CN110158926A - A kind of building wall apparatus of plastering - Google Patents

A kind of building wall apparatus of plastering Download PDF

Info

Publication number
CN110158926A
CN110158926A CN201910577083.3A CN201910577083A CN110158926A CN 110158926 A CN110158926 A CN 110158926A CN 201910577083 A CN201910577083 A CN 201910577083A CN 110158926 A CN110158926 A CN 110158926A
Authority
CN
China
Prior art keywords
point
ash
sliding
baffle
sections
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Granted
Application number
CN201910577083.3A
Other languages
Chinese (zh)
Other versions
CN110158926B (en
Inventor
周昌进
阙文林
周鹏鹏
张国庆
喻娟
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Jiangsu Suzhong Construction Group Co Ltd
Original Assignee
Jiangsu Suzhong Construction Group Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Jiangsu Suzhong Construction Group Co Ltd filed Critical Jiangsu Suzhong Construction Group Co Ltd
Priority to CN201910577083.3A priority Critical patent/CN110158926B/en
Publication of CN110158926A publication Critical patent/CN110158926A/en
Application granted granted Critical
Publication of CN110158926B publication Critical patent/CN110158926B/en
Active legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Classifications

    • EFIXED CONSTRUCTIONS
    • E04BUILDING
    • E04FFINISHING WORK ON BUILDINGS, e.g. STAIRS, FLOORS
    • E04F21/00Implements for finishing work on buildings
    • E04F21/02Implements for finishing work on buildings for applying plasticised masses to surfaces, e.g. plastering walls
    • E04F21/06Implements for applying plaster, insulating material, or the like
    • E04F21/08Mechanical implements

Landscapes

  • Engineering & Computer Science (AREA)
  • Architecture (AREA)
  • Civil Engineering (AREA)
  • Structural Engineering (AREA)
  • Finishing Walls (AREA)
  • Conveying And Assembling Of Building Elements In Situ (AREA)

Abstract

一种建筑墙面抹灰装置,有效的解决了现有抹灰机不能保证墙面平整度的问题;包括底板,底板上设有竖直滑动的灰斗,底板上转动设置有丝杠,灰斗上固定有与丝杠螺纹连接的连接板,丝杠转动带动灰斗上下移动,灰斗前端设有出灰口,出灰口上竖直滑动设置有挡板,挡板的高度小于出灰口的高度,连接板上设置有控制挡板滑动的控制机构;本发明结构巧妙,使用方便,一次抹灰就能够从地面抹灰到天花板,不存在遗漏,减少后期补灰操作,缩短工期,加快施工进度。

A construction wall plastering device, which effectively solves the problem that the existing plastering machines cannot guarantee the smoothness of the wall surface; it includes a base plate, on which a vertically sliding ash hopper is arranged, and a lead screw is arranged on the bottom plate for rotation, and the ash hopper is arranged on the bottom plate. The bucket is fixed with a connecting plate that is threadedly connected with the lead screw. The rotation of the screw drives the ash bucket to move up and down. There is an ash outlet at the front end of the ash bucket, and a baffle is installed vertically on the ash outlet. The height of the baffle is smaller than the ash outlet. The connecting plate is provided with a control mechanism to control the sliding of the baffle; the invention has an ingenious structure and is easy to use. It can be plastered from the ground to the ceiling at one time, without omissions, reducing the later operation of ash filling, shortening the construction period, and speeding up the construction process. Construction Schedule.

Description

一种建筑墙面抹灰装置A plastering device for building walls

技术领域technical field

本发明涉及建筑设备技术领域,特别是涉及一种建筑墙面抹灰装置。The invention relates to the technical field of construction equipment, in particular to a construction wall plastering device.

背景技术Background technique

在对墙面进行抹灰时,为了减轻工人的负担,研发了一种抹灰机,采用机械的抹灰方式来代替原本人工抹灰的方式,目前市场上出售的抹灰机出灰口的上下棱之间距离较小,抹灰装置运行到顶部不能接触到天花板,运行到底部不能接触到地平面,导致墙壁的顶底会留有空位抹不到,还需要后续进行补灰才行。When plastering the walls, in order to reduce the burden on workers, a plastering machine has been developed, which uses mechanical plastering instead of manual plastering. The outlet of the plastering machines currently on the market is The distance between the upper and lower edges is small, and the plastering device cannot touch the ceiling when it is running to the top, and cannot touch the ground plane when it is running to the bottom. As a result, there will be gaps on the top and bottom of the wall that cannot be plastered, and subsequent plastering is required.

为了弥补这个缺陷,有些抹灰机的抹灰板采用可调节式的结构,使其能够在触碰到地面和天花板边缘,从而完成整体的抹灰操作,这样的结构中由于抹灰板处于可移动的状态,所以对其定位以及控制机构要求较高,使得在抹灰板移动前后抹灰板距离发生变化,导致抹灰的厚度变化,影响墙面平整度。In order to make up for this defect, the plastering board of some plastering machines adopts an adjustable structure, so that it can touch the edge of the floor and the ceiling to complete the overall plastering operation. Moving state, so its positioning and control mechanism requirements are high, so that the distance between the plastering boards changes before and after the plastering board moves, resulting in changes in the thickness of the plastering, affecting the flatness of the wall.

发明内容Contents of the invention

针对上述情况,为克服现有技术之缺陷,本发明之目的就是提供一种建筑墙面抹灰装置,有效的解决了现有抹灰机不能保证墙面平整度的问题。In view of the above situation, in order to overcome the defects of the prior art, the object of the present invention is to provide a plastering device for building walls, which effectively solves the problem that the existing plastering machines cannot guarantee the flatness of the wall.

其解决问题的技术方案是,一种建筑墙面抹灰装置,包括底板,底板上设有竖直滑动的灰斗,底板上转动设置有丝杠,灰斗上固定有与丝杠螺纹连接的连接板,丝杠转动带动灰斗上下移动,灰斗前端设有出灰口,出灰口上竖直滑动设置有挡板,挡板的高度小于出灰口的高度,连接板上设置有控制挡板滑动的控制机构,控制机构包括与挡板固定连接的滑块,连接板上滑动设有与滑块配合的楔形块,楔形块移动推动滑块上下移动进而控制挡板的滑动,连接板上设有变速箱,变速箱的输出轴上固定有推动楔形块的推板,变速箱的输入轴上套接有与丝杠啮合的螺母,丝杠带动螺母转动使得输入轴转动,经变速箱调节转速后带动输出轴转动,从而使得推板推动楔形块的移动。The technical solution to solve the problem is a construction wall plastering device, including a bottom plate, the bottom plate is provided with a gray hopper that slides vertically, the bottom plate is rotatably provided with a lead screw, and the ash hopper is fixed with a screw threaded connection with the lead screw. The connecting plate, the rotation of the lead screw drives the ash hopper to move up and down, the front end of the ash hopper is provided with an ash outlet, and a baffle is vertically slid on the ash outlet. The control mechanism of the plate sliding, the control mechanism includes a slider fixedly connected with the baffle, and a wedge-shaped block that cooperates with the slider is slid on the connecting plate, and the wedge-shaped block moves to push the slider to move up and down to control the sliding of the baffle. There is a gearbox, the output shaft of the gearbox is fixed with a push plate that pushes the wedge block, the input shaft of the gearbox is sleeved with a nut that engages with the screw, and the screw drives the nut to rotate to make the input shaft rotate. After the rotating speed, the output shaft is driven to rotate, so that the push plate pushes the movement of the wedge block.

本发明结构巧妙,使用方便,一次抹灰就能够从地面抹灰到天花板,不存在遗漏,减少后期补灰操作,缩短工期,加快施工进度。The present invention is ingenious in structure and easy to use, and can be plastered from the ground to the ceiling at one time without any omissions, thereby reducing later-stage ash filling operations, shortening the construction period, and speeding up the construction progress.

附图说明Description of drawings

图1是本发明的立体示意图一。Fig. 1 is a three-dimensional schematic view of the present invention.

图2是本发明图1中A部的放大示意图。Fig. 2 is an enlarged schematic view of part A in Fig. 1 of the present invention.

图3是本发明的立体示意图二。Fig. 3 is a second perspective view of the present invention.

图4是本发明图3中B部的放大示意图。Fig. 4 is an enlarged schematic diagram of part B in Fig. 3 of the present invention.

图5是本发明的侧视示意图。Fig. 5 is a schematic side view of the present invention.

图6是本发明图5中C部的放大示意图。Fig. 6 is an enlarged schematic view of part C in Fig. 5 of the present invention.

图7是本发明图5中D部的放大剖视图。Fig. 7 is an enlarged sectional view of part D in Fig. 5 of the present invention.

图8是本发明的俯视示意图。Fig. 8 is a schematic top view of the present invention.

图9是本发明图8中E部的放大示意图。Fig. 9 is an enlarged schematic diagram of part E in Fig. 8 of the present invention.

图10是本发明中挡板控制机构的结构示意图。Fig. 10 is a structural schematic diagram of the baffle control mechanism in the present invention.

图11是本发明中滑块的示意图。Fig. 11 is a schematic diagram of the slider in the present invention.

具体实施方式Detailed ways

以下结合附图1至图11对本发明的具体实施方式作进一步详细说明。The specific implementation manner of the present invention will be described in further detail below in conjunction with accompanying drawings 1 to 11 .

由图1至图11可知,一种建筑墙面抹灰装置,包括底板1,底板1上设有竖直滑动的灰斗2,底板1上转动设置有丝杠3,灰斗2上固定有与丝杠3螺纹连接的连接板4,丝杠3转动带动灰斗2上下移动,灰斗2前端设有出灰口5,出灰口5上竖直滑动设置有挡板6,挡板6的高度小于出灰口5的高度,连接板4上设置有控制挡板6滑动的控制机构,控制机构包括与挡板6固定连接的滑块7,连接板4上滑动设有与滑块7配合的楔形块8,楔形块8移动推动滑块7上下移动进而控制挡板6的滑动,连接板4上设有变速箱9,变速箱9的输出轴10上固定有推动楔形块8的推板11,变速箱9的输入轴12上套接有与丝杠3啮合的螺母13,丝杠3带动螺母13转动使得输入轴12转动,经变速箱9调节转速后带动输出轴10转动,从而使得推板11推动楔形块8的移动。As can be seen from Figures 1 to 11, a building wall plastering device includes a bottom plate 1, on which a vertically sliding ash hopper 2 is arranged, on which a lead screw 3 is rotated, and on which the ash hopper 2 is fixed a The connecting plate 4 threadedly connected with the lead screw 3, the rotation of the lead screw 3 drives the ash hopper 2 to move up and down, the front end of the ash hopper 2 is provided with an ash outlet 5, and the ash outlet 5 is vertically slid to be provided with a baffle 6, the baffle 6 The height is less than the height of the ash outlet 5, the connecting plate 4 is provided with a control mechanism that controls the sliding of the baffle plate 6, the control mechanism includes a slider 7 fixedly connected with the baffle plate 6, and the connecting plate 4 is slidably provided with a slider 7 Cooperating wedge block 8, wedge block 8 moves and pushes slide block 7 to move up and down and then controls the sliding of baffle plate 6, and connecting plate 4 is provided with gearbox 9, and the output shaft 10 of gearbox 9 is fixed with the pusher that promotes wedge block 8. The plate 11, the input shaft 12 of the gearbox 9 is sleeved with a nut 13 engaged with the lead screw 3, the lead screw 3 drives the nut 13 to rotate to make the input shaft 12 rotate, and the output shaft 10 is driven to rotate after the speed is adjusted by the gearbox 9, thereby Make the push plate 11 push the movement of the wedge block 8 .

所述的底板1上固定有多个位于灰斗2外侧的滑动杆14,灰斗2外设有套接在滑动杆14外的套管15。The bottom plate 1 is fixed with a plurality of sliding rods 14 located outside the ash hopper 2 , and the ash hopper 2 is provided with sleeves 15 sleeved outside the sliding rods 14 .

所述的灰斗2上卡设有位于出灰口5两侧的滑槽16,挡板6位于滑槽16内滑动,滑槽16的高度大于出灰口5的高度。The ash hopper 2 is clamped with chutes 16 located on both sides of the ash outlet 5 , the baffle plate 6 slides in the chute 16 , and the height of the chute 16 is greater than that of the ash outlet 5 .

所述的滑块7外设有固定在连接板4上的外框17,外框17内高度大于滑块7高度,滑块7顶端设有与外框17连接的弹簧18,滑块7底部与连接板4之间留有空隙19,楔形块8最低端高度小于空隙19高度。Described slide block 7 is provided with outer frame 17 that is fixed on the connecting plate 4, and the inner height of outer frame 17 is greater than the height of slide block 7, and the top of slide block 7 is provided with the spring 18 that is connected with outer frame 17, and the bottom of slide block 7 There is a gap 19 between the connecting plate 4 and the height of the lowest end of the wedge block 8 is smaller than the height of the gap 19 .

所述的滑块7上开设有凹槽20,凹槽20包括AB段、BC段、CD段和DA段,AB段、BC段、CD段和DA段构成一个回路,AB段、BC段、CD段和DA段的连接处分别为A点、B点、C点和D点,外框17上转动连接有插入凹槽20内的拨杆21,当拨杆21位于A点时,挡板6位于出灰口5的下端,当拨杆21位于C点时,挡板6位于出灰口5的上端。Described slide block 7 is provided with groove 20, and groove 20 comprises AB segment, BC segment, CD segment and DA segment, and AB segment, BC segment, CD segment and DA segment form a circuit, and AB segment, BC segment, The joints of the CD segment and the DA segment are points A, B, C and D respectively. The outer frame 17 is rotatably connected with a lever 21 inserted into the groove 20. When the lever 21 is located at point A, the baffle plate 6 is located at the lower end of the ash outlet 5, and when the driving lever 21 is at point C, the baffle plate 6 is located at the upper end of the ash outlet 5.

所述的拨杆21的转动中心设有扭簧,扭簧将拨杆21向顺时针方向转动。The center of rotation of the driving rod 21 is provided with a torsion spring, and the torsion spring rotates the driving rod 21 clockwise.

所述的拨杆21在凹槽20内按A点→B点→C点→D点的方向单向移动。The driving rod 21 moves in one direction in the groove 20 in the direction of point A→point B→point C→point D.

所述的A点、B点、C点和D点处均设有止回台阶22。The points A, B, C and D are all provided with non-return steps 22 .

所述的变速箱9多多级齿轮减速箱。The 9 gearboxes are multi-stage gear reduction boxes.

所述的灰斗2前端为敞口状,当灰斗2位于最下端时,出灰口5下端处于最低点,当灰斗2位于最上端时,出灰口5上端处于最高点。The front end of the ash hopper 2 is open. When the ash hopper 2 is at the lowest end, the lower end of the ash outlet 5 is at the lowest point. When the ash hopper 2 is at the uppermost end, the upper end of the ash outlet 5 is at the highest point.

初始位置时,灰斗2位于最下端位置,挡板6位于出灰口5的上端,当灰斗2达到顶端时,挡板6位于出灰口5的下端。At the initial position, the ash hopper 2 is located at the lowest position, and the baffle plate 6 is located at the upper end of the ash outlet 5 , and when the ash hopper 2 reaches the top, the baffle plate 6 is located at the lower end of the ash outlet 5 .

本发明在使用时,When the present invention is in use,

将本底板1固定在抹灰机上,灰斗2用泵连接灰料,然后调节灰斗2在底板1上的位置,使其处于最低处,灰斗2前端的出灰口5下端接触地面,挡板6位于出灰口5上端,露出出灰口5下端用于出灰,此时的滑块7位于外框17的上端,即拨杆21位于凹槽20内的C点,然后启动设备,丝杠3主动转动带动灰斗2上升,在灰斗2上升的过程中,灰斗2内灰料在泵的作用下从出灰口5被抹到墙面上,同时,螺母13与丝杠3啮合同步转动,带动变速箱9的输入轴12转动,输出轴10带动推板11缓慢转动,推动楔形块8缓慢移动,推动滑块7在外框17内向上移动,拨杆21在凹槽20内从C点向D点移动,当移动到D点时,推板11刚好将楔形块8推动到极限位置,推板11将不会影响楔形块8的移动,弹簧18将滑块7向下推动,使得楔形块8回复到原来的位置,拨杆21从D点移动到A点,挡板6移动到出灰口5的下端,露出上端位置用于出灰,根据墙面的高度进行调节变速箱9的传动比,使得在一次的抹灰过程中,仅进行一次滑块7位置的变换,这样在一次的抹灰过程中,在底部时出灰位置位于底部,当达到顶部时出灰位置位于顶端,从而使地面位置和天花板位置也能够抹灰,在滑块7位置变换的过程中,由于变速箱9的存在,输出轴10的转速较慢,推板11推动楔形块8移动的速度较慢,滑块7切换位置的速度较慢,即出灰口5被挡板6挡住的位置变换处于缓慢的过程中,在该过程中,挡板6会移动到出灰口5的中部,使得出灰口5的上部和下部均露出空当,这样灰料会同时从出灰口5上部和下部出灰,使得在切换挡板6位置时,不会出现出灰口5下部出灰立马切换到上部的情况,避免墙面上灰料的断层,从而使得一次抹灰可以实现从地面到天花板的全部抹灰。Fix the base plate 1 on the plastering machine, connect the ash hopper 2 to the ash material with a pump, then adjust the position of the ash hopper 2 on the base plate 1 so that it is at the lowest position, and the lower end of the ash outlet 5 at the front end of the ash hopper 2 touches the ground. The baffle plate 6 is located at the upper end of the ash outlet 5, and the lower end of the ash outlet 5 is exposed for ash output. At this time, the slider 7 is located at the upper end of the outer frame 17, that is, the lever 21 is located at point C in the groove 20, and then the device is started , the lead screw 3 actively rotates to drive the ash hopper 2 to rise. During the rising process of the ash hopper 2, the ash in the ash hopper 2 is wiped on the wall from the ash outlet 5 under the action of the pump. At the same time, the nut 13 and the wire The lever 3 meshes and rotates synchronously, drives the input shaft 12 of the gearbox 9 to rotate, the output shaft 10 drives the push plate 11 to rotate slowly, pushes the wedge-shaped block 8 to move slowly, pushes the slider 7 to move upward in the outer frame 17, and the lever 21 is in the groove. Move from point C to point D within 20, when moving to point D, push plate 11 just pushes wedge-shaped block 8 to the limit position, push plate 11 will not affect the movement of wedge-shaped block 8, spring 18 will slide block 7 to Push down, so that the wedge-shaped block 8 returns to the original position, the lever 21 moves from point D to point A, and the baffle plate 6 moves to the lower end of the ash outlet 5, exposing the upper end position for ash output, according to the height of the wall. Adjust the transmission ratio of the gearbox 9 so that in one plastering process, the position of the slider 7 is only changed once, so that in one plastering process, the ash output position is at the bottom when it is at the bottom, and the ash output position is at the bottom when it reaches the top. The ash position is located at the top, so that the ground position and the ceiling position can also be plastered. During the position change of the slider 7, due to the existence of the gearbox 9, the output shaft 10 rotates slowly, and the push plate 11 pushes the wedge block 8 to move. The speed of the slider 7 is relatively slow, and the speed of the position switching of the slider 7 is relatively slow, that is, the position change of the ash outlet 5 blocked by the baffle 6 is in a slow process, and during this process, the baffle 6 will move to the position of the ash outlet 5. The middle part, so that the upper and lower parts of the ash outlet 5 are exposed, so that the ash will be discharged from the upper and lower parts of the ash outlet 5 at the same time, so that when the position of the baffle plate 6 is switched, there will be no ash output from the lower part of the ash outlet 5. Immediately switch to the upper part to avoid the dislocation of the plaster on the wall, so that one plaster can be plastered from the ground to the ceiling.

为了实现挡板6位置的变换,在连接板4上设置了控制机构,控制机构包括滑块7、外框17、楔形块8、变速箱9、推板11、螺母13,螺母13与丝杠3啮合为控制机构提供动力,变速箱9将螺母13接收到的动力进行转换,输出到推板11上所需的动力,推板11推动楔形块8移动,楔形块8的楔形面推动滑块7在外框17内滑动,从而实现挡板6在出灰口5位置的变动。In order to realize the conversion of the position of the baffle plate 6, a control mechanism is provided on the connecting plate 4, and the control mechanism includes a slide block 7, an outer frame 17, a wedge block 8, a gearbox 9, a push plate 11, a nut 13, and the nut 13 and the lead screw 3 meshing provides power for the control mechanism, the gearbox 9 converts the power received by the nut 13, and outputs the required power to the push plate 11, the push plate 11 pushes the wedge block 8 to move, and the wedge-shaped surface of the wedge block 8 pushes the slider 7 slides in the outer frame 17, thereby realizing the change of the position of the baffle plate 6 at the ash outlet 5.

为了确定滑块7在外框17内位置的稳定,滑块7上开设了凹槽20,并将凹槽20分为AB段、BC段、CD段和DA段四段,外框17上设置插入凹槽20内的拨杆21,拨杆21在凹槽20内位置固定后即确保滑块7在外框17内位置固定,由于滑块7顶部设有与外框17连接的弹簧18,凹槽20上的A点和C点为拨杆21停留位置,当拨杆21位于A点时,滑块7位于外框17内下端,当拨杆21位于C点时,滑块7位于外框17内上端。In order to ensure the stability of the position of the slider 7 in the outer frame 17, a groove 20 is opened on the slider 7, and the groove 20 is divided into four sections: AB section, BC section, CD section and DA section. The driving rod 21 in the groove 20, after the driving rod 21 is fixed in the groove 20, the position of the slider 7 is fixed in the outer frame 17, because the top of the slider 7 is provided with a spring 18 connected with the outer frame 17, the groove Points A and C on 20 are the rest positions of the lever 21. When the lever 21 is at point A, the slider 7 is located at the lower end of the outer frame 17. When the lever 21 is at point C, the slider 7 is located at the outer frame 17. inner upper end.

为了保证拨杆21能够沿A点→B点→C点→D点的方向单向移动,A点、B点、C点和D点处均设有止回台阶22,使得拨杆21在从A点到B点后,止回台阶22使得拨杆21只能向C点移动不能反向回到A点,同理,拨杆21在C点受到向上的推力时,将会向D点方向移动而不是向B点,拨杆21在D点时只能向A点移动,在A点时只能向B点移动,这样能够保证滑块7在一次位置的变换过程中,必然会产生较大的位移,实现从A点到C点的变换,即挡板6在出灰口5的位置能够从位于上端变换为位于下端,使得在灰斗2到达顶部时出灰口5上的出灰位置发生变换,而不是重新回到下端出灰的状态,从而保证了抹灰的完整。In order to ensure that the lever 21 can move in one direction along the direction of point A→point B→point C→point D, point A, point B, point C and point D are all provided with non-return steps 22, so that the lever 21 moves from After point A arrives at point B, the non-return step 22 makes the lever 21 move only to point C and cannot reversely return to point A. Similarly, when the lever 21 receives an upward thrust at point C, it will move toward point D. Moving instead of point B, the lever 21 can only move to point A when it is at point D, and it can only move to point B when it is at point A, so that it can ensure that the slider 7 will inevitably produce a relatively large position during a position change process. The large displacement realizes the transformation from point A to point C, that is, the position of the baffle plate 6 at the ash outlet 5 can be changed from being located at the upper end to being located at the lower end, so that when the ash hopper 2 reaches the top, the ash on the ash outlet 5 The position is changed, instead of returning to the state of ash coming out of the lower end, thus ensuring the integrity of the plastering.

为了便于挡板6位置的变换,出灰口5两侧的灰斗2内设有滑槽16,且滑槽16的高度要高于出灰口5的高度,挡板6在滑槽16内滑动,由于挡板6与滑块7固定连接,而滑块7在从A点到达C点的过程中,需要先经过B点,A点到B点之间滑块7的位移要大于A点到C点之间的位移,所以滑槽16上下两端要留有挡板6移动的缓冲位置,避免挡板6无法切换位置。In order to facilitate the change of the position of the baffle plate 6, a chute 16 is provided in the ash hopper 2 on both sides of the ash outlet 5, and the height of the chute 16 is higher than that of the ash outlet 5, and the baffle plate 6 is in the chute 16. Sliding, because the baffle 6 is fixedly connected to the slider 7, and the slider 7 needs to pass through the point B in the process from point A to point C, and the displacement of the slider 7 between point A and point B is greater than that of point A To the displacement between point C, so the upper and lower ends of the chute 16 should have a buffer position for the movement of the baffle plate 6, so as to prevent the baffle plate 6 from being unable to switch positions.

为了便于灰斗2的上下移动,在底板1上设置多个滑动杆14,灰斗2上设有套筒,灰斗2在丝杠3的作用下上下移动时,滑动杆14和套筒的配合为灰斗2提供稳定滑动的轨道,使得灰斗2与墙面之间的距离保持稳定,从而保证抹灰层的厚度。In order to facilitate the up and down movement of the ash bucket 2, a plurality of sliding rods 14 are arranged on the bottom plate 1, and a sleeve is provided on the ash bucket 2. When the ash bucket 2 moves up and down under the action of the lead screw 3, the sliding rods 14 and the sleeve The cooperation provides a stable sliding track for the ash hopper 2, so that the distance between the ash hopper 2 and the wall remains stable, thereby ensuring the thickness of the plastering layer.

螺母13与变速箱9的输入轴12之间为单向传动,螺母13与丝杠3啮合始终转动,在灰斗2上升时,螺母13带动输入轴12转动,而在灰斗2下移的过程中,螺母13不能带动输入轴12转动,而挡板6在出灰口5的位置手动调节,推动滑块7改变拨杆21在凹槽20内的位置,从而改变挡板6的位置。There is a one-way transmission between the nut 13 and the input shaft 12 of the gearbox 9. The nut 13 is engaged with the lead screw 3 and rotates all the time. During the process, the nut 13 cannot drive the input shaft 12 to rotate, and the position of the baffle plate 6 at the ash outlet 5 is manually adjusted, and the slide block 7 is pushed to change the position of the driving rod 21 in the groove 20, thereby changing the position of the baffle plate 6.

本发明与现有技术相比,具有以下有益效果:1)在一次的抹灰过程中,实现从地面到天花板整体的抹灰,不会留白,不需要后期进行补灰,减少了工作量,能够缩短一定的施工时间;2)在切换出灰位置的过程中,挡板6的位置是缓慢进行切换的,使得出灰位置不是跳跃性的切换,从而使得在切换过程段的墙面上仍然能实现抹灰,不需要后期补灰,避免在实现地面和天花板出抹灰的同时造成其他的不利影响;3)出灰位置的切换,并没有影响灰斗2和出灰口5与墙面之间的距离与角度,使得抹灰层的厚度保持稳定,避免出现抹灰层厚度变化影响墙面平整度还需要后期整修情况的发生。Compared with the prior art, the present invention has the following beneficial effects: 1) In one plastering process, the entire plastering from the ground to the ceiling is realized without leaving any blanks, and there is no need for post-filling plastering, which reduces the workload , can shorten a certain construction time; 2) In the process of switching the ash outlet position, the position of the baffle plate 6 is switched slowly, so that the ash outlet position is not a jumpy switch, so that the wall surface in the switching process section Plastering can still be achieved, without the need for post-filling, avoiding other adverse effects while achieving plastering on the floor and ceiling; 3) Switching of the ash outlet position does not affect the relationship between the ash hopper 2 and the ash outlet 5 and the wall The distance and angle between the surfaces keeps the thickness of the plastering layer stable, avoiding the occurrence of changes in the thickness of the plastering layer affecting the flatness of the wall and requiring later renovations.

Claims (10)

1. a kind of building wall apparatus of plastering, which is characterized in that including bottom plate (1), bottom plate (1) is equipped with the ash bucket of vertical sliding (2), rotation is provided with lead screw (3) on bottom plate (1), and the connecting plate (4) being threadedly coupled with lead screw (3), silk are fixed on ash bucket (2) Thick stick (3) rotation drives ash bucket (2) to move up and down, and ash bucket (2) front end is equipped with ash hole (5), vertical sliding setting on ash hole (5) Have baffle (6), the height of baffle (6) is less than the height of ash hole (5), and control baffle (6) sliding is provided on connecting plate (4) Control mechanism, control mechanism include the sliding block (7) being fixedly connected with baffle (6), and sliding is equipped with and sliding block (7) on connecting plate (4) The wedge block (8) of cooperation, wedge block (8) is mobile to be pushed sliding block (7) to move up and down and then controls the sliding of baffle (6), connecting plate (4) gearbox (9) are equipped with, the push plate (11) for pushing wedge block (8), speed change is fixed on the output shaft (10) of gearbox (9) Be socketed with the nut (13) engaged with lead screw (3) on the input shaft (12) of case (9), lead screw (3) drive nut (13) to rotate so that Input shaft (12) rotation drives output shaft (10) rotation after gearbox (9) adjust revolving speed, so that push plate (11) pushes wedge The movement of shape block (8).
2. a kind of building wall apparatus of plastering according to claim 1, which is characterized in that fixed on the bottom plate (1) There are multiple sliding bars (14) on the outside of ash bucket (2), ash bucket (2), which is externally provided with, is socketed in the casing (15) of sliding bar (14) outside.
3. a kind of building wall apparatus of plastering according to claim 1, which is characterized in that block on the ash bucket (2) and set There is the sliding slot (16) positioned at ash hole (5) two sides, baffle (6) is located at sliding in sliding slot (16), and the height of sliding slot (16) is greater than The height of grey mouth (5).
4. a kind of building wall apparatus of plastering according to claim 1, which is characterized in that the sliding block (7) is externally provided with The outline border (17) being fixed on connecting plate (4), outline border (17) inner height be greater than sliding block (7) height, sliding block (7) top be equipped with it is outer The spring (18) of frame (17) connection, there are gap (19) between sliding block (7) bottom and connecting plate (4), wedge block (8) least significant end is high Degree is less than gap (19) height.
5. a kind of building wall apparatus of plastering according to claim 1, which is characterized in that opened up on the sliding block (7) Fluted (20), groove (20) include AB sections, BC sections, CD sections and DA sections, one circuit of AB sections, BC sections, CD sections and DA sections compositions, AB sections, BC sections, CD sections and DA sections of junction is respectively A point, B point, C point and D point, and it is recessed that insertion is rotatably connected on outline border (17) Driving lever (21) in slot (20), when driving lever (21) is located at A point, baffle (6) is located at the lower end of ash hole (5), when driving lever (21) When positioned at C point, baffle (6) is located at the upper end of ash hole (5).
6. a kind of building wall apparatus of plastering according to claim 1, which is characterized in that the rotation of the driving lever (21) Center is equipped with torsional spring, and torsional spring rotates driving lever (21) clockwise.
7. a kind of building wall apparatus of plastering according to claim 1, which is characterized in that the driving lever (21) is in groove (20) it is unidirectionally moved in by A point → B point → C point → D point direction.
8. a kind of building wall apparatus of plastering according to claim 1, which is characterized in that A point, B point, C point and the D Non-return step (22) are equipped at point.
9. a kind of building wall apparatus of plastering according to claim 1, which is characterized in that the gearbox (9) is more Grade gear reduction box.
10. a kind of building wall apparatus of plastering according to claim 1, which is characterized in that described ash bucket (2) front end is Open-like shape, when ash bucket (2) is located at bottom, ash hole (5) lower end is in minimum point, when ash bucket (2) is located at the top, out Grey mouth (5) upper end is at the highest notch.
CN201910577083.3A 2019-06-28 2019-06-28 Building wall plastering device Active CN110158926B (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201910577083.3A CN110158926B (en) 2019-06-28 2019-06-28 Building wall plastering device

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201910577083.3A CN110158926B (en) 2019-06-28 2019-06-28 Building wall plastering device

Publications (2)

Publication Number Publication Date
CN110158926A true CN110158926A (en) 2019-08-23
CN110158926B CN110158926B (en) 2020-03-10

Family

ID=67637448

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201910577083.3A Active CN110158926B (en) 2019-06-28 2019-06-28 Building wall plastering device

Country Status (1)

Country Link
CN (1) CN110158926B (en)

Cited By (2)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN113756572A (en) * 2021-10-08 2021-12-07 严晓龙 Automatic dismouting equipment of building aluminum mould board
CN114658194A (en) * 2022-04-13 2022-06-24 重庆电子工程职业学院 Puttying robot

Citations (4)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
US6695181B1 (en) * 2000-08-11 2004-02-24 David F. Kreitzer Mud gun and hopper assembly
CN101285340A (en) * 2007-04-10 2008-10-15 秋莉 Leather surface making machine for sight surface of wall
CN104251060A (en) * 2014-09-22 2014-12-31 山东建筑大学 Pasting machine work pace interlock control mechanism
CN105178578A (en) * 2015-08-14 2015-12-23 王永志 A plastering machine capable of plastering irregular walls

Patent Citations (4)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
US6695181B1 (en) * 2000-08-11 2004-02-24 David F. Kreitzer Mud gun and hopper assembly
CN101285340A (en) * 2007-04-10 2008-10-15 秋莉 Leather surface making machine for sight surface of wall
CN104251060A (en) * 2014-09-22 2014-12-31 山东建筑大学 Pasting machine work pace interlock control mechanism
CN105178578A (en) * 2015-08-14 2015-12-23 王永志 A plastering machine capable of plastering irregular walls

Cited By (3)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN113756572A (en) * 2021-10-08 2021-12-07 严晓龙 Automatic dismouting equipment of building aluminum mould board
CN114658194A (en) * 2022-04-13 2022-06-24 重庆电子工程职业学院 Puttying robot
CN114658194B (en) * 2022-04-13 2023-08-01 重庆电子工程职业学院 Putty scraping robot

Also Published As

Publication number Publication date
CN110158926B (en) 2020-03-10

Similar Documents

Publication Publication Date Title
CN100507186C (en) Automatic tile paste machine
CN110158926A (en) A kind of building wall apparatus of plastering
CN203201122U (en) Plastering machine for construction
CN108372576B (en) automatic brick making machine
CN116696120A (en) Anti-toppling mechanism for assembled building wall
CN106150042A (en) Gua Qiang robot
CN208197096U (en) Automatic brick-equipment
CN111677242B (en) A method of using an automatic plastering machine for construction
CN109025186A (en) A kind of good plastering machine of effect of plastering a wall
CN116335387B (en) Building template and installation method thereof
CN117601261A (en) A kind of construction cement mortar mixer
CN221722077U (en) Reinforcing bar positioning mechanism for construction
CN111945490A (en) Track slab fine adjustment bracket
CN215696049U (en) A scraping device for residual material after molding
CN112144833B (en) An automatic return indoor wall plastering machine
CN216543908U (en) Full-automatic pouring device for production of prefabricated parts
CN110173100B (en) Plastering device for plastering machine
CN221271542U (en) Pouring system of tubular pile die
CN216991632U (en) Full-automatic metal frame splicing forming machine
CN206378924U (en) A kind of ball outdoor vending machine conveyer
CN219219796U (en) Device for controlling position and size of reserved hole of floor slab
CN217812168U (en) Plastering device for constructional engineering
CN221878690U (en) Automatic wall plastering machine
CN221818978U (en) A leveling mechanism for production of prefabricated concrete parts
CN206678134U (en) The preparation facilities of the prefabricated glass magnesium board bloop of cement matrix

Legal Events

Date Code Title Description
PB01 Publication
PB01 Publication
SE01 Entry into force of request for substantive examination
SE01 Entry into force of request for substantive examination
GR01 Patent grant
GR01 Patent grant
PP01 Preservation of patent right
PP01 Preservation of patent right

Effective date of registration: 20250725

Granted publication date: 20200310