[go: up one dir, main page]

CN115893042A - A method for sliding wind power pipe piles onto a ship - Google Patents

A method for sliding wind power pipe piles onto a ship Download PDF

Info

Publication number
CN115893042A
CN115893042A CN202210658138.5A CN202210658138A CN115893042A CN 115893042 A CN115893042 A CN 115893042A CN 202210658138 A CN202210658138 A CN 202210658138A CN 115893042 A CN115893042 A CN 115893042A
Authority
CN
China
Prior art keywords
lifting
sliding
sliding device
ship
pile
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Pending
Application number
CN202210658138.5A
Other languages
Chinese (zh)
Inventor
赵利忠
唐建明
华军明
陈成功
林凯健
汪峥
胡斌
李海军
李向才
王松
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Cccc Third Navigation Nantong Offshore Engineering Co ltd
CCCC Third Harbor Engineering Co Ltd
Original Assignee
Cccc Third Navigation Nantong Offshore Engineering Co ltd
CCCC Third Harbor Engineering Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Cccc Third Navigation Nantong Offshore Engineering Co ltd, CCCC Third Harbor Engineering Co Ltd filed Critical Cccc Third Navigation Nantong Offshore Engineering Co ltd
Priority to CN202210658138.5A priority Critical patent/CN115893042A/en
Publication of CN115893042A publication Critical patent/CN115893042A/en
Pending legal-status Critical Current

Links

Images

Landscapes

  • Ship Loading And Unloading (AREA)

Abstract

本发明公开了一种风电管桩滑移上船的方法,包括以下步骤:码头前沿布设滑移工装、运输船布设滑移工装、将待转运管桩搁置在滚轮架上,并计算出管桩的中心位置,并确认其桩长和桩重,并通过前后两台轴线模块车将其运输至码头;将单桩与前轴线模块车分离、将后轴线模块车从侧面驶出、提升滑移装置下放,带动提升滑移装置提升共同向驾驶室方向移动至指定位置,运输船解缆(起锚),最后按要求海绑固定单桩。本发明能够适用于低潮位的工装,不受码头和码头水深的限制,能用在低潮位时顺畅的将风电管桩平稳的滑移上船,所使用的各类工装,均可重复使用,且使用条件不受潮汐和船只干舷高度的影响,大大降低了上船的费用,缩短了风电管桩的上船时间。

Figure 202210658138

The invention discloses a method for sliding and boarding a wind power pipe pile, which comprises the following steps: laying out the sliding tooling at the front of the wharf, laying out the sliding tooling on the transport ship, placing the pipe pile to be transferred on the roller frame, and calculating the pipe pile The center position of the pile, confirm the pile length and pile weight, and transport it to the dock by two front and rear axis module vehicles; separate the single pile from the front axis module vehicle, drive the rear axis module vehicle from the side, lift and slide The device is lowered, and the lifting and sliding device is driven to lift and move to the designated position in the direction of the cab, the transport ship is unmoored (anchored), and finally the single pile is tied and fixed at sea as required. The present invention can be applied to tooling at low tide level, without being limited by the wharf and water depth of the wharf, and can be used to smoothly slide wind power pipe piles onto the ship at low tide level, and all kinds of tooling used can be reused. And the use conditions are not affected by the tide and the freeboard height of the ship, which greatly reduces the cost of boarding the ship and shortens the boarding time of wind power pipe piles.

Figure 202210658138

Description

一种风电管桩滑移上船的方法A method for sliding wind power pipe piles onto a ship

技术领域technical field

本发明属于风电管桩技术领域,具体涉及一种使用滑移工装将风电管桩滑移上船的方法。The invention belongs to the technical field of wind power pipe piles, and in particular relates to a method for sliding wind power pipe piles onto a ship by using sliding tooling.

背景技术Background technique

传统的风电管桩上船的方法主要为吊装上船或者使用模块车滚装上船;吊装上船(如图1所示),需要配合使用大起重重量的起重机和吊索具,将管桩吊装上船,该方法的主要缺点为吊装的重量会受到起重机的限制,而管桩的重量正常会达到1000吨以上,选择大重量的起重机,会有一定的困难。能够达到要求起重重量的起重机,往往购置费用较高或者租用费用比较昂贵。使用范围也受到码头和码头水深的限制。The traditional method of loading wind power pipe piles on board is mainly hoisting onto the ship or using a module vehicle to roll on the ship; hoisting onto the ship (as shown in Figure 1), it is necessary to use a crane with a large lifting weight and a sling to move the pipe piles to the ship. The main disadvantage of this method is that the weight of the pile will be limited by the crane, and the weight of the pipe pile will normally reach more than 1,000 tons. It will be difficult to choose a heavy crane. Cranes that can reach the required lifting weight are often more expensive to purchase or more expensive to rent. The scope of use is also limited by the water depth of the dock and dock.

滚装上船,单次费用较低且使用方便,但是也受到潮汐的影响和船只干舷高度的影响,只能在高潮位使用,低潮位往往无法使用滚装上船的方法(如图2所示)。Roll-on-roll-on boarding is low cost and easy to use, but it is also affected by the tide and the freeboard height of the ship. It can only be used at high tide levels, and the method of rolling-on-roll-on boarding is often not available at low tide levels (as shown in Figure 2 shown).

发明内容Contents of the invention

本发明的目的在于提供一种风电管桩滑移上船的方法,以解决上述背景技术中提出的问题。The purpose of the present invention is to provide a method for sliding wind power pipe piles onto a ship, so as to solve the problems raised in the above-mentioned background technology.

为实现上述目的,本发明提供如下技术方案:一种风电管桩滑移上船的方法,包括以下步骤:In order to achieve the above object, the present invention provides the following technical solution: a method for sliding wind power pipe piles onto a ship, comprising the following steps:

a):码头前沿布设滑移工装:a): Arrange sliding tooling at the front of the wharf:

涨潮前,将4#提升滑移工装提前布置在码头前沿作为应急备用,在码头面作业地点横向铺设1#岸上滑移轨道和2#岸上滑移轨道,考虑到滑移装船过程中,模块车需从侧面驶出,所述1#岸上滑移轨道暂不通长铺设,轨道铺设完毕后,将3#提升滑移装置和4#提升滑移装置放置在码头上;Before the tide rises, the 4# lifting and sliding tooling is arranged in advance at the front of the wharf as an emergency backup, and the 1# shore sliding track and the 2# shore sliding track are laid horizontally at the working site on the wharf surface. The vehicle needs to drive out from the side, and the 1# shore sliding track is temporarily not laid. After the track is laid, the 3# lifting and sliding device and the 4# lifting and sliding device are placed on the wharf;

b):运输船布设滑移工装:b): The transport ship lays out the sliding tooling:

涨潮前,将运输船(前驾驶船)顺靠码头前沿(正对码头),通过吊机将两条船上滑移轨道铺设在船舶甲板上,并将1#提升滑移装置和2#提升滑移装置放置在船艉处;Before the tide rises, put the transport ship (front driving ship) against the front of the wharf (facing the wharf), lay the two on-board sliding tracks on the deck of the ship through a crane, and place the 1# lifting sliding device and the 2# lifting sliding The shifting device is placed at the stern of the ship;

c):将待转运管桩搁置在滚轮架上,并计算出管桩的中心位置,并确认其桩长和桩重,并通过前后两台轴线模块车将其运输至码头;c): Put the pipe pile to be transferred on the roller frame, calculate the center position of the pipe pile, confirm the pile length and pile weight, and transport it to the wharf through two front and rear axis module vehicles;

d):将两条船上滑移轨道与码头前沿的1#岸上滑移轨道和2#岸上滑移轨道对准在同一轴线上;d): Align the two slip tracks on the ship with the 1# shore slip track and the 2# shore slip track at the front of the wharf on the same axis;

e):将所述1#提升滑移装置缓慢提升,单桩重量部分落在船艉处,因此驳船会下沉,所述1#提升滑移装置支架停止提升,待压舱水的调整和潮水的上涨将驳船抬高,所述1#提升滑移装置继续提升,不断重复上述过程,直到单桩与前轴线模块车分离,然后前轴线模块车从侧面驶出,此时单桩重量由1#提升滑移装置和厚轴线模块车共同承受;e): The 1# lifting and sliding device is slowly lifted, and the weight of the single pile falls on the stern, so the barge will sink, and the support of the 1# lifting and sliding device stops lifting. The rise of the tide raises the barge, and the 1# lifting and sliding device continues to lift, and the above process is repeated until the single pile is separated from the front axis module vehicle, and then the front axis module vehicle drives out from the side. At this time, the weight of the single pile is determined by The 1# lifting and sliding device and the thick axis module car are jointly supported;

f):将3#提升滑移装置从桩底套入,然后3#提升滑移装置提升,将后轴线模块车从侧面驶出,此时单桩重量由1#提升滑移装置和3# 提升滑移装置共同承受,在此过程中及时调整压载水以调节船舶状态;f): Insert the 3# lifting and sliding device from the bottom of the pile, then lift the 3# lifting and sliding device, and drive the rear axis module vehicle out from the side. At this time, the weight of the single pile is determined by the 1# lifting and sliding device and the 3# The lifting and sliding devices are jointly supported, and the ballast water is adjusted in time to adjust the state of the ship during the process;

g):将所述1#岸上滑移轨道铺设完整至预定位置处,保证轴线对齐,所述1#提升滑移装置在自身顶推作用下,带动3#提升滑移装置共同向驾驶室方向移动,此过程中单桩重量由1#提升滑移装置和3# 提升滑移装置共同承受,此过程中及时调整压载水以调节船舶状态;g): Lay the 1# shore sliding track to the predetermined position to ensure that the axes are aligned, and the 1# lifting and sliding device drives the 3# lifting and sliding device to the direction of the cab under the action of its own push During this process, the weight of the single pile is jointly borne by the 1# lifting and sliding device and the 3# lifting and sliding device. During this process, the ballast water is adjusted in time to adjust the state of the ship;

h):所述2#提升滑移装置提升,所述3#提升滑移装置下放,所述1#提升滑移装置1在自身顶推作用下,带动2#提升滑移装置提升共同向驾驶室方向移动,直至到达指定位置,此过程中单桩重量由 1#提升滑移装置和2#提升滑移装置共同承受,此过程中及时调整压载水以调节船舶状态;h): The 2# lifting and sliding device is lifted, the 3# lifting and sliding device is lowered, and the 1# lifting and sliding device 1 is pushed by itself to drive the 2# lifting and sliding device to lift the common driving In this process, the weight of the single pile is jointly borne by the 1# lifting and sliding device and the 2# lifting and sliding device. During this process, the ballast water is adjusted in time to adjust the state of the ship;

i)运输船解缆(起锚),正对2#引桥顺靠于码头前沿,利用吊机调整船上的运输支座,使运输支座均匀分布在桩身下面,所述1#提升滑移装置、2#提升滑移装置卸压,使单桩落在多个运输支座上,然后依次将所述1#提升滑移装置、2#提升滑移装置和滑移轨道吊装至码头面;最后按要求海绑固定单桩。i) The transport ship is unmoored (anchored), facing the 2# approach bridge and leaning against the front of the wharf, using a crane to adjust the transport support on the ship, so that the transport support is evenly distributed under the pile body, and the 1# lifting and sliding device , 2# lifting and sliding device pressure relief, so that the single pile falls on a plurality of transport bearings, then the 1# lifting and sliding device, 2# lifting and sliding device and the sliding track are hoisted to the dock surface in turn; finally Sea tie and fix the single pile as required.

优选的,所述步骤i)中的运输支座至少布置6个。Preferably, at least 6 transport supports in the step i) are arranged.

优选的,所述1#岸上滑移轨道和2#岸上滑移轨道的中心间距为 10m-12m。Preferably, the distance between the centers of the 1# shore slip track and the 2# shore slip track is 10m-12m.

优选的,所述步骤b)中2#提升滑移装置与船艉的距离为3m-5m。Preferably, the distance between the 2# lifting and sliding device and the stern of the ship in the step b) is 3m-5m.

优选的,所述1#提升滑移装置、2#提升滑移装置、3#提升滑移装置和4#提升滑移装置均包括双门框结构、承载梁、顶推装置和顶推限位装置,在所述双门框结构之间套装有承载梁,所述双门框结构的顶部横梁上通过提升缸、提升顶和钢绞线同步提升和下放承载梁,所述顶推装置和顶推限位装置设在双门框结构的底座梁下端。Preferably, the 1# lifting and sliding device, the 2# lifting and sliding device, the 3# lifting and sliding device and the 4# lifting and sliding device all include a double door frame structure, a load beam, a pushing device and a pushing and limiting device , a load-bearing beam is set between the double door frame structures, and the top beam of the double door frame structure is synchronously lifted and lowered by the lifting cylinder, the lifting top and the steel strand, and the pushing device and the pushing limit The device is arranged at the lower end of the base beam of the double door frame structure.

优选的,在所述底座梁上装有倾角传感器。Preferably, an inclination sensor is installed on the base beam.

优选的,在所述双门框结构上还设有防风铁楔装置、锚索装置、重量指示装置和高度指示装置。Preferably, a windproof iron wedge device, an anchor cable device, a weight indicating device and a height indicating device are also provided on the double door frame structure.

优选的,在所述支撑梁上对称设有两个搁置点支座,在每个所述搁置点支座上均设有调节座。Preferably, two rest point supports are arranged symmetrically on the support beam, and an adjustment seat is provided on each of the rest point supports.

优选的,在所述3#提升滑移装置和4#提升滑移装置的底部装有横移装置,以实现横移功能Preferably, a traversing device is installed at the bottom of the 3# lifting and sliding device and the 4# lifting and sliding device to realize the traversing function

本发明的技术效果和优点:Technical effect and advantage of the present invention:

1.本发明能够适用于低潮位的工装,不受码头和码头水深的限制,能用在低潮位时顺畅的将风电管桩平稳的滑移上船。1. The present invention can be applied to tooling at low tide levels, and is not limited by the wharf and water depth of the wharf, and can be used to smoothly slide wind power pipe piles onto the ship at low tide levels.

2.本上船方法中所使用的各类工装,均可重复使用,且使用条件不受潮汐和船只干舷高度的影响,大大降低了上船的费用,缩短了风电管桩的上船时间。2. All kinds of tooling used in this boarding method can be reused, and the use conditions are not affected by the tide and the freeboard height of the ship, which greatly reduces the cost of boarding and shortens the boarding time of wind power pipe piles .

附图说明Description of drawings

图1为目前吊装方式示意图;Figure 1 is a schematic diagram of the current hoisting method;

图2为目前滚装示意图;Figure 2 is a schematic diagram of the current ro-ro;

图3为本发明滑移上船示意图;Fig. 3 is a schematic diagram of skid boarding of the present invention;

图4.1-4.2为提升滑移装置结构示意图;Figure 4.1-4.2 is a schematic structural diagram of the lifting and sliding device;

图5为顶推滑到示意图;Fig. 5 is a schematic diagram of push and slide;

图6为提升滑移装置油缸行程计算示意图;Fig. 6 is a schematic diagram for calculating the cylinder stroke of the lifting and sliding device;

图7为运输船顶靠码头示意图;Fig. 7 is a schematic diagram of a transport ship top docking;

图8为滑移装船准备示意图;Figure 8 is a schematic diagram of preparation for skid loading;

图9为36轴线模块车靠近码头前沿示意图;Figure 9 is a schematic diagram of the 36-axis module vehicle approaching the front of the wharf;

图10为36轴线模块车撤出示意图;Figure 10 is a schematic diagram of the withdrawal of the 36-axis module vehicle;

图11为28轴线模块车靠近码头前沿示意图;Figure 11 is a schematic diagram of the 28-axis module vehicle approaching the front of the wharf;

图12为桩底安装3#提升滑移装置示意图;Figure 12 is a schematic diagram of a 3# lifting and sliding device installed at the bottom of the pile;

图13为28轴线模块车撤出示意图;Figure 13 is a schematic diagram of the withdrawal of the 28-axis module vehicle;

图14为铺设剩余1#滑移轨道示意图;Fig. 14 is the schematic diagram of laying remaining 1# slip track;

图15为3#提升滑移装置靠近码头前沿示意图。Figure 15 is a schematic diagram of the 3# lifting and sliding device approaching the front of the wharf.

图中:1-1#提升滑移装置、2-2#提升滑移装置、3-3#提升滑移装置、4-4#提升滑移装置、11-1#岸上滑移轨道、12-2#岸上滑移轨道、 6-船上滑移轨道、101-双门框结构、102-承载梁、103-顶推装置、104- 顶推限位装置、105-提升缸、106-提升顶、107-钢绞线、108-倾角传感器、109-搁置点支座。In the picture: 1-1# lifting and sliding device, 2-2# lifting and sliding device, 3-3# lifting and sliding device, 4-4# lifting and sliding device, 11-1# shore sliding track, 12- 2# shore sliding track, 6-ship sliding track, 101-double door frame structure, 102-loading beam, 103-jacking device, 104-jacking limit device, 105-lifting cylinder, 106-lifting top, 107 - steel strand, 108 - inclination sensor, 109 - shelving point support.

具体实施方式Detailed ways

下面将结合本发明实施例中的附图,对本发明实施例中的技术方案进行清楚、完整地描述,显然,所描述的实施例仅仅是本发明一部分实施例,而不是全部的实施例。基于本发明中的实施例,本领域普通技术人员在没有做出创造性劳动前提下所获得的所有其他实施例,都属于本发明保护的范围。The following will clearly and completely describe the technical solutions in the embodiments of the present invention with reference to the accompanying drawings in the embodiments of the present invention. Obviously, the described embodiments are only some, not all, embodiments of the present invention. Based on the embodiments of the present invention, all other embodiments obtained by persons of ordinary skill in the art without making creative efforts belong to the protection scope of the present invention.

以1800t承载量为例,如图3-图15示出了本发明一种风电管桩滑移上船的方法的一种具体实施方式:Taking the carrying capacity of 1800t as an example, Figure 3-Figure 15 shows a specific implementation of a method for sliding wind power pipe piles onto a ship according to the present invention:

码头前沿布设滑移工装:Arrange sliding tooling at the front of the wharf:

涨潮前,4#提升滑移装置提前布置在码头前沿作为应急备用,在码头面作业地点横向铺设1#、2#岸上滑移轨道,考虑到滑移装船过程中,模块车需从侧面驶出,1#岸上滑移轨道暂不通长铺设;2条滑移轨道中心间距为11m(每条轨道均坐落在横梁上),轨道铺设完毕后,将3#提升滑移装置放置在码头后沿上;Before the high tide, the 4# lifting and sliding device is arranged in advance at the front of the wharf as an emergency backup, and the 1# and 2# shore sliding tracks are laid horizontally at the working site on the wharf. Considering that during the sliding loading process, the module vehicle needs to drive from the side The length of the 1# shore sliding track will not be laid temporarily; the distance between the centers of the 2 sliding tracks is 11m (each track is located on the beam). After the track is laid, the 3# lifting and sliding device is placed on the rear edge superior;

运输船布设滑移工装:Transport ship layout slip tooling:

涨潮前,运输船(前驾驶船)顺靠码头前沿(正对码头),350t 吊机将2条滑移轨道按要求铺设在船舶甲板上,并将1#、2#提升滑移装置放置在船艉处,其中2#提升滑移装置与船艉距离控制在4m左右;Before the tide rises, the transport ship (front driving ship) is docked at the front of the wharf (facing the wharf), and the 350t crane lays 2 sliding tracks on the ship deck as required, and places the 1# and 2# lifting and sliding devices on the At the stern of the ship, the distance between the 2# lifting and sliding device and the stern is controlled at about 4m;

滑移装船skid loading

(1)运输船上的滑移工装(滑移轨道、提升滑移装置)安装完成后,解缆,顶靠正对2#引桥的码头前沿(如图7所示),船艉带好缆绳,中间系倒八字缆,使船上的滑移轨道与码头面上的滑移轨道在同一轴线上,若是大潮汛期间,船头需抛2个八字锚,接好1#、2#、 3#提升滑移装置的电源线,确保空载试机正常;(1) After the installation of the sliding tooling (sliding track, lifting and sliding device) on the transport ship is completed, untie the mooring, lean against the front of the wharf facing the 2# approach bridge (as shown in Figure 7), put the cable on the stern, and Tie the figure-of-eight cable upside down so that the sliding track on the ship is on the same axis as the sliding track on the wharf. If it is during a flood season, two figure-of-eight anchors need to be thrown at the bow, and the 1#, 2#, and 3# lifting slides should be connected. The power cord of the mobile device to ensure that the no-load test machine is normal;

(2)滑移装船前,再次检查滑移工装,等待合适的潮水,模块车向海侧缓慢行驶,直至36轴线模块车距离码头前沿4m左右停止行驶,此时单桩重量由2个模块车共同承受(如图8-图9所示);(2) Before skidding and loading, check the skidding tooling again, wait for the appropriate tide, and drive the module car slowly to the sea side until the 36-axis module car stops driving about 4m away from the front of the wharf. At this time, the weight of the single pile is divided by 2 modules The car bears jointly (as shown in Fig. 8-Fig. 9);

(3)1#提升滑移装置缓慢提升,单桩重量会有一部分落在船艉处,因此驳船会下沉,1#提升滑移装置停止提升,等待压舱水的调整和潮水的上涨将驳船抬高,1#提升滑移装置继续提升,不断重复上述过程,直到单桩与36轴线模块车分离,然后36轴线模块车从侧面驶出,此时单桩重量由1#提升滑移装置和28轴线模块车共同承受(如图10所示);(3) The 1# lifting and sliding device is slowly lifted, and part of the weight of the single pile will fall on the stern, so the barge will sink, and the 1# lifting and sliding device will stop lifting, waiting for the ballast water to be adjusted and the tide to rise. The barge is raised, the 1# lifting and sliding device continues to lift, and the above process is repeated until the single pile is separated from the 36-axis module vehicle, and then the 36-axis module vehicle drives out from the side. At this time, the weight of the single pile is controlled by the 1# lifting and sliding device. Together with the 28-axis module vehicle (as shown in Figure 10);

(4)28轴线模块车带动1#提升滑移装置继续向驾驶室方向移动,直至28轴线模块车距离码头前沿4m停止行驶,此过程中单桩重量由1#提升滑移装置和28轴线模块车共同承受,过程中及时调整压载水以调节船舶状态(如图11所示);(4) The 28-axis module vehicle drives the 1# lifting and sliding device to continue to move towards the cab until the 28-axis module vehicle stops driving 4m away from the front of the wharf. During this process, the weight of the single pile is determined by the 1# lifting and sliding device and the 28-axis module The vehicle bears it together, and the ballast water is adjusted in time to adjust the state of the ship during the process (as shown in Figure 11);

(5)350t吊机起吊3#提升滑移装置,从桩底套入,放置于距离桩底约8m处,此时单桩重量仍由1#提升滑移装置和28轴线模块车共同承受(如图12所示);(5) The 3# lifting and sliding device is lifted by a 350t crane, inserted from the bottom of the pile, and placed at a distance of about 8m from the bottom of the pile. At this time, the weight of the single pile is still jointly borne by the 1# lifting and sliding device and the 28-axis module vehicle ( as shown in Figure 12);

(6)步骤六:3#提升滑移装置提升,28轴线模块车从侧面驶出,此时单桩重量由1#提升滑移装置和3#提升滑移装置共同承受,过程中及时调整压载水以调节船舶状态(如图13所示);(6) Step 6: The 3# lifting and sliding device is lifted, and the 28-axis module vehicle drives out from the side. At this time, the weight of the single pile is jointly borne by the 1# lifting and sliding device and the 3# lifting and sliding device. Carrying water to adjust the state of the ship (as shown in Figure 13);

(7)铺设剩余的1#岸上滑移轨道至预定位置处,保证轴线对齐, 1#支架在自身顶推作用下,带动3#提升滑移装置提升共同向驾驶室方向移动,直至3#提升滑移装置提升中心距离码头前沿4m处停止移动(此时3#提升滑移装置提升正好坐落在海侧轨道梁上),此过程中单桩重量由1#提升滑移装置提升和3#提升滑移装置提升共同承受,过程中及时调整压载水以调节船舶状态(如图14所示);(7) Lay the remaining 1# shore sliding track to the predetermined position to ensure that the axes are aligned. Under the action of its own push, the 1# bracket drives the 3# lifting and sliding device to lift and move towards the cab until 3# lifts The lifting center of the sliding device stops moving at a distance of 4m from the front of the wharf (at this time, the lifting of the 3# lifting sliding device just sits on the sea side track beam). During this process, the weight of the single pile is lifted by the 1# lifting sliding device and the 3# lifting The sliding device is lifted and bears jointly, and the ballast water is adjusted in time during the process to adjust the state of the ship (as shown in Figure 14);

(8)2#提升滑移装置提升,3#提升滑移装置下放,1#提升滑移装置在自身顶推作用下,带动2#提升滑移装置共同向驾驶室方向移动,直至到达指定位置,此过程中单桩重量由1#提升滑移装置和2# 提升滑移装置共同承受,过程中及时调整压载水以调节船舶状态(如图15所示);(8) The 2# lifting and sliding device is lifted, the 3# lifting and sliding device is lowered, and the 1# lifting and sliding device, under the action of its own push, drives the 2# lifting and sliding device to move towards the cab until it reaches the designated position , during this process, the weight of the single pile is jointly borne by the 1# lifting and sliding device and the 2# lifting and sliding device, and the ballast water is adjusted in time during the process to adjust the state of the ship (as shown in Figure 15);

(9)运输船解缆(起锚),正对2#引桥顺靠于码头前沿,利用 350t吊机调整船上原有的运输支座,使运输支座均匀分布在桩身下面, 1#提升滑移装置、2#提升滑移装置卸压,使单桩落在6个运输支座上,然后依次将1#提升滑移装置、2#提升滑移装置和滑移轨道吊装至码头面,最后按要求海绑固定单桩,运输支座总计最少布置6个。(9) The transport ship is unmoored (anchored), facing the 2# approach bridge and leaning against the front of the wharf, using a 350t crane to adjust the original transport support on the ship, so that the transport support is evenly distributed under the pile body, and the 1# lifting slide The lifting device and 2# lifting and sliding device are depressurized, so that the single pile falls on the 6 transport supports, and then the 1# lifting and sliding device, 2# lifting and sliding device and the sliding track are hoisted to the dock surface in sequence, and finally Sea-tied and fixed single piles are required, and a total of at least 6 transport supports are arranged.

提升滑移装置行程计算:Calculation of the stroke of the lifting skid:

为保证一年中每天都具备滑移装船条件,且每天装船有效工作时间为4小时,故在提升滑移装置设计时,需充分考虑其油缸行程,In order to ensure that the skid loading conditions are available every day of the year, and the effective working time of the daily loading is 4 hours, it is necessary to fully consider the stroke of the oil cylinder when designing the lifting skid device.

通过对《中国沿海潮汐表(上海港、杭州湾)/2020》中的青龙港潮汐表的分析,以2019年4月26日16:50时的高潮位水面计算,该潮位为一年中所有白天的高潮位之中最小的潮位,高程为+2.26m (吴淞高程);Based on the analysis of the tide tables of Qinglong Port in "China Coastal Tide Tables (Shanghai Port, Hangzhou Bay)/2020", based on the high tide level water surface at 16:50 on April 26, 2019, the tide level is all The smallest tide level among the daytime high tide levels, the elevation is +2.26m (Wusong elevation);

拟在当天15:00-19:00时间段进行滑移装船作业,15:00时的水面高程为+1.89m,19:00时的水面高程为+1.92m(吴淞高程)。由于本码头高潮位比吴淞港高潮位高约0.6m,故计算时以(+1.89) m+0.6m=+2.49m作为起始作业潮位;The skid loading operation is planned to be carried out from 15:00 to 19:00 on the same day, the water surface elevation at 15:00 is +1.89m, and the water surface elevation at 19:00 is +1.92m (Wusong elevation). Since the high tide level of this wharf is about 0.6m higher than the high tide level of Wusong Port, (+1.89) m+0.6m=+2.49m is used as the initial operating tide level in the calculation;

考虑到模块车高度为1.5m,模块车上的U型托架底部高度为 0.4m,提升滑移装置底座高度为1.68m(含船上轨道高度)(如图6 所示);Considering that the height of the module car is 1.5m, the bottom height of the U-shaped bracket on the module car is 0.4m, and the base height of the lifting and sliding device is 1.68m (including the height of the track on the ship) (as shown in Figure 6);

故提升滑移装置液压油缸行程L=(+6.7m)+1.5m+0.4m- (2.49+2+1.68)=2.43m;Therefore, the hydraulic cylinder stroke of the lifting and sliding device L=(+6.7m)+1.5m+0.4m- (2.49+2+1.68)=2.43m;

考虑到一定的安全富余,提升滑移装置行程定为3m。Considering a certain safety margin, the stroke of the lifting and sliding device is set at 3m.

申请人又一声明,本发明通过上述实施例来说明本发明的实现方法及装置结构,但本发明并不局限于上述实施方式,即不意味着本发明必须依赖上述方法及结构才能实施。所属技术领域的技术人员应该明了,对本发明的任何改进,对本发明所选用实现方法等效替换及步骤的添加、具体方式的选择等,均落在本发明的保护范围和公开的范围之内。The applicant further stated that the present invention illustrates the implementation method and device structure of the present invention through the above-mentioned embodiments, but the present invention is not limited to the above-mentioned embodiments, that is, it does not mean that the present invention must rely on the above-mentioned methods and structures to be implemented. Those skilled in the art should understand that any improvement to the present invention, the equivalent replacement of the selected implementation method of the present invention, the addition of steps, the selection of specific methods, etc., all fall within the scope of protection and disclosure of the present invention.

本发明并不限于上述实施方式,凡采用和本发明相似结构及其方法来实现本发明目的的所有方式,均在本发明的保护范围之内。The present invention is not limited to the above-mentioned embodiments, and all methods that use structures and methods similar to the present invention to achieve the purpose of the present invention are within the protection scope of the present invention.

Claims (9)

1. A method for sliding a wind power pipe pile onto a ship is characterized by comprising the following steps:
a) The method comprises the following steps Laying a sliding tool at the front edge of the wharf:
before the flood tide, a fourth lifting and sliding tool (4) is arranged at the front edge of the wharf in advance to serve as an emergency standby, a 1# onshore sliding track (11) and a 2# onshore sliding track (12) are transversely laid at a wharf face operation place, the 1# onshore sliding track (11) cannot be laid for a long time, and after the tracks are laid, a 3# lifting and sliding device (3) and a 4# lifting and sliding device (4) are placed on the wharf;
b) The method comprises the following steps Laying a sliding tool for a transport ship:
paving two shipboard sliding tracks (6) on a ship deck by a crane along the front edge of a wharf, and placing a 1# lifting sliding device (1) and a 2# lifting sliding device (2) at the stern of the ship;
c) The method comprises the following steps Placing the tubular pile to be transferred on a roller frame, calculating the central position of the tubular pile, confirming the pile length and the pile weight of the tubular pile, and transporting the tubular pile to a wharf through a front axis module vehicle and a rear axis module vehicle;
d) The method comprises the following steps Aligning two shipboard sliding tracks (6) with a No. 1 shore sliding track (11) and a No. 2 shore sliding track (12) at the front edge of a wharf on the same axis;
e) The method comprises the following steps Slowly lifting the 1# lifting and sliding device (1), wherein the weight of the single pile is partially dropped at the stern of the ship, so that the barge can sink, the bracket of the 1# lifting and sliding device (1) stops lifting, the barge is lifted by adjusting ballast water and rising tide, the 1# lifting and sliding device (1) is continuously lifted, the process is continuously repeated until the single pile is separated from the front axis module vehicle, then the front axis module vehicle is driven out from the side, and the weight of the single pile is jointly borne by the 1# lifting and sliding device (1) and the thick axis module vehicle;
f) The method comprises the following steps Sleeving the 3# lifting sliding device (3) from the pile bottom, then lifting the 3# lifting sliding device (3), driving the rear axis module vehicle out from the side surface, simultaneously bearing the weight of a single pile by the 1# lifting sliding device (1) and the 3# lifting sliding device (3), and adjusting ballast water in time in the process to adjust the state of the ship;
g) The method comprises the following steps Completely paving the No. 1 onshore sliding track (11) to a preset position to ensure that axes are aligned, wherein the No. 1 lifting sliding device (1) drives the No. 3 lifting sliding device (3) to move towards a cab together under the self-pushing action, the weight of a single pile is borne by the No. 1 lifting sliding device (1) and the No. 3 lifting sliding device (3) together in the process, and ballast water is adjusted in time to adjust the state of the ship in the process;
h) The method comprises the following steps The 2# lifting sliding device (2) is lifted, the 3# lifting sliding device (3) is lowered, the 1# lifting sliding device (1) drives the 2# lifting sliding device (2) to lift and move towards the cab together under the self-pushing action until reaching a specified position, in the process, the weight of a single pile is borne by the 1# lifting sliding device (1) and the 2# lifting sliding device (2) together, and in the process, ballast water is adjusted in time to adjust the state of the ship;
i) Untwisting the transport ship, adjusting the transport supports on the ship just against the 2# approach bridge to lean against the front edge of the wharf by using a crane, enabling the transport supports to be uniformly distributed below the pile body, relieving pressure of the 1# lifting sliding device (1) and the 2# lifting sliding device (2), enabling the single pile to fall on the plurality of transport supports, and then sequentially hoisting the 1# lifting sliding device (1), the 2# lifting sliding device (2) and the sliding track (6) to the wharf surface; and finally, fixing the single piles by sea tying according to requirements.
2. The method for sliding the wind power pipe pile on the ship according to claim 1, which is characterized in that: at least 6 transport supports are arranged in step i).
3. The method for sliding the wind power pipe pile on the ship according to claim 1, which is characterized in that: the center distance between the 1# on-shore sliding track (11) and the 2# on-shore sliding track (12) is 10-12 m.
4. The method for sliding the wind power pipe pile on the ship according to claim 1, which is characterized in that: and in the step b), the distance between the No. 2 lifting sliding device (2) and the stern is 3-5 m.
5. The method for sliding the wind power pipe pile on the ship according to claim 1, which is characterized in that: 1# promotes slider (1), 2# promotes slider (2), 3# promotes slider (3) and 4# promotes slider (4) and all includes two door frame structure (101), carrier bar (102), thrustor (103) and top pushing stop device (104) the cover is equipped with carrier bar (102) between two door frame structure (101), promote simultaneously through promoting jar (105), promotion top (106) and steel strand wires (107) on the top crossbeam of two door frame structure (101) and transfer carrier bar (102), base roof beam lower extreme at two door frame structure (101) is established in thrustor (103) and top pushing stop device (104).
6. The method for sliding the wind power pipe pile on the ship according to claim 5, wherein the method comprises the following steps: and the base beam is provided with an inclination angle sensor (108).
7. The method for sliding the wind power pipe pile on the ship according to claim 5, wherein the method comprises the following steps: and a wind-proof iron wedge device, an anchor cable device, a weight indicating device and a height indicating device are further arranged on the double-door-frame structure (101).
8. The method for sliding the wind power pipe pile onto the ship according to claim 5, wherein the method comprises the following steps: two resting point supports (109) are symmetrically arranged on the support beam (102), and an adjusting seat is arranged on each resting point support (109).
9. The method for sliding the wind power pipe pile on the ship according to claim 5, wherein the method comprises the following steps: and a traversing device is arranged at the bottom of the 3# lifting sliding device (3) and the 4# lifting sliding device (4).
CN202210658138.5A 2022-06-10 2022-06-10 A method for sliding wind power pipe piles onto a ship Pending CN115893042A (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN202210658138.5A CN115893042A (en) 2022-06-10 2022-06-10 A method for sliding wind power pipe piles onto a ship

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN202210658138.5A CN115893042A (en) 2022-06-10 2022-06-10 A method for sliding wind power pipe piles onto a ship

Publications (1)

Publication Number Publication Date
CN115893042A true CN115893042A (en) 2023-04-04

Family

ID=86493986

Family Applications (1)

Application Number Title Priority Date Filing Date
CN202210658138.5A Pending CN115893042A (en) 2022-06-10 2022-06-10 A method for sliding wind power pipe piles onto a ship

Country Status (1)

Country Link
CN (1) CN115893042A (en)

Cited By (2)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN116588257A (en) * 2023-07-14 2023-08-15 南通泰胜蓝岛海洋工程有限公司 A method of boarding and transporting offshore wind power pipe piles at full tidal level
CN116692525A (en) * 2023-08-03 2023-09-05 南通泰胜蓝岛海洋工程有限公司 A two-way transport equipment for sea wind pipe piles and its transport method on board

Citations (6)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JPH07149434A (en) * 1992-09-29 1995-06-13 Kawasaki Steel Corp Loading / unloading method and loading / unloading relay device
CN102556691A (en) * 2011-12-29 2012-07-11 武船重型工程有限公司 Roll-on/roll-off shipping method for long large steel box girder segment across obstacles
KR20140029835A (en) * 2012-08-30 2014-03-11 주식회사 동방 Load and unload system of roro ship the tide difference of high and low water
CN106275287A (en) * 2016-09-05 2017-01-04 江苏中铁山桥重工有限公司 A kind of large-scale truss whole sections shipment method
US20180044985A1 (en) * 2016-08-11 2018-02-15 Bobo Ladders Llc Boat or recreatonal vehicle ladder apparatus
CN109607248A (en) * 2018-11-28 2019-04-12 四川路桥华东建设有限责任公司 A kind of applicable tidal waters large-scale component sliding unloading construction method

Patent Citations (6)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JPH07149434A (en) * 1992-09-29 1995-06-13 Kawasaki Steel Corp Loading / unloading method and loading / unloading relay device
CN102556691A (en) * 2011-12-29 2012-07-11 武船重型工程有限公司 Roll-on/roll-off shipping method for long large steel box girder segment across obstacles
KR20140029835A (en) * 2012-08-30 2014-03-11 주식회사 동방 Load and unload system of roro ship the tide difference of high and low water
US20180044985A1 (en) * 2016-08-11 2018-02-15 Bobo Ladders Llc Boat or recreatonal vehicle ladder apparatus
CN106275287A (en) * 2016-09-05 2017-01-04 江苏中铁山桥重工有限公司 A kind of large-scale truss whole sections shipment method
CN109607248A (en) * 2018-11-28 2019-04-12 四川路桥华东建设有限责任公司 A kind of applicable tidal waters large-scale component sliding unloading construction method

Cited By (4)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN116588257A (en) * 2023-07-14 2023-08-15 南通泰胜蓝岛海洋工程有限公司 A method of boarding and transporting offshore wind power pipe piles at full tidal level
CN116588257B (en) * 2023-07-14 2023-10-03 南通泰胜蓝岛海洋工程有限公司 A method for moving offshore wind power pipe piles on board ships at all tide levels
CN116692525A (en) * 2023-08-03 2023-09-05 南通泰胜蓝岛海洋工程有限公司 A two-way transport equipment for sea wind pipe piles and its transport method on board
CN116692525B (en) * 2023-08-03 2023-10-24 南通泰胜蓝岛海洋工程有限公司 Sea wind pipe pile bidirectional transferring equipment and ship-on transferring method thereof

Similar Documents

Publication Publication Date Title
CN103332269B (en) Backpack complete offshore wind power machine transport installation ship
US6802684B2 (en) Container tranfer terminal system and method
US4744697A (en) Installation and removal vessel
CN107499968B (en) Ship unloading method of bridge crane at shallow water wharf
CN115893042A (en) A method for sliding wind power pipe piles onto a ship
CN1926024A (en) Method and apparatus for laterally launching a vessel constructed on the ground
CN111285141B (en) Ship unloader transportation and delivery process
CA1095204A (en) Port ramp for access to a roll-on roll-off ship
CN103670946A (en) Method of installing an offshore wind turbine and a transport vessel thereof
CN109911125A (en) A roll-on-roll-on-ship method for offshore wind power foundation steel pipe piles
CN101844611B (en) A method for loading and launching an ocean engineering drilling platform
CN205819494U (en) Fixed quay self adaptation is gone on board gangway ladder
CN101781887A (en) Overhang installation method for upper structure of offshore platform
CN104420453B (en) The overall folding method of a kind of self-elevating drilling platform cantilever beam
CN114855694B (en) Dock floating roll-on facility suitable for large tidal range condition and operation method
CN115893040A (en) A method for lateral roll-on-roll-off of steel box girder large sections
CN105480387A (en) Overall shipping method for shipbuilding gantry crane
GB2327449A (en) Method of transporting and installing a substructure
CN207208388U (en) A kind of bridge roll-on transport ship
CN216973154U (en) Large-span bridge arch rib lifting, floating and jacking ship-loading structure
US7762744B2 (en) Method and vessel for removing offshore structures
CN114148463B (en) Construction technology of semi-submersible offshore installation platform
CN113605309B (en) Multi-module floating breakwater offshore laying ship and laying method
CN205686577U (en) Self-adjusting boarding ladders based on fixed quay stair
CN111152899B (en) Method for leveling 3000-ton floating crane main arm frame by using semi-submersible barge and floating crane

Legal Events

Date Code Title Description
PB01 Publication
PB01 Publication
SE01 Entry into force of request for substantive examination
SE01 Entry into force of request for substantive examination