment, the
在本实施方式中,所述金属管架112可沿金属底板本体111长度方向并列设置有多组(如图5A~图5C、图6A~图6C所示)。所述金属管架112可采用上述结构并列设置多组(如图5A~图5C所示)。In this embodiment, multiple sets of metal pipe frames 112 can be arranged side by side along the length direction of the metal bottom plate body 111 (as shown in FIGS. 5A-5C and 6A-6C ). The
如图6A~图6C所示,当使用多组金属管架112并列设置时,每组金属管架112的结构也可由沿金属底板本体111横向布置的多个横向支管1124和位于多个横向支管两端并与多个横向支管导通的两个纵向主管1125、1126构成;其中,一个纵向主管1125上设有冷却介质进口,另一纵向主管1126上设有冷却介质出口。As shown in Figures 6A to 6C, when multiple groups of metal pipe frames 112 are arranged side by side, the structure of each group of metal pipe frames 112 can also be composed of a plurality of
在本实施方式中,如图4C、图7A~图7B、图8A~图8B、图9A~图9C、图10A~图10B所示,所述强制冷却金属底板11和各侧板的内侧面均为金属平面;所述强制冷却金属底板11和各侧板上与内侧面相反的背侧面制成网格型凹坑结构7,以减轻相应构件的重量、降低铸模内部应力,降低铸模变形的可能性。In this embodiment, as shown in Figure 4C, Figure 7A-7B, Figure 8A-8B, Figure 9A-9C, Figure 10A-10B, the forced cooling
所述各侧板上与相邻板件的接触面邻近的凹坑7侧面几何中心位置设有用于与相邻板件把合固定的螺栓透孔71。Bolt through
在本实施方式中,如图4A~图6C所示,在所述强制冷却金属底板11上表面靠近四个边的位置设有燕尾槽113,或间隔设有多个放置螺栓的透孔。组装铸模时,在燕尾槽113内设置螺栓,螺栓穿过对应侧板的螺栓透孔71后,将各侧板固定在强制冷却金属底板11上;同理,可将盖板16固定于各侧板之上。In this embodiment, as shown in FIGS. 4A to 6C , dovetail
进一步,如图11A~图11C所示,在本实施方式中,所述盖板16的板面上设有由多个对应的凹坑81和透孔82组成的矩形网格状透孔结构8;在所述网格状透孔结构8内填充有造型型砂5(如图1所示),起到透气保温的作用;所述盖板16的四周侧面凹设有多个凹槽162,凹槽162的下壁面向下设有螺栓透孔1621用以连接各侧板。Further, as shown in FIGS. 11A to 11C , in this embodiment, the surface of the
在本实施方式中,所述上侧板12、下侧板13、左侧板14、右侧板15和盖板16可分别由两块或多块相应板件组装构成,能够根据制造的锭坯规格组装成相应的铸型,降低了制作铸型的费用。各侧板可以由相同高度、不同长度或相同长度、不同高度的几块板件组合而成;盖板可以由相同宽度、不同长度或相同长度、不同宽度的几块板件组合而成;如图12A所示,左侧板14和盖板16分别由两块板件组装构成;如图12B所示,左侧板14和盖板16分别由三块板件组装构成;所述两块或三块板件由螺栓固定连接在一起。In this embodiment, the
如图1~图3所示,在本实施方式中,所述钢液浇注装置3由浇注漏斗31、直浇道32、横浇道33、内浇道34组成;所述直浇道、横浇道、内浇道均是由耐火砖管内腔构成,其中横浇道33与内浇道34的耐火砖管外采用典型的型砂填充,直浇道32耐火砖管外还包括有直浇管金属壳体,在金属壳体与耐火砖管间填充型砂;直浇道32通过内部耐火砖管与横浇道间90°弯头砖管连接在一起,外部用型砂填充将直浇管固定。As shown in Figures 1 to 3, in this embodiment, the molten
该钢液浇注装置3的内浇道34可贯通开设在上侧板12、左侧板14、右侧板15或下侧板13上。The
当钢液浇注装置3贯通开设在上侧板12、左侧板14或右侧板15上时,所述下侧板13内可设置冷却金属管架131(如图10A~图10B所示),该冷却金属管架131由进水主管1311、出水主管1312及导通设置在两主管之间的多个支管1313构成。钢液浇注装置3贯通开设在上侧板12时,内浇道34与铸件型腔连通,内浇道口位于上侧板12高度方向的中下部,多个平行分布的内浇道均匀分布于钢锭宽度方向上。When the molten
当钢液浇注装置3贯通开设在下侧板13上时,下侧板13内不设置冷却金属管架131;此时,内浇道要穿过下侧板13的透孔与铸件型腔连通,内浇道口位于下侧板13高度方向的中下部,多个平行分布的内浇道均匀分布于钢锭宽度方向上。When the molten
如图1~图3所示,在本实施方式中,所述冒口2安装在矩形铸模1的最高位置处,冒口2可安装在倾斜放置的盖板16的最高位置处(如图2、图3所示);冒口2也可安装在倾斜放置的上侧板12的最高位置处(如图1所示)。所述冒口2水平断面形状为沿矩形铸模1宽度方向的矩形结构,冒口2根据铸件宽度可设置为一个或多个,冒口2上平面与钢液浇注装置3的浇注漏斗31下端面平齐。冒口铸型采用树脂砂面砂、传统型砂背砂;冒口内壁表面涂轧2~4mm耐高温涂料(优选醇基氧化锆涂料),冒口钢液面上覆盖发热剂、保温剂。As shown in Figures 1 to 3, in this embodiment, the
当所述冒口2安装在倾斜放置的盖板16最高位置处时,所述盖板16上设置相应的透孔161(如图11A所示),冒口2呈竖直状结构,冒口2内腔穿过盖板16的透孔161与矩形铸模锭型内腔相通;所述透孔161的尺寸应保证开箱时冒口能从透孔中脱出。When the
当所述冒口2安装在倾斜放置的上侧板12的最高位置处时,冒口2呈L形结构,L形的短边为横向连通上侧板12的冒口通道,L形的长边为冒口的补缩部分,横向冒口通道的上沿与矩形铸模锭型内腔的最高点平齐,以利于钢锭浇注过程中杂质上浮到冒口2内。When the
在本实施方式中,采用该组合式制造装置制造超大型矩形锭坯的制造过程包括模具的准备、组装、浇注、冒口点浇、开箱、清整等操作步骤。In this embodiment, the manufacturing process of using the combined manufacturing device to manufacture a super-large rectangular ingot includes operational steps such as mold preparation, assembly, pouring, riser pouring, unpacking, and cleaning.
具体操作步骤如下:The specific operation steps are as follows:
一、模具的准备:包括强制冷却金属底板、左侧板、右侧板、上侧板、下侧板、盖板的清理、造型、涂刷涂料、干燥等;1. Mold preparation: including forced cooling metal bottom plate, left side plate, right side plate, upper side plate, lower side plate, cover plate cleaning, modeling, painting, drying, etc.;
1.首先找出生产所需的强制冷却金属底板、左侧板、右侧板、上侧板、下侧板、盖板等模具,检查模具有无损坏,清理模具上残存的旧砂、锈蚀等,如有损坏进行修复或更换;1. First find out the molds for forced cooling metal bottom plate, left side plate, right side plate, upper side plate, lower side plate, cover plate, etc. required for production, check whether the mold is damaged, and clean the remaining old sand and rust on the mold etc., repair or replace if damaged;
2.清理好的模具进行造型操作:2. Clean the mold for molding operation:
以强制冷却金属底板为代表(包括强制冷却金属底板、左右侧板、上侧板)只需要在接触铸件的面(内侧面)上挂5~20mm面砂,没有开设冒口、浇道等操作的为一类:将模具按照挂砂面冲上水平放置,安装四周挂砂厚度控制板于模具的四个边框上(用螺丝拧紧),将配制好的呋喃树脂面砂导入由挂砂厚度控制板围成的腔体内,轻轻按压将砂子铺实、铺匀,用刮板9沿平行的两对称厚度控制板轨迹将多余面砂刮下,并补足欠缺部位(如图14A~图14C所示);之后准备涂刷涂料。Represented by the forced cooling metal bottom plate (including the forced cooling metal bottom plate, left and right side plates, and upper side plate), it is only necessary to hang 5-20 mm surface sand on the surface (inner side) that contacts the casting, and there is no riser, runner, etc. One type: place the mold horizontally according to the sand surface, install the surrounding sand thickness control boards on the four frames of the mold (tighten with screws), and introduce the prepared furan resin surface sand to be controlled by the thickness of the sand. In the cavity surrounded by the boards, lightly press the sand to spread it evenly, and use the
如图15A、图15B所示,以下侧板为代表(包括下侧板、盖板等)需要在接触铸件的面上挂砂外,还需开设冒口或浇道等:将模具按照挂砂面冲上水平放置,安装四周挂砂厚度控制板于模具的四个边框上;安放进口砖于下侧板透孔中心,在进口砖与透孔壁间填充配制好的呋喃树脂砂至上平面;再由挂砂厚度控制板围成的腔体内添加配制好的呋喃树脂面砂,轻轻按压将砂子铺实、铺匀,用刮板9沿平行的两对称厚度控制板轨迹将多余面砂刮下,并补足欠缺部位;之后准备涂刷涂料。As shown in Figure 15A and Figure 15B, the following side plates (including the lower side plate, cover plate, etc.) need to hang sand on the surface contacting the casting, and also need to set up risers or runners, etc.: the mold is hung according to the sand Place it horizontally on top of the surface, install the surrounding sand thickness control board on the four frames of the mold; place the imported brick in the center of the through hole of the lower side plate, and fill the prepared furan resin sand between the imported brick and the through hole wall to the upper plane; Then add the prepared furan resin surface sand into the cavity surrounded by the thickness control board of hanging sand, press lightly to pave the sand evenly, and use the
3.涂刷涂料:待型砂硬化后,向与铸件接触的水平放置面上,涂轧醇基氧化锆耐火涂料;涂轧方法:将配置好的醇基氧化锆耐火涂料膏倒在砂面上,初步摊平后,再用涂料刮板沿平行的两对称厚度控制板轨迹将涂料膏涂轧到砂面上,并控制均匀的涂料厚度在2~4mm。同样方法将与铸件接触的其他部位也涂轧2~4mm涂料。3. Coating: After the molding sand is hardened, apply the alcohol-based zirconia refractory coating to the horizontal surface in contact with the casting; coating and rolling method: pour the prepared alcohol-based zirconia refractory coating paste on the sand surface , After the initial flattening, then use the paint scraper to apply the paint paste to the sand surface along the track of two parallel symmetrical thickness control plates, and control the uniform paint thickness at 2-4mm. In the same way, other parts that are in contact with the casting are also coated with 2-4mm paint.
4.干燥:将涂轧好的含有大量乙醇的涂料膏,用乙醇拌和的稀涂料对涂料表面粉刷一遍后,用火种点燃涂料,使涂料自燃干燥、硬化。4. Drying: paint the surface of the paint with the paint paste containing a large amount of ethanol mixed with ethanol, and then ignite the paint with a fire to make the paint dry and harden by spontaneous combustion.
二、合箱组装:如图16A~图16F所示,将地坑底平面用干砂在放置强制冷却金属底板的部位铺成所需的坡度(5°~15°),上面放置强制冷却金属底板(带凹坑格子的面朝下),依靠强制冷却金属底板自重将下方的干砂挤满格子内的凹坑,连接强制冷却金属底板进、出介质管路,并经打压试验确认连接良好、无泄露;然后在强制冷却金属底板上方先安放下侧板,安放前将下侧板与强制冷却金属底板接触面的型砂及杂质去除,后在接触面上涂刷1~2mm左右的一层醇基耐火泥膏,依靠下侧板的自重将涂料膏压平压实;穿入紧固螺杆及定位销,将下侧板与底板紧固在一起;将底板内侧面砂与下侧板面砂接触部位的涂料膏沿接触缝填满修平后点燃;依次安装左、右侧板、上侧板并将彼此间紧固;最后在组装好的上侧板、左、右侧板、下侧板上方,安放带冒口的盖板(盖板与左、右侧板、上侧板、下侧板接触面上的型砂不去除),其间靠型砂紧密接触密封;穿入紧固螺杆及定位销使盖板与各侧板紧固;安放浇铸装置,连接下侧板通孔内的浇口砖,铺设横浇道砖管和直浇道砖管,砖间用型砂填实,最后安放浇铸漏斗(漏斗下平面应与冒口上面在一个水平面上),最后在组装好的矩形铸模与地坑内壁间用干砂做背砂填满;连接外部进、回冷却管路,准备浇铸。2. Box assembly: As shown in Figure 16A to Figure 16F, lay the bottom plane of the pit with dry sand to form the required slope (5°~15°) at the place where the forced cooling metal bottom plate is placed, and place the forced cooling metal bottom plate on it. Bottom plate (the side with the pitted grid facing down), rely on the self-weight of the forced cooling metal bottom plate to squeeze the dry sand below into the pits in the grid, connect the forced cooling metal bottom plate into and out of the medium pipeline, and confirm the connection is good through the pressure test , no leakage; then place the lower side plate above the forced cooling metal base plate first, remove the molding sand and impurities on the contact surface between the lower side plate and the forced cooling metal base plate before placing, and then paint a layer of about 1 to 2 mm on the contact surface Alcohol-based refractory mud paste, relying on the self-weight of the lower side plate to flatten and compact the paint paste; penetrate the fastening screw and positioning pin to fasten the lower side plate and the bottom plate; sand the inner side of the bottom plate and the lower side plate surface The paint paste on the sand contact part is filled and smoothed along the contact joint and then ignited; the left and right side panels and the upper side panels are installed in sequence and fastened to each other; finally, the assembled upper side panel, left and right side panels, and the lower side On the top of the plate, place a cover plate with a riser (the molding sand on the contact surface between the cover plate and the left and right side plates, the upper side plate, and the lower side plate is not removed), and the molding sand is tightly contacted and sealed; the fastening screw is penetrated and positioned The pins fasten the cover plate and each side plate; place the casting device, connect the sprue brick in the through hole of the lower side plate, lay the runner brick pipe and the sprue brick pipe, fill the bricks with molding sand, and finally place the casting Funnel (the lower plane of the funnel should be on the same level as the top of the riser), and finally fill the gap between the assembled rectangular mold and the inner wall of the pit with dry sand as back sand; connect the external inlet and return cooling pipelines, and prepare for casting.
三、超大型矩形锭坯的浇注:3. Pouring of super large rectangular ingot:
1.浇铸前需确认冷却介质管道正常无泄露,冷却介质进入阀门处于关闭状态,打开介质流出阀及所有连通排水的通道,保证冷却管内气体能畅通排除。1. Before casting, it is necessary to confirm that the cooling medium pipeline is normal and there is no leakage, the cooling medium inlet valve is closed, and the medium outflow valve and all channels connected to the drainage are opened to ensure that the gas in the cooling pipe can be discharged smoothly.
2.按工艺要求参数浇注钢液,如图17A~图17D所示,经浇注漏斗、直浇道、横浇道、内浇道,钢液由矩形铸模下侧板透孔内的内浇口流入倾斜5°~15°放置的铸模下端,随着钢液的不断冲入,钢液面由下向斜上方推进,夹杂在钢液中的气体、杂质在上浮的过程也随钢液面推移向斜上方移动,直至钢液充满铸型,杂质及气体不断向位于斜上方的冒口内聚集,随着钢液的进一步冲入,杂质及气体被挤压到冒口内部直至距冒口上端面200mm左右停止浇注;冒口上方加保温剂、覆盖剂。2. Molten steel is poured according to the parameters required by the process, as shown in Figure 17A to Figure 17D, through the pouring funnel, sprue, runner, and ingate, the molten steel is poured from the ingate in the through hole of the lower side plate of the rectangular mold It flows into the lower end of the casting mold placed at an inclination of 5°~15°. As the molten steel continues to rush in, the liquid steel surface advances from the bottom to the upward slope, and the gas and impurities mixed in the molten steel are also floating along with the liquid steel surface. Move upwards until the molten steel fills the mold, and impurities and gases continue to accumulate in the riser located at the upper slope. As the molten steel further rushes in, impurities and gases are squeezed into the riser until it is 200mm away from the upper end of the riser. Stop pouring left and right; add insulation and covering agent above the riser.
3.通入冷却介质定向冷却:缓慢打开冷却介质进入管阀门,调整介质进入管压力、流量,控制介质流出管温保持在50℃~80℃间,直至铸件完全凝固。3. Directional cooling by feeding cooling medium: Slowly open the valve of the cooling medium inlet pipe, adjust the pressure and flow rate of the medium inlet pipe, and control the temperature of the medium outflow pipe to maintain between 50°C and 80°C until the casting is completely solidified.
四、停止铸锭操作:待铸锭整体温度达到工艺起模温度后,关闭供冷却管道阀门,待冷却管路介质蒸发完后,卸下连接铸型上的介质进出管。4. Stop the ingot casting operation: After the overall temperature of the ingot reaches the process mold opening temperature, close the valve of the cooling pipeline. After the cooling pipeline medium evaporates, remove the medium inlet and outlet pipes connected to the mold.
五、脱模操作:去除矩形铸模外的背砂,依次卸掉盖板与上侧板、左、右侧板、下侧板间的紧固螺栓,吊起盖板箱;卸掉上侧板、左、右侧板、下侧板与强制冷却金属底板间的紧固螺栓,拆除上侧板、左、右侧板、下侧板,调运钢锭运至清整工序进行清整。5. Demolding operation: Remove the back sand outside the rectangular mold, remove the fastening bolts between the cover plate and the upper side plate, left and right side plates, and the lower side plate in turn, lift the cover plate box; remove the upper side plate , the fastening bolts between the left and right side plates, the lower side plate and the forced cooling metal bottom plate, remove the upper side plate, left and right side plates, and the lower side plate, and transport the steel ingots to the cleaning process for cleaning.
如图18A所示,为利用上述方法和本发明的超大型矩形锭坯倾斜铸造的组合式制造装置,按工艺要求参数浇铸锭坯的仿真结果;图18B为传统铸造自然冷却方法的缺陷仿真结果;图18C为现有技术底面整体水冷的定向凝固法缺陷仿真结果;通过仿真结果对比可知,本发明能够显著提高锭坯质量。As shown in Figure 18A, it is the combined manufacturing device of the super-large rectangular ingot inclined casting using the above method and the present invention, and the simulation result of casting the ingot according to the parameters required by the process; Figure 18B is the defect simulation result of the traditional casting natural cooling method ; FIG. 18C is the defect simulation result of the directional solidification method of the overall water cooling of the bottom surface in the prior art; through the comparison of the simulation results, it can be known that the present invention can significantly improve the quality of the ingot.
本发明具有如下有益的技术效果:The present invention has following beneficial technical effect:
1.采用倾斜铸造方式,大大降低了钢液对铸模的静压力和冲击力,降低了对铸模结合部件间结构强度的要求,使组合式结构的实现成为可能,且大大降低了铸模的结构费用;1. Adopting the inclined casting method greatly reduces the static pressure and impact force of the molten steel on the casting mold, reduces the requirements for the structural strength between the joint parts of the casting mold, makes it possible to realize the combined structure, and greatly reduces the structural cost of the casting mold ;
2.由于强制冷却金属底板的使用使倾斜铸造的大型钢锭由下向上顺序凝固成为可能;2. Due to the use of the forced cooling metal bottom plate, it is possible to sequentially solidify the obliquely cast large steel ingot from bottom to top;
3.由于强制冷却金属底板倾斜放置,保证了大型钢锭在浇铸、凝固的同时杂质、气体等有害物质向斜上方的冒口内聚集排除成为可能;3. Due to the oblique placement of the forced-cooling metal base plate, it is possible to collect and remove impurities, gases and other harmful substances in the riser at the slant above during casting and solidification of large steel ingots;
4.由于倾斜放置的强制冷却金属底板的冷却介质通道采用冷却介质下方进、上方出的方式,铸型受冷却管的冷却下方温度较低,冷却能力较强,随着铸型热量向冷却介质中的传递,冷却介质温度由下向上逐渐升高,冷却能力随之减弱;与铸件要求的冷却顺序一致。4. Since the cooling medium channel of the obliquely placed forced-cooling metal base plate adopts the way of cooling medium entering from below and exiting from above, the temperature of the mold under cooling of the cooling pipe is relatively low, and the cooling capacity is strong. The temperature of the cooling medium gradually increases from the bottom to the top, and the cooling capacity decreases accordingly; it is consistent with the cooling sequence required by the casting.
5.由于强制冷却金属底板中冷却支管采用中间密两侧疏的分布形式,提高了铸件中部传热,可减少疏松;5. Since the cooling branch pipes in the forced cooling metal base plate adopt the distribution form of dense in the middle and sparse on both sides, the heat transfer in the middle of the casting is improved and the looseness can be reduced;
6.由于强制冷却金属底板中冷却金属管架采用多组独立供水的结构,为铸件人为控制顺时冷却创造了条件,使消弱铸件内疏松、消除缩孔成为可能;6. Since the cooling metal pipe frame in the forced cooling metal base plate adopts the structure of multiple sets of independent water supply, it creates conditions for artificially controlled cooling of the castings, making it possible to weaken the looseness in the castings and eliminate shrinkage cavities;
7.由于铸模采用半永久型箱式组合结构,铸模的造型、组装、拆卸更简单灵活;并且使热开箱成为可能;7. Since the casting mold adopts a semi-permanent box-type combined structure, the molding, assembly and disassembly of the casting mold are simpler and more flexible; and it is possible to open the box by heat;
8.由于铸模采用半永久型箱式组合结构,可以通过改变左、右侧板、上、下侧板高度或长度,改变铸模内腔规格尺寸,因此,模具的通用性更强,规格变换更方便,模具费用可大大降低;8. Since the casting mold adopts a semi-permanent box-type combined structure, the specification and size of the cavity of the casting mold can be changed by changing the height or length of the left and right side panels, upper and lower side panels. Therefore, the mold has stronger versatility and more convenient specification conversion , the mold cost can be greatly reduced;
9.由于铸模采用挂砂的半永久型结构,钢液不再直接与金属型接触,避免了钢液飞溅、上升不稳出现的表面冷隔、钢豆等表面缺陷;9. Since the casting mold adopts a semi-permanent structure with hanging sand, the molten steel is no longer in direct contact with the metal mold, which avoids surface defects such as cold shut and steel beans caused by molten steel splashing and unstable rising;
10.由于铸型采用挂砂的半永久型结构,钢液接触砂型表面激冷强度大大降低,降低了表层激冷形核能力,削弱了钢锭表面激冷层极细等轴晶厚度,使得钢锭整体均匀形核倾向大大增加,使得铸锭整体等轴晶比例大大增加;10. Since the casting mold adopts the semi-permanent structure of hanging sand, the quenching strength of the molten steel contacting the sand mold surface is greatly reduced, which reduces the quenching nucleation ability of the surface layer, and weakens the thickness of the ultra-fine equiaxed crystal of the chilling layer on the surface of the steel ingot, making the overall steel ingot The uniform nucleation tendency is greatly increased, which greatly increases the proportion of equiaxed crystals in the whole ingot;
11.由于强制冷却金属底板挂砂厚度的改变(采用下薄、上厚均匀变化),起到了铸模冷却换热的调节和控制作用,有利于疏松、缩孔向冒口方向转移;11. Due to the change of the thickness of the sand hanging on the forced cooling metal bottom plate (the bottom is thin and the top is uniformly changed), it plays a role in regulating and controlling the cooling and heat transfer of the mold, which is conducive to the transfer of loosening and shrinkage holes to the riser;
12.由于半永久型铸模采用树脂砂挂砂材料,砂内不含水及结晶水成分,无需特殊干燥,型砂在浇铸后树脂碳化并溃散后生成物可以避免钢锭表面氧化,溃散后的型砂更有利于脱模;12. Since the semi-permanent casting mold is made of resin sand hanging sand material, the sand does not contain water and crystal water components, and no special drying is required. After casting, the resin carbonization and collapse of the molding sand can avoid the surface oxidation of the steel ingot, and the collapsed molding sand is more beneficial demoulding;
13.由于半永久型铸模树脂砂挂砂层外氧化锆醇基涂料的使用,在钢液的高温烧结下,氧化锆涂料层形成一层坚硬的陶瓷薄壳,一方面阻止了钢液再次向砂层渗透,避免了粘砂,同时有防止型砂卷入钢液污染金属液的作用;13. Due to the use of zirconia alcohol-based coating outside the resin sand hanging sand layer of the semi-permanent casting mold, under the high temperature sintering of molten steel, the zirconia coating layer forms a hard ceramic thin shell, which prevents the molten steel from flowing to the sand again on the one hand. Layer penetration avoids sand sticking, and at the same time prevents molding sand from being involved in molten steel and polluting molten metal;
14.半永久型组合件采用一面为平面,另一面为格子凹坑结构,在保证组合件整体刚度的同时,使该整体铸模重量大大降低(成本降低),同时使应力大大降低(受热变形的可能性降低),使组合件间的固定连接变得更方便。14. The semi-permanent assembly adopts a flat surface on one side and a lattice pit structure on the other side. While ensuring the overall rigidity of the assembly, the weight of the overall mold is greatly reduced (reduced cost), and the stress is greatly reduced (possibility of thermal deformation Reduced sex), making the fixed connection between assemblies more convenient.
综上所述,本发明使得超大型矩形锭坯组合式制造成为可能,同时,具有铸锭等轴晶区大、质量好、金属利用率高等优点。To sum up, the present invention makes it possible to manufacture ultra-large rectangular ingot combined, and at the same time, has the advantages of large equiaxed crystal area, good quality and high metal utilization rate.
以上所述仅为本发明示意性的具体实施方式,并非用以限定本发明的范围。任何本领域的技术人员,在不脱离本发明的构思和原则的前提下所作出的等同变化与修改,均应属于本发明保护的范围。The above descriptions are only illustrative specific implementations of the present invention, and are not intended to limit the scope of the present invention. Any equivalent changes and modifications made by those skilled in the art without departing from the concept and principle of the present invention shall fall within the protection scope of the present invention.
Claims (17)
Priority Applications (1)
| Application Number | Priority Date | Filing Date | Title |
|---|---|---|---|
| CN201110034212A CN102069160B (en) | 2011-01-31 | 2011-01-31 | Combined manufacturing device and method for ultra-large rectangular ingot blank inclined casting |
Applications Claiming Priority (1)
| Application Number | Priority Date | Filing Date | Title |
|---|---|---|---|
| CN201110034212A CN102069160B (en) | 2011-01-31 | 2011-01-31 | Combined manufacturing device and method for ultra-large rectangular ingot blank inclined casting |
Publications (2)
| Publication Number | Publication Date |
|---|---|
| CN102069160A CN102069160A (en) | 2011-05-25 |
| CN102069160B true CN102069160B (en) | 2012-09-12 |
Family
ID=44028037
Family Applications (1)
| Application Number | Title | Priority Date | Filing Date |
|---|---|---|---|
| CN201110034212A Active CN102069160B (en) | 2011-01-31 | 2011-01-31 | Combined manufacturing device and method for ultra-large rectangular ingot blank inclined casting |
Country Status (1)
| Country | Link |
|---|---|
| CN (1) | CN102069160B (en) |
Families Citing this family (5)
| Publication number | Priority date | Publication date | Assignee | Title |
|---|---|---|---|---|
| CN102240779A (en) * | 2011-08-05 | 2011-11-16 | 烟台鲁宝有色合金有限公司 | Process for manufacturing copper alloy in narrow crystallization temperature range |
| CN105728700A (en) * | 2016-02-15 | 2016-07-06 | 柳州职业技术学院 | Casting technique for brass electrode holder |
| CN108555257A (en) * | 2017-12-29 | 2018-09-21 | 中钢集团邢台机械轧辊有限公司 | The pouring procedure of rising pouring steel ingot |
| CN108273959A (en) * | 2018-03-13 | 2018-07-13 | 云南铝业股份有限公司 | A kind of aluminium alloy large-sized thin-wall part sand casting technique |
| CN109808125A (en) * | 2019-01-19 | 2019-05-28 | 湖南上真电子科技有限公司 | A kind of injection molding machine |
Citations (4)
| Publication number | Priority date | Publication date | Assignee | Title |
|---|---|---|---|---|
| CN1269596C (en) * | 2003-06-19 | 2006-08-16 | 哈尔滨工业大学 | Large-scale thin wall aluminium alloy part multi function mobile magnetic field casting device |
| CN201008961Y (en) * | 2007-03-16 | 2008-01-23 | 中国科学院金属研究所 | A casting device for super-large cast steel support rolls of composite material over 100 tons |
| CN101646514A (en) * | 2007-02-28 | 2010-02-10 | 诺维尔里斯公司 | Co-casting of metals by direct-chill casting |
| CN201906799U (en) * | 2011-01-31 | 2011-07-27 | 中冶京诚工程技术有限公司 | Combined manufacturing device for inclined casting of ultra-large rectangular ingot blank |
Family Cites Families (12)
| Publication number | Priority date | Publication date | Assignee | Title |
|---|---|---|---|---|
| US4190096A (en) * | 1978-04-17 | 1980-02-26 | Netes Leonid Y | Manipulator for separating coated permanent moulds |
| US4359202A (en) * | 1980-02-11 | 1982-11-16 | Jones & Laughlin Steel Corporation | Apparatus for bottom casting metal ingots |
| CN2097698U (en) * | 1991-06-29 | 1992-03-04 | 新环公司 | Deep, flat, long type water-cooled steel ingot matrix |
| CN2137572Y (en) * | 1992-10-05 | 1993-07-07 | 胡平 | Horizontal layer-sintered blank mould |
| CN1042000C (en) * | 1995-03-03 | 1999-02-10 | 秦锡满 | Split water-cooling steel inpot dieset and its producing method |
| JPH11309560A (en) * | 1998-04-28 | 1999-11-09 | Sintokogio Ltd | Method for taking out casting and device therefor |
| JP3592252B2 (en) * | 2001-04-05 | 2004-11-24 | 日信工業株式会社 | Casting method and casting apparatus |
| CN1439469A (en) * | 2003-01-26 | 2003-09-03 | 孙柏良 | Vacuum feeding hydrocooling mould cast technology |
| KR100901034B1 (en) * | 2004-04-01 | 2009-06-04 | 신토고교 가부시키가이샤 | Method and device for pouring molten metal in vacuum molding and casting |
| KR101403764B1 (en) * | 2007-08-29 | 2014-06-03 | 노벨리스 인코퍼레이티드 | Sequential casting of metals having the same or similar co-efficients of contraction |
| CN201432080Y (en) * | 2009-07-13 | 2010-03-31 | 齐齐哈尔轨道交通装备有限责任公司 | Casting device |
| CN101791682B (en) * | 2010-04-08 | 2011-09-28 | 中冶京诚工程技术有限公司 | Manufacturing device for rectangular ingot blank of ultra-large extra-thick plate |
-
2011
- 2011-01-31 CN CN201110034212A patent/CN102069160B/en active Active
Patent Citations (4)
| Publication number | Priority date | Publication date | Assignee | Title |
|---|---|---|---|---|
| CN1269596C (en) * | 2003-06-19 | 2006-08-16 | 哈尔滨工业大学 | Large-scale thin wall aluminium alloy part multi function mobile magnetic field casting device |
| CN101646514A (en) * | 2007-02-28 | 2010-02-10 | 诺维尔里斯公司 | Co-casting of metals by direct-chill casting |
| CN201008961Y (en) * | 2007-03-16 | 2008-01-23 | 中国科学院金属研究所 | A casting device for super-large cast steel support rolls of composite material over 100 tons |
| CN201906799U (en) * | 2011-01-31 | 2011-07-27 | 中冶京诚工程技术有限公司 | Combined manufacturing device for inclined casting of ultra-large rectangular ingot blank |
Also Published As
| Publication number | Publication date |
|---|---|
| CN102069160A (en) | 2011-05-25 |
Similar Documents
| Publication | Publication Date | Title |
|---|---|---|
| CN102069160B (en) | Combined manufacturing device and method for ultra-large rectangular ingot blank inclined casting | |
| CN102886501B (en) | Tooling for efficiently manufacturing wide thick plate blank for wide thick plate rolling machine and manufacture method thereof | |
| CN105215303B (en) | A kind of device and method of magnesium alloy slab DC castings | |
| CN107716872A (en) | A kind of casting method of large-scale working ways | |
| CN102114525B (en) | Combined box type water-cooling casting device for ingot blank | |
| CN106475522A (en) | The running gate system of heavy castings and pouring procedure | |
| CN201906799U (en) | Combined manufacturing device for inclined casting of ultra-large rectangular ingot blank | |
| CN111687402A (en) | Tundish composite ladle bottom permanent lining and construction process thereof | |
| CN101905298B (en) | Device and method for manufacturing copper or copper alloy slab | |
| CN201979049U (en) | Box-type water-cooled plate assembly for ingot combined box-type water-cooled casting device | |
| CN201997677U (en) | Ingot combined box-type water-cooled casting device | |
| CN101342574B (en) | Design method for large-scale transverse beam casting parts | |
| CN103464684A (en) | Precise investment casting method | |
| CN106670393A (en) | Core assembling method and die | |
| CN113305268B (en) | Casting method of 12-cubic-meter slag ladle | |
| CN118720055A (en) | A lost foam casting method for square ram of machine tool parts | |
| CN215845577U (en) | Molten iron pouring device for pig casting machine | |
| CN204912687U (en) | Novel rolling ingot mould | |
| CN104985144B (en) | A kind of new rolling ingot mould and its method for designing | |
| CN108213364A (en) | A kind of double cloth flowing water shape of the mouth as one speaks wedge shape current distribution device of twin-roll thin strip continuous casting | |
| CN102126002B (en) | Box-type water-cooling plate assembly for ingot blank combined box-type water-cooling casting device | |
| CN104668521B (en) | Low-pressure casting bath unit | |
| CN207043277U (en) | The casting system of injection machine class template casting | |
| CN114226645A (en) | A casting method for a thin-walled rolling mill stand | |
| CN108705059B (en) | direct forming method for waste casting residue |
Legal Events
| Date | Code | Title | Description |
|---|---|---|---|
| C06 | Publication | ||
| PB01 | Publication | ||
| C10 | Entry into substantive examination | ||
| SE01 | Entry into force of request for substantive examination | ||
| C14 | Grant of patent or utility model | ||
| GR01 | Patent grant |