[go: up one dir, main page]

CN115012989A - Tunnel lining trolley and vibrating system thereof - Google Patents

Tunnel lining trolley and vibrating system thereof Download PDF

Info

Publication number
CN115012989A
CN115012989A CN202210506301.6A CN202210506301A CN115012989A CN 115012989 A CN115012989 A CN 115012989A CN 202210506301 A CN202210506301 A CN 202210506301A CN 115012989 A CN115012989 A CN 115012989A
Authority
CN
China
Prior art keywords
vibrating
group
vibrator
vibration
vibrators
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Pending
Application number
CN202210506301.6A
Other languages
Chinese (zh)
Inventor
李阳
赵崇阳
刘利峰
孙洪勇
王海亮
王俊涛
刘国强
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Sixth Engineering Co Ltd of China Railway 19th Bureau Group Co Ltd
China Railway 19th Bureau Group Co Ltd Survey and Design Institute Branch
Original Assignee
Sixth Engineering Co Ltd of China Railway 19th Bureau Group Co Ltd
China Railway 19th Bureau Group Co Ltd Survey and Design Institute Branch
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Sixth Engineering Co Ltd of China Railway 19th Bureau Group Co Ltd, China Railway 19th Bureau Group Co Ltd Survey and Design Institute Branch filed Critical Sixth Engineering Co Ltd of China Railway 19th Bureau Group Co Ltd
Priority to CN202210506301.6A priority Critical patent/CN115012989A/en
Publication of CN115012989A publication Critical patent/CN115012989A/en
Pending legal-status Critical Current

Links

Images

Classifications

    • EFIXED CONSTRUCTIONS
    • E21EARTH OR ROCK DRILLING; MINING
    • E21DSHAFTS; TUNNELS; GALLERIES; LARGE UNDERGROUND CHAMBERS
    • E21D11/00Lining tunnels, galleries or other underground cavities, e.g. large underground chambers; Linings therefor; Making such linings in situ, e.g. by assembling
    • E21D11/04Lining with building materials
    • E21D11/10Lining with building materials with concrete cast in situ; Shuttering also lost shutterings, e.g. made of blocks, of metal plates or other equipment adapted therefor
    • EFIXED CONSTRUCTIONS
    • E21EARTH OR ROCK DRILLING; MINING
    • E21DSHAFTS; TUNNELS; GALLERIES; LARGE UNDERGROUND CHAMBERS
    • E21D11/00Lining tunnels, galleries or other underground cavities, e.g. large underground chambers; Linings therefor; Making such linings in situ, e.g. by assembling
    • E21D11/04Lining with building materials
    • E21D11/10Lining with building materials with concrete cast in situ; Shuttering also lost shutterings, e.g. made of blocks, of metal plates or other equipment adapted therefor
    • E21D11/102Removable shuttering; Bearing or supporting devices therefor
    • YGENERAL TAGGING OF NEW TECHNOLOGICAL DEVELOPMENTS; GENERAL TAGGING OF CROSS-SECTIONAL TECHNOLOGIES SPANNING OVER SEVERAL SECTIONS OF THE IPC; TECHNICAL SUBJECTS COVERED BY FORMER USPC CROSS-REFERENCE ART COLLECTIONS [XRACs] AND DIGESTS
    • Y02TECHNOLOGIES OR APPLICATIONS FOR MITIGATION OR ADAPTATION AGAINST CLIMATE CHANGE
    • Y02EREDUCTION OF GREENHOUSE GAS [GHG] EMISSIONS, RELATED TO ENERGY GENERATION, TRANSMISSION OR DISTRIBUTION
    • Y02E10/00Energy generation through renewable energy sources
    • Y02E10/20Hydro energy

Landscapes

  • Engineering & Computer Science (AREA)
  • Architecture (AREA)
  • Structural Engineering (AREA)
  • Mining & Mineral Resources (AREA)
  • Civil Engineering (AREA)
  • Life Sciences & Earth Sciences (AREA)
  • General Life Sciences & Earth Sciences (AREA)
  • Geochemistry & Mineralogy (AREA)
  • Geology (AREA)
  • On-Site Construction Work That Accompanies The Preparation And Application Of Concrete (AREA)

Abstract

The invention provides a tunnel lining trolley and a vibration system thereof, wherein the vibration system comprises a steel template, the steel template is provided with two construction areas which are symmetrically arranged, each construction area is provided with a side arch part, a first end part and a second end part, a plurality of layers of casting windows, a plurality of groups of first vibration groups, at least one group of second vibration groups, a third vibration group, a fourth vibration group, a fifth vibration group and a sixth vibration group, the plurality of layers of casting windows and the plurality of groups of first vibration groups are distributed at intervals along the circumferential direction of the steel template, the third vibration groups and the fifth vibration groups are arranged at the first end part, the fourth vibration groups and the sixth vibration groups are arranged at the first end part, in the height direction, the minimum height of the first vibration groups is smaller than the minimum height of the casting windows, the second vibration groups are arranged above the casting windows, the fifth vibration groups are arranged above the third vibration groups, and the sixth vibration groups are arranged above the fourth vibration groups. The tunnel lining trolley comprises a vibration system, the vibration system can improve the integral pouring quality of the two-lining concrete, the inside and outside of the concrete strength are basically consistent, and the strength discrete value is small.

Description

隧道衬砌台车及其振捣系统Tunnel lining trolley and its vibrating system

技术领域technical field

本发明涉及隧道施工技术领域,具体地说,是涉及一种用于隧道衬砌台车的振捣系统以及设置有该振捣系统的隧道衬砌台车。The invention relates to the technical field of tunnel construction, in particular to a vibrating system for a tunnel lining trolley and a tunnel lining trolley equipped with the vibrating system.

背景技术Background technique

随着我国铁路、公路建设的高速发展,隧道工程建设的数量也越来越多,因此,对隧道的衬砌质量及标准化施工要求不断提高。With the rapid development of railway and highway construction in my country, the number of tunnel projects is also increasing. Therefore, the requirements for tunnel lining quality and standardized construction are constantly improving.

在传统的隧道衬砌工艺中,进行二衬混凝土浇筑前,先将隧道衬砌台车移动至指定位置,并使隧道衬砌台车的钢模板与上板混凝土搭接;接着进行二衬混凝土浇筑,浇筑时,采用地泵将混凝土泵送至隧道衬砌台车的进料口,并在每个进料口使用手持式振捣棒进行振捣,当浇筑至拱顶时,采用电动附着式振捣器进行振捣;但是,由于二衬拱顶钢筋密集,使得拱顶混凝土无法进行人工振捣,且电动式振捣器又存在频率不足、振捣半径小等缺点,导致拱顶混凝土难以密实、饱满,因此使得隧道衬砌拱顶混凝土出现空洞、混凝土强度不足、混凝土强度不均匀等质量问题,而这些质量问题会给后期隧道运行带来极大的安全风险,因此,传统的隧道衬砌工艺已无法满足施工需求。In the traditional tunnel lining process, before the secondary lining concrete is poured, the tunnel lining trolley is moved to the designated position, and the steel formwork of the tunnel lining trolley is overlapped with the upper slab concrete; When pouring the concrete to the feed port of the tunnel lining trolley, use the ground pump to pump the concrete, and use a hand-held vibrator at each feed port to vibrate. When pouring to the vault, use an electric attached vibrator. Vibration; however, due to the dense reinforcement of the secondary lining vault, the vault concrete cannot be vibrated manually, and the electric vibrator has shortcomings such as insufficient frequency and small vibration radius, which makes the vault concrete difficult to compact and full. Therefore, quality problems such as voids, insufficient concrete strength, and uneven concrete strength of the tunnel lining vault concrete are caused, and these quality problems will bring great safety risks to the later tunnel operation. Therefore, the traditional tunnel lining technology can no longer meet the requirements. construction needs.

针对上述问题,现有的一种振捣系统,如图1所示,其包括钢模板11、多个自动插入式振捣器12和多个气动振捣器13,该振捣系统通过自动插入式振捣器12将高频振捣棒插入拱顶混凝土以对拱顶混凝土进行插入式自动振捣,从而解决拱顶二衬脱空及混凝土不密实的问题;此外,气动振捣器13具有振捣频率高、振捣半径大等优点,使其能够对深厚混凝土进行振捣,避免深厚混凝土振捣不到位、混凝土不密实。然而,该振捣系统存在以下缺点:In view of the above problems, an existing vibrating system, as shown in FIG. 1, includes a steel template 11, a plurality of automatic insertion vibrators 12 and a plurality of pneumatic vibrators 13. The type vibrator 12 inserts the high-frequency vibrating rod into the concrete of the vault to perform automatic insertion vibration on the concrete of the vault, so as to solve the problems that the second lining of the vault is empty and the concrete is not compact; in addition, the pneumatic vibrator 13 has a vibrator. The advantages of high frequency and large vibration radius make it possible to vibrate the deep concrete, so as to avoid the deep concrete not being vibrated in place and the concrete not being compacted. However, this vibrating system has the following disadvantages:

第一,多个气动振捣器13与多个边墙进料口111之间的相对位置分布不合理,使得多个气动振捣器13对边墙及拱部位置的混凝土的振捣效果相对较差。例如,靠近钢模板11单侧底部的第一排气动振捣器13设置位置过高,即单侧第一排气动振捣器13与矮边墙顶部(即仰拱与二衬之间的施工缝)之间的距离过大,使得仰拱与二衬之间的施工缝处于气动振捣器13的最大振捣半径边缘,因此对仰拱与二衬之间的施工缝处的混凝土振捣效果差,导致仰拱与二衬之间的施工缝处混凝土容易出现病害。又例如,在钢模板的一侧上,由于相邻两排边墙进料口111的环向间距较大,且部分相邻的两排边墙进料口111之间没有设置相应的气动振捣器13,使得该相邻的两排边墙进料口111的区域处于气动振捣器13的最大振捣半径边缘,因此,该相邻的两排边墙进料口111的区域内的混凝土受振捣效果较差,密实度较低且容易出现空洞。First, the relative position distribution between the plurality of pneumatic vibrators 13 and the plurality of side wall feeding ports 111 is unreasonable, so that the vibrating effects of the plurality of pneumatic vibrators 13 on the concrete at the side wall and the arch position are relatively relative. poor. For example, the setting position of the first exhaust dynamic vibrator 13 near the unilateral bottom of the steel formwork 11 is too high, that is, the unilateral first exhaust dynamic vibrator 13 and the top of the short side wall (that is, between the inverted arch and the second lining) The distance between the construction joint) is too large, so that the construction joint between the inverted arch and the second lining is in the maximum vibration radius edge of the pneumatic vibrator 13, so the concrete at the construction joint between the inverted arch and the second lining is The vibrating effect is poor, causing the concrete at the construction joint between the inverted arch and the secondary lining to be prone to disease. For another example, on one side of the steel formwork, due to the large circumferential distance between the two adjacent rows of side wall feed openings 111, and there is no corresponding pneumatic vibration set between the two adjacent rows of side wall feed openings 111. tamper 13, so that the area of the adjacent two rows of side wall feed openings 111 is at the edge of the maximum vibration radius of the pneumatic vibrator 13, therefore, the area within the area of the adjacent two rows of side wall feed openings 111 Concrete is less vibrated, less dense and prone to voids.

第二,位于钢模板11拱顶处的自动插入式振捣器13不在模板中线14上,使得该部分的自动插入式振捣器13与对称分布于模板中线14两侧的拱部位置的其他自动插入式振捣13进行共同作业时,处于拱顶处的自动插入式振捣器13会或多或少的影响模板中线14两侧处的混凝土分布均匀程度及密实度,从而导致拱顶处的混凝土容易出现混凝土强度不均匀的问题。Second, the automatic plug-in vibrator 13 located at the dome of the steel formwork 11 is not on the formwork center line 14, so that the automatic plug-in vibrator 13 of this part is symmetrically distributed on both sides of the formwork centerline 14. When the automatic plug-in vibrators 13 work together, the automatic plug-in vibrators 13 at the dome will more or less affect the uniformity and compactness of the concrete distribution on both sides of the formwork center line 14, resulting in The concrete is prone to the problem of uneven concrete strength.

第三,沿钢模板11的长度方向(平行于模板中线14的方向),钢模板11的两端部112处的振捣器(包括自动插入式振捣器12和气动振捣器13)的布局不合理,对钢模板11端部处的混凝土振捣效果差;而由于浇筑出的二衬需要分别与上一板二衬和下一板二衬衔接,因此,对衔接处(即环向施工缝处)的混凝土的振捣就显得尤为重要,以避免出现混凝土病害。Thirdly, along the length direction of the steel formwork 11 (the direction parallel to the formwork center line 14 ), the vibrators at the two ends 112 of the steel formwork 11 (including the automatic insertion vibrator 12 and the pneumatic vibrator 13 ) The layout is unreasonable, and the vibrating effect of the concrete at the end of the steel formwork 11 is poor; and because the casted secondary lining needs to be connected with the upper plate second lining and the next plate second lining respectively, therefore, the joints (that is, the circumferential direction Vibration of the concrete at the construction joints) is particularly important to avoid concrete diseases.

发明内容SUMMARY OF THE INVENTION

为了解决上述问题,本发明的主要目的是提供一种提高二衬混凝土的整体浇筑质量,防止拱顶混凝土脱空,保证混凝土强度内外基本一致,且强度离散值小的振捣系统。In order to solve the above problems, the main purpose of the present invention is to provide a vibrating system that improves the overall pouring quality of the secondary lining concrete, prevents the dome concrete from emptying, and ensures that the concrete strength is basically consistent inside and outside, and the strength discrete value is small.

本发明的另一目的是提供一种设置有上述振捣系统的隧道衬砌台车。Another object of the present invention is to provide a tunnel lining trolley provided with the above-mentioned vibrating system.

为了实现本发明的主要目的,本发明提供一种振捣系统,包括钢模板,钢模板具有两个关于对称面呈对称设置的施工区,钢模板的高度方向和轴心均在对称面上,其中,每个施工区上均设置有多层浇筑窗、多组第一振捣组、至少一组第二振捣组、第三振捣组、第四振捣组、第五振捣组和第六振捣组;多层浇筑窗沿钢模板的环向分布,浇筑窗包括多个沿第一方向分布的入料口,第一方向平行于轴心;施工区具有边拱部、第一端部和第二端部,沿第一方向,边拱部位于第一端部和第二端部之间,第一振捣组和第二振捣组均设置在边拱部,多组第一振捣组沿环向与多层浇筑窗相间设置,第一振捣组包括多个沿第一方向分布的第一气动振捣器,第二振捣组包括多个沿第一方向分布的第二气动振捣器;第三振捣组和第五振捣组均设置在第一端部上,第三振捣组包括多个沿环向分布的第三气动振捣器,第五振捣组包括至少一个第一插入式振捣器;第四振捣组和第六振捣组均设置在第二端部上,第四振捣组包括多个沿环向分布的第四气动振捣器,第六振捣组包括至少一个第二插入式振捣器;在高度方向上,最下方一组第一振捣组的高度小于最底层的浇筑窗的高度,第二振捣组位于最顶层的浇筑窗的上方,第五振捣组位于第三振捣组的上方,第六振捣组位于第四振捣组的上方;在环向上,相邻两个第一气动振捣器错开设置,相邻的一个第一气动振捣器与一个第二气动振捣器错开设置;钢模板的拱顶设置有多个沿第一方向分布的第三插入式振捣器和多个沿第一方向分布的灌注孔,多个第三插入式振捣器和多个灌注孔均位于对称面上。In order to achieve the main purpose of the present invention, the present invention provides a vibrating system, including a steel formwork, the steel formwork has two construction areas symmetrically arranged with respect to the symmetry plane, and the height direction and the axis of the steel formwork are on the symmetry plane, Wherein, each construction area is provided with multi-layer pouring windows, multiple groups of the first vibrating group, at least one group of the second vibrating group, the third vibrating group, the fourth vibrating group, the fifth vibrating group and the The sixth vibrating group; the multi-layer pouring windows are distributed along the circumferential direction of the steel formwork, and the pouring windows include a plurality of feeding ports distributed along the first direction, and the first direction is parallel to the axis; the construction area has a side arch, a first end and the second end portion, along the first direction, the side arch portion is located between the first end portion and the second end portion, the first vibrating group and the second vibrating group are both arranged on the side arch portion, and multiple groups of first The vibrating groups are arranged alternately with the multi-layer pouring windows in the circumferential direction, the first vibrating group includes a plurality of first pneumatic vibrators distributed along the first direction, and the second vibrating group includes a plurality of first pneumatic vibrators distributed along the first direction. Two pneumatic vibrators; the third vibrating group and the fifth vibrating group are both arranged on the first end, the third vibrating group includes a plurality of third pneumatic vibrators distributed along the circumferential direction, and the fifth vibrating group is The group includes at least one first plug-in vibrator; the fourth vibrator group and the sixth vibrator group are both arranged on the second end, and the fourth vibrator group includes a plurality of fourth pneumatic vibrators distributed along the circumferential direction The sixth vibrating group includes at least one second plug-in vibrator; in the height direction, the height of the first vibrating group in the lowermost group is less than the height of the pouring window at the bottom layer, and the second vibrating group is located at the lowest level. Above the pouring window on the top floor, the fifth vibrating group is located above the third vibrating group, and the sixth vibrating group is located above the fourth vibrating group; in the ring direction, two adjacent first pneumatic vibrators are staggered Arrangement, an adjacent first pneumatic vibrator and a second pneumatic vibrator are staggered; the dome of the steel formwork is provided with a plurality of third plug-in vibrators distributed along the first direction and a plurality of third plug-in vibrators along the first direction. The pouring holes distributed in one direction, the plurality of third insertion-type vibrators and the plurality of pouring holes are all located on the symmetry plane.

由上可见,通过对振捣系统的设计,能够更好的提升对钢模板的边墙及拱部区域、拱顶区域、两端部区域的混凝土的振捣效果,以提高混凝土的密实度,防止混凝土出现空洞。其中,通过对第一振捣组和浇筑窗的相对位置设计,既保证了仰拱与二衬之间的施工缝处的混凝土能够受到全面、充分的振捣,又保证相邻两层浇筑窗之间的混凝土能够受到全面、充分的振捣,从而使得边墙处混凝土能够更加的密实,减少边墙处混凝土的缺陷病害;通过对第二振捣组的位置设置,使得第二振捣组能够对拱部处的混凝土进行全面、充分的振捣,以保证拱部处的混凝土能够密实无缺陷病害,同时,第二振捣组还能够配合位于拱顶处的多个第三插入式振捣器对拱顶处的混凝土进行全面、充分的振捣,以保证拱顶处混凝土分布均匀、密实且强度均匀,并防止由于振捣不到位而导致出现混凝土不密实、蜂窝麻面、拱顶脱空等问题;通过对第三振捣组和第四振捣组的设置,使得第三振捣组和第四振捣组能够对钢模板端部的边墙部分的混凝土进行全面、充分的振捣,以保证环向施工缝处混凝土的浇筑质量,从而保证相邻两板二衬之间的衔接质量;通过对第五振捣组和第六振捣组的设置,使得第一插入式振捣器和第二插入式振捣器能够对钢模板端部的拱顶部分的混凝土进行全面、充分的振捣,以避免混凝土灌入拱顶过程中因局部混凝土聚集而造成小范围内空洞或不密实,从而保证环向施工缝处混凝土的浇筑质量,提高相邻两板二衬的衔接质量。It can be seen from the above that through the design of the vibrating system, the vibrating effect of the concrete in the side wall and the arch area, the vault area and the two end areas of the steel formwork can be better improved, so as to improve the compactness of the concrete. Prevents voids in concrete. Wherein, by designing the relative position of the first vibrating group and the pouring window, it is ensured that the concrete at the construction joint between the inverted arch and the second lining can be fully and fully vibrated, and the adjacent two-story pouring windows are guaranteed. The concrete in between can be fully and fully vibrated, so that the concrete at the side wall can be more dense, and the defects and diseases of the concrete at the side wall can be reduced; by setting the position of the second vibrating group, the second vibrating group can be The concrete at the arch can be fully and fully vibrated to ensure that the concrete at the arch can be dense and free of defects. The tamper vibrates the concrete at the top of the vault comprehensively and fully to ensure that the concrete at the top of the vault is evenly distributed, dense and even in strength, and prevents the occurrence of uncompacted concrete, honeycomb surface, and vault due to insufficient vibration. Problems such as voiding; through the setting of the third and fourth vibrating groups, the third and fourth vibrating groups can comprehensively and fully carry out the concrete of the side wall part at the end of the steel formwork. Vibration to ensure the pouring quality of the concrete at the circumferential construction joint, so as to ensure the connection quality between the two adjacent plates and the second lining; by setting the fifth and sixth vibrating groups, the first plug-in type The vibrator and the second plug-in vibrator can fully and fully vibrate the concrete of the vault at the end of the steel formwork, so as to avoid small-scale voids caused by local concrete accumulation during the process of pouring concrete into the vault Or not dense, so as to ensure the pouring quality of the concrete at the circumferential construction joint and improve the connection quality of the adjacent two plates and two linings.

一个优选的方案是,在高度方向上,第三气动振捣器与矮边墙之间的最小距离介于0.8米至1米之间,第四气动振捣器与矮边墙之间的最小距离介于0.8米至1米之间,第一气动振捣器与矮边墙之间的最小距离介于0.8米至1米之间。A preferred solution is that in the height direction, the minimum distance between the third pneumatic vibrator and the short side wall is between 0.8 m and 1 m, and the minimum distance between the fourth pneumatic vibrator and the short side wall is between 0.8 m and 1 m. The distance is between 0.8m and 1m, and the minimum distance between the first pneumatic vibrator and the low side wall is between 0.8m and 1m.

由上可见,上述设计使得第一气动振捣器、第三气动振捣器、第四气动振捣器能够相互配合以对仰拱与二衬的施工缝处的混凝土进行充分、有效且全面的振捣,进而保证钢模板的边墙、端部边墙区域的混凝土的密实度,提升混凝土的浇筑质量。As can be seen from the above, the above-mentioned design enables the first pneumatic vibrator, the third pneumatic vibrator, the fourth pneumatic vibrator to cooperate with each other to fully, effectively and comprehensively carry out the concrete at the construction joint of the inverted arch and the second lining. Vibration, thereby ensuring the compactness of the concrete in the side wall and end side wall area of the steel formwork, and improving the pouring quality of the concrete.

进一步的方案是,第一气动振捣器的振捣半径介于1.8米至2.5米之间;第二气动振捣器的振捣半径介于1.8米至2.5米之间;第三气动振捣器的振捣半径介于1.8米至2.5米之间;第四气动振捣器的振捣半径介于1.8米至2.5米之间;第一插入式振捣器的振捣半径介于1.2米至1.8米之间;第二插入式振捣器的振捣半径介于1.2米至1.8米之间;第三插入式振捣器的振捣半径介于1.2米至1.8米之间;第一气动振捣器的振捣半径与临近的其他振捣器的振捣半径咬合,第二气动振捣器的振捣半径与临近的其他振捣器的振捣半径咬合,第三气动振捣器的振捣半径与临近的其他振捣器的振捣半径咬合,第四振气动捣器的振捣半径与临近的其他振捣器的振捣半径咬合,第一插入式振捣器的振捣半径与临近的其他振捣器的振捣半径咬合,第二插入式振捣器的振捣半径与临近的其他振捣器的振捣半径咬合,第三插入式振捣器的振捣半径与临近的其他振捣器的振捣半径咬合;在第一方向上,相邻两个入料口之间的距离介于1.8米至2.5米之间,相邻两个灌注孔之间的距离介于1.2米至1.8米之间。A further solution is that the vibrating radius of the first pneumatic vibrator is between 1.8 meters and 2.5 meters; the vibration radius of the second pneumatic vibrator is between 1.8 meters and 2.5 meters; the third pneumatic vibrator is between 1.8 meters and 2.5 meters. The vibration radius of the vibrator is between 1.8m and 2.5m; the vibration radius of the fourth pneumatic vibrator is between 1.8m and 2.5m; the vibration radius of the first plug-in vibrator is between 1.2m between 1.8 m and 1.8 m; the second plug-in vibrator has a vibrating radius between 1.2 m and 1.8 m; the third plug-in vibrator has a vibrating radius between 1.2 m and 1.8 m; the first The vibration radius of the pneumatic vibrator meshes with the vibration radius of other adjacent vibrators, the vibration radius of the second pneumatic vibrator meshes with the vibration radius of other adjacent vibrators, and the third pneumatic vibrator meshes with the vibration radius of other adjacent vibrators. The vibrating radius of the vibrator is meshed with the vibrating radius of other adjacent vibrators, the vibrating radius of the fourth vibrator is meshed with the vibrating radius of other adjacent vibrators, and the vibrating radius of the first plug-in vibrator is The radius is meshed with the vibration radius of other adjacent vibrators, the vibration radius of the second plug-in vibrator is meshed with the vibration radius of other adjacent vibrators, and the vibration radius of the third plug-in vibrator is The vibrating radius of other adjacent vibrators is engaged; in the first direction, the distance between two adjacent feeding ports is between 1.8 meters and 2.5 meters, and the distance between two adjacent filling holes is between 1.8 and 2.5 meters. between 1.2 meters and 1.8 meters.

由上可见,上述设计使得第一振捣组、第二振捣组、第三振捣组、第四振捣组、第五振捣组、第六振捣组及多个第三插入式振捣器的振捣范围能够覆盖整个二衬混凝土,从而保证二衬混凝土的整体质量。As can be seen from the above, the above-mentioned design makes the first vibrating group, the second vibrating group, the third vibrating group, the fourth vibrating group, the fifth vibrating group, the sixth vibrating group and a plurality of third insertion vibrators. The vibrating range of the tamper can cover the entire secondary lining concrete, thereby ensuring the overall quality of the secondary lining concrete.

另一个优选的方案是,每个施工区均设置有至少一个手持插入式振捣棒。Another preferred solution is that each construction area is provided with at least one hand-held plug-in vibrator.

由上可见,通过设置手持插入式振捣棒,使得在向每个入料口浇筑混凝土时,施工人员能够在混凝土浇筑过程中对混凝土进行初步振捣,以使得注入的混凝土能够初步密实,同时,手持插入式振捣棒的设置能够在混凝土浇筑过程中,施工人员能够通过手持插入式振捣棒控制中埋止水带保持顺直,使中埋止水带不被挤压变形以及防止中埋止水带倾倒。It can be seen from the above that by setting the hand-held plug-in vibrator, when pouring concrete into each feeding port, the construction personnel can initially vibrate the concrete during the concrete pouring process, so that the injected concrete can be initially compacted and at the same time. , The setting of the hand-held plug-in vibrator can control the middle-buried waterstop to keep straight during the concrete pouring process, so that the middle-buried waterstop is not squeezed and deformed and prevents the middle-buried waterstop from being squeezed and deformed. Buried waterstop dumped.

进一步的方案是,在环向上,位于相邻两层浇筑窗之间的第一振捣组靠近该两组相邻的浇筑窗中高度低的一层浇筑窗设置。A further solution is that, in the circumferential direction, the first vibrating group located between two adjacent layers of pouring windows is arranged close to the first floor pouring window with a lower height among the two groups of adjacent pouring windows.

由上可见,上述设计能够保证每个入料口附近的混凝土受到更好的振捣,以对手持插入式振捣器的振捣盲区进行填补,从而提高整体二衬混凝土的浇筑质量。It can be seen from the above that the above design can ensure that the concrete near each feeding port is better vibrated, so as to fill the vibration blind area of the hand-held plug-in vibrator, thereby improving the pouring quality of the overall secondary lining concrete.

更进一步的方案是,沿第一方向,钢模板的长度介于10米至14米之间。A further solution is that the length of the steel formwork is between 10 and 14 meters in the first direction.

由上可见,通过对钢模板的长度设计,使得施工出的二衬长度适中且能够符合规范要求,同时能够保证二衬混凝土的整体浇筑质量。It can be seen from the above that by designing the length of the steel formwork, the length of the secondary lining constructed can be moderate and can meet the requirements of the specification, and at the same time, the overall pouring quality of the secondary lining concrete can be guaranteed.

更进一步的方案是,在每个施工区中,浇筑窗的数量为3层,第一振捣组的数量为三组,第二振捣组的数量为两组;在环向上,相邻两个第二气动振捣器错开设置。A further solution is that in each construction area, the number of pouring windows is 3 layers, the number of the first vibrating group is three, and the number of the second vibrating group is two; A second pneumatic vibrator is staggered.

由上可见,上述设计能够进一步优化振捣系统的结构布局,并保证对混凝土的振捣质量及振捣效果。It can be seen from the above that the above design can further optimize the structural layout of the vibrating system, and ensure the vibrating quality and vibrating effect of the concrete.

更进一步的方案是,每层浇筑窗的入料口的数量为四个,且每层浇筑窗中的三个入料口位于边拱部,剩余一个入料口位于第一端部或第二端部,在环向上,相邻两个入料口错开设置;每组第一振捣组的第一气动振捣器的数量为三个;每组第二振捣组的第二气动振捣器的数量为三个。A further solution is that the number of inlets for each layer of pouring windows is four, and three inlets in each layer of pouring windows are located at the side arch, and the remaining one is located at the first end or the second. At the end, in the ring direction, the two adjacent feeding ports are staggered; the number of the first pneumatic vibrators in each first vibrating group is three; the second pneumatic vibrators in each second vibrating group The number of devices is three.

由上可见,上述设计使得入料口、第一气动振捣器、第二气动振捣器之间的相对位置布局更加优化、合理,以进一步保证对混凝土的振捣质量及振捣效果。It can be seen from the above that the above design makes the relative position layout of the feed inlet, the first pneumatic vibrator and the second pneumatic vibrator more optimized and reasonable, so as to further ensure the vibrating quality and vibrating effect of the concrete.

更进一步的方案是,每组第三振捣组的第三气动振捣器的数量为四个;每组第四振捣组的第四气动振捣器的数量为四个;第五振捣组包括两个沿环向分布的第一插入式振捣器;第六振捣组包括两个沿环向分布的第二插入式振捣器;第三插入式振捣器的数量为四个;灌注孔的数量为三个;沿第一方向,钢模板的长度为12米。A further solution is that the number of the third pneumatic vibrators in each third vibrating group is four; the number of the fourth pneumatic vibrators in each fourth vibrating group is four; the fifth vibrating The group includes two first plug-in vibrators distributed in the circumferential direction; the sixth vibration group includes two second plug-in vibrators distributed in the circumferential direction; the number of the third plug-in vibrators is four ; The number of perfusion holes is three; along the first direction, the length of the steel formwork is 12 meters.

由上可见,上述设计能够使振捣系统的整体结构布局处于较优设计,以大幅度降低设置消除衬砌施工中存在的缺陷,使混凝土强度内外基本一致,且强度离散值小,此外,还使拱顶混凝土更加密实,防止出现蜂窝麻面、拱顶混凝土脱空等质量问题。It can be seen from the above that the above design can make the overall structural layout of the vibrating system in a better design, greatly reduce the setting and eliminate the defects existing in the lining construction, so that the concrete strength is basically consistent inside and outside, and the strength dispersion value is small. The vault concrete is more compact to prevent quality problems such as honeycomb pitted surface and voiding of vault concrete.

为了实现本发明的另一目的,本发明提供一种隧道衬砌台车,包括上述的振捣系统。In order to achieve another object of the present invention, the present invention provides a tunnel lining trolley including the above-mentioned vibrating system.

由上可见,设置有上述振捣系统的隧道衬砌台车能够提高二衬混凝土的整体浇筑质量,保证混凝土的密实度及混凝土强度的均匀性,并防止拱顶混凝土脱空;此外,还能够保证混凝土强度内外基本一致,且强度离散值小。It can be seen from the above that the tunnel lining trolley equipped with the above-mentioned vibrating system can improve the overall pouring quality of the secondary lining concrete, ensure the compactness of the concrete and the uniformity of the concrete strength, and prevent the vault concrete from emptying; in addition, it can also ensure The strength of concrete is basically the same inside and outside, and the discrete value of strength is small.

附图说明Description of drawings

图1是现有的振捣系统的结构示意图。FIG. 1 is a schematic structural diagram of a conventional vibrating system.

图2是本发明振捣系统实施例的结构示意图。FIG. 2 is a schematic structural diagram of an embodiment of the vibrating system of the present invention.

图3是本发明振捣系统实施例的浇筑窗分布的结构示意图。FIG. 3 is a schematic structural diagram of the distribution of pouring windows in an embodiment of the vibrating system of the present invention.

图4是本发明振捣系统实施例的第一振捣组和第二振捣组分布的结构示意图。4 is a schematic structural diagram of the distribution of the first vibrating group and the second vibrating group in an embodiment of the vibrating system of the present invention.

图5是本发明振捣系统实施例的使用状态示意图。FIG. 5 is a schematic diagram of a use state of an embodiment of the vibrating system of the present invention.

图6是本发明振捣系统实施例的手持插入式振捣棒在每个入料口的大致振捣范围示意图。Fig. 6 is a schematic diagram showing the approximate vibrating range of the hand-held plug-in vibrator in each feeding port of the vibrating system embodiment of the present invention.

图7是本发明振捣系统实施例的每个第一气动振捣器和每个第二气动振捣器的大致振捣范围示意图。FIG. 7 is a schematic diagram of the approximate vibration range of each first pneumatic vibrator and each second pneumatic vibrator of the vibrating system embodiment of the present invention.

图8是本发明振捣系统实施例的每个第三气动振捣器、每个第四气动振捣器、每个第一插入式振捣器和每个第二插入式振捣器的大致振捣范围示意图。8 is a general view of each third pneumatic vibrator, each fourth pneumatic vibrator, each first plug-in vibrator, and each second plug-in vibrator of the vibrating system embodiment of the present invention Schematic diagram of the vibration range.

图9是本发明振捣系统实施例的每个第三插入式振捣器的大致振捣范围示意图。FIG. 9 is a schematic diagram of the approximate vibrating range of each third insertion vibrator of the vibrating system embodiment of the present invention.

图10是本发明振捣系统实施例的检测波形图。Fig. 10 is a detection waveform diagram of an embodiment of the vibrating system of the present invention.

图11是本发明振捣系统实施例的衬砌拱顶强度声波回弹法检测数据对比表。Fig. 11 is a comparison table of detection data of lining dome strength by acoustic rebound method according to an embodiment of the vibrating system of the present invention.

以下结合附图及实施例对本发明作进一步说明。The present invention will be further described below with reference to the accompanying drawings and embodiments.

具体实施方式Detailed ways

振捣系统实施例Vibration system embodiment

参照图2至图5,振捣系统200包括钢模板2、空气压缩机和控制装置。钢模板2具有两个关于对称面201呈对称设置的施工区20,施工区20具有边拱部202、第一端部203和第二端部204,沿第一方向X,边拱部202位于第一端部203和第二端部204之间。此外,每个施工区20上均设置有多层浇筑窗21、多组第一振捣组22、至少一组第二振捣组23、第三振捣组24、第四振捣组25、第五振捣组26和第六振捣组27。其中,钢模板2的高度方向和轴心均在对称面201上,第一方向X平行于轴心。2 to 5, the vibrating system 200 includes a steel formwork 2, an air compressor and a control device. The steel formwork 2 has two construction areas 20 that are symmetrically arranged with respect to the symmetry plane 201. The construction area 20 has a side arch 202, a first end 203 and a second end 204. Along the first direction X, the side arch 202 is located at between the first end 203 and the second end 204 . In addition, each construction area 20 is provided with multi-layer pouring windows 21, multiple groups of first vibration groups 22, at least one group of second vibration groups 23, third vibration groups 24, fourth vibration groups 25, Fifth vibrating group 26 and sixth vibrating group 27 . Wherein, the height direction and the axis of the steel template 2 are both on the symmetry plane 201, and the first direction X is parallel to the axis.

沿第一方向X,钢模板2的长度介于10米至14米之间,多层浇筑窗21沿钢模板2的环向分布,每层浇筑窗21的包括多个入料口211,多个入料口211沿第一方向X分布。在本实施例中,沿第一方向X,钢模板2的长度为12米,浇筑窗21的数量优选为三层,每层浇筑窗21包括四个入料口211,在第一方向X上,相邻两个入料口211之间的间距优选介于1.8米至2.5米之间;较优地,在第一方向X上,相邻两个入料口211之间的间距为2.2米。其中,三层浇筑窗21位于施工区20的中下部,即对应隧道的边墙区域,每层浇筑窗21中的三个入料口211位于施工区20的边拱部202,剩余一个入料口211则位于第一端部203或第二端部204,且在钢模板2的环向上,相邻两个入料口211错开设置。Along the first direction X, the length of the steel formwork 2 is between 10 meters and 14 meters, and the multi-layer casting windows 21 are distributed along the circumferential direction of the steel formwork 2. The feed ports 211 are distributed along the first direction X. In this embodiment, along the first direction X, the length of the steel formwork 2 is 12 meters, the number of pouring windows 21 is preferably three layers, and each layer of pouring windows 21 includes four feeding ports 211 , in the first direction X , the distance between two adjacent feeding ports 211 is preferably between 1.8 meters and 2.5 meters; preferably, in the first direction X, the distance between two adjacent feeding ports 211 is 2.2 meters . Among them, the three-layer pouring window 21 is located in the middle and lower part of the construction area 20, that is, the side wall area corresponding to the tunnel, and the three feeding ports 211 in each layer of the pouring window 21 are located in the side arch 202 of the construction area 20, and the remaining one feeding The port 211 is located at the first end portion 203 or the second end portion 204 , and in the ring direction of the steel formwork 2 , two adjacent feed ports 211 are staggered.

进一步地,每个施工区20均设置有至少一个手持插入式振捣棒,使得在向每个入料口211浇筑混凝土时,施工人员能够在混凝土浇筑过程中对混凝土进行初步振捣,以使得注入的混凝土能够初步密实,同时,手持插入式振捣棒的设置能够在混凝土浇筑过程中,施工人员能够通过手持插入式振捣棒控制中埋止水带保持顺直,使中埋止水带不被挤压变形以及防止中埋止水带倾倒。Further, each construction area 20 is provided with at least one hand-held plug-in vibrator, so that when pouring concrete into each feeding port 211, the construction personnel can initially vibrate the concrete during the concrete pouring process, so that The injected concrete can be preliminarily compacted. At the same time, the setting of the hand-held plug-in vibrator can make the middle-buried water stop straight and straight during the concrete pouring process. It will not be squeezed and deformed and prevent the dumping of the buried water stop.

多组第一振捣器均设置在施工区20的边拱部202,且多组第一振捣器位于施工区20的中下部,即对应隧道的边墙区域。多组第一振捣组22沿钢模板2的环向分布,且多组第一振捣组22与多层浇筑窗21在钢模板2的环向上相间设置,每组第一振捣组22包括多个第一气动振捣器221,多个第一气动振捣器221沿第一方向X分布。在本实施例中,第一振捣组22的数量优选为三组,每组第一振捣组22包括三个第一气动振捣器221,在第一方向X上,相邻两个第一气动振捣器221之间的间距优选介于1.8米至2.5米之间,第一气动振捣器221的振捣半径优选介于1.8米至2.5米之间;较优地,第一气动振捣器221的振捣半径为2.5米,且在第一方向X上,相邻两个第一气动振捣器221之间的间距为2.2米;此外,在高度方向上,第一气动振捣器221与隧道的矮边墙之间的最小距离优选介于0.8米至1米之间,即最下方一组第一振捣组22的每个第一气动振捣器221的高度与隧道的矮边墙之间的最小距离优选介于0.8米至1米直接,且最下方的一组第一振捣组22的高度小于最底层的浇筑窗21的高度。通过对第一振捣组22和浇筑窗21的相对位置设计,既保证了仰拱与二衬之间的施工缝处的混凝土能够受到全面、充分的振捣,又保证相邻两层浇筑窗21之间的混凝土能够受到全面、充分的振捣,从而使得边墙处混凝土能够更加的密实,减少边墙处混凝土的缺陷病害。The multiple groups of first vibrators are all arranged on the side arch 202 of the construction area 20 , and the multiple groups of first vibrators are located in the middle and lower parts of the construction area 20 , ie, corresponding to the side wall area of the tunnel. Multiple groups of first vibrating groups 22 are distributed along the circumferential direction of the steel formwork 2, and multiple groups of the first vibrating groups 22 and the multi-layer pouring windows 21 are arranged alternately in the circumferential direction of the steel formwork 2, and each group of the first vibrating groups 22 A plurality of first pneumatic vibrators 221 are included, and the plurality of first pneumatic vibrators 221 are distributed along the first direction X. In this embodiment, the number of the first vibrating groups 22 is preferably three groups, and each group of the first vibrating groups 22 includes three first pneumatic vibrators 221 . The distance between a pneumatic vibrator 221 is preferably between 1.8 meters and 2.5 meters, and the vibration radius of the first pneumatic vibrator 221 is preferably between 1.8 meters and 2.5 meters; The vibrating radius of the vibrator 221 is 2.5 meters, and in the first direction X, the distance between two adjacent first pneumatic vibrators 221 is 2.2 meters; The minimum distance between the vibrator 221 and the short side wall of the tunnel is preferably between 0.8 m and 1 m, that is, the height of each first pneumatic vibrator 221 of the lowermost group of first vibrating groups 22 is the same as the height of the tunnel. The minimum distance between the short side walls is preferably between 0.8 m and 1 m directly, and the height of the lowermost group of first vibrating groups 22 is smaller than the height of the lowermost pouring window 21 . By designing the relative positions of the first vibrating group 22 and the pouring window 21, it is not only ensured that the concrete at the construction joint between the inverted arch and the second lining can be fully and fully vibrated, but also the two adjacent layers of pouring windows are guaranteed. The concrete between 21 can be fully and fully vibrated, so that the concrete at the side wall can be more dense, and the defect and disease of the concrete at the side wall can be reduced.

第二振捣组23设置在施工区20的边拱部202,每组第二振捣组23包括多个第二气动振捣器231,多个第二气动振捣器231沿第一方向X分布。在高度方向上,第二振捣组23位于最顶层的浇筑窗21的上方,使得第二振捣组23位于施工区20的中上部,即对应隧道的拱部区域。在本实施例中,第二振捣组23的数量优选为两组,每组第二振捣组23包括三个第二气动振捣器231,在第一方向X上,相邻两个第二气动振捣器231之间的间距优选介于1.8米至2.5米之间,第二气动振捣器231的振捣半径优选介于1.8米至2.5米之间;较优地,第二气动振捣器231的振捣半径为2.5米,且在第一方向X上,相邻两个第二气动振捣器231之间的间距为2.2米。通过对第二振捣组23的位置设置,使得第二振捣组23能够对拱部处的混凝土进行全面、充分的振捣,以保证拱部处的混凝土能够密实无缺陷病害。The second vibrating group 23 is disposed on the side arch 202 of the construction area 20 , and each second vibrating group 23 includes a plurality of second pneumatic vibrators 231 , and the plurality of second pneumatic vibrators 231 are along the first direction X distributed. In the height direction, the second vibrating group 23 is located above the pouring window 21 of the topmost layer, so that the second vibrating group 23 is located in the middle and upper part of the construction area 20 , ie, corresponding to the arch area of the tunnel. In this embodiment, the number of the second vibrating groups 23 is preferably two groups, and each group of the second vibrating groups 23 includes three second pneumatic vibrators 231 . The distance between the two pneumatic vibrators 231 is preferably between 1.8 meters and 2.5 meters, and the vibration radius of the second pneumatic vibrators 231 is preferably between 1.8 meters and 2.5 meters; The vibrating radius of the vibrators 231 is 2.5 meters, and in the first direction X, the distance between two adjacent second pneumatic vibrators 231 is 2.2 meters. By setting the position of the second vibrating group 23, the second vibrating group 23 can fully and fully vibrate the concrete at the arch portion, so as to ensure that the concrete at the arch portion can be dense and free of defects.

在钢模板2的环向上,相邻两个第一气动振捣器221错开设置,相邻两个第二气动振捣器231错开设置,相邻的一个第一气动振捣器221和一个第二气动振捣器231错开设置。再者,在钢模板2的环向上,位于相邻两层浇筑窗21之间的第一振捣组22靠近该两组相邻的浇筑窗21中高度低的一层浇筑窗21设置,从而保证每个入料口211附近的混凝土受到更好的振捣,以对手持插入式振捣器的振捣盲区进行填补,从而提高整体二衬混凝土的浇筑质量。In the ring direction of the steel formwork 2, the adjacent two first pneumatic vibrators 221 are staggered, the adjacent two second pneumatic vibrators 231 are staggered, and the adjacent first pneumatic vibrators 221 and the first The two pneumatic vibrators 231 are staggered. Furthermore, in the circumferential direction of the steel formwork 2, the first vibrating group 22 located between the two adjacent layers of the pouring windows 21 is arranged close to the lower one-layer pouring window 21 among the two adjacent layers of the pouring windows 21, thereby It is ensured that the concrete near each feeding port 211 is better vibrated, so as to fill the vibration blind area of the hand-held plug-in vibrator, thereby improving the pouring quality of the overall secondary lining concrete.

第三振捣组24设置在施工区20的第一端部203,且第三振捣组24位于施工区20的中下部,即对应隧道的边墙区域。第三振捣组24包括多个第三气动振捣器241,多个第三气动振捣器241沿钢模板2的环向分布。在本实施例中,第三振捣组24包括四个第三气动振捣器241,其中,在钢模板2的环向上,相邻两个第三气动振捣器241之间的间距可根据位于第一端部203处的入料口211的位置进行相适应的设置及调整,以保证第三振捣组24对第一端部203处的混凝土的振捣效果。在高度方向上,第三振捣组24中高度位置最低的第三气动振捣器241与矮边墙之间的最小距离优选介于0.8米至1米之间。第三气动振捣器241的振捣半径优选介于1.8米至2.5米之间,较优地,第三气动振捣器241的振捣半径为2.2米。The third vibrating group 24 is arranged at the first end 203 of the construction area 20, and the third vibrating group 24 is located in the middle and lower part of the construction area 20, that is, the side wall area corresponding to the tunnel. The third vibrating group 24 includes a plurality of third pneumatic vibrators 241 , and the plurality of third pneumatic vibrators 241 are distributed along the circumferential direction of the steel formwork 2 . In this embodiment, the third vibrating group 24 includes four third pneumatic vibrators 241, wherein, in the ring direction of the steel template 2, the distance between two adjacent third pneumatic vibrators 241 can be determined according to The position of the feeding port 211 at the first end 203 is appropriately set and adjusted to ensure the vibrating effect of the third vibrating group 24 on the concrete at the first end 203 . In the height direction, the minimum distance between the third pneumatic vibrator 241 at the lowest height position in the third vibrating group 24 and the short side wall is preferably between 0.8 m and 1 m. The vibration radius of the third pneumatic vibrator 241 is preferably between 1.8 meters and 2.5 meters, and preferably, the vibration radius of the third pneumatic vibrator 241 is 2.2 meters.

通过对第三振捣组24的设置,使得第三振捣组24能够对钢模板2端部的边墙部分的混凝土进行全面、充分的振捣,以保证环向施工缝处混凝土的浇筑质量,从而保证相邻两板二衬之间的衔接质量;此外,第三振捣组24还用于配合第一振捣组22对仰拱与二衬之间的施工缝端部处的混凝土进行充分、有效且全面的振捣,进而保证钢模板2的边墙、端部边墙区域的混凝土的密实度,提升混凝土的浇筑质量。By setting the third vibrating group 24, the third vibrating group 24 can fully and fully vibrate the concrete of the side wall part at the end of the steel formwork 2, so as to ensure the pouring quality of the concrete at the circumferential construction joint. , thereby ensuring the connection quality between the adjacent two plates and two linings; in addition, the third vibrating group 24 is also used to cooperate with the first vibrating group 22 to carry out the concrete at the end of the construction joint between the inverted arch and the two linings. Sufficient, effective and comprehensive vibrating, thereby ensuring the compactness of the concrete in the side wall and end side wall areas of the steel formwork 2, and improving the pouring quality of the concrete.

第四振捣组25设置在施工区20的第二端部204,且第四振捣组25位于施工区20的中下部,即对应隧道的边墙区域。第四振捣组25包括多个第四气动振捣器251,多个第四气动振捣器251沿钢模板2的环向分布。在本实施例中,第四振捣组25包括四个第四气动振捣器251,其中,在钢模板2的环向上,相邻两个第四气动振捣器251之间的间距可根据位于第二端部204处的入料口211的位置进行相适应的设置及调整,以保证第四振捣组25对第二端部204处的混凝土的振捣效果。在高度方向上,第四振捣组25中高度位置最低的第四气动振捣器251与矮边墙之间的最小距离优选介于0.8米至1米之间。第四气动振捣器251的振捣半径优选介于1.8米至2.5米之间,较优地,第四气动振捣器251的振捣半径为2.2米。The fourth vibrating group 25 is arranged at the second end 204 of the construction area 20 , and the fourth vibrating group 25 is located in the middle and lower part of the construction area 20 , ie, corresponding to the side wall area of the tunnel. The fourth vibrating group 25 includes a plurality of fourth pneumatic vibrators 251 , and the plurality of fourth pneumatic vibrators 251 are distributed along the circumferential direction of the steel formwork 2 . In this embodiment, the fourth vibrating group 25 includes four fourth pneumatic vibrators 251, wherein, in the ring direction of the steel template 2, the distance between two adjacent fourth pneumatic vibrators 251 can be determined according to The position of the feeding port 211 at the second end 204 is appropriately set and adjusted to ensure the vibrating effect of the fourth vibrating group 25 on the concrete at the second end 204 . In the height direction, the minimum distance between the fourth pneumatic vibrator 251 at the lowest height position in the fourth vibrating group 25 and the short side wall is preferably between 0.8 m and 1 m. The vibration radius of the fourth pneumatic vibrator 251 is preferably between 1.8 meters and 2.5 meters, and preferably, the vibration radius of the fourth pneumatic vibrator 251 is 2.2 meters.

通过对第四振捣组25的设置,使得第四振捣组25能够对钢模板2端部的边墙部分的混凝土进行全面、充分的振捣,以保证环向施工缝处混凝土的浇筑质量,从而保证相邻两板二衬之间的衔接质量;此外,第四振捣组25还用于配合第一振捣组22对仰拱与二衬之间的施工缝端部处的混凝土进行充分、有效且全面的振捣,进而保证钢模板2的边墙、端部边墙区域的混凝土的密实度,提升混凝土的浇筑质量。By setting the fourth vibrating group 25, the fourth vibrating group 25 can fully and fully vibrate the concrete of the side wall part at the end of the steel formwork 2, so as to ensure the pouring quality of the concrete at the circumferential construction joint. , thereby ensuring the connection quality between the adjacent two plates and two linings; in addition, the fourth vibrating group 25 is also used to cooperate with the first vibrating group 22 to carry out the concrete at the end of the construction joint between the inverted arch and the two linings. Sufficient, effective and comprehensive vibrating, thereby ensuring the compactness of the concrete in the side wall and end side wall areas of the steel formwork 2, and improving the pouring quality of the concrete.

第五振捣组26设置在施工区20的第一端部203,在高度方向上,第五振捣组26位于第三振捣组24的上方,使得第五振捣组26位于施工区20的中上部,即对应隧道的拱部区域。第五振捣组26包括至少一个第一插入式振捣器261,在本实施例中,第五振捣组26包括两个第一插入式振捣器261,两个第一插入式振捣器261沿钢模板2的环向分布,其中,在钢模板2的环向上,相邻两个第一插入式振捣器261之间的间距优选介于1.2米至1.8米之间,且第一插入式振捣器261的振捣半径优选介于1.2米至1.8米之间。此外,在钢模板2的环向上,相邻的一个第三气动振捣器241与一个第一插入式振捣器261之间的间距优选介于1.2米至1.8米之间;较优地,相邻两个第一插入式振捣器261之间的间距为1.5米,第一插入式振捣器261的振捣半径为1.5米,相邻的一个第三气动振捣器241与一个第一插入式振捣器261之间的间距为1.5米。The fifth vibrating group 26 is arranged at the first end 203 of the construction area 20 , and in the height direction, the fifth vibrating group 26 is located above the third vibrating group 24 , so that the fifth vibrating group 26 is located in the construction area 20 The middle and upper part of the tunnel corresponds to the arch area of the tunnel. The fifth vibrating group 26 includes at least one first plug-in vibrator 261 . In this embodiment, the fifth vibrating group 26 includes two first plug-in vibrators 261 , two first plug-in vibrators 261 . The vibrators 261 are distributed along the circumferential direction of the steel formwork 2, wherein, in the circumferential direction of the steel formwork 2, the distance between two adjacent first plug-in vibrators 261 is preferably between 1.2 meters and 1.8 meters, and the first The vibrating radius of a plug-in vibrator 261 is preferably between 1.2 meters and 1.8 meters. In addition, in the ring direction of the steel formwork 2, the distance between an adjacent third pneumatic vibrator 241 and a first plug-in vibrator 261 is preferably between 1.2 meters and 1.8 meters; preferably, The distance between two adjacent first plug-in vibrators 261 is 1.5 meters, and the vibration radius of the first plug-in vibrators 261 is 1.5 meters. The spacing between a plug-in vibrator 261 is 1.5 meters.

通过对第五振捣组26的设置,使得第一插入式振捣器261能够对钢模板2端部的拱顶部分的混凝土进行全面、充分的振捣,以避免混凝土灌入拱顶过程中因局部混凝土聚集而造成小范围内空洞或不密实,从而保证环向施工缝处混凝土的浇筑质量,提高相邻两板二衬的衔接质量;此外,第五振捣组26还用于配合第二振捣组23对拱顶处的混凝土进行振捣,以提高对钢模板2拱顶部分的混凝土的振捣效果。Through the arrangement of the fifth vibrating group 26, the first insertion vibrator 261 can fully and fully vibrate the concrete of the vault portion at the end of the steel formwork 2, so as to avoid the concrete pouring into the vault during the process of pouring into the vault. Due to the local concrete accumulation, there are voids or non-compactness in a small area, so as to ensure the pouring quality of the concrete at the circumferential construction joints and improve the connection quality of the adjacent two plates and two linings; in addition, the fifth vibrating group 26 is also used to cooperate with the first The second vibrating group 23 vibrates the concrete at the vault, so as to improve the vibrating effect of the concrete at the vault of the steel formwork 2 .

第六振捣组27设置在施工区20的第一端部203,在高度方向上,第六振捣组27位于第四振捣组25的上方,使得第六振捣组27位于施工区20的中上部,即对应隧道的拱部区域。第六振捣组27包括至少一个第二插入式振捣器271,在本实施例中,第五振捣组26包括两个第二插入式振捣器271,两个第二插入式振捣器271沿钢模板2的环向分布,其中,在钢模板2的环向上,相邻两个第二插入式振捣器271之间的间距优选介于1.2米至1.8米之间,且第二插入式振捣器271的振捣半径优选介于1.2米至1.8米之间。此外,在钢模板2的环向上,相邻的一个第四气动振捣器251与一个第二插入式振捣器271之间的间距优选介于1.2米至1.8米之间;较优地,相邻两个第二插入式振捣器271之间的间距为1.5米,第二插入式振捣器271的振捣半径为1.5米,相邻的一个第四气动振捣器251与一个第二插入式振捣器271之间的间距为1.5米。The sixth vibrating group 27 is arranged at the first end 203 of the construction area 20. In the height direction, the sixth vibrating group 27 is located above the fourth vibrating group 25, so that the sixth vibrating group 27 is located in the construction area 20. The middle and upper part of the tunnel corresponds to the arch area of the tunnel. The sixth vibrating group 27 includes at least one second plug-in vibrator 271, and in this embodiment, the fifth vibrating group 26 includes two second plug-in vibrators 271, two second plug-in vibrators The vibrators 271 are distributed along the circumferential direction of the steel formwork 2, wherein, in the circumferential direction of the steel formwork 2, the distance between two adjacent second insertion vibrators 271 is preferably between 1.2 meters and 1.8 meters, and the first The vibrating radius of the two insertion vibrators 271 is preferably between 1.2 meters and 1.8 meters. In addition, in the ring direction of the steel formwork 2, the distance between an adjacent fourth pneumatic vibrator 251 and a second plug-in vibrator 271 is preferably between 1.2 meters and 1.8 meters; preferably, The distance between two adjacent second plug-in vibrators 271 is 1.5 meters, the vibration radius of the second plug-in vibrators 271 is 1.5 meters, and an adjacent fourth pneumatic vibrator 251 and a first The distance between the two plug-in vibrators 271 is 1.5 meters.

通过对第六振捣组27的设置,使得第二插入式振捣器271能够对钢模板2端部的拱顶部分的混凝土进行全面、充分的振捣,以避免混凝土灌入拱顶过程中因局部混凝土聚集而造成小范围内空洞或不密实,从而保证环向施工缝处混凝土的浇筑质量,提高相邻两板二衬的衔接质量;此外,第六振捣组27还用于配合第二振捣组23对拱顶处的混凝土进行振捣,以提高对钢模板2拱顶部分的混凝土的振捣效果。Through the arrangement of the sixth vibrating group 27, the second inserting vibrator 271 can fully and fully vibrate the concrete of the vault portion at the end of the steel formwork 2, so as to avoid the concrete pouring into the vault during the process of pouring into the vault. Due to the local concrete accumulation, there are voids or non-compactness in a small area, so as to ensure the pouring quality of the concrete at the circumferential construction joints and improve the connection quality of the adjacent two plates and two linings; in addition, the sixth vibrating group 27 is also used to cooperate with the first The second vibrating group 23 vibrates the concrete at the vault, so as to improve the vibrating effect of the concrete at the vault of the steel formwork 2 .

钢模板2的拱顶设置有多个第三插入式振捣器28和多个灌注孔29,多个第三插入式振捣器28沿第一方向X分布,多个灌注孔29沿第一方向X分布。在第一方向X上,多个第三插入式振捣器28和多个灌注孔29相间设置,且多个第三插入式振捣器28和多个灌注孔29均位于对称面201上,优选地,在第一方向X上,第三插入式振捣器28与灌注孔29之间的间距介于1.2米至1.8米之间;较优地,在第一方向X上,第三插入式振捣器28与灌注孔29之间的间距为1.5米。The dome of the steel formwork 2 is provided with a plurality of third plug-in vibrators 28 and a plurality of filling holes 29, the plurality of third plug-in vibrators 28 are distributed along the first direction X, and the plurality of filling holes 29 are along the first direction X. Direction X distribution. In the first direction X, the plurality of third insertion vibrators 28 and the plurality of filling holes 29 are alternately arranged, and the plurality of third insertion vibrators 28 and the plurality of filling holes 29 are all located on the symmetry plane 201, Preferably, in the first direction X, the distance between the third insertion vibrator 28 and the filling hole 29 is between 1.2 meters and 1.8 meters; The distance between the vibrator 28 and the filling hole 29 is 1.5 meters.

第三插入式振捣器28用于对钢模板2拱顶处的混凝土进行振捣,并在第二振捣组23的配合对拱顶处的混凝土进行更全面、更充分的振捣,以保证拱顶处混凝土分布均匀、密实且强度均匀,并防止由于振捣不到位而导致出现混凝土不密实、蜂窝麻面、拱顶脱空等问题。The third plug-in vibrator 28 is used to vibrate the concrete at the dome of the steel formwork 2, and with the cooperation of the second vibrating group 23, it can vibrate the concrete at the dome more comprehensively and fully, so that the Ensure that the concrete at the vault is evenly distributed, dense and even in strength, and prevent the occurrence of problems such as uncompacted concrete, honeycomb pitted surface, and voiding of the vault due to insufficient vibration.

结合图6至图9,第一气动振捣器221的振捣半径与临近的其他振捣器的振捣半径咬合,第二气动振捣器231的振捣半径与临近的其他振捣器的振捣半径咬合,第三气动振捣器241的振捣半径与临近的其他振捣器的振捣半径咬合,第四气动振捣器251的振捣半径与临近的其他振捣器的振捣半径咬合,第一插入式振捣器261的振捣半径与临近的其他振捣器的振捣半径咬合,第二插入式振捣器271的振捣半径与临近的其他振捣器的振捣半径咬合,第三插入式振捣器28的振捣半径与临近的其他振捣器的振捣半径咬合;上述设计使得第一振捣组22、第二振捣组23、第三振捣组24、第四振捣组25、第五振捣组26、第六振捣组27及多个第三插入式振捣器28的振捣范围能够覆盖整个二衬混凝土,从而保证二衬混凝土的整体质量。6 to 9 , the vibration radius of the first pneumatic vibrator 221 meshes with the vibration radius of other adjacent vibrators, and the vibration radius of the second pneumatic vibrator 231 is the same as that of other adjacent vibrators. The vibration radius is meshed, the vibration radius of the third pneumatic vibrator 241 is meshed with the vibration radius of other adjacent vibrators, and the vibration radius of the fourth pneumatic vibrator 251 is meshed with the vibration radius of other adjacent vibrators. The radius is engaged, the vibration radius of the first plug-in vibrator 261 is meshed with the vibration radius of other adjacent vibrators, and the vibration radius of the second plug-in vibrator 271 is adjacent to the vibration radius of other vibrators Radius bite, the vibration radius of the third plug-in vibrator 28 and the vibration radius of other adjacent vibrators bite; the above design makes the first vibration group 22, the second vibration group 23, the third vibration group 24. The vibration range of the fourth vibrating group 25 , the fifth vibrating group 26 , the sixth vibrating group 27 and the plurality of third insert vibrators 28 can cover the entire secondary lining concrete, thereby ensuring the protection of the secondary lining concrete. overall quality.

空气压缩机通过阀门单元分别与每个第一气动振捣器221、每个第二气动振捣器231、每个第三气动振捣器241、每个第四气动振捣器251、每个第一插入式振捣器261、每个第二插入式振捣器271和每个第三插入式振捣器28连接,控制装置分别与空气压缩机和阀门单元电连接,从而使得控制装置能够通过空气压缩机和阀门单元控制第一振捣组22、第二振捣组23、第三振捣组24、第四振捣组25、第五振捣组26、第六振捣组27和第三插入式振捣器28进行相应的振捣作业。The air compressor is respectively connected with each first pneumatic vibrator 221, each second pneumatic vibrator 231, each third pneumatic vibrator 241, each fourth pneumatic vibrator 251, each The first plug-in vibrator 261, each second plug-in vibrator 271 and each third plug-in vibrator 28 are connected, and the control device is electrically connected to the air compressor and the valve unit, respectively, so that the control device can The first vibrating group 22, the second vibrating group 23, the third vibrating group 24, the fourth vibrating group 25, the fifth vibrating group 26, the sixth vibrating group 27 and the The third plug-in vibrator 28 performs the corresponding vibrating operation.

振捣系统的施工方法实施例Example of construction method of vibrating system

本实施例采用上述振捣系统200实施例中的振捣系统200进行施工,具体的施工方法如下:This embodiment adopts the vibrating system 200 in the above-mentioned vibrating system 200 embodiment for construction, and the specific construction method is as follows:

施工时,振捣系统200的钢模板2与已浇筑成型的二衬、当前施工段的初次衬砌、仰拱及矮边墙及端头模板之间形成当前施工段的二衬浇筑腔。During construction, the steel formwork 2 of the vibrating system 200 and the casted secondary lining, the primary lining of the current construction section, the inverted arch, the short side wall and the end formwork form the secondary lining pouring cavity of the current construction section.

接着,向施工区20的最底层浇筑窗21浇筑混凝土,浇筑过程中,由工人操作手持插入式振捣器对最底层浇筑窗21处浇筑的混凝土进行振捣。工人操作手持插入式振捣器进行振捣时,分多次、多区域进行,即手持插入式振捣器会对最底层浇筑窗21的每个入料口211附近浇筑的混凝土进行振捣,单次振捣时间优选介于15秒至25秒之间,混凝土振捣后状态以混凝土振捣密实,表面浆体出现为宜,振捣过程中缓插慢拔,使混凝土中气泡充分排出。Next, pour concrete to the bottom pouring window 21 of the construction area 20 . During the pouring process, the worker operates a hand-held plug-in vibrator to vibrate the concrete poured at the bottom pouring window 21 . When the worker operates the hand-held plug-in vibrator to vibrate, it is carried out in multiple times and in multiple areas, that is, the hand-held plug-in vibrator will vibrate the concrete poured near each feeding port 211 of the bottom pouring window 21, The single vibrating time is preferably between 15 seconds and 25 seconds. After the concrete is vibrated, the concrete is compacted and the surface slurry appears. Slowly insert and pull out during the vibrating process to fully discharge the air bubbles in the concrete.

当混凝土漫过最底层浇筑窗21所对应的第一区域内的第三气动振捣器241时,控制装置控制空气压缩机和阀门单元中相应的阀门启动,以使得第三气动振捣器241进行第一预设时长的振捣作业;同样地,当混凝土漫过最底层浇筑窗21所对应的第一区域内的第四气动振捣器251时,控制装置控制空气压缩机和阀门单元中相应的阀门启动,以使得第四气动振捣器251进行第一预设时长的振捣作业。其中,第一预设时长优选介于50秒至70秒之间。When the concrete flows over the third pneumatic vibrator 241 in the first area corresponding to the bottommost pouring window 21 , the control device controls the air compressor and the corresponding valve in the valve unit to activate, so that the third pneumatic vibrator 241 is activated. Carry out the vibrating operation for the first preset duration; similarly, when the concrete overflows the fourth pneumatic vibrator 251 in the first area corresponding to the bottom pouring window 21, the control device controls the air compressor and the valve unit. The corresponding valve is activated, so that the fourth pneumatic vibrator 251 performs the vibrating operation for the first preset duration. Wherein, the first preset duration is preferably between 50 seconds and 70 seconds.

当完成最底层浇筑窗21的浇筑后,先将手持插入式振捣器从入料口211中取出,再关闭最底层浇筑窗21的各个入料口211,随后控制装置控制空气压缩机和阀门单元中相应的阀门启动以使得最下方的一组第一振捣组22及第一区域内的第三气动振捣器241、第四气动振捣器251进行第二预设时长振捣。其中,第二预设时长优选介于30秒至50秒之间。When the pouring of the bottommost pouring window 21 is completed, first take out the hand-held plug-in vibrator from the feeding port 211, then close each feeding port 211 of the bottommost pouring window 21, and then the control device controls the air compressor and the valve The corresponding valve in the unit is activated to make the lowermost group of the first vibrating group 22 and the third pneumatic vibrator 241 and the fourth pneumatic vibrator 251 in the first area to vibrate for the second preset duration. Wherein, the second preset duration is preferably between 30 seconds and 50 seconds.

优选地,在最底层浇筑窗21浇筑完成后且最底层浇筑窗21关闭前,由工人操作手持插入式振捣器对施工区20的第一端部203处、第二端部204处的中埋止水带周边混凝土进行振捣,使中埋止水带呈顺直状态;该操作能够避免中埋止水带被挤压变形和/或倾倒,以使止水带保持顺直状态,从而保证中埋止水带的防水效果。Preferably, after the pouring of the bottommost pouring window 21 is completed and before the bottommost pouring window 21 is closed, the hand-held plug-in vibrator is operated by a worker to align the center of the first end 203 and the second end 204 of the construction area 20 . The concrete surrounding the buried waterstop is vibrated to make the middle buried waterstop straight; this operation can prevent the middle buried waterstop from being squeezed and deformed and/or toppled, so as to keep the waterstop straight, thereby Guarantee the waterproof effect of the buried water stop.

接着,向施工区20的第二层浇筑窗21浇筑混凝土,浇筑过程中,由工人操作手持插入式振捣器对第二层浇筑窗21处浇筑的混凝土进行振捣。工人操作手持插入式振捣器进行振捣时,分多次、多区域进行,即手持插入式振捣器会对最底层浇筑窗21的每个入料口211附近浇筑的混凝土进行振捣,单次振捣时间优选介于15秒至25秒之间,混凝土振捣后状态以混凝土振捣密实,表面浆体出现为宜,振捣过程中缓插慢拔,使混凝土中气泡充分排出。Next, pour concrete to the pouring window 21 of the second floor of the construction area 20. During the pouring process, the worker operates a hand-held plug-in vibrator to vibrate the concrete poured at the pouring window 21 of the second floor. When the worker operates the hand-held plug-in vibrator to vibrate, it is carried out in multiple times and in multiple areas, that is, the hand-held plug-in vibrator will vibrate the concrete poured near each feeding port 211 of the bottom pouring window 21, The single vibrating time is preferably between 15 seconds and 25 seconds. After the concrete is vibrated, the concrete is compacted and the surface slurry appears. Slowly insert and pull out during the vibrating process to fully discharge the air bubbles in the concrete.

当混凝土漫过第二层浇筑窗21所对应的第二区域内的第三气动振捣器241时,控制装置控制空气压缩机和阀门单元中相应的阀门启动,以使得第三气动振捣器241进行第三预设时长的振捣作业;同样地,当混凝土漫过第二层浇筑窗21所对应的第二区域内的第四气动振捣器251时,控制装置控制空气压缩机和阀门单元中相应的阀门启动,以使得第四气动振捣器251进行第三预设时长的振捣作业。其中,第三预设时长优选介于30秒至50秒之间。When the concrete flows over the third pneumatic vibrator 241 in the second area corresponding to the second layer pouring window 21, the control device controls the air compressor and the corresponding valve in the valve unit to activate, so that the third pneumatic vibrator is activated 241 performs the vibrating operation for the third preset duration; similarly, when the concrete overflows the fourth pneumatic vibrator 251 in the second area corresponding to the second layer pouring window 21, the control device controls the air compressor and the valve The corresponding valve in the unit is activated, so that the fourth pneumatic vibrator 251 performs the vibrating operation for the third preset duration. Wherein, the third preset duration is preferably between 30 seconds and 50 seconds.

当完成第二层浇筑窗21的浇筑后,先将手持插入式振捣器从入料口211中取出,再关闭第二层浇筑窗21的各个入料口211,随后控制装置控制空气压缩机和阀门单元中相应的阀门启动以使得第二组第一振捣组22、第二区域内的第三气动振捣器241及第四气动振捣器251进行第四预设时长振捣;以及使得最底层的一组第一振捣组22进行第五预设时长振捣。其中,第四预设时长优选介于30秒至50秒之间;第五预设时长优选介于40秒至60秒之间。When the pouring of the second-layer pouring window 21 is completed, the hand-held plug-in vibrator is first taken out from the feeding port 211, and then each feeding port 211 of the second-layer pouring window 21 is closed, and then the control device controls the air compressor. and the corresponding valve in the valve unit is activated to cause the second group of the first vibrating group 22, the third pneumatic vibrator 241 and the fourth pneumatic vibrator 251 in the second area to vibrate for a fourth preset duration; and The first vibrating group 22 at the bottom layer is made to vibrate for a fifth preset duration. Wherein, the fourth preset duration is preferably between 30 seconds and 50 seconds; the fifth preset duration is preferably between 40 seconds and 60 seconds.

接着,向施工区20的最顶层浇筑窗21浇筑混凝土,浇筑过程中,由工人操作手持插入式振捣器对最顶层浇筑窗21处浇筑的混凝土进行振捣。工人操作手持插入式振捣器进行振捣时,分多次、多区域进行,即手持插入式振捣器会对最顶层浇筑窗21的每个入料口211附近浇筑的混凝土进行振捣,单次振捣时间优选介于15秒至25秒之间,混凝土振捣后状态以混凝土振捣密实,表面浆体出现为宜,振捣过程中缓插慢拔,使混凝土中气泡充分排出。Next, pour concrete to the topmost pouring window 21 of the construction area 20 . During the pouring process, the worker operates a hand-held plug-in vibrator to vibrate the concrete poured at the topmost pouring window 21 . When the worker operates the hand-held plug-in vibrator to vibrate, it is carried out in multiple times and in multiple areas, that is, the hand-held plug-in vibrator will vibrate the concrete poured near each feeding port 211 of the topmost pouring window 21, The single vibrating time is preferably between 15 seconds and 25 seconds. After the concrete is vibrated, the concrete is compacted and the surface slurry appears. Slowly insert and pull out during the vibrating process to fully discharge the air bubbles in the concrete.

当混凝土漫过最顶层浇筑窗21所对应的第三区域内的第三气动振捣器241时,控制装置控制空气压缩机和阀门单元中相应的阀门启动,以使得第三气动振捣器241进行第六预设时长的振捣作业;同样地,当混凝土漫过最顶层浇筑窗21所对应的第二区域内的第四气动振捣器251时,控制装置控制空气压缩机和阀门单元中相应的阀门启动,以使得第四气动振捣器251进行第六预设时长的振捣作业。其中,第六预设时长优选介于30秒至50秒之间。When the concrete overflows the third pneumatic vibrator 241 in the third area corresponding to the topmost pouring window 21 , the control device controls the air compressor and the corresponding valve in the valve unit to activate, so that the third pneumatic vibrator 241 is activated. Carry out the vibrating operation for the sixth preset duration; similarly, when the concrete overflows the fourth pneumatic vibrator 251 in the second area corresponding to the topmost pouring window 21, the control device controls the air compressor and the valve unit. The corresponding valve is activated, so that the fourth pneumatic vibrator 251 performs the vibrating operation for the sixth preset duration. Wherein, the sixth preset duration is preferably between 30 seconds and 50 seconds.

当完成最顶层浇筑窗21的浇筑后,先将手持插入式振捣器从入料口211中取出,再关闭最顶层浇筑窗21的各个入料口211,随后控制装置控制空气压缩机和阀门单元中相应的阀门启动以使得最上方的一组第一振捣组22、第三区域内的第三气动振捣器241及第四气动振捣器251进行第七预设时长振捣;以及使得第二组第一振捣组22进行第八预设时长振捣。其中,第七预设时长优选介于30秒至50秒之间;第五预设时长优选介于40秒至60秒之间。When the pouring of the topmost pouring window 21 is completed, first take out the hand-held plug-in vibrator from the feeding port 211, then close each feeding port 211 of the topmost pouring window 21, and then the control device controls the air compressor and the valve The corresponding valve in the unit is activated to cause the uppermost group of the first vibrating group 22, the third pneumatic vibrator 241 and the fourth pneumatic vibrator 251 in the third area to vibrate for a seventh preset duration; and The second group of the first vibrating group 22 is made to vibrate for the eighth preset duration. Wherein, the seventh preset duration is preferably between 30 seconds and 50 seconds; the fifth preset duration is preferably between 40 seconds and 60 seconds.

接着,向灌注孔29浇筑混凝土,浇筑过程中,根据要求启动第三插入式振捣器28进行第一预设模式振捣,具体地,当混凝土漫过位于拱顶的第三插入式振捣器28时,控制装置控制空气压缩机和阀门单元中相应的阀门启动以使第三插入式振捣器28进行第一预设模式振捣,第一预设振捣模式为:控制第三插入式振捣器28间歇启动两次至四次,单次启动进行第十三预设时长振捣,其中,第十四预设时长优选介于20秒至35秒之间。Next, pour concrete into the pouring hole 29. During the pouring process, start the third plug-in vibrator 28 to perform the first preset mode vibration according to the requirements. Specifically, when the concrete overflows the third plug-in vibrator located on the vault When the device 28 is activated, the control device controls the air compressor and the corresponding valve in the valve unit to activate to make the third plug-in vibrator 28 vibrate in the first preset mode, and the first preset vibrating mode is: controlling the third plug-in vibrator The vibrator 28 is intermittently started twice to four times, and the thirteenth preset time duration is vibrated for a single start, wherein the fourteenth preset time length is preferably between 20 seconds and 35 seconds.

当混凝土漫过第一组第二振捣组23第一预设距离时,启动第一组第二振捣组23进行第九预设时长振捣。其中,第一预设距离优选介于0.5米至0.6米之间,第九预设时长优选介于25秒至40秒之间。When the concrete spreads over the first preset distance of the first group of the second vibrating groups 23, the first group of the second vibrating groups 23 is activated to vibrate for a ninth preset duration. Wherein, the first preset distance is preferably between 0.5 meters and 0.6 meters, and the ninth preset duration is preferably between 25 seconds and 40 seconds.

当混凝土漫过第二组第二振捣组23第二预设距离时,启动第二组第二振捣组23进行第十预设时长振捣、启动第一组第二振捣组23进行第十一预设时长振捣。其中,第二预设距离优选介于0.5米至0.6米之间,第十预设时长优选介于25秒至40秒之间,第十一预设时长优选介于30秒至50秒之间。When the concrete overflows the second preset distance of the second vibrating group 23, the second vibrating group 23 of the second group is activated to vibrate for the tenth preset duration, and the first vibrating group 23 of the first group is activated to vibrate for the tenth preset duration The eleventh preset duration vibrates. Wherein, the second preset distance is preferably between 0.5 meters and 0.6 meters, the tenth preset duration is preferably between 25 seconds and 40 seconds, and the eleventh preset duration is preferably between 30 seconds and 50 seconds. .

当第一插入式振捣器261和第二插入式振捣器271被混凝土漫过时,启动并进行第二预设模式振捣。第二预设振捣模式为:控制第一插入式振捣器261间歇启动两次至四次,单次启动进行第十五预设时长振捣;控制第二插入式振捣器271间歇启动两次至四次,单次启动进行第十五预设时长振捣。其中,第十五预设时长优选介于20秒至35秒之间。When the first insert vibrator 261 and the second insert vibrator 271 are flooded with concrete, a second preset mode of vibrating is activated and performed. The second preset vibrating mode is: controlling the first plug-in vibrator 261 to start intermittently two to four times, and performing the vibration for the fifteenth preset duration for a single start; controlling the second plug-in vibrator 271 to start intermittently Two to four times, a single start for the fifteenth preset duration of vibration. Wherein, the fifteenth preset duration is preferably between 20 seconds and 35 seconds.

此外,在高度方向上,当混凝土漫过最顶层浇筑窗211米至1.5米时,启动最上方的一组第一振捣组22进行第十二预设时长振捣,第十二预设时长优选介于30秒至50秒之间。当完成混凝土浇筑结束时,启动第二组第二振捣组23进行第十三时长振捣,第十三预设时长优选介于30秒至50秒之间。In addition, in the height direction, when the concrete overflows the topmost pouring window 211m to 1.5m, the topmost first vibrating group 22 is activated to vibrate for the twelfth preset duration, and the twelfth preset duration Preferably between 30 seconds and 50 seconds. When the concrete pouring is completed, the second group of the second vibrating group 23 is activated to vibrate for a thirteenth duration, and the thirteenth preset duration is preferably between 30 seconds and 50 seconds.

其中,需要说明的是,上述施工过程是单独针对一个施工区20的混凝土浇筑施工顺序进行举例说明,以便于本领域技术人员了解施工区20的混凝土浇筑过程,而在实际混凝土浇筑施工过程中,两个施工区20需要进行对称浇筑,具体两个施工区20切换混凝土浇筑的时机优选包括以下两种:Among them, it should be noted that the above-mentioned construction process is an example for the concrete pouring construction sequence of a construction area 20 alone, so that those skilled in the art can understand the concrete pouring process of the construction area 20, and in the actual concrete pouring construction process, The two construction areas 20 need to be placed symmetrically. Specifically, the timing for switching concrete pouring between the two construction areas 20 preferably includes the following two:

第一种,当完成第一个施工区20的最底层浇筑窗21的浇筑及振捣后,进行第二个施工区20的最底层浇筑窗21的浇筑及振捣;当完成第二个施工区20的最底层浇筑窗21的浇筑及振捣后,进行第一个施工区20的第二层浇筑窗21的浇筑及振捣;当完成第一个施工区20的第二层浇筑窗21的浇筑及振捣后,进行第二个施工区20的第二层浇筑窗21的浇筑及振捣;当完成第二个施工区20的第二层浇筑窗21的浇筑及振捣后,进行第一个施工区20的最顶层浇筑窗21的浇筑及振捣;当完成第一个施工区20的最顶层浇筑窗21的浇筑及振捣后,进行第二个施工区20的最顶层浇筑窗21的浇筑及振捣;当完成第二个施工区20的最顶层浇筑窗21的浇筑及振捣后,向灌注孔29浇筑混凝土。在向灌注孔29浇筑混凝土过程中,优选先向第一个施工区20浇筑混凝土漫过第一组第二振捣组23第一预设距离后,切换至第二个施工区20进行混凝土浇筑;当第二个施工区20的混凝土漫过第一组第二振捣组23第一预设距离后,切换至第一个施工区20进行混凝土浇筑;当第一个施工区20的混凝土漫过第二组第二振捣组23第二预设距离后,切换至第二个施工区20进行混凝土浇筑;当第二个施工区20的混凝土漫过第二组第二振捣组23第二预设距离后,切换至第一个施工区20进行混凝土浇筑。如此循环浇筑,当混凝土接近钢模板2拱顶区域时,可同时向两个施工区20进行混凝土浇筑。First, when the pouring and vibrating of the bottommost pouring windows 21 in the first construction area 20 are completed, the pouring and vibrating of the bottommost pouring windows 21 in the second construction area 20 are performed; when the second construction area 20 is completed After pouring and vibrating the pouring windows 21 of the bottommost floor of the area 20, the pouring and vibrating of the second floor pouring windows 21 of the first construction area 20 are performed; when the second floor pouring windows 21 of the first construction area 20 are completed After the pouring and vibrating of the second floor of the second construction area 20, the pouring and vibrating of the second floor pouring window 21 of the second construction area 20 are performed; The pouring and vibrating of the topmost pouring windows 21 in the first construction area 20; when the pouring and vibrating of the topmost pouring windows 21 in the first construction area 20 are completed, the topmost pouring in the second construction area 20 is carried out. The pouring and vibrating of the window 21 ; when the pouring and vibrating of the topmost pouring window 21 of the second construction area 20 is completed, the concrete is poured into the pouring hole 29 . In the process of pouring concrete into the pouring hole 29 , it is preferable to pour the concrete into the first construction area 20 first, and then switch to the second construction area 20 for concrete pouring after the first preset distance of the first group of the second vibrating group 23 ; When the concrete of the second construction area 20 overflows the first preset distance of the second vibrating group 23 of the first group, switch to the first construction area 20 for concrete pouring; when the concrete of the first construction area 20 overflows After passing the second preset distance of the second vibrating group 23, switch to the second construction area 20 for concrete pouring; when the concrete of the second construction area 20 overflows the second vibrating group 23 After two preset distances, switch to the first construction area 20 for concrete pouring. In this way, when the concrete is close to the vault area of the steel formwork 2, the concrete can be poured to the two construction areas 20 at the same time.

第二种,同一车次的混凝土浇筑至同一个施工区20,当完成当前车次混凝土的浇筑后,下一车次的混凝土切换至另一个施工区20进行浇筑,如此循环直至完成对两个施工区20的三层浇筑窗21的混凝土浇筑。同理地,在向灌注孔29浇筑混凝土过程中,优选先向第一个施工区20浇筑混凝土漫过第一组第二振捣组23第一预设距离后,切换至第二个施工区20进行混凝土浇筑;当第二个施工区20的混凝土漫过第一组第二振捣组23第一预设距离后,切换至第一个施工区20进行混凝土浇筑;当第一个施工区20的混凝土漫过第二组第二振捣组23第二预设距离后,切换至第二个施工区20进行混凝土浇筑;当第二个施工区20的混凝土漫过第二组第二振捣组23第二预设距离后,切换至第一个施工区20进行混凝土浇筑。如此循环浇筑,当混凝土接近钢模板2拱顶区域时,可同时向两个施工区20进行混凝土浇筑。The second type is that the concrete of the same train is poured into the same construction area 20. After the concrete of the current train is poured, the concrete of the next train is switched to another construction area 20 for pouring, and this cycle is repeated until the completion of the two construction areas 20. The concrete pouring of the three-story pouring window 21. Similarly, in the process of pouring concrete into the pouring hole 29, it is preferable to pour the concrete into the first construction area 20 first, after the first preset distance of the first group of the second vibrating group 23, and then switch to the second construction area. 20 for concrete pouring; when the concrete of the second construction area 20 overflows the first preset distance of the first group of the second vibrating group 23, switch to the first construction area 20 for concrete pouring; when the first construction area After the concrete of 20 overflows the second preset distance of the second group of the second vibration group 23, switch to the second construction area 20 for concrete pouring; when the concrete of the second construction area 20 overflows the second group of the second vibration After the second preset distance of the tamping group 23, switch to the first construction area 20 for concrete pouring. In this way, when the concrete is close to the vault area of the steel formwork 2, the concrete can be poured to the two construction areas 20 at the same time.

此外,在对每层浇筑窗21进行混凝土浇筑时,在第一方向X上按顺序依次向多个入料口211浇筑预设高度的混凝土;在对拱顶的多个灌注孔29进行混凝土浇筑时,在第一方向X上按顺序依次向多个灌注孔29浇筑预设高度的混凝土。当振捣系统200处于斜坡时,在对每层浇筑窗21进行混凝土浇筑时,从高度低的入料口211依次向高度高的入料口211浇筑混凝土;在对拱顶的多个灌注孔29进行混凝土浇筑时,从高度低的灌注孔29依次向高度高的灌注孔29浇筑混凝土。In addition, when pouring concrete on each floor of the pouring windows 21, in the first direction X, pour concrete with a preset height to the plurality of feeding ports 211 in sequence; , pour concrete of a preset height into the plurality of pouring holes 29 in sequence in the first direction X. When the vibrating system 200 is on a slope, when pouring concrete for each layer of the pouring windows 21, the concrete is poured from the low-height feed port 211 to the high-height feed port 211; 29 When the concrete is poured, concrete is poured from the lower pouring hole 29 to the higher pouring hole 29 in order.

结合图10,利用地质雷达和弹性波法对本振捣系统200的插入式高频振捣器和附着气动振捣器结构布局及使用效果进行强度和密实度比较,其中,雷达波形无明显差异,弹性波法结果表明插入式振捣比气动式振捣的衬砌混凝土更密实,尤其是靠近防水板区域效果更明显。With reference to Fig. 10, the structural layout and use effect of the plug-in high-frequency vibrator and the attached pneumatic vibrator of the local vibrating system 200 are compared using the geological radar and elastic wave method. The results of the method show that the lining concrete of the plug-in vibrator is denser than that of the pneumatic vibrator, especially in the area close to the flashing plate.

在本振捣系统200施工过程中,随机选取连续3板检测,每板测2个点,分别测出表层及深层强度分析,其中,衬砌台车改装前后衬砌拱顶强度声波回弹法检测数据请见图11。可见,改装前后施工混凝土强度均能满足设计要求;但对比数据,改装后施工衬砌强度表层与深层强度离散较小基本一致,而改装前施工的衬砌表层与深层强度离散较大,这与混凝土振捣不到位,造成骨料分布不均匀有一定关系,因此,改装后衬砌拱顶靠近防水板深层区域强度稍高。During the construction process of the local vibrating system 200, three consecutive plates were randomly selected for inspection, and each plate was measured at two points, respectively, to measure the surface and deep strength analysis. See Figure 11. It can be seen that the strength of the construction concrete before and after the modification can meet the design requirements; but the comparison data shows that the strength of the surface layer and the deep layer of the lining construction after the modification is relatively small and basically consistent, while the strength of the surface layer and the deep layer of the lining constructed before the modification is relatively large, which is consistent with the vibration of the concrete. It is related to the uneven distribution of aggregate due to improper tamping. Therefore, the strength of the modified lining vault near the deep layer of the waterproof board is slightly higher.

综上可见,本发明提供的振捣系统及其施工方法能更好的提升钢模板的边墙及拱部区域、拱顶区域、两端部区域的混凝土的振捣效果,以提高混凝土的密实度,防止混凝土出现空洞,并降低纵向施工缝和环向施工的混凝土病害,从而有效提高二衬混凝土的整体浇筑质量,防止拱顶混凝土脱空,保证混凝土强度内外基本一致,且强度离散值小。To sum up, the vibrating system and its construction method provided by the present invention can better improve the vibrating effect of the concrete in the side wall and the arch area, the vault area and the two end areas of the steel formwork, so as to improve the compaction of the concrete. It can effectively improve the overall pouring quality of the secondary lining concrete, prevent the concrete of the vault from emptying, and ensure that the strength of the concrete is basically the same inside and outside, and the discrete value of the strength is small. .

隧道衬砌台车实施例Example of tunnel lining trolley

隧道衬砌台车包括上述振捣系统实施例中的振捣系统,并实用上述振捣系统的施工方法对隧道二衬进行施工,可见,采用振捣系统及其施工方法的隧道衬砌台车能够提高二衬混凝土的整体浇筑质量,保证混凝土的密实度及混凝土强度的均匀性,并防止拱顶混凝土脱空;此外,还能够保证混凝土强度内外基本一致,且强度离散值小。The tunnel lining trolley includes the vibrating system in the above-mentioned embodiment of the vibrating system, and the construction method of the above-mentioned vibrating system is used to construct the secondary lining of the tunnel. It can be seen that the tunnel lining trolley using the vibrating system and the construction method can improve the performance of the tunnel lining trolley. The overall pouring quality of the secondary lining concrete ensures the compactness of the concrete and the uniformity of the concrete strength, and prevents the vault concrete from emptying; in addition, it can also ensure that the concrete strength is basically the same inside and outside, and the strength dispersion value is small.

最后需要强调的是,以上所述仅为本发明的优选实施例,并不用于限制本发明,对于本领域的技术人员来说,本发明可以有各种变化和更改,凡在本发明的精神和原则之内,所做的任何修改、等同替换、改进等,均应包含在本发明的保护范围之内。Finally, it should be emphasized that the above descriptions are only preferred embodiments of the present invention, and are not intended to limit the present invention. For those skilled in the art, the present invention may have various changes and modifications. Within the scope of the present invention, any modifications, equivalent replacements, improvements, etc. made should be included within the protection scope of the present invention.

Claims (10)

1. The system of vibrating, including the steel form, the steel form has two construction areas that personally submit the symmetry setting about the symmetry, the direction of height and the axle center of steel form are all in on the symmetry, its characterized in that:
each construction area is provided with a plurality of layers of pouring windows, a plurality of groups of first vibrating groups, at least one group of second vibrating groups, third vibrating groups, fourth vibrating groups, fifth vibrating groups and sixth vibrating groups;
the multiple layers of pouring windows are distributed along the circumferential direction of the steel formwork, each pouring window comprises a plurality of feeding ports distributed along a first direction, and the first direction is parallel to the axis;
the construction area is provided with a side arch part, a first end part and a second end part, the side arch part is positioned between the first end part and the second end part along the first direction, the first vibration group and the second vibration group are arranged on the side arch part, a plurality of groups of first vibration groups are arranged alternately with the plurality of layers of pouring windows along the annular direction, each first vibration group comprises a plurality of first pneumatic vibrators distributed along the first direction, and each second vibration group comprises a plurality of second pneumatic vibrators distributed along the first direction;
the third vibrating group and the fifth vibrating group are both arranged on the first end part, the third vibrating group comprises a plurality of third pneumatic vibrators distributed along the circumferential direction, and the fifth vibrating group comprises at least one first plug-in vibrator;
the fourth vibrating group and the sixth vibrating group are both arranged on the second end part, the fourth vibrating group comprises a plurality of fourth pneumatic vibrators distributed along the circumferential direction, and the sixth vibrating group comprises at least one second plug-in vibrator;
in the height direction, the height of the first vibrating group in the bottommost group is smaller than that of the pouring window in the bottommost layer, the second vibrating group is located above the pouring window in the topmost layer, the fifth vibrating group is located above the third vibrating group, and the sixth vibrating group is located above the fourth vibrating group;
in the ring direction, two adjacent first pneumatic vibrators are arranged in a staggered manner, and one adjacent first pneumatic vibrator and one adjacent second pneumatic vibrator are arranged in a staggered manner;
the vault of steel form is provided with a plurality of edges the third bayonet vibrator that first direction distributes and a plurality of edge the pouring hole that first direction distributes, it is a plurality of the third bayonet vibrator with a plurality of the pouring hole all is located on the plane of symmetry.
2. The tamper system of claim 1, wherein:
in the height direction, the minimum distance between the third pneumatic vibrator and the short side wall is between 0.8 and 1 meter, the minimum distance between the fourth pneumatic vibrator and the short side wall is between 0.8 and 1 meter, and the minimum distance between the first pneumatic vibrator and the short side wall is between 0.8 and 1 meter.
3. The tamper system of claim 2, wherein:
the vibration radius of the first pneumatic vibrator is between 1.8 and 2.5 meters;
the vibration radius of the second pneumatic vibrator is between 1.8 and 2.5 meters;
the vibration radius of the third pneumatic vibrator is between 1.8 and 2.5 meters;
the vibration radius of the fourth pneumatic vibrator is between 1.8 and 2.5 meters;
the vibration radius of the first plug-in vibrator is between 1.2 meters and 1.8 meters;
the vibration radius of the second plug-in vibrator is between 1.2 meters and 1.8 meters;
the vibrating radius of the third plug-in vibrator is between 1.2 meters and 1.8 meters;
the vibrating radius of the first pneumatic vibrator is meshed with the vibrating radius of other adjacent vibrators, the vibrating radius of the second pneumatic vibrator is meshed with the vibrating radius of other adjacent vibrators, the vibrating radius of the third pneumatic vibrator is meshed with the vibrating radius of other adjacent vibrators, the vibrating radius of the fourth pneumatic vibrator is meshed with the vibrating radius of other adjacent vibrators, the vibrating radius of the first plug-in vibrator is meshed with the vibrating radius of other adjacent vibrators, the vibrating radius of the second plug-in vibrator is meshed with the vibrating radius of other adjacent vibrators, and the vibrating radius of the third plug-in vibrator is meshed with the vibrating radius of other adjacent vibrators;
in the first direction, the distance between two adjacent feeding ports is between 1.8 and 2.5 meters, and the distance between two adjacent pouring holes is between 1.2 and 1.8 meters.
4. The vibrating system of claim 1, wherein:
each construction area all is provided with at least one handheld bayonet vibrating spear.
5. The tamper system of claim 4, wherein:
in the circumferential direction, the first vibrating group positioned between the two adjacent layers of the pouring windows is arranged close to the lower layer of the two adjacent layers of the pouring windows.
6. The vibrating system according to any one of claims 1 to 5, wherein:
the length of the steel form along the first direction is between 10 and 14 meters.
7. The tamper system of claim 6, wherein:
in each construction area, the number of the pouring windows is three, the number of the first vibrating groups is three, and the number of the second vibrating groups is two;
and two adjacent second pneumatic vibrators are arranged in a staggered manner in the upward direction of the ring.
8. The tamper system of claim 7, wherein:
the number of the feeding ports of each layer of the pouring window is four, three feeding ports in each layer of the pouring window are located at the side arch part, the rest feeding ports are located at the first end part or the second end part, and two adjacent feeding ports are arranged in a staggered mode in the annular direction;
the number of the first pneumatic vibrators of each first vibrating group is three;
the number of the second pneumatic vibrators of each second vibrating group is three.
9. The tamper system of claim 8, wherein:
the number of the third pneumatic vibrators of each third vibrating group is four;
the number of the fourth pneumatic vibrators of each fourth vibrating group is four;
the fifth vibrating group comprises two first plug-in vibrators distributed along the annular direction;
the sixth vibrating group comprises two second plug-in vibrators distributed along the annular direction;
the number of the third plug-in vibrators is four;
the number of the perfusion holes is three;
along the first direction, the length of steel form is 12 meters.
10. A tunnel lining trolley including a tamper system as claimed in any one of claims 1 to 9.
CN202210506301.6A 2022-05-09 2022-05-09 Tunnel lining trolley and vibrating system thereof Pending CN115012989A (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN202210506301.6A CN115012989A (en) 2022-05-09 2022-05-09 Tunnel lining trolley and vibrating system thereof

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN202210506301.6A CN115012989A (en) 2022-05-09 2022-05-09 Tunnel lining trolley and vibrating system thereof

Publications (1)

Publication Number Publication Date
CN115012989A true CN115012989A (en) 2022-09-06

Family

ID=83069923

Family Applications (1)

Application Number Title Priority Date Filing Date
CN202210506301.6A Pending CN115012989A (en) 2022-05-09 2022-05-09 Tunnel lining trolley and vibrating system thereof

Country Status (1)

Country Link
CN (1) CN115012989A (en)

Citations (11)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
RU2008151523A (en) * 2008-12-25 2009-05-20 Закрытое акционерное общество Производственно-строительная фирма "Грантстрой" (RU) METHOD AND INSTALLATION OF PREPARATION AND INERTIAL LAYING WITH SEALING OF CONCRETE MIX
CN107448217A (en) * 2017-09-25 2017-12-08 中铁十七局集团第工程有限公司 A kind of practical tunnel lining trolley vibrating system
WO2018014607A1 (en) * 2016-07-18 2018-01-25 河海大学 Combined cooling heating power diaphragm wall apparatus and construction method therefor
CN206987834U (en) * 2017-11-08 2018-02-09 青岛市地铁一号线有限公司 A kind of lining trolley attached vibrator structure
CN109611123A (en) * 2019-01-11 2019-04-12 中铁十局集团第四工程有限公司 Tunnel double-lining concreting control system and control method
CN109630159A (en) * 2019-01-11 2019-04-16 中铁十局集团第四工程有限公司 Tunnel double-lining concrete casting system
CN109707409A (en) * 2019-01-11 2019-05-03 中铁十一局集团第四工程有限公司 A kind of tunnel double-lining concrete vibrating system
CN110374630A (en) * 2019-06-12 2019-10-25 中电建十一局工程有限公司 A kind of construction method of tunnel vault concrete vibrating
WO2020199741A1 (en) * 2019-04-04 2020-10-08 山东大学 Tbm rock breaking mechanism model test system and method taking rock fragment characteristics into consideration
CN215718805U (en) * 2021-07-13 2022-02-01 成都科利特机械制造有限公司 Tunnel lining trolley vibrating mechanism
CN217950389U (en) * 2022-05-09 2022-12-02 中铁十九局集团第六工程有限公司 Tunnel lining trolley and vibrating system thereof

Patent Citations (11)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
RU2008151523A (en) * 2008-12-25 2009-05-20 Закрытое акционерное общество Производственно-строительная фирма "Грантстрой" (RU) METHOD AND INSTALLATION OF PREPARATION AND INERTIAL LAYING WITH SEALING OF CONCRETE MIX
WO2018014607A1 (en) * 2016-07-18 2018-01-25 河海大学 Combined cooling heating power diaphragm wall apparatus and construction method therefor
CN107448217A (en) * 2017-09-25 2017-12-08 中铁十七局集团第工程有限公司 A kind of practical tunnel lining trolley vibrating system
CN206987834U (en) * 2017-11-08 2018-02-09 青岛市地铁一号线有限公司 A kind of lining trolley attached vibrator structure
CN109611123A (en) * 2019-01-11 2019-04-12 中铁十局集团第四工程有限公司 Tunnel double-lining concreting control system and control method
CN109630159A (en) * 2019-01-11 2019-04-16 中铁十局集团第四工程有限公司 Tunnel double-lining concrete casting system
CN109707409A (en) * 2019-01-11 2019-05-03 中铁十一局集团第四工程有限公司 A kind of tunnel double-lining concrete vibrating system
WO2020199741A1 (en) * 2019-04-04 2020-10-08 山东大学 Tbm rock breaking mechanism model test system and method taking rock fragment characteristics into consideration
CN110374630A (en) * 2019-06-12 2019-10-25 中电建十一局工程有限公司 A kind of construction method of tunnel vault concrete vibrating
CN215718805U (en) * 2021-07-13 2022-02-01 成都科利特机械制造有限公司 Tunnel lining trolley vibrating mechanism
CN217950389U (en) * 2022-05-09 2022-12-02 中铁十九局集团第六工程有限公司 Tunnel lining trolley and vibrating system thereof

Similar Documents

Publication Publication Date Title
CN105401958B (en) Tunnel cable trench cover uses movable prefabricated chassis precast construction method
CN105839850A (en) Basement reverse-construction scape post-casting pre-stressed construction method
CN109555027A (en) A kind of beam sections concrete casting system and its construction method
CN103388402B (en) Waffle beam hollow floor slab construction method
CN110195413A (en) A kind of box culvert construct method based on mould trolley in movable type
CN107363980A (en) A kind of concrete locking plate mechanized method for making and system
CN102535746A (en) Concrete-filled steel tube column and casting method thereof
CN109610842A (en) A kind of concrete jacking pump send construction method
CN108130863A (en) Precast T-Beam hydraulic self-traveling integral mold plate and its construction method
CN217950389U (en) Tunnel lining trolley and vibrating system thereof
CN202401668U (en) Concrete column structure of steel pipe
CN108705668A (en) A kind of concrete pipe sheet pours the system of smashing and concrete pipe sheet pours the method for smashing
CN115012989A (en) Tunnel lining trolley and vibrating system thereof
CN114083641A (en) Combined structure of vibrators in prefabricated T beam concrete pouring process and its use method
CN114876520A (en) Tunnel secondary lining construction process
CN115012988A (en) Construction method of tunnel lining trolley vibrating system and tunnel lining trolley
CN206070290U (en) Subgrade drainage structures former
CN111996923B (en) Closed type in-column concrete pouring method
CN111485910B (en) Construction method of secondary lining of steel-concrete composite pipe joint pipe jacking channel
CN109056527A (en) Anchor ceiling board construction method before anchorage
CN205224044U (en) Steel lining bottom plate concrete placement device
CN205999731U (en) A kind of concreting template
CN209538047U (en) A kind of beam sections concrete casting system
CN104563392B (en) The regenerative mixed beam of a kind of built-in box shaped steel and construction technology thereof
CN211774796U (en) Cross wall connection department constructional column exempts from formwork structure

Legal Events

Date Code Title Description
PB01 Publication
PB01 Publication
SE01 Entry into force of request for substantive examination
SE01 Entry into force of request for substantive examination