CN103618251A - Technology for electrified overhaul of +-800kV ultrahigh voltage direct-current transmission line - Google Patents
Technology for electrified overhaul of +-800kV ultrahigh voltage direct-current transmission line Download PDFInfo
- Publication number
- CN103618251A CN103618251A CN201310617102.3A CN201310617102A CN103618251A CN 103618251 A CN103618251 A CN 103618251A CN 201310617102 A CN201310617102 A CN 201310617102A CN 103618251 A CN103618251 A CN 103618251A
- Authority
- CN
- China
- Prior art keywords
- insulator
- live
- card
- wire
- equipotential
- Prior art date
- Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
- Pending
Links
Images
Classifications
-
- H—ELECTRICITY
- H02—GENERATION; CONVERSION OR DISTRIBUTION OF ELECTRIC POWER
- H02G—INSTALLATION OF ELECTRIC CABLES OR LINES, OR OF COMBINED OPTICAL AND ELECTRIC CABLES OR LINES
- H02G1/00—Methods or apparatus specially adapted for installing, maintaining, repairing or dismantling electric cables or lines
- H02G1/02—Methods or apparatus specially adapted for installing, maintaining, repairing or dismantling electric cables or lines for overhead lines or cables
Landscapes
- Electric Cable Installation (AREA)
- Insulators (AREA)
Abstract
本发明提供一种±800kV特高压直流输电线路带电检修工艺。其中进入等电位的作业方法包括以下步骤:等电位工人按照着装规范穿戴完毕后,沿着耐张塔登塔至横担处,系好绝缘保护绳进入横担侧金具联接处,将安全带系在手扶的绝缘子串上;检查屏蔽服装各部分连接良好后,携带电位转移棒准备进入绝缘子串;进入电位时双手抓扶一串绝缘子串,双脚踩另一串绝缘子串,采用横跨两片绝缘子的方式平行移动至距导线侧均压环0.5m处停止;快速伸出电位转移棒,将其钩在最近的子导线或连接金具上进行电位转移。本发明的±800kV特高压直流输电线路带电检修工艺,通过±800kV特高压直流输电线路的特点的研究实现了对项目研究工作的完成及研究成果的应用,填补了国内外特高压直流带电作业、带电检修应用技术领域的空白。
The invention provides a ±800kV ultra-high voltage direct current transmission line live maintenance process. The operation method of entering the equipotential includes the following steps: After the equipotential worker wears clothes according to the dress code, climb the tower to the crossarm along the tension tower, fasten the insulating protection rope and enter the fitting joint on the side of the crossarm, and fasten the safety belt. On the hand-held insulator string; after checking that all parts of the shielding clothing are well connected, carry the potential transfer rod to prepare to enter the insulator string; Parallel movement in the form of a sheet insulator until it stops at 0.5m from the grading ring on the conductor side; quickly extend the potential transfer rod and hook it to the nearest sub-conductor or connecting fitting for potential transfer. The ±800kV UHV DC transmission line live maintenance process of the present invention realizes the completion of the project research work and the application of the research results through the research on the characteristics of the ±800kV UHV DC transmission line, filling the domestic and foreign UHV DC live operation, Blank in the field of live maintenance application technology.
Description
【技术领域】【Technical field】
本发明涉及特高压输变电领域,尤其涉及一种±800kV特高压直流输电线路带电检修工艺。The invention relates to the field of ultra-high voltage power transmission and transformation, in particular to a live maintenance process for ±800kV ultra-high voltage direct current transmission lines.
【背景技术】【Background technique】
输电线路运行维护检修工作是掌握电网运行情况、及时发现和处理设备缺陷的重要手段,也是确保线路安全稳定运行的基础工作。由于特高压电网在整个国家电网运行中处于核心地位,因此特高压电网的运行检修工作对于保证特高压电网乃至整个国家电网的安全、稳定、可靠运行具有十分重要的意义。Transmission line operation, maintenance and repair work is an important means to grasp the operation of the power grid, discover and deal with equipment defects in time, and is also the basic work to ensure the safe and stable operation of the line. Since the UHV power grid is at the core of the operation of the entire national grid, the operation and maintenance of the UHV power grid is of great significance to ensure the safe, stable and reliable operation of the UHV power grid and even the entire national power grid.
±800kV特高压直流线路是一个全新的电压等级,其运行电压、线路结构、窗口间隙等与其它工程相比有大区别,尤其是导线分裂数,绝缘子串组装型式发生了很大的变化。因此,传统的作业方法和检修工器具不能满足特高压直流线路检修的需要。如要进行检修作业、带电作业,首先是必须研究一套科学的作业方法,特高压直流线路检修、带电作业方法及作业工器具的研究将是我们目前急待解决的问题。The ±800kV UHV DC line is a brand-new voltage level. Compared with other projects, its operating voltage, line structure, window gap, etc. are quite different, especially the number of wire splits and the assembly type of insulator strings have undergone great changes. Therefore, traditional operation methods and maintenance tools cannot meet the needs of UHV DC line maintenance. If you want to carry out maintenance work and live work, you must first study a set of scientific work methods. The research on UHV DC line maintenance, live work methods and work tools will be an urgent problem to be solved.
±800kV特高压直流线路检修作业、带电作业是线路运行检修工作的一个重要内容。该课题的研究成果将填补我国特高压直流输电线路检修及带电作业工器具研制和带电作业检修应用技术上的空白。对开创特高压直流线路检修,保证特高压直流带电作业的安全,提高线路检修效率,保证设备的健康水平起到巨大的作用。其次,带电作业技术的应用将大大降低特高压直流线路的停电小时数,提高了线路的可用率,保证了线路的经济、可靠运行。±800kV UHV DC line maintenance work and live work is an important content of line operation maintenance work. The research results of this subject will fill in the gaps in my country's UHV DC transmission line maintenance and live work tool development and live work maintenance application technology gaps. It plays a huge role in creating the maintenance of UHV DC lines, ensuring the safety of UHV DC live work, improving the efficiency of line maintenance, and ensuring the health of equipment. Secondly, the application of live working technology will greatly reduce the number of outage hours of UHV DC lines, improve the availability of lines, and ensure the economical and reliable operation of lines.
【发明内容】【Content of invention】
有鉴于此,为克服现有技术的不足,有必要提供一种适用于±800kV特高压直流输电线路的带电检修工艺。In view of this, in order to overcome the deficiencies of the existing technology, it is necessary to provide a live maintenance process suitable for ±800kV UHV DC transmission lines.
一种±800kV特高压直流输电线路带电检修工艺,所述带电检修工艺包括进入等电位的作业方法,所述进入等电位的作业方法包括以下步骤:等电位工人按照着装规范穿戴完毕后,沿着耐张塔登塔至横担处,系好绝缘保护绳进入横担侧金具联接处,将安全带系在手扶的绝缘子串上;检查屏蔽服装各部分连接良好后,携带电位转移棒准备进入绝缘子串;进入电位时双手抓扶一串绝缘子串,双脚踩另一串绝缘子串,手脚采用最多横跨两片绝缘子的方式平行移动至距导线侧均压环0.5m处停止;快速伸出电位转移棒,将其钩在最近的子导线或连接金具上进行电位转移。A live overhaul process for ±800kV UHVDC transmission lines, the live overhaul process includes an operation method for entering equipotentiality, and the operation method for entering equipotentiality includes the following steps: after equipotential workers are dressed in accordance with the dress code, wear along Ascend the tension tower to the cross arm, fasten the insulation protection rope and enter the metal fitting joint on the cross arm side, tie the safety belt on the hand-held insulator string; after checking that all parts of the shielding clothing are well connected, carry the potential transfer rod and prepare to enter Insulator strings; when entering the potential, grasp one string of insulator strings with both hands, step on the other string of insulator strings with both feet, move hands and feet in parallel across two insulators at most, and stop at a distance of 0.5m from the voltage equalizing ring on the conductor side; quickly extend Potential transfer rod, hook it on the nearest sub-wire or connecting hardware for potential transfer.
在其中至少一个实施例中,在所述进入等电位的作业方法中,等电位工人进入电位后系好安全带,并根据作业需要来确定是否解除绝缘保护绳。In at least one of the embodiments, in the working method of entering the equipotential, the equipotential worker fastens the safety belt after entering the potential, and determines whether to release the insulation protection rope according to the operation requirements.
在其中至少一个实施例中,所述着装规范包括穿着全套屏蔽服装以及屏蔽服装内穿阻燃内衣,所述屏蔽服装包括屏蔽帽、屏蔽衣裤、屏蔽手套、屏蔽袜、屏蔽鞋以及屏蔽面罩。In at least one of the embodiments, the dress code includes wearing a full set of shielding clothing and wearing flame-resistant underwear inside the shielding clothing, and the shielding clothing includes shielding hats, shielding underwear, shielding gloves, shielding socks, shielding shoes and shielding masks.
在其中至少一个实施例中,如果所述带电检修工艺中包括玻璃绝缘子的检修和/或更换,等电位工人在进入等电位前还要佩戴护目镜。In at least one of the embodiments, if the live repair process includes the repair and/or replacement of glass insulators, the equipotential workers must wear goggles before entering the equipotential.
在其中至少一个实施例中,在带电检修工作完成后,等电位工人按照以下步骤退出等电位:检查屏蔽服装各部分连接良好后,将电位转移棒的金属端钩在子导线或连接金具上,一只手握紧绝缘手柄,进入绝缘子串距导线侧均压环0.5m处停止(保持手臂伸直状态);迅速脱开电位转移棒与子导线或连接金具的连接,并将电位转移棒收回牢固放置在身上,按照手脚最多横跨两片绝缘子(“跨二短三”)的方式退出等电位返回横担;检查塔上无遗留物后,携带绝缘传递绳下塔。In at least one of the embodiments, after the live maintenance work is completed, the equipotential worker exits the equipotential according to the following steps: After checking that all parts of the shielding clothing are well connected, hook the metal end of the potential transfer rod on the sub-conductor or the connecting hardware, Hold the insulated handle firmly with one hand, enter the insulator string and stop at 0.5m from the voltage equalizing ring on the conductor side (keep the arm straight); quickly disconnect the potential transfer rod from the sub-conductor or the connecting fitting, and retract the potential transfer rod Put it firmly on the body, and exit the equipotential return cross arm in a way that the hands and feet span at most two pieces of insulators ("cross two short three"); after checking that there is no residue on the tower, carry the insulation transmission rope down the tower.
在其中至少一个实施例中,所述带电检修工艺包括更换直线双“V”绝缘子串、硬转双“L”绝缘子串的作业方法,所述更换直线双“V”绝缘子串、硬转双“L”绝缘子串的作业方法包括以下步骤:从直线塔进入电位后,利用绝缘子串挂点处预留施工孔或挂点处主材做工具的塔上支点,安装杆塔横担专用卡具,利用导线侧二联板做工具的导线侧支点安装大刀卡;通过提线装置、高强度绝缘拉杆与塔上专用卡具相连,组成绝缘子串的机械荷载转移系统;利用大刀卡的卡背与二联板接触处作为支点,并将大刀卡分成作用臂和操作臂,操作提线装置进行小距离的提线变位,驱动大刀卡操作臂转动,带动作用臂转移绝缘子串上荷载,使被检修绝缘子串机械荷载转移到提线系统,实现绝缘子串的检修和更换。In at least one of the embodiments, the live maintenance process includes the operation method of replacing straight double "V" insulator strings and hard turning double "L" insulator strings. The operation method of the L” insulator string includes the following steps: After entering the potential from the straight tower, use the reserved construction hole at the hanging point of the insulator string or the main material at the hanging point as the upper fulcrum of the tool tower, install the special fixture for the cross arm of the pole tower, use The two-piece plate on the wire side is used as the fulcrum of the wire side of the tool to install the big knife card; it is connected with the special clamp on the tower through the wire lifting device and the high-strength insulating pull rod to form a mechanical load transfer system for the insulator string; the back of the big knife card and the two The contact point of the connecting plate is used as a fulcrum, and the big knife card is divided into an action arm and an operating arm, and the wire lifting device is operated to carry out a small-distance lifting displacement, driving the big knife card operating arm to rotate, and driving the action arm to transfer the load on the insulator string, so that the overhauled The mechanical load of the insulator string is transferred to the wire lifting system to realize the maintenance and replacement of the insulator string.
在其中至少一个实施例中,在所述更换直线双“V”绝缘子串、硬转双“L”绝缘子串的作业方法中,所述导线侧二联板包括L-6465S、L-8465S、Z-6450S和Z-84S二联板,所述提线装置包括机械丝杆和液压丝杆。In at least one of the embodiments, in the operation method of replacing straight double "V" insulator strings and hard-turned double "L" insulator strings, the two-connector plate on the conductor side includes L-6465S, L-8465S, Z -6450S and Z-84S two-joint plate, the thread lifting device includes a mechanical screw rod and a hydraulic screw rod.
在其中至少一个实施例中,所述带电检修工艺包括更换直线单“V”、双“V”绝缘子串的作业方法,所述更换直线单“V”、双“V”绝缘子串的作业方法包括以下步骤:用导线联板正上方处预留施工孔或主材做工具的横担侧支点,安装横担侧工具或连接工具;通过横担侧卡具连接高强度绝缘拉杆、液压丝杆以及六分裂提线器,组成两套独立受力的提线系统;操作液压丝杆提升导线转移绝缘子串的机械荷载,实现绝缘子串的检修和更换。In at least one of the embodiments, the live maintenance process includes the operation method of replacing the straight single "V" and double "V" insulator strings, and the operation method of replacing the straight single "V" and double "V" insulator strings includes The following steps: Use the reserved construction hole or the main material directly above the wire connecting plate as the cross-arm side fulcrum of the tool, install the cross-arm side tool or connecting tool; connect the high-strength insulating pull rod and hydraulic screw rod through the cross-arm side clamp And a six-split wire lifter to form two sets of independent force-bearing wire lifting systems; operate the hydraulic screw to lift the wire to transfer the mechanical load of the insulator string, and realize the maintenance and replacement of the insulator string.
在其中至少一个实施例中,所述带电检修工艺包括更换耐张绝缘子的作业方法,所述更换耐张绝缘子的作业方法包括以下步骤:利用P-42S-120联板做支点安装牵引板翼型卡,利用绝缘子钢帽做支点安装绝缘子闭式卡前卡,用液压丝杆连接翼型卡和闭式卡组成紧线系统;利用绝缘子钢帽做支点分别安装绝缘子闭式卡的前卡和后卡,用液压丝杆连接绝缘子闭式卡的前卡和后卡组成紧线系统;利用绝缘子钢帽做支点安装绝缘子闭式卡后卡,利用牵引板和平行挂板支点安装三联耐张卡,用液压丝杆连接闭式卡和三联耐张卡组成紧线系统;操作液压丝杆收紧紧线系统,转移被检修绝缘子上的机械荷载,实现绝缘子的更换和检修。In at least one of the embodiments, the live maintenance process includes the operation method of replacing the tension insulator, and the operation method of replacing the tension insulator includes the following steps: using the P-42S-120 connecting plate as a fulcrum to install the traction plate airfoil Use the insulator steel cap as the fulcrum to install the front card of the insulator closed card, and use the hydraulic screw to connect the airfoil card and the closed card to form a tight line system; use the insulator steel cap as the fulcrum to install the front card and the rear of the insulator closed card respectively The clamp is connected with the front clamp and the rear clamp of the closed clamp of the insulator by a hydraulic screw rod to form a tight line system; the steel cap of the insulator is used as the fulcrum to install the rear clamp of the closed clamp of the insulator, and the triple tension clamp is installed by using the traction plate and the fulcrum of the parallel hanging plate. A hydraulic screw rod is used to connect closed clamps and triple tension clamps to form a tightening system; operate a hydraulic screw rod to tighten the tightening system, transfer the mechanical load on the overhauled insulator, and realize the replacement and maintenance of the insulator.
本发明的±800kV特高压直流输电线路带电检修工艺,是国内外第一个特高压带电作业应用技术研究项目,通过±800kV特高压直流输电线路的特点的研究实现了对项目研究工作的完成及研究成果的应用,填补了国内外特高压直流带电作业、带电检修应用技术领域的空白。The ±800kV UHV DC transmission line live maintenance process of the present invention is the first UHV live operation application technology research project at home and abroad, and the completion of the project research work has been realized through the research on the characteristics of the ±800kV UHV DC transmission line. The application of research results has filled the gaps in the field of UHV DC live work and live maintenance application technology at home and abroad.
【附图说明】【Description of drawings】
图1为采用本发明的较佳实施例±800kV特高压直流输电线路带电检修工艺中进入等电位的方法的示意图。Fig. 1 is a schematic diagram of a method for entering equipotentiality in the live maintenance process of a ±800kV UHV DC transmission line according to a preferred embodiment of the present invention.
图2为“正提线”方法更换绝缘子串的示意图。Fig. 2 is a schematic diagram of replacing the insulator string by the method of "lifting the line".
图3A、3B分别为更换直线双“V”绝缘子串、硬转双“L”绝缘子串作业方法中采用的大刀卡的主视图和俯视图。Figures 3A and 3B are the front view and top view of the big knife card used in the replacement of straight double "V" insulator strings and hard-turned double "L" insulator strings, respectively.
图4为采用图3中的大刀卡更换直线双“V”绝缘子串、硬转双“L”绝缘子串的操作示意图。Fig. 4 is a schematic diagram of the operation of replacing straight double "V" insulator strings and hard-turned double "L" insulator strings using the big knife card in Fig. 3.
图5为“双提线法”更换直线单“V”、双“V”绝缘子串的作业方法的示意图。Fig. 5 is a schematic diagram of the operation method of replacing straight single "V" and double "V" insulator strings by "double lifting method".
图6为更换耐张绝缘子的作业方法的操作示意图。Fig. 6 is an operation schematic diagram of a working method for replacing a tension insulator.
图7A、7B分别为更换耐张绝缘子的方法中所采用的液压式闭式卡前卡和后卡的结构示意图。7A and 7B are structural schematic diagrams of the front and rear hydraulic clamps used in the method of replacing the tension insulator respectively.
图8A、8B分别为更换耐张绝缘子的方法中所采用的三联耐张卡的局部剖视图和另一角度的局部剖视图。8A and 8B are a partial cross-sectional view and a partial cross-sectional view from another angle of the triple strain card used in the method of replacing the strain insulator, respectively.
图9为更换耐张绝缘子的方法中所采用的牵引板翼型卡的结构示意图。Fig. 9 is a schematic structural diagram of the traction plate airfoil card used in the method for replacing the tension insulator.
【具体实施方式】【Detailed ways】
为更好地理解本发明,以下将结合附图和具体实例对发明进行详细的说明。In order to better understand the present invention, the invention will be described in detail below in conjunction with the accompanying drawings and specific examples.
在对本发明的技术方案进行详细的介绍之前,首先对项目研究的理论基础进行简单的陈述:Before the technical scheme of the present invention is introduced in detail, at first the theoretical basis of the project research is briefly stated:
(1)依据中国电力工程顾问集团公司等设计单位提供的特高压直流线路杆塔结构、绝缘子串型、金具连接形式、导地线布置方式以及线路机械荷载水平和空气间隙形式;(1) According to the UHV DC line tower structure, insulator string type, fitting connection form, ground wire layout, line mechanical load level and air gap form provided by China Electric Engineering Consulting Group Corporation and other design units;
(2)依据中国电力科学研究院±800kV向上直流输电线路过电压水平的分析计算及±800kV带电作业间隙试验研究,提出的特高压直流带电作业最小安全距离、最小组合间隙、工具有效绝缘长度和有效绝缘子片数等带电作业绝缘配合理论值;(2) Based on the analysis and calculation of the overvoltage level of the ±800kV upward DC transmission line of the China Electric Power Research Institute and the experimental research on the ±800kV live working gap, the minimum safe distance for UHV DC live working, the minimum combined gap, the effective insulation length of tools and The theoretical value of insulation coordination for live work such as the number of effective insulators;
(3)依据中国电力科学研究院±800kV特高压直流带电作业人员安全防护措施研究,提交的带电作业人员安全防护数据。(3) According to the research on the safety protection measures for live workers of ±800kV UHV DC by China Electric Power Research Institute, the safety protection data of live workers are submitted.
在本发明的技术项目进行研究之时,±800kV特高压直流输电工程正在建设或是刚入投运期,直流特高压输电线路检修、带电作业工作在国内外尚未开展。虽然中国电力科学研究院在±800kV带电作业基本技术理论上进行了大量的试验研究工作,但要进行实际的带电作业,还需在严格的理论论证和技术试验的基础上,进行带电作业项目实用化研究。在认真分析了±800kV向上特高压直流输电线路设计参数,充分探讨了±800kV与之前的电压等级带电作业的差异性、特殊性,确定±800kV特高压直流线路带电作业绝缘配合参数,验证了带电作业人员防护的具体措施。When the technical project of the present invention was researched, the ±800kV UHV DC transmission project was under construction or had just entered into operation, and the maintenance and live work of DC UHV transmission lines had not yet been carried out at home and abroad. Although the China Electric Power Research Institute has carried out a lot of experimental research work on the basic technical theory of ±800kV live work, but to carry out the actual live work, it is necessary to carry out live work projects on the basis of strict theoretical demonstration and technical tests. chemical research. After carefully analyzing the design parameters of the ±800kV UHV DC transmission line upwards, fully discussing the differences and particularities of the ±800kV and previous voltage level live work, the insulation coordination parameters of the ±800kV UHV DC line live work were determined, and the liveline work was verified. Specific measures for worker protection.
首先,进入等电位作业是带电作业基本作业方式,又是其他带电作业项目实现的基础。首先突破进入电位的难关,根据±800kV直流输电线路设计结构特点,杆塔窗口尺寸以及作业要求的间隙形式和空气间隙水平,摒弃了传统的横担挂软梯垂直进入等电位的方式,研究设计了耐张塔沿双串绝缘子串自由作业水平进入等电位的作业方法。First of all, entering the equipotential operation is the basic operation method of live work, and it is also the basis for the realization of other live work projects. First of all, break through the difficulty of entering the potential. According to the structural characteristics of the ±800kV DC transmission line design, the size of the tower window, the gap form and the air gap level required by the operation, and abandoning the traditional method of vertically entering the equipotential with a soft ladder hanging on the cross-arm, the design of the resistance The operation method of Zhangta entering the equipotential horizontally along the double string insulator string free operation.
以下将对耐张塔沿双串绝缘子串自由作业水平进入等电位的作业方法进行详细地介绍。The following will introduce in detail the operation method of the strain tower entering the equipotential horizontally along the free operation of the double string insulator strings.
在进入等电位前,等电位工人必须穿着全套屏蔽服装,包括帽、衣裤、手套、袜和鞋,并戴好屏蔽面罩。此外,屏蔽服装内还应穿阻燃内衣。如果绝缘子串为玻璃绝缘子,则还需要佩戴护目镜。Before entering the equipotential, equipotential workers must wear a full set of shielding clothing, including caps, underwear, gloves, socks and shoes, and wear a shielding mask. In addition, flame-retardant underwear should be worn under the shielding clothing. If the insulator string is a glass insulator, you also need to wear goggles.
等电位工人按照上述着装规范穿戴完毕后,按照下面的步骤进入等电位:After equipotential workers are dressed in accordance with the above dress code, follow the steps below to enter equipotential:
(1)沿着耐张塔登塔至横担处后,系好绝缘保护绳进入横担侧金具联接处,将安全带系在手扶的绝缘子串上;(1) After ascending the tower along the tension tower to the cross arm, fasten the insulation protection rope and enter the fitting joint on the cross arm side, and tie the safety belt to the hand-held insulator string;
(2)检查屏蔽服装各部分连接良好后,携带电位转移棒准备进入绝缘子串;(2) After checking that all parts of the shielding clothing are well connected, carry the potential transfer rod and prepare to enter the insulator string;
(3)进入电位时双手抓扶一串绝缘子串,双脚踩另一串绝缘子串,手脚最采用最多横跨两片绝缘子(“跨二短三”)的方式平行移动至距导线侧均压环0.5m处停止;(3) When entering the potential, grasp a string of insulators with both hands, step on the other string of insulators with both feet, and move the hands and feet in parallel to the side of the wire to equalize the voltage by straddling two insulators at most ("cross two short three") Stop at 0.5m from the ring;
(4)快速伸出电位转移棒,将其钩在最近的子导线或连接金具上进行电位转移;(4) Quickly stretch out the potential transfer rod and hook it to the nearest sub-wire or connecting fitting for potential transfer;
(5)进入电位后系好安全带,并根据作业需要来确定是否解除绝缘保护绳。作业人员系着保护绳和安全带是起着双保护的作用。然而,因为保护绳的长度有限,进入电位后在保护绳长度范围内作业时可不用解除,比如更换导线侧金具、均压环等;但是如果要是到更远的地方作业,例如更换导线间隔棒、修补导线等,保护绳长度不够的话就需要解除保护绳,解除保护绳后退出时仍需要打好保护绳。(5) After entering the potential, fasten the safety belt, and determine whether to release the insulation protection rope according to the needs of the operation. Operators wear protective ropes and safety belts for double protection. However, because the length of the protection rope is limited, it is not necessary to release it when working within the length of the protection rope after entering the potential, such as replacing the metal fittings on the wire side, the pressure equalizing ring, etc.; but if you want to work at a farther place, such as replacing the wire spacer , repair wires, etc., if the length of the protection rope is not enough, you need to remove the protection rope, and you still need to lay the protection rope when you exit after removing the protection rope.
进入等电位后,即可进行±800kV直流输电线路的带电检修工作。例如,带电更换导线防振锤、带电更换耐张导线侧金具、带电更换调整导线间隔棒以及带电更换绝缘子等。下文中将对其中部分部件的检修工艺进行详细地说明。After entering the equipotential, the live maintenance work of ±800kV DC transmission line can be carried out. For example, live replacement of anti-vibration hammers, live replacement of tension wire side fittings, live replacement of adjustable wire spacers, and live replacement of insulators, etc. The maintenance process of some of the components will be described in detail below.
在带电检修工作完成后,等电位工人可按照如下方法退出等电位:After the live maintenance work is completed, the equipotential worker can exit the equipotential according to the following methods:
(1)检查屏蔽服装各部分连接良好后,将电位转移棒的金属端钩在子导线或连接金具上,一只手握紧绝缘手柄,进入绝缘子串距导线侧均压环0.5m处停止(保持手臂伸直状态);(1) After checking that all parts of the shielding clothing are well connected, hook the metal end of the potential transfer rod on the sub-conductor or connecting hardware, hold the insulating handle tightly with one hand, enter the insulator string and stop at a place 0.5m away from the equalizing ring on the conductor side ( keep your arms straight);
(2)迅速脱开电位转移棒与子导线或连接金具的连接,并将电位转移棒收回牢固放置在身上,按照手脚最多横跨两片绝缘子(“跨二短三”)的方式退出等电位返回横担;(2) Quickly disengage the connection between the potential transfer rod and the sub-conductor or connecting fittings, retract the potential transfer rod and place it firmly on the body, and exit the equipotential in the way that the hands and feet span at most two pieces of insulators ("cross two short three") return crossarm;
(3)检查塔上无遗留物后,携带绝缘传递绳下塔。(3) After checking that there are no residues on the tower, carry the insulating transmission rope and go down the tower.
根据上述进入和退出电位的方法,即可对±800kV直流输电线路耐张塔上的部件进行检修。由于±800kV直流输电线路中的作业项目多,部分部件的检修方式与之前的作业方法相同,因此在此不做赘述。下面将对带电更换耐张绝缘子等带电检修工艺的重点操作方法进行详细地说明。According to the above method of entering and exiting the potential, the components on the tension tower of the ±800kV direct current transmission line can be overhauled. Since there are many work items in the ±800kV DC transmission line, the maintenance method of some components is the same as the previous work method, so it will not be repeated here. The following will describe in detail the key operation methods of the live overhaul process such as live replacement of tension insulators.
首先,对“杠杆原理微提线法”更换直线双“V”绝缘子串、硬转双“L”绝缘子串的作业方法进行说明。First of all, the operating method of replacing straight double "V" insulator strings and hard-turning double "L" insulator strings with the "lever principle micro-lifting method" is explained.
在±800kV特高压直流向上工程设计中,一般线路段大量采用双“V”绝缘子串和双“L”绝缘子串的组装方式。当绝缘子串零部件出现缺陷时,一般采用“正提线”方式转移绝缘子串的机械荷载,检修和更换绝缘子串。请参阅图2,所谓的“正提线”方式主要是指,用导线联板正上方处预留施工孔(或主材)做工具的塔上支点,安装杆塔横担专用卡具(或连接工具),通过连接提线装置(机械丝杆或液压丝杆)、高强度绝缘拉杆、六分裂提线器相连与导线相连,组成绝缘子串的机械荷载转移系统。通过操作机械丝杆或液压丝杆使荷载转移系统收紧受力,缓慢将导线提起,使被检修绝缘子串机械荷载转移到提线系统,实现绝缘子串的检修。然而,这种“正提线”的作业方式的提线工器具的机械荷载大,可能会造成检修侧绝缘子串水平方向受力变小,从而使导线向相反方向偏移,当且在检修有缺陷的绝缘子串时,绝缘子串复位时还要采用防止导线横向位移措施,以免检修绝缘子串复位困难。In the engineering design of ±800kV UHV DC upward, a large number of general line sections adopt the assembly method of double "V" insulator strings and double "L" insulator strings. When the parts of the insulator string are defective, the mechanical load of the insulator string is generally transferred by the method of "positive lifting" to repair and replace the insulator string. Please refer to Figure 2. The so-called "positive wire lifting" method mainly refers to using the reserved construction hole (or main material) directly above the wire connecting plate as the upper fulcrum of the tool, and installing the special fixture (or connecting Tools), by connecting the wire lifting device (mechanical screw or hydraulic screw), high-strength insulating pull rod, six-split wire lifting device connected to the wire, to form a mechanical load transfer system of the insulator string. By operating the mechanical screw or hydraulic screw to tighten the load transfer system and slowly lift the wires, the mechanical load of the insulator string to be inspected is transferred to the wire lifting system to realize the inspection of the insulator string. However, the mechanical load of the wire lifting tool in this "positive wire lifting" operation method may cause the horizontal force of the insulator string on the maintenance side to be reduced, so that the wires will deviate in the opposite direction. In the case of defective insulator strings, measures should be taken to prevent the lateral displacement of the wires when the insulator strings are reset, so as to avoid the difficulty of repairing the insulator strings.
因此,根据±800kV特高压直流输电线路设计的结构特点,在本项目中更换直线双“V”绝缘子串、硬转双“L”绝缘子串作业采用大刀卡并利用“杠杆原理微提线作业法”转移绝缘子串的机械荷载。大刀卡的结构如图3A、3B中所示。请结合参阅图4,大刀卡的一端为与倒三角二联板的穿心螺杆相匹配的挂钩,另一端为用于外接丝杆的开口。连接挂钩和开口的腰部上设有与倒三角二联板的底侧面相接触的平台。大刀卡的挂钩端开有将其套装在倒三角二联板两侧的卡口,卡口的根部平台与倒三角二联板底侧面相接触。大刀卡的开口两侧设有安装滚花螺钉的通孔,该通孔用于外接丝杆。大刀卡的腰部还设有凹槽。如果需要在相对于三角二联板上某一侧面上的金具进行预维护和检修,则首先将大刀卡的卡口卡装在倒三角二联板该侧面底部的同时,挂钩勾住处于倒三角二联板中心的穿心螺杆,卡口的根部平台托起倒三角二联板的预维护和检修的一端,这样倒三角二联板上侧面的另一端即为支点,开口端即为杠杆末端。然后再在开口端外接丝杆,通过人工调节丝杆来对开口端施加力,这样杠杆末端即开口处只需施加较小的力量便可将三角二联板的预维护和检修的一端上的较重载荷卸掉。Therefore, according to the structural characteristics of the ±800kV UHV DC transmission line design, in this project, the operation of replacing the straight double "V" insulator string and the hard-turned double "L" insulator string is carried out using a large knife card and using the "leverage principle micro-lifting operation method" "Transfer the mechanical load of the insulator string. The structure of the knife card is shown in Fig. 3A, 3B. Please refer to Fig. 4, one end of the big knife card is a hook matched with the through-hole screw of the inverted triangular double plate, and the other end is an opening for an external screw. The waist connecting the hook and the opening is provided with a platform in contact with the bottom side of the inverted triangular double plate. The hook end of the big knife card is provided with a bayonet for fitting it on both sides of the inverted triangular double plate, and the root platform of the bayonet is in contact with the bottom side of the inverted triangular double plate. There are through holes for installing knurled screws on both sides of the opening of the large knife card, and the through holes are used for external screw rods. There are also grooves on the waist of the big knife card. If it is necessary to carry out pre-maintenance and overhaul of the hardware on one side of the triangular two-joint plate, firstly install the bayonet of the big knife card on the bottom of the side of the inverted triangular two-joint plate, and at the same time hook the hook on the inverted triangle The center-piercing screw in the center of the double plate, the root platform of the bayonet supports one end of the pre-maintenance and inspection of the inverted triangular double plate, so that the other end of the side of the inverted triangular double plate is the fulcrum, and the open end is the end of the lever . Then externally connect the screw mandrel at the opening end, and apply force to the opening end by manually adjusting the screw mandrel, so that the end of the lever, that is, the opening, only needs to apply a small force to move the triangular double plate on one end of the pre-maintenance and overhaul. Heavy loads are shed.
采用大刀卡并利用“杠杆原理微提线作业法”更换直线双“V”绝缘子串、硬转双“L”绝缘子串的作业方法的具体操作如下:The operation method of replacing the straight double "V" insulator string and the hard-turned double "L" insulator string by using the big knife card and using the "leverage principle micro-lifting operation method" is as follows:
(1)从直线塔进入电位后,利用绝缘子串挂点处预留施工孔(或挂点处主材)做工具的塔上支点,安装杆塔横担卡具,利用导线侧二联板(L-6465S、或L-8465S、或Z-6450S、或Z-84S)做工具的导线侧支点安装大刀卡;(1) After entering the potential from the straight tower, use the reserved construction hole (or the main material at the hanging point) at the hanging point of the insulator string as the upper fulcrum of the tool, install the cross-arm fixture of the pole tower, and use the two-piece plate on the wire side (L -6465S, or L-8465S, or Z-6450S, or Z-84S) as the wire side fulcrum of the tool to install the big knife card;
(2)通过提线装置(机械丝杆或液压丝杆)、高强度绝缘拉杆与塔上专用卡具相连,组成绝缘子串的机械荷载转移系统;(2) Through the wire lifting device (mechanical screw or hydraulic screw), the high-strength insulating pull rod is connected with the special fixture on the tower to form a mechanical load transfer system for the insulator string;
(3)利用大刀卡的卡背与二联板接触处作为支点,并将大刀卡分成作用臂和操作臂,操作提线装置进行小距离的提线变位,驱动大刀卡操作臂转动,带动作用臂转移绝缘子串上荷载,使被检修绝缘子串机械荷载转移到提线系统,实现绝缘子串的检修。(3) Use the contact between the card back of the big knife card and the two-piece plate as the fulcrum, and divide the big knife card into an action arm and an operating arm, operate the thread lifting device to carry out small-distance lifting displacement, drive the big knife card operating arm to rotate, and drive The action arm transfers the load on the insulator string, so that the mechanical load of the overhauled insulator string is transferred to the wire lifting system, and the maintenance of the insulator string is realized.
在上述工艺中,双“V”绝缘子串、硬转双“L”绝缘子串大刀卡的工作负荷为50KN。上述工艺由于利用了杠杆原理,操作提线装置进行小距离的提线变位,即可驱动大刀卡操作臂转动,带动作用臂转移绝缘子串上荷载,可方便、快捷地更换双“V”绝缘子串、硬转双“L”绝缘子串。In the above process, the working load of double "V" insulator strings and hard-to-double "L" insulator strings is 50KN. Due to the utilization of the lever principle, the above-mentioned process can drive the operating arm of the large knife card to rotate by operating the wire lifting device to carry out a small-distance lifting displacement, and drive the action arm to transfer the load on the insulator string, which can easily and quickly replace the double "V" insulators String, hard to double "L" insulator string.
接下来,将对“双提线法”更换直线单“V”、双“V”绝缘子串的作业方法进行说明。Next, the operation method of replacing straight single "V" and double "V" insulator strings by "double lifting method" will be described.
±800kV特高压直流输电线路向上线中,一般线路段平原地区虽然平均使用档距较大,但大多垂直档距并不大,所以大量采用了单“V”绝缘子串的组装形式。当需进行绝缘子串检修时,可采用“双提线方式”转移绝缘子串的机械荷载。请结合参阅图5,其具体操作方式如下:In the upward line of the ±800kV UHV DC transmission line, although the average span of the plain area of the general line section is large, most of the vertical spans are not large, so a large number of assembly forms of single "V" insulator strings are used. When the maintenance of insulator strings is required, the mechanical load of the insulator strings can be transferred by the "double lifting method". Please refer to Figure 5, the specific operation method is as follows:
(1)用导线联板正上方处预留施工孔(或主材)做工具的横担侧支点,安装横担侧专用工具(或连接工具);(1) Use the construction hole (or main material) reserved directly above the wire connecting plate as the cross-arm side fulcrum of the tool, and install the special tool (or connection tool) for the cross-arm side;
(2)通过横担侧专用卡具连接高强度绝缘拉杆、液压丝杆以及六分裂提线器与六分裂导线,组成两套独立受力的提线系统;(2) Connect high-strength insulating pull rods, hydraulic screw rods, six-split wire lifters and six-split wires through special fixtures on the cross-arm side to form two sets of independent force-bearing wire lifting systems;
(3)操作液压丝杆提升导线转移绝缘子串的机械荷载,实现绝缘子串的检修。(3) Operate the hydraulic screw rod to lift the wire to transfer the mechanical load of the insulator string to realize the maintenance of the insulator string.
向上线直线塔在最大垂直档距时,双“V”绝缘子串的垂直机械荷载可达12.26T,若采用传统的提线法提线转移绝缘子串的机械荷载,提线工具的提线荷载为6.7T,很难保证满足要求。上述双提线法更换双“V”绝缘子串,相对于承担相同荷载时,因具有两套独立受力的提线系统进行保护,其采用的工器具相对单提线系统中工器具承担荷载小,其工器具尺寸可适当较小,如此也就相应地增大了导线距横担的间隙距离,更有利于带电作业的安全进行。此外,因工器具的尺寸变小,在运输、安装以及提高检修效率方面也存在相当大的优势。When the straight-line tower of the upward line is at the maximum vertical span, the vertical mechanical load of the double "V" insulator string can reach 12.26T. If the mechanical load of the insulator string is transferred by using the traditional wire-lifting method, the wire-lifting load of the wire-lifting tool is 6.7T, it is difficult to guarantee to meet the requirements. Compared with the double "V" insulator strings replaced by the above-mentioned double-lifting method, compared with bearing the same load, because there are two sets of independent force-bearing wire-lifting systems for protection, the tools used in it are relatively small in load compared with the single-lifting system. , the size of the tool can be appropriately smaller, so that the gap distance between the wire and the cross arm is correspondingly increased, which is more conducive to the safe operation of live work. In addition, due to the smaller size of tools, there are also considerable advantages in terms of transportation, installation and improved maintenance efficiency.
最后,将对更换耐张绝缘子的作业方法进行详细的说明。Finally, the working method of replacing the tension insulator will be described in detail.
更换耐张绝缘子、绝缘子串是输电线路检修和带电作业的常规项目,也是输电线路运行检修的日常工作。一般的检修工艺中更换耐张绝缘子、绝缘子串有传统的采用托瓶架更换耐张绝缘子法和改进后的旋放法更换耐张绝缘子法。托瓶架法是,在检修绝缘子串两端安装紧线系统,并在其下方放置托瓶架,收紧紧线系统使绝缘子串免受导线张力,然后脱开绝缘子串与导线、横担的链接,然后通过绝缘吊绳用托瓶架将检修绝缘子串放置地面,之后反作业流程完成检修作业。旋放法是,先用绝缘子串张力调整器放松绝缘子,然后用牵引系统反牵绝缘子将导线侧瓷瓶脱开,沿塔悬挂点旋放瓷瓶串至垂直位置后再放至地面。反作业流程完成检修作业。Replacing tension insulators and insulator strings is a routine item for transmission line maintenance and live work, and it is also a daily work for transmission line operation and maintenance. In the general maintenance process, the replacement of strain insulators and insulator strings includes the traditional method of replacing strain insulators with bottle holders and the improved method of replacing strain insulators with rotary release. The bottle support method is to install a tightening system at both ends of the insulator string for inspection and maintenance, and place a bottle holder below it, tighten the tightening system to protect the insulator string from the tension of the wire, and then disengage the insulator string from the wire and the cross arm. Link, and then place the overhaul insulator string on the ground with the bottle holder through the insulating sling, and then reverse the operation process to complete the overhaul operation. The method of rotation is to loosen the insulator with the insulator string tension adjuster first, then use the traction system to pull the insulator back to disengage the porcelain bottle on the wire side, and rotate the porcelain bottle string along the suspension point of the tower to a vertical position before placing it on the ground. Reverse the operation process to complete the maintenance work.
在±800kV特高压直流输电线路向上直流线路中,耐张绝缘子串设计成水平三联串组装方式,一般串长达18m,单串重量达1.5T。虽然整串更换的检修方式,采用传统的耐张绝缘子串更换方法进行施工机具的组织和现场的实际操作在技术上都是可以实现的,但作为常规检修,特别是采取带电作业的方式进行检修还是有相当大的难度。因此,本项目根据向上特高压直流工程三联耐张的设计结构和采用的绝缘形式(盘型瓷瓶绝缘子),选用单片更换的作业方式。请结合参阅图6,其具体的操作流程如下:In the upward DC line of the ±800kV UHV DC transmission line, the tension insulator strings are designed to be assembled in horizontal triple strings. Generally, the string length is 18m, and the weight of a single string is 1.5T. Although the maintenance method of whole string replacement, the organization of construction equipment and the actual operation on site by using the traditional tension insulator string replacement method are technically achievable, but as a routine maintenance, especially live work is used for maintenance. Still have considerable difficulty. Therefore, this project adopts the operation method of single-piece replacement based on the design structure of the triple-strength tensile structure of the UHV DC project and the insulation form (disk-shaped porcelain insulators) adopted. Please refer to Figure 6, the specific operation process is as follows:
(1)利用联板(P-42S-120型)做支点安装牵引板翼型卡(如图9所示),利用绝缘子钢帽做支点安装绝缘子闭式卡前卡(如图7A中所示)用液压丝杆连接翼型卡和闭式卡组成紧线系统;(1) Use the joint plate (P-42S-120 type) as the fulcrum to install the traction plate airfoil card (as shown in Figure 9), and use the insulator steel cap as the fulcrum to install the insulator closed card front card (as shown in Figure 7A ) Use a hydraulic screw rod to connect the airfoil card and the closed card to form a tightening system;
(2)利用绝缘子钢帽做支点分别安装绝缘子闭式卡的前卡和后卡(如图7A、7B中所示),用液压丝杆连接绝缘子闭式卡的前卡和后卡组成紧线系统;(2) Use the steel cap of the insulator as the fulcrum to install the front card and the rear card of the insulator closed card respectively (as shown in Figure 7A and 7B), and connect the front card and the rear card of the insulator closed card with a hydraulic screw rod to form a tight line system;
(3)利用绝缘子钢帽做支点安装绝缘子闭式卡后卡,利用做牵引板(QY-42S型)和平行挂板(P-4215S)支点安装三联耐张专用卡(如图8中所示),用液压丝杆连接闭式卡和三联耐张卡组成紧线系统;(3) Use the steel cap of the insulator as the fulcrum to install the insulator closed card rear card, and use the traction plate (QY-42S type) and parallel hanging plate (P-4215S) as the fulcrum to install the triple tension-resistant special card (as shown in Figure 8 ), using a hydraulic screw rod to connect the closed card and the triple tension card to form a tensioning system;
(4)操作液压丝杆收紧紧线系统,转移被检修绝缘子上的机械荷载,实现绝缘子的更换和检修。(4) Operate the hydraulic screw rod to tighten the tightening system, transfer the mechanical load on the overhauled insulator, and realize the replacement and overhaul of the insulator.
通过上述工艺,可实现对耐张绝缘子的单片更换,保证了耐张绝缘子作为常规检修的作业便捷。Through the above process, the single-piece replacement of the tension insulator can be realized, which ensures the convenient operation of the tension insulator as a routine maintenance.
综上所述,本发明的±800kV特高压直流输电线路带电检修工艺,是国内外第一个特高压带电作业应用技术研究项目,项目研究工作的完成及研究成果的应用,填补了国内外特高压直流带电作业、带电检修应用技术领域的空白。本发明的±800kV特高压直流输电线路带电检修工艺中的具体的作业方法涵盖了±800kV特高压直流输电线路检修、带电作业常规检修工作内容,其中的杠杆原理微提升转移多联绝缘子串荷载作业方法和大吨位组合液压丝杆应用到带电作业,特别是应用到±800kV特高压直流带电的等电位作业方法中,是带电作业应用技术领域的重大突破。In summary, the ±800kV UHV DC transmission line live overhaul technology of the present invention is the first UHV live work application technology research project at home and abroad. Blank in the field of high-voltage DC live work and live maintenance application technology. The specific operation method in the ±800kV UHV DC transmission line live maintenance process of the present invention covers the work content of ±800kV UHV DC transmission line maintenance and live work routine maintenance, wherein the lever principle micro-lifts and transfers the multi-connected insulator string load operation The application of the method and large-tonnage combined hydraulic screw rod to live work, especially to the equipotential work method of ±800kV UHV DC live, is a major breakthrough in the field of live work application technology.
以上所述实施例仅表达了本发明的几种实施方式,其描述较为具体和详细,但并不能因此而理解为对本发明专利范围的限制。应当指出的是,对于本领域的普通技术人员来说,在不脱离本发明构思的前提下,还可以做出若干变形和改进,这些都属于本发明的保护范围。因此,本发明专利的保护范围应以所附权利要求为准。The above-mentioned embodiments only express several implementation modes of the present invention, and the description thereof is relatively specific and detailed, but should not be construed as limiting the patent scope of the present invention. It should be pointed out that those skilled in the art can make several modifications and improvements without departing from the concept of the present invention, and these all belong to the protection scope of the present invention. Therefore, the protection scope of the patent for the present invention should be based on the appended claims.
Claims (9)
Priority Applications (2)
| Application Number | Priority Date | Filing Date | Title |
|---|---|---|---|
| CN201310617102.3A CN103618251A (en) | 2013-11-27 | 2013-11-27 | Technology for electrified overhaul of +-800kV ultrahigh voltage direct-current transmission line |
| PCT/CN2014/090447 WO2015078279A1 (en) | 2013-11-27 | 2014-11-06 | Live overhaul process for ±800 kv ultra-high voltage dc power transmission line |
Applications Claiming Priority (1)
| Application Number | Priority Date | Filing Date | Title |
|---|---|---|---|
| CN201310617102.3A CN103618251A (en) | 2013-11-27 | 2013-11-27 | Technology for electrified overhaul of +-800kV ultrahigh voltage direct-current transmission line |
Publications (1)
| Publication Number | Publication Date |
|---|---|
| CN103618251A true CN103618251A (en) | 2014-03-05 |
Family
ID=50168954
Family Applications (1)
| Application Number | Title | Priority Date | Filing Date |
|---|---|---|---|
| CN201310617102.3A Pending CN103618251A (en) | 2013-11-27 | 2013-11-27 | Technology for electrified overhaul of +-800kV ultrahigh voltage direct-current transmission line |
Country Status (2)
| Country | Link |
|---|---|
| CN (1) | CN103618251A (en) |
| WO (1) | WO2015078279A1 (en) |
Cited By (12)
| Publication number | Priority date | Publication date | Assignee | Title |
|---|---|---|---|---|
| CN104218493A (en) * | 2014-08-13 | 2014-12-17 | 国家电网公司 | Process for electrified replacing of tension-resistant hard tube bus jumper insulator for +/-800kV extra-high-voltage direct-current line |
| CN104600629A (en) * | 2015-02-12 | 2015-05-06 | 中国南方电网有限责任公司超高压输电公司百色局 | Compact-circuit six-bundled conductor linkage plate fixture and application thereof |
| CN104638566A (en) * | 2015-01-30 | 2015-05-20 | 国家电网公司 | Method for vertically entering strong electric field along insulator string and tool used by method |
| WO2015078279A1 (en) * | 2013-11-27 | 2015-06-04 | 国家电网公司 | Live overhaul process for ±800 kv ultra-high voltage dc power transmission line |
| CN105337215A (en) * | 2015-11-26 | 2016-02-17 | 国网河南省电力公司检修公司 | Tool and method for replacing earth electrode circuit corner tension-resistant hardware fitting |
| WO2016023141A1 (en) * | 2014-08-13 | 2016-02-18 | 国家电网公司 | Process for live replacement of tension hard-tube bus-bar jumper insulator of +/- 800kv ultra-high-voltage dc transmission line |
| CN105576550A (en) * | 2014-10-11 | 2016-05-11 | 国家电网公司 | Method for live-line replacement of high voltage power transmission line monolithic strain insulator |
| CN107681538A (en) * | 2017-09-12 | 2018-02-09 | 金华送变电工程有限公司 | Anti- operating personnel turns over the aid fallen on a kind of transmission of electricity strain rod tower insulator chain |
| CN108050009A (en) * | 2017-12-05 | 2018-05-18 | 华北电力大学 | A kind of high potential energy supplying system and its construction method based on insulating liquid driving |
| CN108448488A (en) * | 2018-05-25 | 2018-08-24 | 国网河南省电力公司检修公司 | 840kN grade tension quadruple cross-arm side insulator replacement tool and method |
| CN111162482A (en) * | 2020-02-11 | 2020-05-15 | 中国电力科学研究院有限公司 | Potential transfer device for live work on the tension string of UHV transmission poles and towers |
| CN112103838A (en) * | 2020-08-05 | 2020-12-18 | 国网浙江省电力有限公司金华供电公司 | Auxiliary tool for climbing insulator string in heavy ice region and using method thereof |
Families Citing this family (30)
| Publication number | Priority date | Publication date | Assignee | Title |
|---|---|---|---|---|
| CN108206482B (en) * | 2018-01-23 | 2024-01-05 | 国网福建省电力有限公司 | Live replacement operation method for LF type yoke plate insulator without operation hole |
| CN108462106A (en) * | 2018-03-29 | 2018-08-28 | 国家电网公司 | Extra-high voltage alternating current-direct current transmission line of electricity Combined line presss from both sides electrification replacing tool and method |
| CN108512122A (en) * | 2018-06-13 | 2018-09-07 | 云南电网有限责任公司德宏供电局 | A kind of tangent tower conducting wire supporter |
| CN109217170A (en) * | 2018-08-01 | 2019-01-15 | 国网浙江省电力有限公司金华供电公司 | The replacement tool of ground electrode circuit insulator and fitting |
| CN109386158B (en) * | 2018-11-28 | 2024-02-06 | 中国电力工程顾问集团西北电力设计院有限公司 | Large-corner single-loop gate-type drilling tower for crossing |
| CN109545051A (en) * | 2018-12-12 | 2019-03-29 | 国网浙江余姚市供电有限公司 | A kind of electrical employee livewire work training device and method |
| CN109742679B (en) * | 2018-12-21 | 2024-03-29 | 国网浙江省电力有限公司杭州供电公司 | Hardware string handrail device for ultra-high voltage transmission line |
| CN109638715B (en) * | 2018-12-26 | 2024-05-10 | 国网福建省电力有限公司宁德供电公司 | Movable insulating hard ladder for live working of power transmission line and working method thereof |
| CN109742708B (en) * | 2019-03-10 | 2024-07-23 | 国网福建省电力有限公司福州供电公司 | A wind-proof dancing device for power transmission lines |
| CN110147954A (en) * | 2019-05-17 | 2019-08-20 | 国网天津市电力公司 | A kind of determination method of the composite insulator the piece number for shaft tower insulation |
| CN110492384A (en) * | 2019-08-21 | 2019-11-22 | 国网宁夏电力有限公司电力科学研究院 | A kind of disengaging extra-high voltage strain rod tower insulator chain supplementary insulation bar |
| CN110601074B (en) * | 2019-10-12 | 2024-06-18 | 国网新疆电力有限公司伊犁供电公司 | Portable wire lifter |
| CN111079743A (en) * | 2019-12-04 | 2020-04-28 | 国网新疆电力有限公司乌鲁木齐供电公司 | Data acquisition method for automatic identification of insulators based on UAV aerial photography data |
| CN110854742A (en) * | 2019-12-06 | 2020-02-28 | 国网辽宁省电力有限公司检修分公司 | Special device for replacing four-bundle conductor spacer |
| CN110970851B (en) * | 2019-12-06 | 2024-04-12 | 中国电力工程顾问集团西南电力设计院有限公司 | Windproof bias-used 'shaped' hanging string |
| CN111293630B (en) * | 2020-03-23 | 2024-07-26 | 国网福建省电力有限公司 | Insulated bottle support rack front end fixing ring position adjustable device and working method thereof |
| CN111313324A (en) * | 2020-03-30 | 2020-06-19 | 国网江苏省电力有限公司电力科学研究院 | Adjustable monitoring type replacing device for light large-tonnage porcelain insulator |
| CN111342394A (en) * | 2020-04-26 | 2020-06-26 | 国网甘肃省电力公司白银供电公司 | A maintenance device for a tension tower |
| CN111668747B (en) * | 2020-05-08 | 2022-09-20 | 中国电力科学研究院有限公司 | Device and method for entering and exiting alternating-current extra-high voltage composite cross arm live working area |
| CN111627620B (en) * | 2020-06-29 | 2024-05-24 | 中国电力工程顾问集团西南电力设计院有限公司 | Upper-carrying type suspension V-shaped insulator string |
| CN112412145B (en) * | 2020-11-25 | 2024-11-01 | 国网江苏省电力有限公司南通供电分公司 | A shaft tower for transmission line prevent wind off tracking |
| CN113937661B (en) * | 2021-11-12 | 2024-10-18 | 国网青海省电力公司检修公司 | A special tool for replacing the overhead ground wire suspension fittings of a power transmission line |
| CN114389058B (en) * | 2021-12-13 | 2024-07-23 | 新昌县新明实业有限公司 | Distribution overhead line earth connection articulates robot |
| CN114614399B (en) * | 2022-03-04 | 2023-10-20 | 国网浙江省电力有限公司金华供电公司 | Operating method for on-load migration tension rod |
| CN114530793B (en) * | 2022-03-08 | 2024-08-02 | 国网甘肃省电力公司超高压公司 | Insulation rope throwing and hanging method for assisting tower climbing maintenance by combining unmanned aerial vehicle with electric lifting device |
| CN115021142B (en) * | 2022-05-06 | 2024-08-09 | 国网山东省电力公司青岛供电公司 | Tool for replacing top cap of 10kV distribution line pole in electrified mode and replacement method |
| CN115596270A (en) * | 2022-11-11 | 2023-01-13 | 山东电力工程咨询院有限公司(Cn) | Staggered-layer arrangement structure and method for single-side breaking of tension tower of 500KV line |
| CN115882408B (en) * | 2022-11-24 | 2025-08-15 | 山东大学 | Wind deflection prevention energy consumption device for traction type power transmission line |
| CN117712915B (en) * | 2023-12-05 | 2024-06-11 | 江苏恒康电力科技有限公司 | Maintenance device and maintenance method for drilling span type angle steel tower insulator |
| CN118100667B (en) * | 2024-04-18 | 2024-06-25 | 江苏江东电力器材有限公司 | High-pressure valve hall valve tower hardware fitting |
Citations (4)
| Publication number | Priority date | Publication date | Assignee | Title |
|---|---|---|---|---|
| JP2001112153A (en) * | 1997-10-24 | 2001-04-20 | Sediver Soc Europ Isolateurs En Verre & Composite | Lightning arrester assembly for aerial line equipped with device for informing user of function trouble of the lightning arrester |
| CN101227068A (en) * | 2007-12-27 | 2008-07-23 | 国网武汉高压研究院 | Equipotential access method and potential transfer rod for live work on AC super/ultra-high voltage lines |
| CN102136695A (en) * | 2010-12-28 | 2011-07-27 | 河北省电力公司超高压输变电分公司 | Overhauling tool used for +/-660kV direct-current transmission line |
| CN102403672A (en) * | 2011-08-30 | 2012-04-04 | 国网电力科学研究院 | Super/ultrahigh voltage alternating and direct-current mixed compression line live-line work equipotential transfer safety method |
Family Cites Families (5)
| Publication number | Priority date | Publication date | Assignee | Title |
|---|---|---|---|---|
| JP2004171946A (en) * | 2002-11-20 | 2004-06-17 | Chubu Electric Power Co Inc | Method for replacing all or part of insulator device and support used for this method |
| CN201629517U (en) * | 2009-12-15 | 2010-11-10 | 湖北省电力公司超高压输变电公司 | Large knife card of direct-current extra-high voltage line insulator string |
| CN202014054U (en) * | 2010-12-28 | 2011-10-19 | 河北省电力公司超高压输变电分公司 | Overhaul tool for dead end insulator on +/- 660kV DC power transmission line |
| CN202014055U (en) * | 2010-12-28 | 2011-10-19 | 河北省电力公司超高压输变电分公司 | Overhauling device of V-shaped double-string insulator for +-660KV direct current transmission line |
| CN103618251A (en) * | 2013-11-27 | 2014-03-05 | 国家电网公司 | Technology for electrified overhaul of +-800kV ultrahigh voltage direct-current transmission line |
-
2013
- 2013-11-27 CN CN201310617102.3A patent/CN103618251A/en active Pending
-
2014
- 2014-11-06 WO PCT/CN2014/090447 patent/WO2015078279A1/en active Application Filing
Patent Citations (4)
| Publication number | Priority date | Publication date | Assignee | Title |
|---|---|---|---|---|
| JP2001112153A (en) * | 1997-10-24 | 2001-04-20 | Sediver Soc Europ Isolateurs En Verre & Composite | Lightning arrester assembly for aerial line equipped with device for informing user of function trouble of the lightning arrester |
| CN101227068A (en) * | 2007-12-27 | 2008-07-23 | 国网武汉高压研究院 | Equipotential access method and potential transfer rod for live work on AC super/ultra-high voltage lines |
| CN102136695A (en) * | 2010-12-28 | 2011-07-27 | 河北省电力公司超高压输变电分公司 | Overhauling tool used for +/-660kV direct-current transmission line |
| CN102403672A (en) * | 2011-08-30 | 2012-04-04 | 国网电力科学研究院 | Super/ultrahigh voltage alternating and direct-current mixed compression line live-line work equipotential transfer safety method |
Non-Patent Citations (3)
| Title |
|---|
| 刘振亚: "《特高压直流输电技术研究成果专辑》", 31 October 2011, article "特高压直流输电工程运行技术" * |
| 耿波: "陕西地区大范围开展750kV带电作业管理研究", 《电网与清洁能源》, no. 12, 31 December 2012 (2012-12-31) * |
| 胡毅,刘凯等: "《超/特高压交直流输电线路带电作业》", 31 December 2011, article "直流输电线路带电作业" * |
Cited By (17)
| Publication number | Priority date | Publication date | Assignee | Title |
|---|---|---|---|---|
| WO2015078279A1 (en) * | 2013-11-27 | 2015-06-04 | 国家电网公司 | Live overhaul process for ±800 kv ultra-high voltage dc power transmission line |
| CN104218493A (en) * | 2014-08-13 | 2014-12-17 | 国家电网公司 | Process for electrified replacing of tension-resistant hard tube bus jumper insulator for +/-800kV extra-high-voltage direct-current line |
| WO2016023141A1 (en) * | 2014-08-13 | 2016-02-18 | 国家电网公司 | Process for live replacement of tension hard-tube bus-bar jumper insulator of +/- 800kv ultra-high-voltage dc transmission line |
| CN104218493B (en) * | 2014-08-13 | 2017-03-01 | 国家电网公司 | ± 800kV UHVDC Transmission Lines live-line replacing strain hard tube mother's wire jumper insulator technique |
| CN105576550B (en) * | 2014-10-11 | 2018-08-14 | 国家电网公司 | A kind of charged for replacement UHV transmission line single chip tension insulator method |
| CN105576550A (en) * | 2014-10-11 | 2016-05-11 | 国家电网公司 | Method for live-line replacement of high voltage power transmission line monolithic strain insulator |
| CN104638566A (en) * | 2015-01-30 | 2015-05-20 | 国家电网公司 | Method for vertically entering strong electric field along insulator string and tool used by method |
| CN104638566B (en) * | 2015-01-30 | 2016-06-29 | 国家电网公司 | Vertical type enters method and the used tool of highfield along insulator chain |
| CN104600629A (en) * | 2015-02-12 | 2015-05-06 | 中国南方电网有限责任公司超高压输电公司百色局 | Compact-circuit six-bundled conductor linkage plate fixture and application thereof |
| CN105337215A (en) * | 2015-11-26 | 2016-02-17 | 国网河南省电力公司检修公司 | Tool and method for replacing earth electrode circuit corner tension-resistant hardware fitting |
| CN105337215B (en) * | 2015-11-26 | 2018-11-02 | 国网河南省电力公司检修公司 | A kind of tool and method for replacing ground electrode circuit corner strain hardware fitting |
| CN107681538A (en) * | 2017-09-12 | 2018-02-09 | 金华送变电工程有限公司 | Anti- operating personnel turns over the aid fallen on a kind of transmission of electricity strain rod tower insulator chain |
| CN108050009A (en) * | 2017-12-05 | 2018-05-18 | 华北电力大学 | A kind of high potential energy supplying system and its construction method based on insulating liquid driving |
| CN108050009B (en) * | 2017-12-05 | 2019-10-01 | 华北电力大学 | A kind of high potential energy supplying system and its construction method based on insulating liquid driving |
| CN108448488A (en) * | 2018-05-25 | 2018-08-24 | 国网河南省电力公司检修公司 | 840kN grade tension quadruple cross-arm side insulator replacement tool and method |
| CN111162482A (en) * | 2020-02-11 | 2020-05-15 | 中国电力科学研究院有限公司 | Potential transfer device for live work on the tension string of UHV transmission poles and towers |
| CN112103838A (en) * | 2020-08-05 | 2020-12-18 | 国网浙江省电力有限公司金华供电公司 | Auxiliary tool for climbing insulator string in heavy ice region and using method thereof |
Also Published As
| Publication number | Publication date |
|---|---|
| WO2015078279A1 (en) | 2015-06-04 |
Similar Documents
| Publication | Publication Date | Title |
|---|---|---|
| CN103618251A (en) | Technology for electrified overhaul of +-800kV ultrahigh voltage direct-current transmission line | |
| CN103618249B (en) | ± 500kV common-tower double-return DC power transmission line hotline maintenance techniques | |
| WO2012088987A1 (en) | Maintenance tool for insulator of direct current transmission line | |
| CN102882153B (en) | Phase replacing insulator string method in charged for replacement circuit many times towers | |
| WO2016023141A1 (en) | Process for live replacement of tension hard-tube bus-bar jumper insulator of +/- 800kv ultra-high-voltage dc transmission line | |
| CN105337217B (en) | A kind of instrument and its method of charged for replacement extra-high voltage ground electrode circuit linear insulator | |
| CN107104387A (en) | One kind can second lift wire insulation cross-arm and lifting wire method | |
| CN103427370B (en) | The live replacing device of ultra-high-tension power transmission line strain insulator string | |
| CN105932601A (en) | Method for repairing break strand of overhead ground wire | |
| CN201466574U (en) | A device for equipotential replacement of transmission line tower insulators and accessories | |
| CN203367880U (en) | 760kN disk-shaped insulator holder | |
| CN105162028A (en) | Method for replacing linear insulator of 220kV steel pipe tower in live working state | |
| CN103887735A (en) | Linear charged wire lifting device of electric transmission line | |
| CN102255260B (en) | Integrated type live-line working ten-splitting line lifter | |
| CN104538888B (en) | A kind of distribution line straight line pole cross-arm charged for replacement method | |
| CN104113007A (en) | Operation method for replacing strain insulator of 35kV overhead distribution line in live state | |
| CN205882560U (en) | Special circulation cord rack device of distribution live working earth potential | |
| CN102290738B (en) | Construction method for replacing 35kV line tension pole cross arm | |
| CN106207850B (en) | The operational method of charged for replacement holes duplex board linear insulator chain | |
| CN211701243U (en) | Electrified defect eliminating device for jumper spacer | |
| CN204144800U (en) | The special cross-arm card of a kind of ZML type tower | |
| CN204030430U (en) | A kind of conductors on quad bundled protects line hook | |
| CN202159929U (en) | Integrated ten-division wire lifting device for live-wire work | |
| CN206820360U (en) | A kind of double-lifting wire insulation cross arm | |
| CN104158118B (en) | A kind of conductors on quad bundled protects line hook |
Legal Events
| Date | Code | Title | Description |
|---|---|---|---|
| PB01 | Publication | ||
| PB01 | Publication | ||
| C10 | Entry into substantive examination | ||
| SE01 | Entry into force of request for substantive examination | ||
| RJ01 | Rejection of invention patent application after publication | ||
| RJ01 | Rejection of invention patent application after publication |
Application publication date: 20140305 |