[go: up one dir, main page]

CN116145723A - A Construction Method for Covering and Excavating Permanent Steel Pipe Columns - Google Patents

A Construction Method for Covering and Excavating Permanent Steel Pipe Columns Download PDF

Info

Publication number
CN116145723A
CN116145723A CN202211491345.2A CN202211491345A CN116145723A CN 116145723 A CN116145723 A CN 116145723A CN 202211491345 A CN202211491345 A CN 202211491345A CN 116145723 A CN116145723 A CN 116145723A
Authority
CN
China
Prior art keywords
steel pipe
pipe column
construction method
pile
main
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Pending
Application number
CN202211491345.2A
Other languages
Chinese (zh)
Inventor
吴东
朱桢华
刘小滔
郭继禄
卢凯
王柏程
王杰军
李信运
方自山
龚文波
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
China Railway Guangzhou Engineering Group Co Ltd CRECGZ
CRECGZ Shenzhen Engineering Co Ltd
Original Assignee
China Railway Guangzhou Engineering Group Co Ltd CRECGZ
CRECGZ Shenzhen Engineering Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by China Railway Guangzhou Engineering Group Co Ltd CRECGZ, CRECGZ Shenzhen Engineering Co Ltd filed Critical China Railway Guangzhou Engineering Group Co Ltd CRECGZ
Priority to CN202211491345.2A priority Critical patent/CN116145723A/en
Publication of CN116145723A publication Critical patent/CN116145723A/en
Pending legal-status Critical Current

Links

Images

Classifications

    • EFIXED CONSTRUCTIONS
    • E02HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
    • E02DFOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
    • E02D29/00Independent underground or underwater structures; Retaining walls
    • E02D29/045Underground structures, e.g. tunnels or galleries, built in the open air or by methods involving disturbance of the ground surface all along the location line; Methods of making them
    • EFIXED CONSTRUCTIONS
    • E02HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
    • E02DFOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
    • E02D5/00Bulkheads, piles, or other structural elements specially adapted to foundation engineering
    • E02D5/22Piles
    • E02D5/34Concrete or concrete-like piles cast in position ; Apparatus for making same
    • EFIXED CONSTRUCTIONS
    • E04BUILDING
    • E04BGENERAL BUILDING CONSTRUCTIONS; WALLS, e.g. PARTITIONS; ROOFS; FLOORS; CEILINGS; INSULATION OR OTHER PROTECTION OF BUILDINGS
    • E04B1/00Constructions in general; Structures which are not restricted either to walls, e.g. partitions, or floors or ceilings or roofs
    • E04B1/38Connections for building structures in general
    • E04B1/58Connections for building structures in general of bar-shaped building elements
    • EFIXED CONSTRUCTIONS
    • E04BUILDING
    • E04BGENERAL BUILDING CONSTRUCTIONS; WALLS, e.g. PARTITIONS; ROOFS; FLOORS; CEILINGS; INSULATION OR OTHER PROTECTION OF BUILDINGS
    • E04B1/00Constructions in general; Structures which are not restricted either to walls, e.g. partitions, or floors or ceilings or roofs
    • E04B1/38Connections for building structures in general
    • E04B1/58Connections for building structures in general of bar-shaped building elements
    • E04B1/5825Connections for building structures in general of bar-shaped building elements with a closed cross-section
    • E04B1/5837Connections for building structures in general of bar-shaped building elements with a closed cross-section of substantially circular form
    • EFIXED CONSTRUCTIONS
    • E04BUILDING
    • E04CSTRUCTURAL ELEMENTS; BUILDING MATERIALS
    • E04C3/00Structural elongated elements designed for load-supporting
    • E04C3/30Columns; Pillars; Struts
    • E04C3/34Columns; Pillars; Struts of concrete other stone-like material, with or without permanent form elements, with or without internal or external reinforcement, e.g. metal coverings
    • EFIXED CONSTRUCTIONS
    • E04BUILDING
    • E04GSCAFFOLDING; FORMS; SHUTTERING; BUILDING IMPLEMENTS OR AIDS, OR THEIR USE; HANDLING BUILDING MATERIALS ON THE SITE; REPAIRING, BREAKING-UP OR OTHER WORK ON EXISTING BUILDINGS
    • E04G21/00Preparing, conveying, or working-up building materials or building elements in situ; Other devices or measures for constructional work
    • E04G21/02Conveying or working-up concrete or similar masses able to be heaped or cast
    • E04G21/04Devices for both conveying and distributing
    • EFIXED CONSTRUCTIONS
    • E04BUILDING
    • E04GSCAFFOLDING; FORMS; SHUTTERING; BUILDING IMPLEMENTS OR AIDS, OR THEIR USE; HANDLING BUILDING MATERIALS ON THE SITE; REPAIRING, BREAKING-UP OR OTHER WORK ON EXISTING BUILDINGS
    • E04G21/00Preparing, conveying, or working-up building materials or building elements in situ; Other devices or measures for constructional work
    • E04G21/02Conveying or working-up concrete or similar masses able to be heaped or cast
    • E04G21/06Solidifying concrete, e.g. by application of vacuum before hardening
    • E04G21/08Internal vibrators, e.g. needle vibrators
    • EFIXED CONSTRUCTIONS
    • E04BUILDING
    • E04GSCAFFOLDING; FORMS; SHUTTERING; BUILDING IMPLEMENTS OR AIDS, OR THEIR USE; HANDLING BUILDING MATERIALS ON THE SITE; REPAIRING, BREAKING-UP OR OTHER WORK ON EXISTING BUILDINGS
    • E04G21/00Preparing, conveying, or working-up building materials or building elements in situ; Other devices or measures for constructional work
    • E04G21/14Conveying or assembling building elements
    • E04G21/16Tools or apparatus
    • E04G21/18Adjusting tools; Templates
    • E04G21/1841Means for positioning building parts or elements

Landscapes

  • Engineering & Computer Science (AREA)
  • Architecture (AREA)
  • Structural Engineering (AREA)
  • Civil Engineering (AREA)
  • Mechanical Engineering (AREA)
  • Mining & Mineral Resources (AREA)
  • Paleontology (AREA)
  • General Life Sciences & Earth Sciences (AREA)
  • General Engineering & Computer Science (AREA)
  • Life Sciences & Earth Sciences (AREA)
  • Physics & Mathematics (AREA)
  • Electromagnetism (AREA)
  • Environmental & Geological Engineering (AREA)
  • Placing Or Removing Of Piles Or Sheet Piles, Or Accessories Thereof (AREA)

Abstract

本申请涉及钢管柱施工的技术领域,本申请在浇筑完灌注桩混凝土后,便可将钢管柱吊入至护筒内,经由调节驱动机构对钢管柱进行下插并校核调整垂直度与桩位偏差后便可实现钢管柱固定在灌注桩顶端,无需等待灌注桩凝结完成后再进行钢管柱的安装,使得钢管柱的安装更加简单方便,便于减少钢管柱的施工工期。

Figure 202211491345

This application relates to the technical field of steel pipe column construction. In this application, after pouring concrete for cast-in-situ piles, the steel pipe column can be hoisted into the casing, and the steel pipe column can be inserted down through the adjustment drive mechanism, and the verticality and pile alignment can be checked and adjusted. After the position deviation, the steel pipe column can be fixed on the top of the cast-in-place pile, and there is no need to wait for the cast-in-situ pile to solidify before installing the steel pipe column, which makes the installation of the steel pipe column more simple and convenient, and facilitates the reduction of the construction period of the steel pipe column.

Figure 202211491345

Description

一种盖挖逆作永久钢管柱的施工方法A Construction Method for Covering and Excavating Permanent Steel Pipe Columns

技术领域technical field

本申请涉及钢管柱施工的技术领域,尤其是涉及一种盖挖逆作永久钢管柱的施工方法。The present application relates to the technical field of steel pipe column construction, in particular to a construction method for cover-excavation and upside-down permanent steel pipe columns.

背景技术Background technique

目前在建造大型地下建筑时通常采用盖挖逆作法进行施工,盖挖逆作法施工时通常需要先施作支撑桩作为后续地下建筑结构的支撑体系,支撑体系包括灌注桩以及固定在灌注桩顶部的钢管柱。钢管桩内填充有混凝土,钢管柱外周设置有连接节点。At present, when constructing large-scale underground buildings, the cover-excavation method is usually used for construction. During the construction of the cover-excavation method, support piles are usually firstly installed as the support system for the subsequent underground building structure. steel column. The steel pipe pile is filled with concrete, and the outer circumference of the steel pipe pile is provided with connection nodes.

施工支撑体系的钢管柱时,需要等到灌注桩混凝土凝结后,通过人工下孔到灌注柱顶部,将灌注桩顶端端面进行休整找平后安装定位器,再吊装钢管桩使钢管桩底端卡入定位器,实现钢管柱的定位,之后再往钢管柱与灌注桩之间浇筑混凝土,实现钢管柱与灌注桩的连接。When constructing the steel pipe column of the support system, it is necessary to wait until the concrete of the cast-in-place pile is set, and manually drill a hole to the top of the cast-in-place column, rest and level the top end of the cast-in-place pile, install the positioner, and then hoist the steel pipe pile so that the bottom end of the steel pipe pile is stuck. Insert the locator to realize the positioning of the steel pipe column, and then pour concrete between the steel pipe column and the cast-in-situ pile to realize the connection between the steel pipe column and the cast-in-place pile.

人工安装定位器由于是在封闭且狭窄的空间下进行,不仅存在操作困难且存在定位误差较大等缺点,更重要的是定位器的安装需要在灌注桩完全凝结后进行,延长了钢管柱整体施工周期,导致钢管柱的施工较为不便。Since the manual installation of the locator is carried out in a closed and narrow space, there are not only disadvantages such as difficult operation and large positioning errors, but more importantly, the installation of the locator needs to be carried out after the cast-in-place pile is completely condensed, which prolongs the overall length of the steel pipe column. The construction period makes the construction of steel pipe columns more inconvenient.

发明内容Contents of the invention

为了使钢管柱的施工更加简单方便,本申请提供了一种盖挖逆作永久钢管柱的施工方法。In order to make the construction of the steel pipe column simpler and more convenient, the present application provides a construction method of cover-excavation and reverse construction of the permanent steel pipe column.

本申请提供的一种盖挖逆作永久钢管柱的施工方法,采用如下的技术方案:The application provides a construction method for cover-excavation and upside-down construction of permanent steel pipe columns, which adopts the following technical scheme:

一种盖挖逆作永久钢管柱的施工方法,包括以下步骤:A construction method for cover excavation and reverse construction of permanent steel pipe columns, comprising the following steps:

S1:预制驱动调节机构与钢管柱,所述钢管柱包括标准节以及同轴连接在标准节顶端的工具节,所述标准节上沿长度方向设置有若干连接节点,所述连接节点包括均匀环绕设置在标准节外周的若干牛腿;S1: Prefabricated driving adjustment mechanism and steel pipe column. The steel pipe column includes a standard section and a tool section coaxially connected to the top of the standard section. Several connection nodes are arranged along the length direction of the standard section. The connection nodes include uniform surrounding A number of corbels arranged on the periphery of the standard joint;

S2:场地平整以及灌注桩桩位放线定位;S2: Leveling of the site and positioning of cast-in-place piles;

S3:灌注桩桩位钻孔施工:插打护筒并清除护筒内废土;S3: Drilling construction of cast-in-place piles: Insert and drill the casing and remove the waste soil in the casing;

S4:灌注桩浇筑施工:往护筒内放入钢筋笼并注入混凝土形成灌注桩;S4: Pouring construction of cast-in-place piles: put steel cages into the casing and inject concrete to form cast-in-place piles;

S5:安装驱动调节机构并校核调整驱动调节机构的安装位置,使主通孔与副通孔两者轴线与护筒轴线重合;S5: Install the drive adjustment mechanism and check and adjust the installation position of the drive adjustment mechanism so that the axis of the main through hole and the auxiliary through hole coincide with the axis of the casing;

S6:在灌注桩初凝前,将钢管柱插入至护筒内并使钢管柱基本对中;S6: Before the initial setting of the cast-in-situ pile, insert the steel pipe column into the casing and make the steel pipe column basically centered;

S7:牛腿位置定位:转动钢管柱,直至将钢管柱外周的牛腿移动至指定安装位置;S7: Positioning of the corbel: rotate the steel pipe column until the corbel on the outer periphery of the steel pipe column is moved to the designated installation position;

S8:钢管柱定位:通过驱动调节机构将钢管柱的标准节插入灌注桩顶端至指定深度;配合全站仪并通过驱动调节机构校核调整钢管柱的垂直度与桩位偏差;S8: Steel pipe column positioning: Insert the standard section of the steel pipe column into the top of the cast-in-place pile to the specified depth through the drive adjustment mechanism; cooperate with the total station and check and adjust the verticality of the steel pipe column and the pile position deviation through the drive adjustment mechanism;

S9:往标准节内注入混凝土并进行养护;S9: pour concrete into the standard section and perform curing;

S10:往标准节与护筒之间的间隙回填填料;S10: Backfill the gap between the standard section and the casing;

所述驱动调节机构包括底板以及架设在底板上的顶板,所述底板上设置有驱使顶板升降的升降组件;所述顶板与底板分别开设有供钢管柱穿设的主通孔与副通孔;所述顶板与底板分别设置有主夹持组件与副夹持组件;所述主夹持组件包括设置在顶板的若干主千斤顶,所述主千斤顶环绕主通孔设置且主千斤顶轴向均与主通孔轴向垂直;所述副夹持组件包括设置在底板上的若干副千斤顶,若干所述副千斤顶环绕副通孔设置且若干副千斤顶轴向均与副通孔轴向垂直。The drive adjustment mechanism includes a bottom plate and a top plate erected on the bottom plate, and the bottom plate is provided with a lifting assembly that drives the top plate to rise and fall; the top plate and the bottom plate are respectively provided with a main through hole and a secondary through hole for the steel pipe column to pass through; The top plate and the bottom plate are respectively provided with a main clamping assembly and a secondary clamping assembly; the main clamping assembly includes several main jacks arranged on the top plate, the main jacks are arranged around the main through hole and the main jacks are axially aligned with the main jacks. The axial direction of the through hole is vertical; the auxiliary clamping assembly includes several auxiliary jacks arranged on the bottom plate, the auxiliary jacks are arranged around the auxiliary through hole, and the axial directions of the auxiliary jacks are all perpendicular to the axial direction of the auxiliary through hole.

通过采用上述技术方案,相比传统在灌注桩凝结完成后载进行钢管柱施工的方式,本申请无需等待灌注桩凝结完成便可进行钢管柱施工,便于减少支钢管柱的施工周期,使得钢管柱的施工更加简单方便。通过驱动调节机构的设置,当需要将钢管柱的标准节插入至指定深度时,通过驱使若干主千斤顶活塞杆抵紧钢管柱并驱使副千斤顶活塞杆远离钢管柱,通过升降组件驱使顶板带动钢管柱下移至行程极限后,驱使副千斤顶活塞杆与钢管柱外周抵紧后驱使主千斤顶活塞杆远离钢管柱,最后通过升降组件驱使主板上移复位,重复以上步骤直至将钢管柱插入至指定深度,使灌注桩在下移过程中不易发生偏位。当需要校核钢管柱的垂直度与桩位偏差时,先通过驱使若干主千斤顶与副千斤顶的活塞杆均与钢管柱抵接,配合全站仪并通过控制主千斤顶与副千斤顶驱使自身活塞杆伸缩以实现钢管柱垂直度与桩位偏差的调节,使得钢管柱的定位更加简单方便。By adopting the above technical scheme, compared with the traditional method of carrying out steel pipe column construction after the cast-in-situ pile has solidified, this application can carry out steel pipe column construction without waiting for the cast-in-situ pile to solidify, which is convenient to reduce the construction period of the steel pipe column and make the steel pipe column The construction is more simple and convenient. Through the setting of the driving adjustment mechanism, when the standard joint of the steel pipe column needs to be inserted to the specified depth, the piston rods of the main jacks are pressed against the steel pipe column and the piston rods of the auxiliary jacks are driven away from the steel pipe column, and the top plate is driven to drive the steel pipe column through the lifting assembly After moving down to the stroke limit, drive the piston rod of the auxiliary jack against the outer circumference of the steel pipe column, then drive the piston rod of the main jack away from the steel pipe column, and finally drive the main board to move up and reset through the lifting component, repeat the above steps until the steel pipe column is inserted to the specified depth, Make the cast-in-situ pile less prone to misalignment during the downward movement. When it is necessary to check the verticality of the steel pipe column and the deviation of the pile position, first drive the piston rods of several main jacks and auxiliary jacks to contact the steel pipe column, cooperate with the total station and drive the piston rod of itself by controlling the main jack and auxiliary jacks Telescoping to realize the adjustment of the verticality of the steel pipe column and the deviation of the pile position, making the positioning of the steel pipe column easier and more convenient.

优选的,所述标准节底端呈倒锥形且标准节底端封堵设置。Preferably, the bottom end of the standard joint is in an inverted tapered shape and the bottom end of the standard joint is sealed.

通过采用上述技术方案,通过标准段底端封堵设置,后续往钢管柱内注入混凝土时,有利于减少混凝土从钢管柱底端溢出进而造成浪费,通过钢管柱底端呈倒锥形,便于减少标准节底端端部与灌注桩混凝土的接触面积,进而有利于减少标准节插入灌注桩顶端时的阻力。By adopting the above-mentioned technical scheme, through the sealing setting at the bottom of the standard section, when concrete is poured into the steel pipe column later, it is beneficial to reduce the overflow of concrete from the bottom of the steel pipe column and cause waste. The contact area between the bottom end of the standard section and the concrete of the cast-in-situ pile is beneficial to reduce the resistance when the standard section is inserted into the top of the cast-in-situ pile.

优选的,在步骤S2中,场地平整后,在待施工区域上浇筑加固垫层,所述加固垫层内设置有钢筋网,所述加固垫层还开设有供护筒穿设的穿孔。Preferably, in step S2, after the site is leveled, a reinforcement cushion is poured on the area to be constructed, the reinforcement cushion is provided with a steel mesh, and the reinforcement cushion is also provided with perforations for the casing to pass through.

通过采用上述技术方案,通过加固垫层的设置,便于通过加固垫层对支撑桩周围的地面进行加固,有利于减少安装驱动调节机构以及通过驱动调节结构下放调节钢管柱时,对支撑桩周围地基造成不规则沉降的情况。By adopting the above technical scheme and setting the reinforcement cushion, it is convenient to reinforce the ground around the support pile through the reinforcement cushion, which is beneficial to reduce the impact on the foundation around the support pile when installing the drive adjustment mechanism and lowering the steel pipe column through the drive adjustment structure. causing irregular settlement.

优选的,在步骤S6中,将钢管柱下移至护筒内后,往标准节内注入水以提升钢管柱整体重量;Preferably, in step S6, after the steel pipe column is moved down into the casing, water is injected into the standard section to increase the overall weight of the steel pipe column;

在步骤9中,往标准节内注入混凝土前,将标准节内的水抽出。In step 9, before pouring concrete into the standard section, the water in the standard section is pumped out.

通过采用上述技术方案,通过往钢管柱内加入水,便于提升钢管柱的整体自重,进而便于钢管柱克服灌注桩混凝土浮力以插入灌注桩顶端。By adopting the above-mentioned technical scheme, by adding water into the steel pipe column, it is convenient to increase the overall dead weight of the steel pipe column, and then it is convenient for the steel pipe column to overcome the concrete buoyancy of the cast-in-place pile and insert into the top of the cast-in-place pile.

优选的,所述工具节还同轴架设有限位环,所述限位环内同轴插接有连接管,所述连接管底端延伸至标准节底端;所述限位环外周螺纹穿设有锁紧螺栓且锁紧螺栓的一端与连接管外周抵紧。Preferably, the tool joint is also coaxially provided with a limit ring, and a connecting pipe is coaxially inserted into the limit ring, and the bottom end of the connecting pipe extends to the bottom end of the standard joint; the outer circumference of the limit ring is threaded A locking bolt is provided, and one end of the locking bolt is pressed against the outer periphery of the connecting pipe.

通过采用上述技术方案,通过连接管的设置,便于通过连接管往钢管柱内注入水以增大钢管柱自重;后续往钢管柱内注射混凝土前可通过连接管将钢管柱内的水抽出至钢管柱外,同时可通过连接管往钢管柱内注入混凝土,通过连接管往钢管柱内注入混凝土的时,拧松锁紧螺栓,边注入混凝土边向上提升连接管,直至将连接管移出标准节;便于连接管的周转使用。限位环的设置,后续往钢管柱内注入混凝土后,可将用于振捣钢管柱内混凝土的振捣棒穿入限位环再移入钢管柱底端,通过限位环对振捣棒进行限位,有利于减少振捣棒与钢管柱管壁抵接造成钢管柱移位的情况。By adopting the above-mentioned technical scheme, through the setting of the connecting pipe, it is convenient to inject water into the steel pipe column through the connecting pipe to increase the self-weight of the steel pipe column; before injecting concrete into the steel pipe column, the water in the steel pipe column can be pumped out through the connecting pipe Outside the column, concrete can be injected into the steel pipe column through the connecting pipe at the same time. When injecting concrete into the steel pipe column through the connecting pipe, loosen the locking bolt, and lift the connecting pipe upward while injecting concrete until the connecting pipe is moved out of the standard section; It is convenient for the turnover and use of the connecting pipe. For the setting of the limit ring, after injecting concrete into the steel pipe column, the vibrating rod used for vibrating the concrete in the steel pipe column can be penetrated into the limit ring and then moved into the bottom of the steel pipe column, and the vibrating rod can be controlled by the limit ring. The position limit is beneficial to reduce the displacement of the steel pipe column caused by the contact between the vibrating rod and the pipe wall of the steel pipe column.

优选的,所述标准节与工具节相互靠近一端分别设置有主连接环与副连接环,所述主连接环同轴固定在标准节内腔,所述副连接环同轴固定在工具节内腔,所述主连接环与副连接环通过若干螺栓螺母副相连接,所述工具节内腔还设置有爬梯。Preferably, the ends of the standard joint and the tool joint are respectively provided with a main connecting ring and a secondary connecting ring, the main connecting ring is coaxially fixed in the inner cavity of the standard joint, and the secondary connecting ring is coaxially fixed in the tool joint cavity, the main connecting ring and the secondary connecting ring are connected by a number of bolts and nuts, and the inner cavity of the tool section is also provided with a ladder.

通过采用上述技术方案,后续施工完成后,施工人员可通过爬梯进入工具节底端并拆除主连接环与副连接环上的螺栓螺母副,便可分离工具节与标准节,便于工具节的周转使用。By adopting the above technical scheme, after the follow-up construction is completed, the construction personnel can enter the bottom of the tool joint through the ladder and remove the bolts and nuts on the main connecting ring and the secondary connecting ring, so that the tool joint and the standard joint can be separated, which facilitates the turnover of the tool joint use.

优选的,在步骤S6中,将钢管柱吊入护筒内前,在工具节顶端焊接若干驱动杆。Preferably, in step S6, before hoisting the steel pipe column into the casing, several driving rods are welded on the top of the tool joint.

通过采用上述技术方案,通过在工具节上焊接驱动杆,后续将钢管柱吊入护筒内后,便于施工人员通过驱动杆摆动钢管柱,进而便于通过驱动杆将钢管柱上的牛腿移动至制定位置。By adopting the above technical scheme, by welding the driving rod on the tool joint, after the steel pipe column is subsequently hoisted into the casing, it is convenient for the construction personnel to swing the steel pipe column through the driving rod, and then it is convenient to move the corbel on the steel pipe column to the Make a location.

优选的,在步骤S6中,将钢管柱吊入护筒内前,在工具节顶端安装倾角传感器;将倾角传感器与倾斜显示仪电性连接;Preferably, in step S6, before the steel pipe column is hoisted into the casing, an inclination sensor is installed on the top of the tool joint; the inclination sensor is electrically connected to the inclination display;

在步骤S7中,牛腿位置调节完成后,配合全站仪并通过调节驱动机构校正调节钢管柱的垂直度,并校准记录此时倾角传感器反馈至在倾斜显示仪的数据作为垂直度初始值;In step S7, after the adjustment of the position of the corbel is completed, cooperate with the total station and adjust the verticality of the steel pipe column by adjusting the driving mechanism, and calibrate and record the data fed back by the inclination sensor to the tilt display at this time as the initial value of the verticality;

在步骤S8中,驱动调节机构驱使钢管柱下移过程中,通过倾角传感器反馈至倾斜显示仪上的数据监测钢管柱下插过程中的垂直度。In step S8, during the downward movement of the steel pipe column by driving the adjustment mechanism, the verticality of the steel pipe column during the downward insertion process is monitored through the data fed back from the inclination sensor to the tilt display.

通过采用上述技术方案,通过倾角传感器以及倾斜检测仪的设置,当钢管柱下插后,倾角传感器反馈至倾斜显示仪的数据与钢管柱垂直度初始值不同时,表示钢管柱垂直度发生变化,便于及时提醒施工人员通过驱动调节机构及时调整钢管柱的垂直度。By adopting the above-mentioned technical scheme, through the setting of the inclination sensor and the inclination detector, when the steel pipe column is lowered, the data fed back to the inclination display by the inclination sensor is different from the initial value of the verticality of the steel pipe column, indicating that the verticality of the steel pipe column has changed. It is convenient to promptly remind the construction personnel to adjust the verticality of the steel pipe column in time by driving the adjustment mechanism.

综上所述,本申请包括以下至少一种有益技术效果:In summary, the present application includes at least one of the following beneficial technical effects:

1.本申请在浇筑完灌注桩混凝土后,便可将钢管柱吊入至护筒内,经由调节驱动机构对钢管柱进行下插并校核调整垂直度与桩位偏差后便可实现钢管柱固定在灌注桩顶端,无需等待灌注桩凝结完成后再进行钢管柱的安装,使得钢管柱的安装更加简单方便,便于减少钢管柱的施工工期。1. In this application, after pouring the concrete of the cast-in-place pile, the steel pipe column can be hoisted into the casing, and the steel pipe column can be realized after the adjustment of the driving mechanism to insert the steel pipe column and check and adjust the verticality and the deviation of the pile position. It is fixed on the top of the cast-in-place pile, and there is no need to wait for the concrete pile to be solidified before installing the steel pipe column, which makes the installation of the steel pipe column more simple and convenient, and facilitates the reduction of the construction period of the steel pipe column.

2.当需要调节钢管柱的垂直度时,通过驱使主千斤顶与副千斤顶活塞杆均与钢管柱抵接,配合全站仪,控制主千斤顶与副千斤顶伸缩便可调节钢管柱的垂直度;当需要将钢管柱下插时,通过主夹持组件夹持钢管柱后,通过升降组件驱使顶板带动钢管柱下移至极限状态后,副夹持组件夹持钢管柱,然后主夹持板松开钢管柱,待升降组件驱使顶板上移复位后,松开副夹持组件并重复以上步骤,便可实现将钢管柱插入至指定深度。2. When it is necessary to adjust the verticality of the steel pipe column, the verticality of the steel pipe column can be adjusted by driving the piston rods of the main jack and the auxiliary jack to contact the steel pipe column, and cooperating with the total station to control the expansion and contraction of the main jack and the auxiliary jack; When the steel pipe column needs to be inserted down, after the steel pipe column is clamped by the main clamping component, the top plate is driven by the lifting component to drive the steel tube column to move down to the limit state, the secondary clamping component clamps the steel tube column, and then the main clamping plate is released For the steel pipe column, after the lifting component drives the top plate to move and reset, loosen the auxiliary clamping component and repeat the above steps to realize the insertion of the steel pipe column to the specified depth.

3.通过工具节内设置有限位环,限位环内插接有连接管,安装钢管柱时,可通过连接管往钢管柱内注水以提升钢管柱的自重,往钢管柱内注射混凝土时,可通过连接管往钢管柱内注射混凝土,同时,后续对钢管柱内的混凝土进行振捣时,可将振捣棒穿入限位环内后再进行振捣棒下放,减少振捣棒使用过程中与钢管柱发生碰撞导致钢管柱移位的情况。3. The limit ring is set in the tool section, and the connecting pipe is inserted into the limit ring. When installing the steel pipe column, water can be injected into the steel pipe column through the connecting pipe to increase the self-weight of the steel pipe column. When injecting concrete into the steel pipe column, Concrete can be injected into the steel pipe column through the connecting pipe. At the same time, when vibrating the concrete in the steel pipe column, the vibrating rod can be inserted into the limit ring and then lowered to reduce the use of the vibrating rod In the case of collision with the steel pipe column, the displacement of the steel pipe column is caused.

附图说明Description of drawings

图1是本申请实施例用于示意驱动调节机构的示意图。FIG. 1 is a schematic diagram for illustrating a driving adjustment mechanism according to an embodiment of the present application.

图2是本申请实施例用于使钢管柱施工时的状态示意图。Fig. 2 is a schematic diagram of the state when the embodiment of the present application is used for the construction of steel pipe columns.

图3是本申请实施例用于示意钢管柱的内部结构示意图Figure 3 is a schematic diagram of the internal structure of the steel pipe column in the embodiment of the present application

图4是图3中A部的放大示意图。FIG. 4 is an enlarged schematic view of part A in FIG. 3 .

附图标记说明:Explanation of reference signs:

1、驱动调节机构;11、底板;111、副通孔;112、副千斤顶;113、副限位槽;114、支脚;12、顶板;121、主通孔;122、主千斤顶;123、主限位槽;13、升降组件;3、加固垫层;4、护筒;5、灌注桩;6、钢管柱;61、标准节;62、工具节;620、驱动杆;621、吊环;622、限位环;623、锁紧螺栓;624、爬梯;625、支撑杆;626、倾角传感器;63、牛腿;64、连接管;65、副连接环;66、主连接环。1. Drive adjustment mechanism; 11. Bottom plate; 111. Auxiliary through hole; 112. Auxiliary jack; 113. Auxiliary limit slot; 114. Leg; 12. Top plate; 121. Main through hole; 122. Main jack; 123. Main Limiting slot; 13. Lifting component; 3. Reinforced cushion; 4. Casing; 5. Cast-in-place pile; 6. Steel pipe column; 61. Standard section; 62. Tool section; 620. Driving rod; , limit ring; 623, locking bolt; 624, ladder; 625, support rod; 626, inclination sensor; 63, corbel; 64, connecting pipe; 65, secondary connecting ring;

具体实施方式Detailed ways

以下结合附图1-4对本申请作进一步详细说明。The present application will be described in further detail below in conjunction with accompanying drawings 1-4.

本申请实施例公开一种盖挖逆作永久钢管柱的施工方法,参照图1及图2,包括以下步骤:The embodiment of the present application discloses a construction method of cover excavation and reverse construction of permanent steel pipe columns, referring to Figure 1 and Figure 2, including the following steps:

S1:预制驱动调节机构1、钢管柱6。S1: prefabricated driving adjustment mechanism 1, steel pipe column 6.

驱动调节机构1包括底板11以及架设在底板11正上方的顶板12,底板11底部设置有若干支脚114,底板11上表面还设置有驱使顶板12升降的升降组件13,升降组件13包括固定在底板11四个顶角处的升降千斤顶,升降千斤顶活塞杆与顶板12固定。The drive adjustment mechanism 1 includes a base plate 11 and a top plate 12 erected directly above the base plate 11. A number of feet 114 are provided on the bottom of the base plate 11. The upper surface of the base plate 11 is also provided with a lifting assembly 13 that drives the top plate 12 to lift. The lifting assembly 13 includes a 11 lift jacks at the four corners, the lift jack piston rod is fixed with top plate 12.

顶板12与底板11分别开设有供钢管柱6穿设的主通孔121与副通孔111,顶板12上还设置有主夹持组件,底板11上设置有副夹持组件。The top plate 12 and the bottom plate 11 are respectively provided with a main through hole 121 and a secondary through hole 111 for the steel pipe column 6 to pass through.

主夹持组件包括固定在顶板12上的四组主千斤顶122,四组主千斤顶122均匀环绕主通孔121设置且主千斤顶122的轴向均垂直于主通孔121轴向。顶板12对四组主千斤顶122开设有四组主限位槽123,主限位槽123均与主通孔121连通,主千斤顶122均嵌入至对应的主限位槽123内。The main clamping assembly includes four sets of main jacks 122 fixed on the top plate 12 , the four sets of main jacks 122 are evenly arranged around the main through hole 121 and the axial directions of the main jacks 122 are perpendicular to the main through hole 121 . The top plate 12 is provided with four sets of main limiting grooves 123 for the four sets of main jacks 122 , and the main limiting grooves 123 are all connected to the main through holes 121 , and the main jacks 122 are embedded in the corresponding main limiting grooves 123 .

副夹持组件包括固定在底板11上的四组副千斤顶112,四组副千斤顶112均匀环绕副通孔111设置且副千斤顶112的轴向均垂直于副通孔111轴向。底板11对四组副千斤顶112开设有四组副限位槽113,副限位槽113均与副通孔111连通,副千斤顶112均嵌入至对应的副限位槽113内。The auxiliary clamping assembly includes four sets of auxiliary jacks 112 fixed on the bottom plate 11 , the four sets of auxiliary jacks 112 are evenly arranged around the auxiliary through hole 111 and the axial directions of the auxiliary jacks 112 are perpendicular to the axial direction of the auxiliary through hole 111 . The bottom plate 11 is provided with four sets of auxiliary limiting slots 113 for the four sets of auxiliary jacks 112. The auxiliary limiting slots 113 are all connected to the auxiliary through holes 111, and the auxiliary jacks 112 are embedded in the corresponding auxiliary limiting slots 113.

参照图3及图4,钢管柱6包括标准节61以及同轴可拆卸连接在标准节61顶端的工具节62;标准节61底端封堵设置且标准节61底端呈倒锥形,便于标准节61底端插入至灌注将顶端混凝土内。标准节61与工具节62相互靠近的一端分别设置有主连接环66与副连接环65,主连接环66同轴固定在标准节61内腔,副连接环65同轴固定在工具节62内腔,主连接环66与副连接环65通过若干螺栓螺母副固定,实现工具节62与标准节61的可拆卸连接。3 and 4, the steel pipe column 6 includes a standard section 61 and a tool section 62 coaxially detachably connected to the top of the standard section 61; The bottom end of the standard section 61 is inserted into the pouring concrete at the top. The ends of the standard section 61 and the tool section 62 are respectively provided with a main connecting ring 66 and a secondary connecting ring 65, the main connecting ring 66 is coaxially fixed in the inner cavity of the standard section 61, and the secondary connecting ring 65 is coaxially fixed in the tool section 62 cavity, the main connecting ring 66 and the secondary connecting ring 65 are fixed by several bolts and nuts, so as to realize the detachable connection between the tool section 62 and the standard section 61.

工具节62内腔还固定有爬梯624,便于施工人员通过爬梯624进入工具节62底部拆装主连接环66与副连接环65,工具节62顶端端面均匀环绕固定有四组吊环621。A ladder 624 is also fixed in the cavity of the tool section 62, which is convenient for construction workers to enter the bottom of the tool section 62 through the ladder 624 to disassemble the main connecting ring 66 and the secondary connecting ring 65.

工具节62顶端内壁还同轴架设有限位环622,限位环622外周固定有支撑杆625且支撑杆625远离限位环622的一端与工具节62内壁连接。限位环622还同轴插接有连接管64,限位环622外周还螺纹穿设有锁紧螺栓623,锁紧螺栓623的轴向与限位环622的轴向垂直且锁紧螺栓623的一端伸入限位环622内腔并与连接管64外周抵紧,实现对连接管64的限位。The inner wall of the top end of the tool section 62 is also coaxially provided with a limit ring 622 , the outer periphery of the limit ring 622 is fixed with a support rod 625 and the end of the support rod 625 away from the limit ring 622 is connected to the inner wall of the tool section 62 . The limit ring 622 is also coaxially inserted with a connecting pipe 64, and the outer circumference of the limit ring 622 is also threaded with a locking bolt 623. The axial direction of the locking bolt 623 is perpendicular to the axial direction of the limit ring 622 and the locking bolt 623 One end extends into the cavity of the limit ring 622 and is pressed against the outer circumference of the connecting pipe 64 to realize the limit of the connecting pipe 64 .

S2:场地平整以及灌注桩5放线定位。S2: The site is leveled and the cast-in-situ pile 5 is set out and positioned.

灌注桩5桩位放线定位时,使用全站仪进行轴线引测,以保证桩心定位准确,为便于施工过程中桩心位置的校核,再由桩中心引出4个方向控制点,测定桩位后,做好标识,并注意保护,以便施工过程中随时复核桩位,保持桩位的准确性。When setting out and positioning the 5 pile positions of cast-in-place piles, use the total station to conduct axis measurement to ensure the accurate positioning of the pile core. After the piles are located, mark them well and pay attention to protection, so that the pile locations can be checked at any time during the construction process to maintain the accuracy of the pile locations.

场地排平整后在施工区域浇筑加固垫层3,加固垫层3内设置有钢筋网,以对施工区域周围土体进行硬化,减少后续施工时桩位附近土体产生不均匀沉降。加固垫层3还开设有穿孔,用于供后续护筒4穿设。After the site is leveled, a reinforcement cushion 3 is poured in the construction area. A reinforcement mesh is arranged in the reinforcement cushion 3 to harden the soil around the construction area and reduce uneven settlement of the soil near the pile during subsequent construction. The reinforcement pad 3 is also provided with perforations for the subsequent casing 4 to pass through.

S3:灌注桩5桩位钻孔施工:插打护筒4并清除护筒4内废土;具体操作如下:S3: Drilling construction of cast-in-place pile 5: insert and drill the casing 4 and remove the waste soil in the casing 4; the specific operations are as follows:

S3.1:在加固垫层3上安装全回转钻机。S3.1: Install the azimuth drilling rig on the reinforced cushion 3.

S3.2:通过全回转钻机将护筒4打入地面;护筒4埋设完成后,采用超声波测壁仪检测护筒4垂直度。S3.2: Drive the casing 4 into the ground with a full-turn drilling rig; after the casing 4 is buried, use an ultrasonic wall measuring instrument to detect the verticality of the casing 4.

S3.3:通过旋挖钻机挖除护筒4内土体,在本实施例中,旋挖钻机为中联重科ZR400L旋挖钻机。S3.3: Excavate the soil inside the casing 4 with a rotary drilling rig. In this embodiment, the rotary drilling rig is a Zoomlion ZR400L rotary drilling rig.

S3.4:土体挖除后对护筒4内进行清孔处理,清孔方法采用气体反循环方法将孔底沉渣清出。S3.4: After the soil is excavated, clean the hole in the casing 4. The hole cleaning method adopts the gas reverse circulation method to clear out the sediment at the bottom of the hole.

S3.5:拆除全回转钻机。S3.5: Dismantle the azimuth drilling rig.

S4:灌注桩5施工:往护筒4内放入钢筋笼并灌入混凝土形成灌注桩5。本工程灌注桩5采用超缓凝混凝土进行浇筑,灌注过程连续紧凑进行,避免钢管柱6安装过程中混凝土出现初凝,导致后续钢管柱6无法安装,造成废桩的风险。S4: Construction of the cast-in-place pile 5: Put a reinforcement cage into the casing 4 and pour concrete to form the cast-in-place pile 5 . The cast-in-situ pile 5 of this project is poured with ultra-retarded concrete, and the pouring process is carried out continuously and compactly, so as to avoid the initial setting of the concrete during the installation of the steel pipe column 6, resulting in the inability to install the subsequent steel pipe column 6, resulting in the risk of pile waste.

S5:安装驱动调节机构1并校核调整驱动调节机构1的安装位置,使主通孔121与副通孔111两者轴线与护筒4轴线重合。S5: Install the drive adjustment mechanism 1 and check and adjust the installation position of the drive adjustment mechanism 1 so that the axes of the main through hole 121 and the auxiliary through hole 111 coincide with the axis of the casing 4 .

S6:在灌注桩5初凝前,将钢管柱6插入至护筒4内并使钢管柱6基本对中;具体操作步骤如下:S6: Before the initial setting of the cast-in-place pile 5, insert the steel pipe column 6 into the casing 4 and make the steel pipe column 6 basically centered; the specific operation steps are as follows:

S6.1:通过推车将钢管柱6运输至施工现场。S6.1: Transport the steel pipe column 6 to the construction site by cart.

S6.2:在钢管柱6的工具节62顶端外周焊接两组驱动杆620,在本实施例中,驱动杆620为螺纹钢筋。S6.2: Weld two sets of driving rods 620 on the outer periphery of the top end of the tool joint 62 of the steel pipe column 6 , in this embodiment, the driving rods 620 are threaded steel bars.

S6.3:在工具节62内腔顶部焊接固定板并在固定板上安装倾角传感器626;S6.3: Weld a fixed plate on the top of the inner cavity of the tool section 62 and install an inclination sensor 626 on the fixed plate;

S6.4:通过履带吊将钢管柱6吊入至护筒4内。S6.4: Lift the steel pipe column 6 into the casing 4 by a crawler crane.

S6.5:在钢管柱6下移护筒4内;通过连接管64往标准节61内注入清水以增加钢管柱6自重。S6.5: Move down the steel pipe column 6 into the casing 4; inject clean water into the standard section 61 through the connecting pipe 64 to increase the self-weight of the steel pipe column 6 .

S7:牛腿63位置定位:配合全站仪,通过两组驱动杆620转动钢管柱6,直至将钢管柱6外周的牛腿63移动至指定安装位置。S7: Positioning of the corbel 63: Cooperate with the total station, rotate the steel pipe column 6 through two sets of driving rods 620 until the corbel 63 on the outer periphery of the steel pipe column 6 is moved to the designated installation position.

在牛腿63位置调节完成后,将倾角传感器626与倾斜显示仪电性连接;驱使若干主千斤顶122与副千斤顶112的活塞杆与工具节62抵紧;配合全站仪,通过控制主千斤顶122与副千斤顶112活塞杆伸缩以校核调整钢管柱6的垂直度与桩位偏差。同时记录此时倾角传感器626反馈至倾斜显示仪的数据作为钢管柱6的垂直度初始值。After the adjustment of the position of the corbel 63 is completed, the inclination sensor 626 is electrically connected to the tilt display; the piston rods of several main jacks 122 and auxiliary jacks 112 are driven against the tool joint 62; With auxiliary jack 112 piston rod telescopic to check and adjust the verticality and pile position deviation of steel pipe column 6. At the same time, the data fed back to the tilt display by the inclination sensor 626 at this time is recorded as the initial value of the verticality of the steel pipe column 6 .

S8:钢管柱6定位:通过驱动调节机构1将钢管柱6的标准节61插入灌注桩5顶端至指定深度;配合全站仪通过驱动调节机构1校核调整钢管柱6的垂直度与桩位偏差;具体操作步骤如下:S8: Positioning of the steel pipe column 6: insert the standard joint 61 of the steel pipe column 6 into the top of the cast-in-place pile 5 to the specified depth through the drive adjustment mechanism 1; check and adjust the verticality and pile position of the steel pipe column 6 through the drive adjustment mechanism 1 with the total station Deviation; the specific operation steps are as follows:

S8.1:驱使主千斤顶122的活塞杆与工具节62外周抵紧,同时驱使副千斤顶112活塞杆远离工具节62。S8.1: Drive the piston rod of the main jack 122 against the outer circumference of the tool joint 62 , and drive the piston rod of the auxiliary jack 112 away from the tool joint 62 at the same time.

S8.2:通过升降组件13驱使顶板12带动钢管柱6下移。S8.2: The top plate 12 is driven by the lifting assembly 13 to drive the steel pipe column 6 to move down.

S8.3:驱使副千斤顶112活塞杆抵紧工具节62,然后驱使主千斤顶122活塞杆远离工具节62。S8.3: Drive the piston rod of the auxiliary jack 112 against the tool section 62 , and then drive the piston rod of the main jack 122 away from the tool section 62 .

S8.4:升降组件13带动顶板12上移复位;S8.4: The lifting component 13 drives the top plate 12 to move up and reset;

S8.5:重复步骤S8.1至S8.4,直至将钢管柱6下插至设计标深。S8.5: Repeat steps S8.1 to S8.4 until the steel pipe column 6 is lowered to the design depth.

S8.6:钢管柱6插入至设计标深后,重新校核钢管柱6的垂直度与桩位偏差,校核时先通过驱使若干主千斤顶122与副千斤顶112的活塞杆均与工具节62抵接;配合全站仪,通过控制主千斤顶122与副千斤顶112活塞杆伸缩以校核调整钢管柱6的垂直度与桩位偏差。S8.6: After the steel pipe column 6 is inserted to the design depth, re-check the verticality of the steel pipe column 6 and the pile position deviation. When checking, first drive the piston rods of several main jacks 122 and auxiliary jacks 112 to align with the tool joint 62 Butting; cooperate with the total station to check and adjust the verticality and pile position deviation of the steel pipe column 6 by controlling the expansion and contraction of the piston rods of the main jack 122 and the auxiliary jack 112.

驱动调节机构1带动钢管柱6下插后,通过倾角传感器626反馈至倾斜显示仪的数据实时监控钢管柱6的垂直度,若倾角传感器626反馈至倾斜显示仪的数据与钢管柱6的垂直度初始值不同,则说明钢管柱6垂直度发生变化,施工人员可及时通过驱动调节机构1校核调整钢管柱6的垂直度。After driving the adjustment mechanism 1 to drive the steel pipe column 6 down, monitor the verticality of the steel pipe column 6 in real time through the data fed back to the inclination display by the inclination sensor 626. If the initial values are different, it means that the verticality of the steel pipe column 6 changes, and the construction personnel can check and adjust the verticality of the steel pipe column 6 by driving the adjustment mechanism 1 in time.

S9:往钢管柱6的标准节61内注入混凝土并进行养护;注入混凝土时,驱使若干主千斤顶122与副千斤顶112的活塞杆抵紧钢管柱6的工具节62,实现对钢管柱6的限位。具体操作步骤如下:S9: Inject concrete into the standard section 61 of the steel pipe column 6 and perform curing; when injecting concrete, drive the piston rods of several main jacks 122 and auxiliary jacks 112 against the tool section 62 of the steel pipe column 6 to realize the restraint of the steel pipe column 6 bit. The specific operation steps are as follows:

S9.1:通过连接管64将标准节61内的清水抽出。S9.1: Pump out the clean water in the standard section 61 through the connecting pipe 64.

S9.2:通过连接管64往标准节61内注入混凝土,混凝土注入过程中,拧松锁紧螺栓623并逐步上移连接管64。值得注意的是,钢管柱6混凝土的浇筑应待灌注桩5混凝土凝结强度达到25%(约24小时)后,再对钢管柱6内进行混凝土浇筑,减少浇筑混凝土造成钢管柱6下沉,影响钢管最终定位的准确性。S9.2: Inject concrete into the standard section 61 through the connecting pipe 64. During the concrete injection process, loosen the locking bolt 623 and move the connecting pipe 64 up gradually. It is worth noting that the concrete pouring of the steel pipe column 6 should wait until the concrete setting strength of the cast-in-situ pile 5 reaches 25% (about 24 hours), and then pour concrete into the steel pipe column 6 to reduce the sinking of the steel pipe column 6 caused by pouring concrete. The accuracy of the final positioning of the steel pipe.

S9.3:将连接管64从限位环622上抽出后,将振捣棒从限位环622内插入并下移至标准节61内对标准节61内的混凝土进行振捣。S9.3: After pulling out the connecting pipe 64 from the limiting ring 622, insert the vibrating rod from the limiting ring 622 and move it down to the standard section 61 to vibrate the concrete in the standard section 61.

S9.4:对标准节61内混凝土进行养护。S9.4: Carry out curing to the concrete in standard section 61.

S10:往钢管柱6与护筒4之间的间隙回填填料;在本实施例中,填料为中砂。回填需要在灌注桩5混凝土的凝结强度达50%后进行。回填后应及时往填料内注水使其密实。S10: Backfilling the gap between the steel pipe column 6 and the casing 4 with filler; in this embodiment, the filler is medium sand. Backfilling needs to be carried out after the setting strength of concrete in cast-in-situ pile 5 reaches 50%. After backfilling, water should be injected into the filler in time to make it compact.

回填前,驱使主千斤顶122与副千斤顶112的活塞杆与工具节62抵紧。同时回填前在工具节62伸出护筒4外一端的外周均匀环绕焊接固定支撑环,并往支撑环内插入注射管,通过若干注射管同时往护筒4与钢管柱6之间的间隙注入填料。便于均匀往钢管柱6与护筒4之间的间隙注入填料,有利于避免回填填料时因填料回填不均匀导致钢管柱6一侧压力过大造成钢管柱6偏位的情况;同时后续填料回填后,还可通过注射管往填料内注水。Before backfilling, the piston rods of the main jack 122 and the auxiliary jack 112 are pressed against the tool joint 62 . At the same time, before backfilling, the outer circumference of the outer end of the tool section 62 protruding from the casing 4 is uniformly welded around the fixed support ring, and the injection pipe is inserted into the support ring, and injected into the gap between the casing 4 and the steel pipe column 6 through several injection pipes. filler. It is convenient to evenly inject filler into the gap between the steel pipe column 6 and the casing 4, which is beneficial to avoid the deviation of the steel pipe column 6 caused by the excessive pressure on one side of the steel pipe column 6 due to uneven backfilling when backfilling the filler; at the same time, the subsequent filler backfill Finally, water can also be injected into the filler through the injection tube.

本申请在浇筑完灌注桩5的混凝土后,便可将钢管柱6吊入至护筒4内,经由调节驱动机构对钢管柱6进行下插至指定深度并校核调整钢管柱的垂直度与桩位偏差后便可实现钢管柱6固定在灌注桩5顶端,无需等待灌注桩5凝结完成后再进行钢管柱6的施工,使得钢管柱6的安装更加简单方便。After pouring the concrete of the cast-in-place pile 5, the application can hoist the steel pipe column 6 into the casing 4, insert the steel pipe column 6 to the specified depth through the adjustment drive mechanism, and check and adjust the verticality of the steel pipe column. After the pile position deviates, the steel pipe column 6 can be fixed on the top of the cast-in-place pile 5, and there is no need to wait for the cast-in-situ pile 5 to solidify before carrying out the construction of the steel pipe column 6, which makes the installation of the steel pipe column 6 easier and more convenient.

以上均为本申请的较佳实施例,并非依此限制本申请的保护范围,故:凡依本申请的结构、形状、原理所做的等效变化,均应涵盖于本申请的保护范围之内。All of the above are preferred embodiments of the application, and are not intended to limit the protection scope of the application. Therefore, all equivalent changes made according to the structure, shape, and principle of the application should be covered by the protection scope of the application. Inside.

Claims (8)

1. A construction method for a cover-excavation reverse-acting permanent steel pipe column is characterized by comprising the following steps of: the method comprises the following steps:
s1: the steel pipe column (6) comprises a standard section (61) and a tool section (62) coaxially connected to the top end of the standard section (61), a plurality of connecting nodes are arranged on the standard section (61) along the length direction, and each connecting node comprises a plurality of brackets (63) uniformly encircling the periphery of the standard section (61);
s2: leveling the site and paying-off and positioning the pile position of the cast-in-place pile (5);
s3: drilling construction of pile positions of cast-in-place piles (5): inserting and beating the protective cylinder (4) and removing waste soil in the protective cylinder (4);
s4: pouring construction of the cast-in-place pile (5): placing a reinforcement cage into the pile casing (4) and injecting concrete to form a cast-in-place pile (5);
s5: installing a driving adjustment mechanism (1) and checking and adjusting the installation position of the driving adjustment mechanism (1) to enable the axes of the main through hole (121) and the auxiliary through hole (111) to coincide with the axis of the protective cylinder (4);
s6: before the initial setting of the filling pile (5), the steel pipe column (6) is inserted into the pile casing (4) and the steel pipe column (6) is basically centered;
s7: bracket (63) position location: rotating the steel pipe column (6) until the bracket (63) on the periphery of the steel pipe column (6) is moved to a specified mounting position;
s8: positioning a steel pipe column (6): the standard section (61) of the steel pipe column (6) is inserted into the top end of the filling pile (5) to a specified depth by driving the adjusting mechanism (1); matching with a total station and checking and adjusting the verticality and pile position deviation of the steel pipe column (6) through a driving and adjusting mechanism (1);
s9: injecting concrete into the standard section (61) and curing;
s10: backfilling filler into the gap between the standard joint (61) and the protective cylinder (4);
the driving and adjusting mechanism (1) comprises a bottom plate (11) and a top plate (12) erected on the bottom plate (11), and a lifting assembly (13) for driving the top plate (12) to lift is arranged on the bottom plate (11); a main through hole (121) and a secondary through hole (111) for the steel pipe column (6) to penetrate are respectively formed in the top plate (12) and the bottom plate (11); the top plate (12) and the bottom plate (11) are respectively provided with a main clamping assembly and a secondary clamping assembly; the main clamping assembly comprises a plurality of main jacks (122) arranged on the top plate (12), the main jacks (122) are arranged around the main through holes (121), and the axial directions of the main jacks (122) are all perpendicular to the axial directions of the main through holes (121); the auxiliary clamping assembly comprises a plurality of auxiliary jacks (112) arranged on the bottom plate (11), the auxiliary jacks (112) are arranged around the auxiliary through holes (111), and the axial directions of the auxiliary jacks (112) are all perpendicular to the axial directions of the auxiliary through holes (111).
2. The construction method of the cover-excavation reverse-acting permanent steel pipe column according to claim 1, wherein the construction method comprises the following steps: the bottom end of the standard joint (61) is in an inverted cone shape, and the bottom end of the standard joint (61) is plugged.
3. The construction method of the cover-excavation reverse-acting permanent steel pipe column according to claim 1, wherein the construction method comprises the following steps: in step S2, after the site leveling, a reinforcing cushion layer (3) is poured on the area to be constructed, a reinforcing mesh is arranged in the reinforcing cushion layer (3), and the reinforcing cushion layer (3) is also provided with a perforation for the protective cylinder (4) to penetrate.
4. The construction method of the cover-excavation reverse-acting permanent steel pipe column according to claim 2, wherein the construction method comprises the following steps: in the step S6, after the steel pipe column (6) is moved down into the pile casing (4), water is injected into the standard knot (61) to lift the whole weight of the steel pipe column (6);
in step 9, water in the standard joint (61) is pumped out before concrete is poured into the standard joint (61).
5. The construction method of the cover-excavation reverse-acting permanent steel pipe column according to claim 4, wherein the construction method comprises the following steps: the tool joint (62) is also coaxially provided with a limiting ring (622), a connecting pipe (64) is coaxially inserted into the limiting ring (622), and the bottom end of the connecting pipe (64) extends to the bottom end of the standard joint (61); the locking bolt (623) is arranged on the periphery of the limiting ring (622) in a threaded manner, and one end of the locking bolt (623) is abutted against the periphery of the connecting pipe (64).
6. The construction method of the cover-excavation reverse-acting permanent steel pipe column according to claim 5, wherein the construction method comprises the following steps: the utility model discloses a tool joint, including standard festival (61), tool joint (62), main go-between (66) and auxiliary connection ring (65) are provided with respectively to standard festival (61) and tool joint (62) one end that is close to each other, main go-between (66) coaxial fixation is in standard festival (61) inner chamber, auxiliary connection ring (65) coaxial fixation is in tool joint (62) inner chamber, main go-between (66) are connected through a plurality of bolt and nut pair with auxiliary connection ring (65), tool joint (62) inner chamber still is provided with cat ladder (624).
7. The construction method of the cover-excavation reverse-acting permanent steel pipe column according to claim 1, wherein the construction method comprises the following steps: in step S6, a plurality of driving rods (620) are welded to the top end of the tool joint (62) before the steel pipe column (6) is suspended in the casing (4).
8. The construction method of the cover-excavation reverse-acting permanent steel pipe column according to claim 1, wherein the construction method comprises the following steps: in step S6, before the steel pipe column (6) is hung into the pile casing (4), an inclination sensor (626) is installed at the top end of the tool section (62); electrically connecting an inclination sensor (626) with the inclination display;
in the step S7, after the position adjustment of the bracket (63) is completed, the total station is matched, the verticality of the steel pipe column (6) is corrected and adjusted through the adjusting driving mechanism, and the data fed back to the inclination angle sensor (626) at the moment is calibrated and recorded as the initial value of the verticality;
in step S8, the driving adjustment mechanism (1) monitors the verticality of the steel pipe column (6) during the insertion process by feeding back the data to the tilt indicator through the tilt sensor (626) during the downward movement of the steel pipe column (6).
CN202211491345.2A 2022-11-25 2022-11-25 A Construction Method for Covering and Excavating Permanent Steel Pipe Columns Pending CN116145723A (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN202211491345.2A CN116145723A (en) 2022-11-25 2022-11-25 A Construction Method for Covering and Excavating Permanent Steel Pipe Columns

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN202211491345.2A CN116145723A (en) 2022-11-25 2022-11-25 A Construction Method for Covering and Excavating Permanent Steel Pipe Columns

Publications (1)

Publication Number Publication Date
CN116145723A true CN116145723A (en) 2023-05-23

Family

ID=86339739

Family Applications (1)

Application Number Title Priority Date Filing Date
CN202211491345.2A Pending CN116145723A (en) 2022-11-25 2022-11-25 A Construction Method for Covering and Excavating Permanent Steel Pipe Columns

Country Status (1)

Country Link
CN (1) CN116145723A (en)

Cited By (2)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN116950063A (en) * 2023-06-27 2023-10-27 中铁十四局集团有限公司 Pile-column integrated construction process in subway station by hole pile method
CN118933041A (en) * 2024-10-15 2024-11-12 杭州江润科技有限公司 Rotary drilling and hole pouring concrete embedded rock locking steel pipe pile cofferdam and construction method

Citations (5)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JP2004162370A (en) * 2002-11-13 2004-06-10 Takenaka Komuten Co Ltd Steel pipe structural permanent column erection method
CN104141301A (en) * 2014-03-25 2014-11-12 中国建筑第四工程局有限公司 Construction method and structure for mounting reverse-construction steel pipe column in rotary drilled pile hole
CN212984357U (en) * 2020-07-08 2021-04-16 天津广原基础工程有限公司 Post-cast steel pipe column for top-down construction and primary and secondary column hoisting system
CN112900450A (en) * 2021-01-20 2021-06-04 深圳市工勘岩土集团有限公司 Rotary drilling and full-rotation combined back-inserting method positioning method for steel pipe structure pile by reverse construction method
CN114775586A (en) * 2022-04-20 2022-07-22 深圳市工勘岩土集团有限公司 A kind of foundation pit reverse method rotary excavation and bottom expansion, full rotation positioning construction method

Patent Citations (5)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JP2004162370A (en) * 2002-11-13 2004-06-10 Takenaka Komuten Co Ltd Steel pipe structural permanent column erection method
CN104141301A (en) * 2014-03-25 2014-11-12 中国建筑第四工程局有限公司 Construction method and structure for mounting reverse-construction steel pipe column in rotary drilled pile hole
CN212984357U (en) * 2020-07-08 2021-04-16 天津广原基础工程有限公司 Post-cast steel pipe column for top-down construction and primary and secondary column hoisting system
CN112900450A (en) * 2021-01-20 2021-06-04 深圳市工勘岩土集团有限公司 Rotary drilling and full-rotation combined back-inserting method positioning method for steel pipe structure pile by reverse construction method
CN114775586A (en) * 2022-04-20 2022-07-22 深圳市工勘岩土集团有限公司 A kind of foundation pit reverse method rotary excavation and bottom expansion, full rotation positioning construction method

Non-Patent Citations (2)

* Cited by examiner, † Cited by third party
Title
刘宗仁: "土木工程施工", 28 February 2003, 高等教育出版社, pages: 58 *
郑宏伟: "拱桥缆索吊装施工安全技术", 31 August 2019, 武汉理工大学出版社, pages: 58 - 59 *

Cited By (2)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN116950063A (en) * 2023-06-27 2023-10-27 中铁十四局集团有限公司 Pile-column integrated construction process in subway station by hole pile method
CN118933041A (en) * 2024-10-15 2024-11-12 杭州江润科技有限公司 Rotary drilling and hole pouring concrete embedded rock locking steel pipe pile cofferdam and construction method

Similar Documents

Publication Publication Date Title
CN108086340B (en) Open caisson construction structure and construction method thereof
CN103195076B (en) Muddy Bottoms deep-excavation tower crane foundation construction method
CN111962504A (en) Construction method for covering and digging top-down permanent steel pipe column
CN116145723A (en) A Construction Method for Covering and Excavating Permanent Steel Pipe Columns
CN114108624A (en) Two-adjustment one-control type perpendicularity control construction method for one-column one-pile steel pipe column
CN114134928B (en) Construction method of steel pipe column tower crane foundation
CN114737602A (en) Positioning method of concrete-filled steel tubular central column for cover excavation of subway station
CN114837213A (en) Tower crane foundation structure and construction method thereof
CN111945714B (en) Steel sleeve guiding method combined with steel upright column inserting construction method
JPH0464620A (en) Construction method for open caisson and its device
CN115573378A (en) Bearing platform construction method
CN114718053A (en) Method for installing and positioning foundation pit steel stand column by reverse construction method and installation structure
CN217870505U (en) Excavation supporting construction of tunnel top foundation ditch excavation
CN116044150B (en) A construction method for structural columns in reserved soil platform
CN218148483U (en) Tower crane foundation structure
CN115387328B (en) Beach cast-in-place pile construction method based on ultra-long spiral drilling machine
CN117846021A (en) Rear-insertion steel pipe column positioning and verticality adjusting device in reverse construction method and construction method thereof
CN116905726A (en) Reverse construction method steel pipe column installation method
CN114775586A (en) A kind of foundation pit reverse method rotary excavation and bottom expansion, full rotation positioning construction method
CN111877315B (en) Partial prefabricated ground connecting wall guide wall under underground facility and construction method
CN115324105A (en) A kind of cover and excavation reverse method permanent steel pipe column positioning and vertical adjustment device and construction method
CN116163295A (en) Low-clearance full-pile casing bored pile construction method
JP6792239B2 (en) Scuttling prevention device for steel pipe piles and scuttling prevention method
JP2858998B2 (en) Construction method of temporary supporting column for reverse driving method
CN221053224U (en) High-precision control device for spatial posture based on reverse method of embedded column installation

Legal Events

Date Code Title Description
PB01 Publication
PB01 Publication
SE01 Entry into force of request for substantive examination
SE01 Entry into force of request for substantive examination
CB03 Change of inventor or designer information

Inventor after: Zhu Zhenhua

Inventor after: Fang Zishan

Inventor after: Zhao Gang

Inventor after: Han Gang

Inventor after: Guo Jilu

Inventor after: Shen Kaifei

Inventor after: Lu Kai

Inventor after: Wang Jiejun

Inventor after: Wang Baicheng

Inventor after: Li Xinyun

Inventor after: Gong Wenbo

Inventor before: Wu Dong

Inventor before: Gong Wenbo

Inventor before: Zhu Zhenhua

Inventor before: Liu Xiaotao

Inventor before: Guo Jilu

Inventor before: Lu Kai

Inventor before: Wang Baicheng

Inventor before: Wang Jiejun

Inventor before: Li Xinyun

Inventor before: Fang Zishan

CB03 Change of inventor or designer information