CN116220807A - Support rod and airtight wall - Google Patents
Support rod and airtight wall Download PDFInfo
- Publication number
- CN116220807A CN116220807A CN202310344378.2A CN202310344378A CN116220807A CN 116220807 A CN116220807 A CN 116220807A CN 202310344378 A CN202310344378 A CN 202310344378A CN 116220807 A CN116220807 A CN 116220807A
- Authority
- CN
- China
- Prior art keywords
- support
- rod body
- elastic member
- rod
- support plate
- Prior art date
- Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
- Pending
Links
Images
Classifications
-
- E—FIXED CONSTRUCTIONS
- E21—EARTH OR ROCK DRILLING; MINING
- E21F—SAFETY DEVICES, TRANSPORT, FILLING-UP, RESCUE, VENTILATION, OR DRAINING IN OR OF MINES OR TUNNELS
- E21F17/00—Methods or devices for use in mines or tunnels, not covered elsewhere
- E21F17/103—Dams, e.g. for ventilation
Landscapes
- Engineering & Computer Science (AREA)
- Mining & Mineral Resources (AREA)
- Life Sciences & Earth Sciences (AREA)
- General Life Sciences & Earth Sciences (AREA)
- Geochemistry & Mineralogy (AREA)
- Geology (AREA)
- Road Signs Or Road Markings (AREA)
Abstract
Description
技术领域technical field
本公开涉及煤矿安全施工技术领域,具体地,涉及一种支撑杆和密闭墙。The disclosure relates to the technical field of coal mine safety construction, in particular, to a support rod and a closed wall.
背景技术Background technique
煤矿井下临时密闭墙构筑是双巷开采的高效煤矿在井下生产中必不可少的一项技术,在控制通风、阻隔采空区瓦斯和一氧化碳等有害气体的过程中均起到重要的作用。其中,在相关技术中煤矿井下临时密闭墙构筑可以是通过若干的金属杆搭建形成密闭墙的骨架,在将密封布布设在密闭墙骨架上,最终形成煤矿井下临时密闭墙构筑,通过若干的金属杆搭建形成密闭墙的骨架时,为了保证密闭墙骨架的整体稳定性,可以将金属杆的端部部分插入至煤矿巷道壁内,采用这种固定方式可能会对巷道壁造成损坏,存在安全隐患。The construction of temporary airtight walls in coal mines is an indispensable technology in the underground production of high-efficiency coal mines with double lane mining. It plays an important role in the process of controlling ventilation and blocking harmful gases such as gas and carbon monoxide in gobs. Among them, in the related art, the construction of the temporary airtight wall under the coal mine can be constructed by a number of metal rods to form the skeleton of the airtight wall; When the poles are built to form the skeleton of the closed wall, in order to ensure the overall stability of the closed wall skeleton, the end part of the metal rod can be inserted into the coal mine roadway wall. This fixing method may cause damage to the roadway wall and pose a safety hazard .
发明内容Contents of the invention
本公开的目的是提供一种支撑杆和密闭墙,可以避免在巷道的内壁面上开孔以供杆体插入,从而可以减少甚至避免对巷道造成损坏通过若干支撑杆搭建形成的密闭墙骨架可以稳定的支撑在巷道内,且减少对巷道壁的损坏,以至少部分地解决上述技术问题。The purpose of the present disclosure is to provide a support rod and an airtight wall, which can avoid opening holes on the inner wall of the roadway for rod insertion, thereby reducing or even avoiding damage to the roadway. The skeleton of the airtight wall formed by several support rods can be stabilized The support is in the roadway, and the damage to the roadway wall is reduced, so as to at least partly solve the above-mentioned technical problems.
为了实现上述目的,本公开的第一方面提供一种支撑杆,包括:In order to achieve the above object, the first aspect of the present disclosure provides a support rod, comprising:
杆体;和rod body; and
支撑机构,包括第一支撑组件和第二支撑组件,所述第一支撑组件通过第一弹性件连接在所述杆体的第一端,所述第二支撑组件安装在所述杆体的背离所述第一弹性件的第二端,所述第一弹性件用于使得所述第一支撑组件和所述第二支撑组件各自抵接于巷道的内壁面,以使得所述杆体支撑在所述巷道内。The support mechanism includes a first support assembly and a second support assembly, the first support assembly is connected to the first end of the rod body through a first elastic member, and the second support assembly is installed on the rod body away from the The second end of the first elastic member, the first elastic member is used to make the first support assembly and the second support assembly abut against the inner wall surface of the roadway, so that the rod body is supported on the roadway Inside.
可选地,所述杆体构造为空心管体,所述第一支撑组件包括第一支撑板和导向柱,所述导向柱的一端固连于所述第一支撑板,另一端可移动地插接于所述杆体,所述第一弹性件抵接在所述杆体与所述第一支撑板之间,所述第一支撑板用于直接或间接抵接于所述巷道的内壁面。Optionally, the rod body is configured as a hollow pipe, the first support assembly includes a first support plate and a guide column, one end of the guide column is fixedly connected to the first support plate, and the other end is movably inserted into the first support plate. Connected to the rod body, the first elastic member abuts between the rod body and the first support plate, and the first support plate is used to directly or indirectly abut against the inner wall surface of the tunnel.
可选地,所述杆体的朝向所述第一弹性件的一端设有第一止挡件,所述第一弹性件抵接在所述第一止挡件与所述第一支撑板之间。Optionally, one end of the rod body facing the first elastic member is provided with a first stopper, and the first elastic member abuts between the first stopper and the first support plate .
可选地,所述第一弹性件套接在所述导向柱上,所述第一支撑组件还包括套接在所述第一弹性件外侧的第二弹性件,所述第二弹性件的一端固连于所述第一支撑板,所述第二弹性件的另一端用于抵接于所述第一止挡件。Optionally, the first elastic member is sleeved on the guide column, and the first support assembly further includes a second elastic member sleeved on the outside of the first elastic member, and the second elastic member is One end is fixedly connected to the first support plate, and the other end of the second elastic member is used to abut against the first stopper.
可选地,所述第一弹性件与所述第二弹性件均构造为弹簧,所述第二弹性件的弹力大于所述第一弹性件的弹力。Optionally, both the first elastic member and the second elastic member are configured as springs, and the elastic force of the second elastic member is greater than that of the first elastic member.
可选地,所述第一支撑板背离所述导向柱一端的端面上设有第一柔性垫片。Optionally, a first flexible gasket is provided on the end surface of the first support plate away from the end of the guide column.
可选地,所述第二支撑组件包括第二支撑板、螺杆以及螺纹连接在所述螺杆上的螺母,所述螺杆的一端固连于所述第一支撑板,另一端可移动地插接于所述杆体,所述杆体的第二端设有用以抵接所述螺母的第二止挡件,所述第二支撑板用于直接或间接抵接于所述巷道的内壁面。Optionally, the second support assembly includes a second support plate, a screw and a nut threadedly connected to the screw, one end of the screw is fixedly connected to the first support plate, and the other end is movably inserted into the On the rod body, the second end of the rod body is provided with a second stopper for abutting against the nut, and the second support plate is for directly or indirectly abutting against the inner wall of the tunnel.
可选地,所述第二支撑板背离所述螺杆一端的端面上设有第二柔性垫片。Optionally, a second flexible gasket is provided on the end surface of the second support plate away from the end of the screw rod.
本公开的第二方面还提供一种密闭墙,包括:The second aspect of the present disclosure also provides an airtight wall, comprising:
骨架,所述骨架包括沿竖直方向延伸且沿水平方向间隔布置的多根纵向支撑杆以及沿水平方向延伸且沿竖直方向间隔布置的多根横向支撑杆,所述纵向支撑杆和/或所述横向支撑杆采用如上所述的支撑杆;以及A skeleton, the skeleton includes a plurality of longitudinal support rods extending in the vertical direction and arranged at intervals in the horizontal direction, and a plurality of transverse support rods extending in the horizontal direction and arranged at intervals in the vertical direction, the longitudinal support rods and/or The transverse support rod adopts the above-mentioned support rod; and
密封布,所述密封布铺设在所述骨架上。Sealing cloth, the sealing cloth is laid on the skeleton.
可选地,所述纵向支撑杆和所述横向支撑杆的交叉处通过固定件连接。Optionally, intersections of the longitudinal support rods and the lateral support rods are connected by a fixing piece.
通过上述技术方案,通过若干根支撑杆搭接形成密闭墙的骨架,其中,设置在杆体第一端的第一支撑组件与设置在杆体第二端的第二支撑组件可以通过第一弹性件各自抵接于巷道的内壁面,由此可以避免在巷道的内壁面上开孔以供杆体插入,从而可以减少甚至避免对巷道造成损坏并且不会对巷道壁造成损坏。Through the above technical solution, several support rods are overlapped to form the skeleton of the airtight wall, wherein the first support assembly arranged at the first end of the rod body and the second support assembly arranged at the second end of the rod body can respectively resist each other through the first elastic member Connected to the inner wall of the roadway, thereby avoiding opening holes on the inner wall of the roadway for rod insertion, thereby reducing or even avoiding damage to the roadway without causing damage to the roadway wall.
本公开的其他特征和优点将在随后的具体实施方式部分予以详细说明。Other features and advantages of the present disclosure will be described in detail in the detailed description that follows.
附图说明Description of drawings
附图是用来提供对本公开的进一步理解,并且构成说明书的一部分,与下面的具体实施方式一起用于解释本公开,但并不构成对本公开的限制。在附图中:The accompanying drawings are used to provide a further understanding of the present disclosure, and constitute a part of the description, together with the following specific embodiments, are used to explain the present disclosure, but do not constitute a limitation to the present disclosure. In the attached picture:
图1是本公开示例性实施方式中提供的支撑架整体的结构示意图;FIG. 1 is a schematic diagram of the overall structure of a support frame provided in an exemplary embodiment of the present disclosure;
图2是本公开示例性实施方式中提供的杆体的结构示意图;Fig. 2 is a schematic structural view of a rod body provided in an exemplary embodiment of the present disclosure;
图3是本公开示例性实施方式中提供的第二支撑组件的结构示意图;Fig. 3 is a schematic structural diagram of a second support assembly provided in an exemplary embodiment of the present disclosure;
图4是本公开示例性实施方式中提供的第一支撑组件的结构示意图;Fig. 4 is a schematic structural diagram of a first support assembly provided in an exemplary embodiment of the present disclosure;
图5是本公开示例性实施方式中提供的密闭墙骨架的结构示意图。Fig. 5 is a schematic structural view of the airtight wall skeleton provided in the exemplary embodiment of the present disclosure.
附图标记说明Explanation of reference signs
1-杆体;2-支撑机构;201-第一支撑组件;2011-第一支撑板;2012-导向柱;202-第二支撑组件;2021-第二支撑板;2022-螺杆;2023-螺母;3-第一弹性件;4-第一止挡件;5-第二弹性件;6-第一柔性垫片;7-第二止挡件;8-第二柔性垫片;9-骨架;10-巷道。1-rod body; 2-support mechanism; 201-first support component; 2011-first support plate; 2012-guiding column; 202-second support component; 2021-second support plate; 2022-screw; 3-the first elastic member; 4-the first stopper; 5-the second elastic member; 6-the first flexible gasket; 7-the second stopper; 8-the second flexible gasket; 9-skeleton; 10 - Laneway.
具体实施方式Detailed ways
以下结合附图对本公开的具体实施方式进行详细说明。应当理解的是,此处所描述的具体实施方式仅用于说明和解释本公开,并不用于限制本公开。Specific embodiments of the present disclosure will be described in detail below in conjunction with the accompanying drawings. It should be understood that the specific embodiments described here are only used to illustrate and explain the present disclosure, and are not intended to limit the present disclosure.
在本公开中,在未作相反说明的情况下,“内、外”是指相应零部件的本身轮廓而言的,此外,本公开中使用的术语“第一”、“第二”等是为了区别一个要素和另一个要素,不具有顺序性和重要性。下面的描述涉及附图时,除非另有表示,不同附图中的相同数字表示相同或相似的要素。In the present disclosure, unless stated otherwise, "inner and outer" refer to the contours of the corresponding components. In addition, the terms "first", "second" and the like used in the present disclosure are To distinguish one element from another, without order or importance. When the following description refers to the accompanying drawings, the same numerals in different drawings refer to the same or similar elements unless otherwise indicated.
相关技术中,煤矿井下临时密闭墙构筑是双巷开采的高效煤矿在井下生产中必不可少的一项技术,在控制巷道通风、阻隔采空区瓦斯和一氧化碳等有害气体的过程中均起到重要的作用。其中,对于密闭墙的构建可以是通过若干的支撑杆搭建形成密闭墙的骨架,在将密封布布设在密闭墙骨架上,最终形成煤矿井下临时密闭墙,然而,在实际的施工过程中,人员为了提高密闭墙的整体稳定性,可以将支撑杆的两端均埋设至巷道壁内部,以使得密闭墙更牢固,但是,这种支撑杆的固定形式会对巷道壁造成损坏,存在有一定的安全隐患。Among related technologies, the construction of temporary airtight walls in coal mines is an indispensable technology in the underground production of high-efficiency coal mines mined with double lanes. important role. Among them, the construction of the airtight wall can be constructed by a number of support rods to form the skeleton of the airtight wall, and the sealing cloth is laid on the airtight wall skeleton to form a temporary airtight wall in the coal mine. However, in the actual construction process, personnel In order to improve the overall stability of the airtight wall, both ends of the support rods can be buried inside the roadway wall to make the airtight wall stronger. However, the fixing form of the support rods will cause damage to the roadway wall, and there are certain problems. Security risks.
基于此,本公开的第一方面提供一种支撑杆,参考图1所示,该支撑杆包括杆体1和支撑机构2,杆体1包括第一支撑组件201和第二支撑组件202,第一支撑组件201通过第一弹性件3连接在杆体1的第一端,第二支撑组件202安装在杆体1的背离第一弹性件3的第二端,第一弹性件3用于使得第一支撑组件201和第二支撑组件202各自抵接于巷道10的内壁面,以使得杆体1支撑在巷道10内。Based on this, the first aspect of the present disclosure provides a support rod. Referring to FIG. 1 , the support rod includes a
在本公开中,支撑杆的两端均不会埋设在巷道10内,尽可能地避免支撑杆对巷道10造成人为损坏。具体地,设置在杆体1两端的第一支撑组件201和第二支撑组件202各自抵接于巷道10的内壁面,可以通过第一弹性件3的弹力来实现支撑杆支撑在巷道10中。In the present disclosure, both ends of the support rods are not buried in the
在一些实施方式中,参考图2和图3所示,杆体1构造为空心管体,第一支撑组件201包括第一支撑板2011和导向柱2012,导向柱2012的一端固连于第一支撑板2011,另一端可移动地插接于杆体1,第一弹性件3抵接在杆体1与第一支撑板2011之间,第一支撑板2011用于直接或间接抵接于巷道10的内壁面。In some embodiments, as shown in FIG. 2 and FIG. 3 , the
在本公开中,第一支撑组件201包括第一支撑板2011和导向柱2012,并且杆体1构造为空心管体,导向柱2012的一端固连于第一支撑板2011,另一端可移动地插接于杆体1,第一弹性件3抵接在杆体1与第一支撑板2011之间,当对一根支撑杆进行安装,可以通过调节导向柱2012伸入杆体1内的长度,即,改变第一弹性件3的压缩量,来实现杆体1两端的第一支撑组件201和第二支撑组件202各自抵接于巷道10的内壁面。In the present disclosure, the
在本公开中,未安装在巷道10内的支撑杆的整体长度要大于巷道10的宽度或高度,即,在安装支撑杆时,需要将导向柱2012朝向第二支撑组件202一端移动,使得第一弹性件3被压缩,此时的支撑杆的整体长度要小于巷道10的宽度或高度,之后将支撑杆横置或竖直放置在巷道10内,随后可以使得导向柱2012在第一弹性件3的弹力作用下朝向背离第二支撑组件202的一端移动,当导向柱2012停止移动,即为完成一根支撑杆的安装,此时的第一弹性件3仍处于压缩状态。In the present disclosure, the overall length of the support rods not installed in the
在本公开中,参考图1和图4所示,当支撑杆固定在巷道10内后,第一支撑板2011可以直接抵接巷道10的内壁面,第一支撑板2011的构造可以是圆形垫板,第一支撑板2011的直径大于导向柱2012以及杆体1的直径,可以使得第一支撑板2011接触到的巷道10内壁面的面积更大,为杆体1提供良好地稳定性。In the present disclosure, as shown in FIG. 1 and FIG. 4 , when the support rod is fixed in the
在一些实施方式中,参考图1和图4所示,在本公开中,考虑到杆体1的管壁较薄,为了使得第一弹性件3与杆体1之间的接触更稳定,可以在杆体1的朝向第一弹性件3的一端设有第一止挡件4,通过第一止挡件4接触第一弹性件3。In some embodiments, as shown in FIG. 1 and FIG. 4 , in the present disclosure, considering that the tube wall of the
在本公开中,第一止挡件4可以选用法兰盘焊接在杆体1上。In the present disclosure, the
在一些实施方式中,参考图1和图4所示,第一弹性件3可以套接在导向柱2012上,并且为了使得支撑杆可以更牢固地设置在巷道10内,第一支撑组件201还包括套接在第一弹性件3外侧的第二弹性件5,并且第二弹性件5的一端固连于第一支撑板2011,第二弹性件5的另一端用于抵接于第一止挡件4,在第一弹性件3与第二弹性件5的共同作用下,支撑杆可以更牢固的设置在巷道10内。In some embodiments, as shown in FIG. 1 and FIG. 4 , the first
在一些实施方式中,参考图1和图4所示,在本公开中,第一弹性件3与第二弹性件5均构造为弹簧,且第二弹性件5的弹力大于第一弹性件3的弹力。In some embodiments, as shown in FIG. 1 and FIG. 4 , in the present disclosure, both the first
在一些实施方式中,参考图1和图4所示,在本公开中,可以在第一支撑板2011背离导向柱2012一端的端面上设有第一柔性垫片6,第一柔性垫片6可以采用橡胶材质的原料制成,增大第一支撑板2011与巷道10内壁面的摩擦力,使得支撑杆在安装后不易发生晃动,同时若巷道壁为强度较低的煤岩体的矿井壁时,杆体1两端的第一支撑组件201和第二支撑组件202朝向背离杆体1的方向挤压巷道壁仍存在损坏巷道壁的风险,因此,第一柔性垫片6还起到保护巷道壁的作用。In some implementations, as shown in FIG. 1 and FIG. 4 , in the present disclosure, a first
在一些实施方式中,参考图1至图3所示,第二支撑组件202包括第二支撑板2021、螺杆2022以及螺纹连接在螺杆2022上的螺母2023,螺杆2022的一端固连于第一支撑板2011,另一端可移动地插接于杆体1,杆体1的第二端设有用以抵接螺母2023的第二止挡件7,第二支撑板2021用于直接或间接抵接于巷道10的内壁面。In some embodiments, as shown in FIGS. 1 to 3 , the
在本公开中,第二止挡件7可以选用法兰盘焊接在杆体1上。In the present disclosure, the
具体地,在第一种实施方式中,当对一根支撑杆进行安装时,可以对支撑杆进行组装,其中,可以是先将螺母2023旋转至贴合第二支撑板2021,之后将螺杆2022插入杆体1的一端内,此时的螺母2023接触第二止挡件7,将导向柱2012插入杆体1的另一端,此时第一弹性件3仅接触第一止挡件4但未发生压缩,并且支撑杆的整体长度小于巷道10的宽度或高度,支撑杆组装完成后,人员将组装完毕的支撑杆移动至预先选定构建密闭墙的位置,人员手握杆体1将其水平或竖直摆放,之后转动螺母2023(螺母2023转动时需确保螺杆2022不会绕自身轴线转动),随着螺母2023的转动,螺母2023与第二支撑板2021之间的距离逐渐变大,杆体1逐渐朝向第一弹性件3一端移动,并使得第一弹性件3和第二弹性件5开始收缩,通过第一弹性件3和第二弹性件5的弹力提供支撑杆可以固定在巷道10内的支撑力。此外,通过调节螺母2023的位置,可以间接调整第一弹性件3和第二弹性件5的压缩量,即可以调整第一弹性件3和第二弹性件5的弹力大小。Specifically, in the first embodiment, when a support rod is installed, the support rod can be assembled, wherein, the
在第二种实施方式中,当对一根支撑杆进行安装时,可以对支撑杆进行组装,其中,可以是先将螺母2023旋转至贴合第二支撑板2021,之后将螺杆2022插入杆体1的一端内,此时的螺母2023接触第二止挡件7,将导向柱2012插入杆体1的另一端,此时第一弹性件3仅接触第一止挡件4但未发生压缩,并且支撑杆的整体长度小于巷道10的宽度或高度,支撑杆组装完成后,人员将组装完毕的支撑杆移动至预先选定构建密闭墙的位置,人员手握杆体1将其水平或竖直摆放;In the second embodiment, when a support rod is installed, the support rod can be assembled, wherein the
摆放完毕后,因第一弹性件3的弹力小于第二弹性件5,并且为了尽可能地减少支撑杆固定在巷道10内时所需的时长,可以是通过人员手动移动杆体1的方式(此时人员可以是手握杆体1的方式移动杆体1),让第一止挡件4挤压第一弹性件3使其压缩(因第一弹性件3的弹力较小,人员无需使用较大的力,即可较为轻松的使得第一弹性件3被第一止挡件4挤压),直至第一止挡件4靠近第二弹性件5背离第一支撑板2011的一端(此时的第二弹性件5未被第一止挡件4挤压),之后需要人员持续对杆体1施加挤压第一弹性件3的力,在人员持续对杆体1施加挤压第一弹性件3的力的过程中转动螺母2023,之后,当螺母2023接触到第二止挡件7时,人员可以去除施加在杆体1上用以挤压第一弹性件3的力,此时,通过第一弹性件3提供的弹力可以初步将支撑杆固定在巷道10内;After placing, because the elastic force of the first elastic member 3 is less than the second elastic member 5, and in order to reduce the time required for the support rod to be fixed in the roadway 10 as much as possible, the mode of manually moving the rod body 1 by personnel can be used ( At this time, the personnel can move the rod body 1 by holding the rod body 1), and let the first stopper 4 squeeze the first elastic member 3 to compress it (because the elastic force of the first elastic member 3 is small, the personnel do not need to use a larger force, that is, the first elastic member 3 can be easily squeezed by the first stopper 4), until the first stopper 4 is close to the end of the second elastic member 5 away from the first support plate 2011 (at this time The second elastic member 5 is not squeezed by the first stopper 4), and then the staff needs to continue to apply the force of squeezing the first elastic member 3 to the rod body 1, and the personnel continue to apply the force of squeezing the first elastic member 3 to the rod body 1 Turn the nut 2023 during the force process, and then when the nut 2023 touches the second stopper 7, the personnel can remove the force applied on the rod body 1 to squeeze the first elastic member 3, at this time, through the first elastic The elastic force provided by part 3 can preliminarily fix the support rod in the roadway 10;
最后,为了确保支撑杆可以更加牢固地固定在巷道10内,还需继续转动螺母2023,随着螺母2023的转动,第一止挡件4开始挤压第二弹性件5并使得第二弹性件5收缩,可以通过人员经验进行判断,当第二弹性件5压缩至一定程度时,停止转动螺母2023。完成对一根支撑杆的固定。Finally, in order to ensure that the support rod can be more firmly fixed in the
在上述的第二种实施方式中,第一弹性件3的作用在于为支撑杆初步安装提供初始的支撑弹力,当支撑杆通过第一弹性件3初步固定在巷道10内时,可以继续转动螺母2023使得第二弹性件5被压缩并为支撑杆提供强有力的支撑。In the above-mentioned second embodiment, the function of the first
在本公开中,参考图1和图3所示,当支撑杆固定在巷道10内后,第二支撑板2021可以直接抵接巷道10的内壁面,第二支撑板2021可以构造为圆形垫板,第二支撑板2021的直径大于螺杆2022以及杆体1的直径,可以使得第二支撑板2021接触到的巷道10内壁面的面积更大,为杆体1提供良好的稳定性。In the present disclosure, as shown in FIG. 1 and FIG. 3 , when the support rod is fixed in the
在一些实施方式中,参考图1和图3所示,在本公开中,可以在第二支撑板2021背离螺杆2022一端的端面上设有第二柔性垫片8,第二柔性垫片8可以采用橡胶材质的原料制成,增大第二支撑板2021与巷道10内壁面的摩擦力,使得支撑杆在安装后不易发生晃动,同时若巷道10壁为强度较低的煤岩体的矿井壁时,杆体1两端的第一支撑组件201和第二支撑组件202朝向背离杆体1的方向挤压巷道10壁仍存在损坏巷道10壁的风险,因此,第二柔性垫片8起到保护巷道10壁的作用。In some embodiments, as shown in FIG. 1 and FIG. 3 , in the present disclosure, a second
在上述技术方案的基础上,本公开的第二方面还提供一种密闭墙,该密闭墙包括骨架9和密封布,骨架9包括沿竖直方向延伸且沿水平方向间隔布置的多根纵向支撑杆以及沿水平方向延伸且沿竖直方向间隔布置的多根横向支撑杆,纵向支撑杆和/或横向支撑杆采用上述第一方面或者上述第一方面中任意实施例的支撑杆;密封布铺设在骨架9上。On the basis of the above technical solution, the second aspect of the present disclosure also provides an airtight wall, the airtight wall includes a
在本公开中,参考图5所示,通过上述的第一种实施方式或第二种实施方式对若干根支撑杆进行固定后,形成密闭墙的骨架9,可以在该骨架9上铺设密封布,铺设完毕后,可以采用在其表面喷涂砂浆的方式对密闭墙进行最终密封,使得密封布与巷道10壁之间不会存在间隙。In the present disclosure, as shown in FIG. 5 , after fixing several support rods through the above-mentioned first embodiment or second embodiment, a
在一些实施方式中,纵向支撑杆和横向支撑杆的交叉处通过固定件连接,其中,固定件可以是现有器件,例如,环箍、十字固定夹等,或者是采用铁丝拧紧的方式对纵向支撑杆和横向支撑杆的交叉处进行连接固定。In some embodiments, the intersections of the longitudinal support rods and the horizontal support rods are connected by a fixing piece, wherein the fixing piece can be an existing device, such as a hoop, a cross fixing clip, etc., or a wire tightening method is used to tighten the longitudinal The intersection of the support bar and the transverse support bar is connected and fixed.
支撑架构建密闭墙的流程说明:在本公开中,支撑杆采用分体式设计且主要包括三部分,分别为杆体1、第一支撑组件201和第二支撑组件202,当需要在巷道10内搭建密闭墙时,考虑到巷道10内的空间较为狭窄,可以将若干的杆体1、若干的第一支撑组件201和若干的第二支撑组件202分批次地运输至巷道10内,之后可以按照上述的第一种实施方式或第二种实施方式将若干根支撑杆安装需要进行固定并形成骨架9,之后将密封布铺设在骨架9上,铺设完成后,喷涂砂浆对密封布与巷道10壁之间的间隙进行彻底密封。Description of the process of building a closed wall with a support frame: In this disclosure, the support rod adopts a split design and mainly includes three parts, namely the
以上结合附图详细描述了本公开的优选实施方式,但是,本公开并不限于上述实施方式中的具体细节,在本公开的技术构思范围内,可以对本公开的技术方案进行多种简单变型,这些简单变型均属于本公开的保护范围。The preferred embodiments of the present disclosure have been described in detail above in conjunction with the accompanying drawings. However, the present disclosure is not limited to the specific details of the above embodiments. Within the scope of the technical concept of the present disclosure, various simple modifications can be made to the technical solutions of the present disclosure. These simple modifications all belong to the protection scope of the present disclosure.
另外需要说明的是,在上述具体实施方式中所描述的各个具体技术特征,在不矛盾的情况下,可以通过任何合适的方式进行组合,为了避免不必要的重复,本公开对各种可能的组合方式不再另行说明。In addition, it should be noted that the various specific technical features described in the above specific embodiments can be combined in any suitable manner if there is no contradiction. The combination method will not be described separately.
此外,本公开的各种不同的实施方式之间也可以进行任意组合,只要其不违背本公开的思想,其同样应当视为本公开所公开的内容。In addition, various implementations of the present disclosure can be combined arbitrarily, as long as they do not violate the idea of the present disclosure, they should also be regarded as the content disclosed in the present disclosure.
Claims (10)
Priority Applications (1)
| Application Number | Priority Date | Filing Date | Title |
|---|---|---|---|
| CN202310344378.2A CN116220807A (en) | 2023-03-31 | 2023-03-31 | Support rod and airtight wall |
Applications Claiming Priority (1)
| Application Number | Priority Date | Filing Date | Title |
|---|---|---|---|
| CN202310344378.2A CN116220807A (en) | 2023-03-31 | 2023-03-31 | Support rod and airtight wall |
Publications (1)
| Publication Number | Publication Date |
|---|---|
| CN116220807A true CN116220807A (en) | 2023-06-06 |
Family
ID=86569651
Family Applications (1)
| Application Number | Title | Priority Date | Filing Date |
|---|---|---|---|
| CN202310344378.2A Pending CN116220807A (en) | 2023-03-31 | 2023-03-31 | Support rod and airtight wall |
Country Status (1)
| Country | Link |
|---|---|
| CN (1) | CN116220807A (en) |
Citations (8)
| Publication number | Priority date | Publication date | Assignee | Title |
|---|---|---|---|---|
| FR1310787A (en) * | 1961-11-21 | 1962-11-30 | Maschfab Eisengiesserei Beien | Improvements to movable supports for mine clearance lanes |
| CN207848767U (en) * | 2017-06-26 | 2018-09-11 | 信锦企业股份有限公司 | support module |
| CN208088133U (en) * | 2018-02-02 | 2018-11-13 | 南通城欣市政工程有限公司 | A kind of supporting bridge device |
| CN212359808U (en) * | 2020-04-23 | 2021-01-15 | 杨小军 | Tunnel construction strutting arrangement for coal mining |
| CN212583759U (en) * | 2020-07-13 | 2021-02-23 | 中国水利水电第六工程局有限公司 | Reinforcement jacking pillar for tunnel fault broken zone |
| CN214170197U (en) * | 2020-12-08 | 2021-09-10 | 山西西山煤电股份有限公司西曲矿 | Flexible protective fence outside coal mine tunnel sealing wall |
| CN215633054U (en) * | 2021-09-18 | 2022-01-25 | 山西潞安环保能源开发股份有限公司王庄煤矿 | U type rack coal mine tunnel supporting construction |
| CN216240732U (en) * | 2021-11-06 | 2022-04-08 | 魏新峰 | Temporary roadway supporting device for mining engineering |
-
2023
- 2023-03-31 CN CN202310344378.2A patent/CN116220807A/en active Pending
Patent Citations (8)
| Publication number | Priority date | Publication date | Assignee | Title |
|---|---|---|---|---|
| FR1310787A (en) * | 1961-11-21 | 1962-11-30 | Maschfab Eisengiesserei Beien | Improvements to movable supports for mine clearance lanes |
| CN207848767U (en) * | 2017-06-26 | 2018-09-11 | 信锦企业股份有限公司 | support module |
| CN208088133U (en) * | 2018-02-02 | 2018-11-13 | 南通城欣市政工程有限公司 | A kind of supporting bridge device |
| CN212359808U (en) * | 2020-04-23 | 2021-01-15 | 杨小军 | Tunnel construction strutting arrangement for coal mining |
| CN212583759U (en) * | 2020-07-13 | 2021-02-23 | 中国水利水电第六工程局有限公司 | Reinforcement jacking pillar for tunnel fault broken zone |
| CN214170197U (en) * | 2020-12-08 | 2021-09-10 | 山西西山煤电股份有限公司西曲矿 | Flexible protective fence outside coal mine tunnel sealing wall |
| CN215633054U (en) * | 2021-09-18 | 2022-01-25 | 山西潞安环保能源开发股份有限公司王庄煤矿 | U type rack coal mine tunnel supporting construction |
| CN216240732U (en) * | 2021-11-06 | 2022-04-08 | 魏新峰 | Temporary roadway supporting device for mining engineering |
Similar Documents
| Publication | Publication Date | Title |
|---|---|---|
| KR101721362B1 (en) | Safety chain channel system | |
| CN106150526B (en) | A kind of roadway support device | |
| CN116220807A (en) | Support rod and airtight wall | |
| CN205330704U (en) | Hydraulic support top anchor rope protection device and hydraulic support | |
| CN207298085U (en) | Particularly for optical or photographic antidetonation door shaped stent | |
| CN207646924U (en) | A kind of assembled architecture energy-consumption shock-absorption device | |
| CN210135365U (en) | A protection device for buried oil and gas pipelines in coal mining subsidence areas | |
| CN206472082U (en) | photovoltaic panel roof mounting assembly | |
| CN203807940U (en) | Bridge expansion device | |
| CN209353479U (en) | Prefabricated wall and concrete structure connection structure | |
| CN104500843A (en) | Support system for horizontal steel tube | |
| CN104912225B (en) | A joint structure of seismic joint and its construction method | |
| CN207598253U (en) | A kind of prefabrication and assembly construction push pipe waterproof system | |
| CN218116777U (en) | A pre-embedded protective mechanism for civil construction | |
| US20190078324A1 (en) | Wet seal system | |
| CN206736706U (en) | A kind of concrete cast-in-situ bridge anti-fall girder apparatus | |
| CN112683735B (en) | A simulation test device for directional drilling grouting slurry diffusion | |
| CN205397518U (en) | Split type cement pump truck elbow | |
| CN216305975U (en) | Anchor trays for corners | |
| CN219691086U (en) | Adjustable horizontal tunnel portal protection device | |
| CN218813907U (en) | A basement expansion joint waterproof fixture | |
| CN114319811A (en) | A on-spot antidetonation strutting arrangement of building for civil engineering | |
| CN211735500U (en) | A comprehensive pipe gallery structure across ground fissures | |
| CN206607610U (en) | A kind of waterstop auxiliary positioning support | |
| CN217629402U (en) | Non-deformable's bridge telescoping device for track traffic |
Legal Events
| Date | Code | Title | Description |
|---|---|---|---|
| PB01 | Publication | ||
| PB01 | Publication | ||
| SE01 | Entry into force of request for substantive examination | ||
| SE01 | Entry into force of request for substantive examination |