CN115306956A - Pipeline installation process of nuclear power station - Google Patents
Pipeline installation process of nuclear power station Download PDFInfo
- Publication number
- CN115306956A CN115306956A CN202210899571.8A CN202210899571A CN115306956A CN 115306956 A CN115306956 A CN 115306956A CN 202210899571 A CN202210899571 A CN 202210899571A CN 115306956 A CN115306956 A CN 115306956A
- Authority
- CN
- China
- Prior art keywords
- pipeline
- pipe
- nuclear power
- installation
- welding
- Prior art date
- Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
- Pending
Links
Images
Classifications
-
- F—MECHANICAL ENGINEERING; LIGHTING; HEATING; WEAPONS; BLASTING
- F16—ENGINEERING ELEMENTS AND UNITS; GENERAL MEASURES FOR PRODUCING AND MAINTAINING EFFECTIVE FUNCTIONING OF MACHINES OR INSTALLATIONS; THERMAL INSULATION IN GENERAL
- F16L—PIPES; JOINTS OR FITTINGS FOR PIPES; SUPPORTS FOR PIPES, CABLES OR PROTECTIVE TUBING; MEANS FOR THERMAL INSULATION IN GENERAL
- F16L5/00—Devices for use where pipes, cables or protective tubing pass through walls or partitions
-
- F—MECHANICAL ENGINEERING; LIGHTING; HEATING; WEAPONS; BLASTING
- F16—ENGINEERING ELEMENTS AND UNITS; GENERAL MEASURES FOR PRODUCING AND MAINTAINING EFFECTIVE FUNCTIONING OF MACHINES OR INSTALLATIONS; THERMAL INSULATION IN GENERAL
- F16L—PIPES; JOINTS OR FITTINGS FOR PIPES; SUPPORTS FOR PIPES, CABLES OR PROTECTIVE TUBING; MEANS FOR THERMAL INSULATION IN GENERAL
- F16L3/00—Supports for pipes, cables or protective tubing, e.g. hangers, holders, clamps, cleats, clips, brackets
- F16L3/08—Supports for pipes, cables or protective tubing, e.g. hangers, holders, clamps, cleats, clips, brackets substantially surrounding the pipe, cable or protective tubing
- F16L3/10—Supports for pipes, cables or protective tubing, e.g. hangers, holders, clamps, cleats, clips, brackets substantially surrounding the pipe, cable or protective tubing divided, i.e. with two members engaging the pipe, cable or protective tubing
- F16L3/1008—Supports for pipes, cables or protective tubing, e.g. hangers, holders, clamps, cleats, clips, brackets substantially surrounding the pipe, cable or protective tubing divided, i.e. with two members engaging the pipe, cable or protective tubing with two members engaging the pipe, cable or tubing, both being made of thin band material completely surrounding the pipe
- F16L3/1016—Supports for pipes, cables or protective tubing, e.g. hangers, holders, clamps, cleats, clips, brackets substantially surrounding the pipe, cable or protective tubing divided, i.e. with two members engaging the pipe, cable or protective tubing with two members engaging the pipe, cable or tubing, both being made of thin band material completely surrounding the pipe the members being joined by means of two screws
Landscapes
- Engineering & Computer Science (AREA)
- General Engineering & Computer Science (AREA)
- Mechanical Engineering (AREA)
- Supports For Pipes And Cables (AREA)
Abstract
Description
技术领域technical field
本发明涉及核电领域,更具体地说,涉及一种核电站的管道安装工艺。The invention relates to the field of nuclear power, in particular to a pipeline installation process for a nuclear power plant.
背景技术Background technique
由于核电站系统的复杂性,在核电工程建设过程中有大量的管道和支架施工,大约占整个核电站建设工程量的一半以上。而且核岛厂房的房间布置紧凑密集,施工空间狭小。Due to the complexity of the nuclear power plant system, there are a large number of pipeline and support constructions during the construction of nuclear power plants, accounting for more than half of the entire nuclear power plant construction volume. Moreover, the rooms of the nuclear island plant are compactly arranged, and the construction space is small.
按照常规的施工逻辑,一般是房间移交之后,先将一阶段支架焊接到房间的预埋板上,然后引入管道进行焊接施工,最后将管道固定到支架上。According to the conventional construction logic, generally after the room is handed over, the first-stage support is welded to the pre-embedded board of the room, then the pipeline is introduced for welding construction, and finally the pipeline is fixed to the support.
这种施工逻辑需要在房间内进行大量坡口打磨和焊接工作,一方面受到房间移交的制约,一方面工效也比较低,施工环境不友好。This kind of construction logic requires a lot of groove grinding and welding work in the room. On the one hand, it is restricted by the handover of the room, on the other hand, the work efficiency is relatively low, and the construction environment is not friendly.
核电站管道支架施工的一般逻辑是:房间移交→支架材料引入→一阶段支架安装和焊接→管道部件引入→管道组对、焊接和打磨→二阶段支架安装→管道最终调整、固定。The general logic for the construction of pipe supports in nuclear power plants is: room handover → introduction of support materials → first-stage support installation and welding → introduction of pipe components → pipe assembly, welding and grinding → second-stage support installation → final adjustment and fixing of pipes.
以房间管道和支架的安装活动为例,包含7根管段和3个支架的安装工作,管道共有6条焊缝,每个支架有3条焊缝,具体施工步骤如下:Taking the installation of pipes and brackets in a room as an example, it includes the installation of 7 pipe sections and 3 brackets. There are 6 welds in the pipeline and 3 welds in each bracket. The specific construction steps are as follows:
1.房间移交后,分别将3个支架方钢焊接到墙壁预埋板上,即完成支架焊缝1;1. After the room is handed over, weld the three bracket square steels to the pre-embedded panels on the wall to complete the bracket weld 1;
2.进行支架1、支架2的护板和管卡座的焊接,完成支架焊缝3;2. Carry out the welding of bracket 1, bracket 2 guard plate and pipe holder, and complete bracket welding seam 3;
3.将直管段和弯头管段引入房间,依次完成管道焊缝1和焊缝2;3. Lead the straight pipe section and the elbow pipe section into the room, and complete the pipe weld 1 and weld 2 in sequence;
4.根据管道与墙壁的距离,计算和切割支架1和支架2的方钢;4. According to the distance between the pipe and the wall, calculate and cut the square steel of support 1 and support 2;
5.将支架1、支架2的护板焊接在支架方钢上,完成支架焊缝2;5. Weld the guard plates of bracket 1 and bracket 2 to the bracket square steel to complete the bracket weld 2;
6.安装支架1、支架2的管卡卡箍,固定管段1、管段2;6. Install the pipe clamps of bracket 1 and bracket 2, and fix pipe section 1 and pipe section 2;
7.继续依次完成管道焊缝3和焊缝4;7. Continue to complete the pipe weld 3 and weld 4 in sequence;
8.根据管道与墙壁的距离,计算和切割支架3的方钢;8. According to the distance between the pipe and the wall, calculate and cut the square steel of support 3;
9.焊接支架3的护板,并安装支架3的管卡卡箍固定管道;9. Weld the guard plate of the bracket 3, and install the pipe clamp of the bracket 3 to fix the pipe;
10.继续完成管道焊缝5和管道焊缝6;10. Continue to complete the pipe weld 5 and pipe weld 6;
11.将止3个支架的挡块焊接在管道上,完成管道最终固定。11. Weld the stoppers of the three brackets on the pipe to complete the final fixing of the pipe.
现行的这种施工逻辑下,整个施工过程基本上是串行的。管道焊接和支架焊接交叉进行,还涉及到多次测量、调整和切割打磨,全部都在现场房间内完成。整个施工工期较长,受房间移交的制约影响。Under the current construction logic, the entire construction process is basically serial. Pipe welding and bracket welding are carried out crosswise, and it also involves multiple measurements, adjustments, cutting and grinding, all done in the on-site room. The entire construction period is relatively long, subject to the constraints of room handover.
而且房间狭小空间内切割打磨和焊接作业多,施工环境恶劣。大部分管道支架还处于高处或者空间狭小的位置,不利于现场安装和焊接工作的实施。Moreover, there are many cutting, grinding and welding operations in the narrow space of the room, and the construction environment is harsh. Most of the pipe supports are still in high places or in narrow spaces, which is not conducive to the implementation of on-site installation and welding work.
发明内容Contents of the invention
本发明要解决的技术问题在于,针对现有技术的上述缺陷,提供一种核电站的管道安装工艺。The technical problem to be solved by the present invention is to provide a pipeline installation process for a nuclear power plant in view of the above-mentioned defects of the prior art.
本发明解决其技术问题所采用的技术方案是:构造一种核电站的管道安装工艺,包括以下步骤:The technical solution adopted by the present invention to solve the technical problem is: to construct a pipeline installation process for a nuclear power plant, comprising the following steps:
S1、根据安装空间的管道进出位置预设管道的走管方式;S1. Preset the pipe routing method according to the pipe entry and exit positions of the installation space;
S2、获取安装空间内对所述管道定位的定位结构的位置数据;S2. Obtain the position data of the positioning structure for positioning the pipeline in the installation space;
S3、根据走管方式,制作管道的各管段;S3. According to the pipe routing method, make each pipe section of the pipeline;
S4、对各管段进行预定位,将各所述管段焊接,得到预制管道;S4. Pre-positioning each pipe section, welding each pipe section to obtain a prefabricated pipe;
S5、将所述预制管道安装到安装空间的所述定位结构。S5. Install the prefabricated pipeline to the positioning structure of the installation space.
在一些实施例中,所述步骤S3中,根据所述走管方式,设定各管段的长度,切割制作各所述管段。In some embodiments, in the step S3, the length of each pipe section is set according to the pipe routing method, and each pipe section is cut and manufactured.
在一些实施例中,所述步骤S4中,在对各管段进行预定位时,对各管段的位置进行监测。In some embodiments, in the step S4, when pre-positioning each pipe section, the position of each pipe section is monitored.
在一些实施例中,利用三维测量工具对所述管段的定位监测。In some embodiments, the position monitoring of the pipe section is performed using a three-dimensional measurement tool.
在一些实施例中,在所述管道的位置偏位时,对各管段的位置进行调节。In some embodiments, when the position of the pipeline deviates, the position of each pipe segment is adjusted.
在一些实施例中,所述定位结构包括在安装空间设置、以供所述管道的至少一端穿过的孔洞,所述步骤S5中包括,将所述管道的端部穿过所述孔洞。In some embodiments, the positioning structure includes a hole provided in the installation space for at least one end of the pipe to pass through, and the step S5 includes passing the end of the pipe through the hole.
在一些实施例中,所述管道包括依次连接的第一直伸段、第一弯管段、第二直伸段,所述第一弯管段呈圆弧形,所述第一直伸段第三直伸段与所述第二直伸段呈夹角。In some embodiments, the pipeline includes a first straight section, a first elbow section, and a second straight section connected in sequence, the first elbow section is arc-shaped, and the first straight section and the third straight section The segment forms an included angle with the second straight segment.
在一些实施例中,所述步骤S1还包括根据安装空间预设对所述管道支撑的支撑结构的规格;In some embodiments, the step S1 further includes presetting the specifications of the support structure supporting the pipeline according to the installation space;
所述步骤S2还包括获取所述定位结构对所述支撑结构定位的位置数据;The step S2 also includes acquiring position data of the positioning structure for positioning the support structure;
所述步骤S3还包括制作所述支撑结构;The step S3 also includes making the support structure;
所述步骤S4还包括将所述支撑结构安装到所述管道上,得到预制管道;The step S4 also includes installing the support structure on the pipeline to obtain a prefabricated pipeline;
所述步骤S5还包括将所述支撑结构安装到安装空间的所述定位结构。The step S5 also includes installing the support structure to the positioning structure of the installation space.
在一些实施例中,所述定位结构包括在安装空间设置的预埋件,所述步骤S5包括,将所述支撑结构安装到所述预埋件。In some embodiments, the positioning structure includes an embedded part arranged in the installation space, and the step S5 includes installing the support structure to the embedded part.
在一些实施例中,所述支撑结构包括支撑座、卡箍,所述步骤S4还包括,将所述支撑座、卡箍夹设在所述管道,锁合所述支撑座和卡箍;In some embodiments, the support structure includes a support base and a clamp, and the step S4 further includes clamping the support base and the clamp on the pipeline, and locking the support base and the clamp;
所述步骤S5还包括,将所述支撑座焊接至所述预埋件。The step S5 also includes welding the support seat to the embedded part.
在一些实施例中,所述支撑座包括卡座、护板、支架,所述步骤S3还包括,将所述卡座、支架分别焊接到所述护板的两侧,让所述卡座与所述卡箍夹持所述管道;In some embodiments, the support seat includes a card seat, a guard plate, and a bracket, and the step S3 further includes welding the card seat and the bracket to both sides of the guard plate, so that the card seat and the the clamp clamps the pipe;
所述步骤S5还包括,将所述支架焊接至所述预埋件。The step S5 also includes welding the bracket to the embedded part.
在一些实施例中,所述卡座、卡箍上分别设有锁孔,所述步骤S3还包括:锁固件穿设所述卡座、卡箍上的锁孔,将所述卡座、卡箍锁合,夹持所述管道。In some embodiments, lock holes are respectively provided on the card seat and the clamp, and the step S3 further includes: the locking member penetrates through the lock holes on the card seat and the clamp, and inserts the card seat and the clamp The hoop locks, gripping the pipe.
在一些实施例中,采用机械手自动焊接和组装。In some embodiments, robots are used to automate welding and assembly.
在一些实施例中,所述预制管道在预制车间制作完成。In some embodiments, the prefabricated pipeline is manufactured in a prefabricated workshop.
实施本发明的核电站的管道安装工艺,具有以下有益效果:预制管道可以在现场房间外或预制车间完成预制,然后整体运输到现场房间内进行安装焊接提前制作好,不受安装空间制作进度的影响,避免工期受到相互的影响,提升效率,节约成本。Implementation of the pipeline installation process for nuclear power plants of the present invention has the following beneficial effects: the prefabricated pipeline can be prefabricated outside the on-site room or in the prefabrication workshop, and then the whole is transported to the on-site room for installation and welding. It is made in advance and is not affected by the progress of the installation space , to avoid mutual influence on the construction period, improve efficiency and save costs.
附图说明Description of drawings
下面将结合附图及实施例对本发明作进一步说明,附图中:The present invention will be further described below in conjunction with accompanying drawing and embodiment, in the accompanying drawing:
图1是本发明实施例中采用核电站的管道安装工艺安装管道后的结构示意图;Fig. 1 is the structural representation after adopting the pipeline installation process of nuclear power plant installation pipeline in the embodiment of the present invention;
图2是图1中支撑结构与管道、预埋件组装后的结构示意图。Fig. 2 is a structural schematic diagram of the supporting structure in Fig. 1 after being assembled with pipes and embedded parts.
具体实施方式Detailed ways
为了对本发明的技术特征、目的和效果有更加清楚的理解,现对照附图详细说明本发明的具体实施方式。In order to have a clearer understanding of the technical features, purposes and effects of the present invention, the specific implementation manners of the present invention will now be described in detail with reference to the accompanying drawings.
如图1所示,本发明一个优选实施例中的核电站的管道安装工艺拟采用管道1及其支撑结构2离线组装的施工方法,在现场房间外或预制车间,完成管道1和支撑结构2的预制和装配,然后整体运输到现场房间内进行安装焊接。As shown in Figure 1, the pipeline installation process of the nuclear power plant in a preferred embodiment of the present invention intends to adopt the construction method of offline assembly of the pipeline 1 and its supporting structure 2, and complete the installation of the pipeline 1 and the supporting structure 2 outside the on-site room or in the prefabricated workshop Prefabricated and assembled, and then transported as a whole to the on-site room for installation and welding.
核电站的管道安装工艺以组建“小型化、快捷化、灵活化”的离线组合构件为出发点,以管道1、支撑结构2施工工序和流程优化为落脚点,集成应BIM仿真、自动焊、三维测量和物联网等先进技术用,实现了管道1、支撑结构2施工与上游供货和房间移交等条件最大程度“解耦”。The pipeline installation process of nuclear power plants is based on the establishment of "miniature, fast and flexible" offline composite components, with the pipeline 1 and support structure 2 construction procedures and process optimization as the foothold, integrating BIM simulation, automatic welding, and three-dimensional measurement With the use of advanced technologies such as the Internet of Things, the construction of the pipeline 1 and the support structure 2 has been "decoupled" to the greatest extent from upstream supply and room handover.
此技术摆脱了一般“模块化”、“工厂化”技术应用对设计资质、制造资质,及作业场所等诸多因素制约,其“小、快、灵”的特点使得应用场景更多、应用面更广、应用后的规模效应和价值贡献更明显。This technology gets rid of many factors such as general "modularization" and "factoryization" technology application to design qualifications, manufacturing qualifications, and workplaces. The scale effect and value contribution after wide application are more obvious.
该技术大范围使用将对工程安全、质量、进度、成本控制起到有效的促进作用。The large-scale use of this technology will effectively promote the control of project safety, quality, schedule and cost.
具体地,在本实施例中,核电站的管道安装工艺包括以下步骤:Specifically, in this embodiment, the pipeline installation process of the nuclear power plant includes the following steps:
S1、根据安装空间3的管道1进出位置预设管道1的走管方式;S1. Preset the route of the pipeline 1 according to the entrance and exit position of the pipeline 1 in the installation space 3;
S2、获取安装空间3内对所述管道1定位的定位结构4的位置数据;S2. Obtain the position data of the positioning structure 4 for positioning the pipeline 1 in the installation space 3;
S3、根据走管方式,制作管道1的各管段;S3. According to the pipe routing method, make each pipe section of the pipeline 1;
S4、对各管段进行预定位,将各所述管段焊接,得到预制管道10;S4. Pre-positioning each pipe section, welding each pipe section to obtain a prefabricated pipeline 10;
S5、将所述预制管道10安装到安装空间3的所述定位结构4。S5 , installing the prefabricated pipeline 10 to the positioning structure 4 of the installation space 3 .
可以理解地,本申请中的安装空间3通常为核电站内管道1需要安装的房间、容腔等位置,可供核电站工程中的预制管道10安装,预制管道10可以提前制作好,不受安装空间3制作进度的影响,避免工期受到相互的影响,提升效率,节约成本。It can be understood that the installation space 3 in this application is usually the room, the cavity, etc. where the pipeline 1 needs to be installed in the nuclear power plant, and can be used for the installation of the prefabricated pipeline 10 in the nuclear power plant project. 3. The impact of production progress, avoid mutual influence on construction period, improve efficiency and save cost.
优选地,由于管道1的长度可能会较长,为了对管道1提供较好的支撑,预制管道10还需要设置与安装空间3连接的支撑结构2,避免管道1的变形,提升稳定性。Preferably, since the length of the pipeline 1 may be longer, in order to provide better support for the pipeline 1, the prefabricated pipeline 10 also needs to be provided with a support structure 2 connected to the installation space 3, so as to avoid deformation of the pipeline 1 and improve stability.
具体地,核电站的管道安装工艺还包括以下步骤:Specifically, the pipeline installation process of the nuclear power plant also includes the following steps:
步骤S1还包括根据安装空间3预设对所述管道1支撑的支撑结构2的规格;Step S1 also includes presetting the specifications of the support structure 2 supporting the pipeline 1 according to the installation space 3;
步骤S2还包括获取所述定位结构4对所述支撑结构2定位的位置数据;Step S2 also includes obtaining the position data of the positioning structure 4 positioning the support structure 2;
步骤S3还包括制作所述支撑结构2;Step S3 also includes making the supporting structure 2;
步骤S4还包括将所述支撑结构2安装到所述管道1上,得到预制管道10;Step S4 also includes installing the support structure 2 on the pipeline 1 to obtain a prefabricated pipeline 10;
步骤S5还包括将所述支撑结构2安装到安装空间3的所述定位结构4。Step S5 also includes installing the support structure 2 to the positioning structure 4 of the installation space 3 .
在本实施例中,管道1、支撑结构2都得到安装定位,便于管道1的定位和整体安装。当然,在管道1长度不长时,也可将支撑结构2取消。In this embodiment, both the pipeline 1 and the support structure 2 are installed and positioned, which facilitates the positioning and overall installation of the pipeline 1 . Certainly, when the length of the pipeline 1 is not long, the supporting structure 2 can also be canceled.
为了不相互影响工期和制作,预制管道10在预制车间制作完成,完成后运输到房间等安装空间3进行安装。In order not to interfere with the construction period and production, the prefabricated pipeline 10 is completed in the prefabricated workshop, and then transported to the installation space 3 such as a room for installation.
进一步地,管道1通常由多个管段焊接形成,可以理解地,在步骤S3中,根据所述走管方式,设定各管段的长度,切割制作各所述管段,以妈祖管道1的功能和安装尺寸的需求。当然,各管段也可根据设计的标准尺寸加工,再根据实际的安装尺寸进一步加工得出。Further, the pipeline 1 is usually formed by welding a plurality of pipe sections. It can be understood that in step S3, according to the pipe routing method, the length of each pipe section is set, and each pipe section is cut and manufactured. installation size requirements. Of course, each pipe section can also be processed according to the designed standard size, and then further processed according to the actual installation size.
对应地,在制作管段时,加工出管段端部的坡口,利于相邻管段的端部拼接后焊接。Correspondingly, when making the pipe section, the bevel at the end of the pipe section is processed to facilitate welding after splicing the ends of adjacent pipe sections.
具体地,在本实施例中,管道1包括依次连接的第一直伸段11、第一弯管段12、第二直伸段13、第二弯管段14、第三直伸段15、第三弯管段16、第四直伸段17,所述第一弯管段12、第二弯管段14、第三弯管段16均呈圆弧形,且为90°弯头,在其他实施例中,也可为60°、120°等角度的弯头,可以根据管道1的走向方向选择合适弯度的第一弯管段12、第二弯管段14、第三弯管段16。Specifically, in this embodiment, the pipeline 1 includes a first straight section 11, a first bent section 12, a second straight section 13, a second bent section 14, a third
所述第一直伸段11、第三直伸段15分别与所述第二直伸段13呈夹角,进一步地,所述第一直伸段11、第三直伸段15呈夹角,第三直伸段15、第四直伸段17呈夹角,优选地,相互之间呈直角夹角。管道1的各管段呈夹角可以调节管道1两端的朝向,满足管道1两端的进出方向的需求。The first straight section 11, the third
当然,管道1的弯曲状态也可根据安装空间3的实际需求,制作出合适数量的直伸段、弯管段。Of course, the bending state of the pipeline 1 can also be produced with a suitable number of straight stretching sections and bent pipe sections according to the actual requirements of the installation space 3 .
进一步地,在步骤S4中,在对各管段进行预定位时,对各管段的位置进行监测,防止在焊接时出现偏位,影响焊接后的尺寸,避免装配过程中出现位置偏差,影响后续到房间的装配。Further, in step S4, when each pipe section is pre-positioned, the position of each pipe section is monitored to prevent deviation during welding, which affects the size after welding, and avoids position deviation during assembly, which affects the follow-up Assembly of the room.
优选地,由于管道1的长度较大,为了能对管道1的各个位置同时同步实现监测,可以利用三维测量工具对所述管段的定位监测,做到定位稳定和监测准确,不易出现定位偏差。Preferably, due to the relatively long length of the pipeline 1, in order to monitor each position of the pipeline 1 synchronously, a three-dimensional measurement tool can be used to monitor the position of the pipe section, so as to achieve stable positioning and accurate monitoring, and less likely to cause positioning deviation.
另外,在所述管道1的位置偏位时,对各管段的位置进行调节,优选地,可采用支座对管段进行定位,在支座上设置与管道1、支撑结构2匹配的夹具夹持,定位准确,不易偏移。In addition, when the position of the pipeline 1 is displaced, the position of each pipe section is adjusted. Preferably, a support can be used to position the pipe section, and a clamp matching the pipeline 1 and the support structure 2 is set on the support to clamp , accurate positioning, not easy to shift.
进一步地,可以将对各管段的位置进行监测的数据与支座的位置进行关联,在管段的位置偏位时,调整支座的位置,让管段调整到正确的位置。Further, the monitored data of the position of each pipe section can be associated with the position of the support, and when the position of the pipe section is misaligned, the position of the support can be adjusted so that the pipe section can be adjusted to the correct position.
在一些实施例中,定位结构4包括在安装空间3设置、以供所述管道1的端部穿过的孔洞41,进一步地,所述步骤S5中包括,将所述管道1的端部穿过所述孔洞41,管道1可以一端安装到孔洞41穿出,也可只有一端安装到孔洞41后穿出。In some embodiments, the positioning structure 4 includes a
当预制管道10要有支撑结构2时,定位结构4包括在安装空间3设置的预埋件42,所述步骤S5包括,将所述支撑结构2安装到所述预埋件42。When the prefabricated pipeline 10 needs a supporting structure 2 , the positioning structure 4 includes an embedded
进一步地,如图2所示,在本实施例中,支撑结构2包括支撑座21、卡箍22,所述步骤S4还包括,将所述支撑座21、卡箍22夹设在所述管道1,锁合所述支撑座21和卡箍22,让支撑座21、卡箍22从两侧夹持固定住管道1。Further, as shown in FIG. 2 , in this embodiment, the support structure 2 includes a
另外,在将预制管道10安装到安装空间3时,步骤S5还包括,将所述支撑座21焊接至所述预埋件42。In addition, when installing the prefabricated pipeline 10 into the installation space 3 , step S5 also includes welding the
进一步地,在本实施例中,支撑座21包括卡座211、护板212、支架213,所述步骤S3还包括,将所述卡座211、支架213分别焊接到所述护板212的两侧,让所述卡座211与所述卡箍22夹持所述管道1;Further, in this embodiment, the
步骤S5还包括,将所述支架213焊接至所述预埋件42。Step S5 also includes welding the
卡座211、卡箍22上分别设有锁孔,所述步骤S3还包括:锁固件23穿设所述卡座211、卡箍22上的锁孔,将所述卡座211、卡箍22锁合,夹持所述管道1。The
管道1的焊接、支撑结构2的组装均可采用机械手自动焊接和组装,提升了品质,节省了人力,提升焊接效率和质量。The welding of the pipeline 1 and the assembly of the support structure 2 can be automatically welded and assembled by a robot, which improves the quality, saves manpower, and improves welding efficiency and quality.
预制管道10在预制车间制作完成,再运输到安装空间3,制作不受狭小的安装空间3的限制,让制作更容易展开。The prefabricated pipeline 10 is manufactured in the prefabricated workshop, and then transported to the installation space 3. The fabrication is not restricted by the narrow installation space 3, which makes the fabrication easier.
可以理解地,本发明采用的核电站的管道安装工艺主要包括以下几点:It can be understood that the pipeline installation process of the nuclear power plant adopted in the present invention mainly includes the following points:
1.在施工准备阶段,根据房间和进出通道大小,分析并合理切分管道1、支撑结构2的模块大小,并形成车间预制技术方案;1. In the construction preparation stage, according to the size of the room and the access channel, analyze and reasonably divide the module size of the pipeline 1 and the support structure 2, and form a workshop prefabrication technical plan;
2.提前介入土建施工,对房间内相关预埋件42和孔洞41进行三维测量,形成管道1、支撑结构2预制的输入参数;2. Intervene in the civil construction in advance, conduct three-dimensional measurement of the relevant embedded
3.结合房间实测数据和设计理论数据,计算管道1、支撑结构2切割尺寸;3. Combining the measured data of the room and the theoretical design data, calculate the cutting size of the pipeline 1 and the support structure 2;
4.在预制车间分别完成支撑结构2的组装焊接和管道1的组装焊接,同时引入自动焊工艺和流水线作业提高车间预制工效;4. Complete the assembly and welding of the support structure 2 and the assembly and welding of the pipeline 1 in the prefabrication workshop, and introduce automatic welding technology and assembly line operations to improve the prefabrication efficiency of the workshop;
5.将焊接完成的支撑结构2和管道1组合装配成一个整体模块,并利用三维测量技术,在车间内完成管道1最终坡口的计算和切割;5. Assemble the welded supporting structure 2 and the pipe 1 into an integral module, and use the three-dimensional measurement technology to complete the calculation and cutting of the final groove of the pipe 1 in the workshop;
6.待房间移交之后将管道1和支撑结构2组合件引入房间,即在车间或厂房外将管道1和支撑结构2组合完成并整体引入;6. After the room is handed over, the assembly of pipeline 1 and support structure 2 is introduced into the room, that is, the combination of pipeline 1 and support structure 2 is completed outside the workshop or factory building and introduced as a whole;
7.完成最终的管道1焊缝和支撑结构2与预埋板的焊接;7. Complete the welding of the final pipeline 1 weld and the support structure 2 and the embedded plate;
具体地,本发明创造技术方案带来的技术效果主要包括以下几点:Specifically, the technical effects brought about by the technical solution of the present invention mainly include the following points:
1.解除了房间移交制约,有利于现场进度;1. Removed the restriction of room handover, which is conducive to the progress of the site;
2.离线作业,扩大了施工作业面,有利于进度;2. Offline operation expands the construction area and facilitates progress;
3.部分焊口现场高空作业或者狭窄空间位置,变成车间焊接,工作环境等更好,有利于进度和质量;3. Part of the welding site works at high altitude or in a narrow space, which becomes workshop welding, and the working environment is better, which is conducive to progress and quality;
4.部分焊口焊接位置由全位置焊接,变成水平位置焊接,降低了焊接难度,同时易于自动焊设备使用,有利于进度和质量;4. The welding position of part of the welding port is changed from full position welding to horizontal position welding, which reduces the difficulty of welding, and is easy to use with automatic welding equipment, which is conducive to progress and quality;
5.焊口的射线探伤更加方便,以前需要现场建立控制区,影响整个工程进度,而现在可以随时拉进探伤间探伤;5. The radiographic testing of welding joints is more convenient. In the past, it was necessary to establish a control area on site, which affected the progress of the entire project, but now it can be pulled into the testing room for testing at any time;
6.在工程早期可以缓解房间移交压力,在工程高峰期也可大大减少了房间内的交叉施工,降低了施工安全风险,减少了施工接口协调;6. It can relieve the pressure of room handover in the early stage of the project, and can also greatly reduce the cross construction in the room during the peak period of the project, reducing the construction safety risk and reducing the coordination of construction interfaces;
7.由于车间焊接条件更好,可以降低对高技术焊工资源的需求,节约人力资源成本。7. Due to the better welding conditions in the workshop, the demand for high-tech welder resources can be reduced and the cost of human resources can be saved.
本发明的技术关键点包括一种管道1和支撑结构2分阶段整体预制的施工方法,包括管道1、支撑结构2的组合方案、施工逻辑优化、精密三维测量技术对管道1预制的控制等。The technical key points of the present invention include a construction method for the integral prefabrication of the pipeline 1 and the support structure 2 in stages, including the combination scheme of the pipeline 1 and the support structure 2, construction logic optimization, control of the prefabrication of the pipeline 1 by precise three-dimensional measurement technology, etc.
具体预保护点包括:Specific pre-protection points include:
1)根据厂房进出通道大小和房间内物项的布置合理划分管道1、支撑结构2组合件的模块大小。1) According to the size of the entrance and exit passages of the factory building and the arrangement of items in the room, the module size of the pipeline 1 and support structure 2 assemblies should be reasonably divided.
2)采用精密三维测量技术提前对房间内相关预埋件42和孔洞41等接口位置进行测量定位,为管道1、支撑结构2精确预制提供输入条件。2) Precise three-dimensional measurement technology is used to measure and locate the interface positions of relevant embedded
3)将原本房间内管道1、支撑结构2的串行施工逻辑优化为场外预制车间的并行流水线施工,提高工效。3) Optimize the original serial construction logic of the pipeline 1 and support structure 2 in the room to the parallel assembly line construction of the off-site prefabrication workshop to improve work efficiency.
4)将原本房间内的手工焊工艺优化为预制车间的自动焊工艺,提高焊接质量和效率。4) Optimize the manual welding process in the original room to the automatic welding process in the prefabrication workshop to improve the welding quality and efficiency.
可以理解地,上述各技术特征可以任意组合使用而不受限制。It can be understood that the above technical features can be used in any combination without limitation.
以上所述仅为本发明的实施例,并非因此限制本发明的专利范围,凡是利用本发明说明书及附图内容所作的等效结构或等效流程变换,或直接或间接运用在其他相关的技术领域,均同理包括在本发明的专利保护范围内。The above is only an embodiment of the present invention, and does not limit the patent scope of the present invention. Any equivalent structure or equivalent process transformation made by using the description of the present invention and the contents of the accompanying drawings, or directly or indirectly used in other related technologies fields, all of which are equally included in the scope of patent protection of the present invention.
Claims (14)
Priority Applications (1)
| Application Number | Priority Date | Filing Date | Title |
|---|---|---|---|
| CN202210899571.8A CN115306956A (en) | 2022-07-28 | 2022-07-28 | Pipeline installation process of nuclear power station |
Applications Claiming Priority (1)
| Application Number | Priority Date | Filing Date | Title |
|---|---|---|---|
| CN202210899571.8A CN115306956A (en) | 2022-07-28 | 2022-07-28 | Pipeline installation process of nuclear power station |
Publications (1)
| Publication Number | Publication Date |
|---|---|
| CN115306956A true CN115306956A (en) | 2022-11-08 |
Family
ID=83857898
Family Applications (1)
| Application Number | Title | Priority Date | Filing Date |
|---|---|---|---|
| CN202210899571.8A Pending CN115306956A (en) | 2022-07-28 | 2022-07-28 | Pipeline installation process of nuclear power station |
Country Status (1)
| Country | Link |
|---|---|
| CN (1) | CN115306956A (en) |
Citations (6)
| Publication number | Priority date | Publication date | Assignee | Title |
|---|---|---|---|---|
| US20060284026A1 (en) * | 2005-06-03 | 2006-12-21 | Wirth John Jr | Pipe brackets and pipe hanging system |
| CN106949315A (en) * | 2017-04-05 | 2017-07-14 | 中国核工业第五建设有限公司 | The installation method of main steam line in AP1000 nuclear power stations |
| CN111120733A (en) * | 2020-01-17 | 2020-05-08 | 重庆华西易通建设股份有限公司 | Super high-rise pumping pipeline mounting and fixing structure |
| CN113268794A (en) * | 2021-04-27 | 2021-08-17 | 广州市机电安装有限公司 | DFMA-based fire pump house construction method |
| JP2022088024A (en) * | 2020-12-02 | 2022-06-14 | 株式会社昭和コーポレーション | Support bracket for floor piping |
| CN217045254U (en) * | 2021-11-12 | 2022-07-26 | 中国核工业二三建设有限公司 | Adjustable pipeline mounting support in pipe gallery |
-
2022
- 2022-07-28 CN CN202210899571.8A patent/CN115306956A/en active Pending
Patent Citations (6)
| Publication number | Priority date | Publication date | Assignee | Title |
|---|---|---|---|---|
| US20060284026A1 (en) * | 2005-06-03 | 2006-12-21 | Wirth John Jr | Pipe brackets and pipe hanging system |
| CN106949315A (en) * | 2017-04-05 | 2017-07-14 | 中国核工业第五建设有限公司 | The installation method of main steam line in AP1000 nuclear power stations |
| CN111120733A (en) * | 2020-01-17 | 2020-05-08 | 重庆华西易通建设股份有限公司 | Super high-rise pumping pipeline mounting and fixing structure |
| JP2022088024A (en) * | 2020-12-02 | 2022-06-14 | 株式会社昭和コーポレーション | Support bracket for floor piping |
| CN113268794A (en) * | 2021-04-27 | 2021-08-17 | 广州市机电安装有限公司 | DFMA-based fire pump house construction method |
| CN217045254U (en) * | 2021-11-12 | 2022-07-26 | 中国核工业二三建设有限公司 | Adjustable pipeline mounting support in pipe gallery |
Similar Documents
| Publication | Publication Date | Title |
|---|---|---|
| US20140189995A1 (en) | Methods for installing reactor coolant loop piping in a nuclear power plant | |
| CN102689142B (en) | Tube truss manufacture process | |
| CN211540098U (en) | Quick assembly device for flanges of prefabricated pipelines | |
| CN113814676B (en) | Manufacturing method of large-diameter tower equipment | |
| CN115229436B (en) | Large double-amplitude bolting type steel box girder total splicing method | |
| CN117141674A (en) | Method for modularly constructing large LNG ship cable channel pipe system outfitting | |
| CN105171342A (en) | Making and forming method for model of siphon type water outlet passage of large pump station | |
| CN101323069B (en) | Whole interchanging quick fix tower section engaging eared plate welding fixture | |
| CN110814640A (en) | Stainless steel welding air pipe product production management system based on BIM | |
| CN113550223A (en) | Pre-assembly process of truss bridge with double-assembly bolt holes | |
| CN115306956A (en) | Pipeline installation process of nuclear power station | |
| KR101801225B1 (en) | A combination worktable and moving cart for rack module | |
| WO2017070987A1 (en) | Construction method for gas pipeline system | |
| CN119616207A (en) | A construction method for a large-span glass curtain wall with a through-pull rod composite frame | |
| CN213329466U (en) | Rigid connection node of rectangular steel column | |
| KR20120074413A (en) | Apparatus for measuring cross section of adjusting pipe installation for butt welding | |
| CN109909631B (en) | Construction process of super-thick-wall super-long composite pipe manifold | |
| CN109967975B (en) | Method for building large floating access door | |
| CN117027258A (en) | Inner inclined curved surface glass curtain wall structure and construction method | |
| CN115306948A (en) | Pipeline installation process for on-line components of nuclear power station | |
| CN114215269B (en) | Auxiliary fixture for producing prefabricated reinforcement cages of integrated beam members and connecting templates | |
| CN204735897U (en) | A frame set is to anchor clamps that is used for high pressure notes steam turbine group to prepare | |
| CN110252912B (en) | Concentric welding construction method for main reinforcement of reinforcement cage | |
| KR100667480B1 (en) | Manufacturing method of single and double pipes applying narrow milling device for grooving | |
| CN103028877B (en) | Method for forming large elbow and tool for forming large elbow |
Legal Events
| Date | Code | Title | Description |
|---|---|---|---|
| PB01 | Publication | ||
| PB01 | Publication | ||
| SE01 | Entry into force of request for substantive examination | ||
| SE01 | Entry into force of request for substantive examination |