CN111287194A - Recyclable foundation pit support structure using inclined steel sheet piles and its support method - Google Patents
Recyclable foundation pit support structure using inclined steel sheet piles and its support method Download PDFInfo
- Publication number
- CN111287194A CN111287194A CN202010102565.6A CN202010102565A CN111287194A CN 111287194 A CN111287194 A CN 111287194A CN 202010102565 A CN202010102565 A CN 202010102565A CN 111287194 A CN111287194 A CN 111287194A
- Authority
- CN
- China
- Prior art keywords
- steel sheet
- pile
- piles
- foundation pit
- sheet piles
- Prior art date
- Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
- Pending
Links
- 229910000831 Steel Inorganic materials 0.000 title claims abstract description 132
- 239000010959 steel Substances 0.000 title claims abstract description 132
- 238000000034 method Methods 0.000 title claims description 33
- 238000010276 construction Methods 0.000 claims abstract description 38
- 239000002689 soil Substances 0.000 claims abstract description 27
- 230000005484 gravity Effects 0.000 claims abstract description 6
- 230000008093 supporting effect Effects 0.000 claims description 29
- 230000003068 static effect Effects 0.000 claims description 6
- 239000004519 grease Substances 0.000 claims description 4
- 238000004458 analytical method Methods 0.000 claims description 3
- 238000004364 calculation method Methods 0.000 claims description 3
- 238000003466 welding Methods 0.000 claims description 3
- 238000004140 cleaning Methods 0.000 claims description 2
- 239000011248 coating agent Substances 0.000 claims 1
- 238000000576 coating method Methods 0.000 claims 1
- 238000012544 monitoring process Methods 0.000 claims 1
- 230000035515 penetration Effects 0.000 claims 1
- 238000007789 sealing Methods 0.000 claims 1
- 230000000694 effects Effects 0.000 abstract description 2
- 238000013461 design Methods 0.000 description 11
- 238000009412 basement excavation Methods 0.000 description 10
- 239000002002 slurry Substances 0.000 description 8
- 239000004568 cement Substances 0.000 description 7
- 239000004567 concrete Substances 0.000 description 7
- 230000002787 reinforcement Effects 0.000 description 7
- 238000009415 formwork Methods 0.000 description 5
- 238000002156 mixing Methods 0.000 description 5
- 238000010586 diagram Methods 0.000 description 4
- 235000014121 butter Nutrition 0.000 description 2
- 238000006073 displacement reaction Methods 0.000 description 2
- 238000003780 insertion Methods 0.000 description 2
- 230000037431 insertion Effects 0.000 description 2
- 239000000463 material Substances 0.000 description 2
- 238000002360 preparation method Methods 0.000 description 2
- 238000003825 pressing Methods 0.000 description 2
- 238000004873 anchoring Methods 0.000 description 1
- 230000009286 beneficial effect Effects 0.000 description 1
- 239000000498 cooling water Substances 0.000 description 1
- 230000008878 coupling Effects 0.000 description 1
- 238000010168 coupling process Methods 0.000 description 1
- 238000005859 coupling reaction Methods 0.000 description 1
- 238000005520 cutting process Methods 0.000 description 1
- 238000001035 drying Methods 0.000 description 1
- 238000005516 engineering process Methods 0.000 description 1
- 238000007667 floating Methods 0.000 description 1
- 239000003673 groundwater Substances 0.000 description 1
- 238000012986 modification Methods 0.000 description 1
- 230000004048 modification Effects 0.000 description 1
- 239000004570 mortar (masonry) Substances 0.000 description 1
- 238000005192 partition Methods 0.000 description 1
- 239000011178 precast concrete Substances 0.000 description 1
- 238000001556 precipitation Methods 0.000 description 1
- 230000003014 reinforcing effect Effects 0.000 description 1
- 238000012552 review Methods 0.000 description 1
- 238000005507 spraying Methods 0.000 description 1
- 238000003756 stirring Methods 0.000 description 1
- XLYOFNOQVPJJNP-UHFFFAOYSA-N water Substances O XLYOFNOQVPJJNP-UHFFFAOYSA-N 0.000 description 1
Images
Classifications
-
- E—FIXED CONSTRUCTIONS
- E02—HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
- E02D—FOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
- E02D17/00—Excavations; Bordering of excavations; Making embankments
- E02D17/02—Foundation pits
- E02D17/04—Bordering surfacing or stiffening the sides of foundation pits
Landscapes
- Engineering & Computer Science (AREA)
- Mining & Mineral Resources (AREA)
- Life Sciences & Earth Sciences (AREA)
- General Life Sciences & Earth Sciences (AREA)
- Paleontology (AREA)
- Civil Engineering (AREA)
- General Engineering & Computer Science (AREA)
- Structural Engineering (AREA)
- Bulkheads Adapted To Foundation Construction (AREA)
Abstract
本发明公开了一种利用倾斜钢板桩的可回收基坑支护结构,包括钢板支护排桩,钢板支护排桩包括多个插入土体的钢板桩,钢板桩包括桩体,钢板桩上在桩体位于插入土体的一端为桩尖,另一端为桩尾,钢板桩由梯形槽钢构成,在钢板桩宽度方向的两侧均设有锁口,相邻钢板桩之间通过锁口咬合连接;所有钢板桩的桩尾均与冠梁固定;所有钢板桩呈与重力方向倾斜且向基坑内侧倾斜的插入土体中。可以改善基坑支护效果,更好的适用于软土地区超深、超大基坑的支护。本发明施工简单,工期缩短;使用钢板桩能提供必要的安全性,不受天气条件的制约,而且能降低对空间的要求,互换性良好;在使用完毕,钢板桩可以回收重复利用,节约资金。
The invention discloses a recyclable foundation pit support structure using inclined steel sheet piles, comprising steel sheet support row piles, the steel sheet support row piles comprising a plurality of steel sheet piles inserted into soil bodies, the steel sheet piles comprising a pile body, and the steel sheet piles on the piles. One end of the pile body that is inserted into the soil body is the pile tip and the other end is the pile tail. The steel sheet pile is composed of trapezoidal channel steel. There are locks on both sides in the width direction of the steel sheet piles, and the locks pass between the adjacent steel sheet piles. Occlusal connection; the pile tails of all steel sheet piles are fixed with the crown beam; all steel sheet piles are inserted into the soil body inclined to the direction of gravity and inclined to the inside of the foundation pit. It can improve the effect of foundation pit support, and is better suitable for the support of ultra-deep and super-large foundation pits in soft soil areas. The invention has simple construction and shortened construction period; the use of steel sheet piles can provide necessary safety, is not restricted by weather conditions, and can reduce the requirements for space, and has good interchangeability; after use, the steel sheet piles can be recycled and reused, saving energy funds.
Description
技术领域technical field
本发明涉及建筑基坑技术领域,尤其涉及一种利用可回收倾斜钢板桩的基坑支护方法。The invention relates to the technical field of construction foundation pits, in particular to a foundation pit support method using recyclable inclined steel sheet piles.
背景技术Background technique
桩排支护是目前国内应用最广泛的基坑支护形式之一。桩排结构与地下连续墙相比,具有施工工艺简单、成本低、平面布置灵活等诸多优点。间隔排列的桩排式支护适用于无地下水或允许坑外降水的情况,当设置止水帷幕或与其他混合式桩组成并排连续墙体时,也可用于软弱含水地层。Pile row support is one of the most widely used foundation pit support forms in China. Compared with the underground diaphragm wall, the pile row structure has many advantages, such as simple construction technology, low cost and flexible layout. The spaced pile row type support is suitable for situations where there is no groundwater or precipitation outside the pit is allowed, and it can also be used in weak water-bearing strata when a water-stop curtain is set or a side-by-side continuous wall is formed with other mixed piles.
目前所采用的排桩均为竖直桩,其在进行基坑支护时有诸多缺点,影响了排桩的应用。首先,相同开挖深度的桩顶位移大,内力大,使桩后地面产生较大变形,危及周围环境。其次,当桩的强度不够时容易导致护坡桩折断而使基坑失稳。再次,采用竖直排桩使基坑可能开挖的深度较小,在开挖深度较大时,排桩很容易发生倾覆破坏,因此支护结构需要更大截面和插入深度。The currently used row piles are all vertical piles, which have many shortcomings in the foundation pit support, which affects the application of the row piles. First of all, the displacement of the pile top at the same excavation depth is large, and the internal force is large, which causes a large deformation of the ground behind the pile and endangers the surrounding environment. Secondly, when the strength of the pile is not enough, it is easy to cause the slope protection pile to break and cause the foundation pit to become unstable. Third, the use of vertical piles makes the excavation depth of the foundation pit smaller. When the excavation depth is large, the piles are prone to overturning damage, so the support structure needs a larger section and insertion depth.
相比于预制混凝土桩,基坑支护采用钢板桩具有以下优势:钢板桩施工简单,工期短;对于建设任务而言,能降低对空间的要求;钢板桩使用后可以重复使用。可以回收重复利用,节约资金。Compared with precast concrete piles, the use of steel sheet piles for foundation pit support has the following advantages: steel sheet piles are simple to construct and have a short construction period; for construction tasks, the space requirements can be reduced; steel sheet piles can be reused after use. Can be recycled and reused, saving money.
发明内容SUMMARY OF THE INVENTION
针对上述现有技术,本发明提出一种利用倾斜钢板桩的可回收基坑支护结构及其支护方法,适用于使用单排倾斜桩进行基坑支护又期望对桩回收利用以减少造价的基坑支护工程。本发明施工简单,工期缩短,节约资金。In view of the above-mentioned prior art, the present invention proposes a recyclable foundation pit support structure using inclined steel sheet piles and a support method thereof, which are suitable for using a single row of inclined piles for foundation pit support and are expected to recycle the piles to reduce the cost. foundation pit support project. The invention is simple in construction, shortens construction period and saves money.
为了解决上述技术问题,本发明提出的一种利用倾斜钢板桩的可回收基坑支护结构,包括钢板支护排桩,所述钢板支护排桩包括多个插入土体的钢板桩,所述钢板桩包括桩体,所述钢板桩上在桩体位于插入土体的一端为桩尖,另一端为桩尾,所述钢板桩由梯形槽钢构成,在所述钢板桩宽度方向的两侧均设有锁口,相邻钢板桩之间通过锁口咬合连接;所有钢板桩的桩尾均与冠梁固定;所有钢板桩呈与重力方向倾斜的插入土体中,倾斜角度为α,α在0°到30°,但不包括0°,从而使所述钢板桩支护排桩向基坑内侧倾斜。In order to solve the above technical problems, the present invention proposes a recyclable foundation pit support structure using inclined steel sheet piles, including steel plate support row piles, and the steel plate support row piles include a plurality of steel sheet piles inserted into the soil. The steel sheet pile includes a pile body, and the end of the pile body at the end of the pile body that is inserted into the soil body is a pile tip, and the other end is a pile tail. The steel sheet pile is composed of trapezoidal channel steel. There are locks on the sides, and the adjacent steel sheet piles are connected by locking; the pile tails of all the steel sheet piles are fixed with the crown beam; α is in the range of 0° to 30°, but not including 0°, so that the steel sheet pile supporting row is inclined to the inside of the foundation pit.
进一步讲,倾斜角度优选的是α=15°~20°。Further, the inclination angle is preferably α=15° to 20°.
所述钢板桩沿待挖基坑边沿方向的长度为L,所述钢板桩沿待挖基坑边沿方向的桩间距为H,H=2~2.5L。The length of the steel sheet piles along the edge direction of the foundation pit to be excavated is L, and the pile spacing of the steel sheet piles along the edge direction of the foundation pit to be excavated is H, where H=2˜2.5L.
所述冠梁的横截面是边长为A的方形,A>0.6L。The cross section of the crown beam is a square with side length A, A>0.6L.
所述冠梁的横截面是矩形,该矩形的长边为B、短边为C,短边C的走向与重力方向重合,B>0.6L。The cross section of the crown beam is a rectangle, the long side of the rectangle is B, the short side is C, and the direction of the short side C coincides with the direction of gravity, B>0.6L.
同时,本发明中还提出了利用倾斜钢板桩的可回收基坑支护结构的支护方法,步骤如下:At the same time, the present invention also proposes a supporting method for a recyclable foundation pit supporting structure using inclined steel sheet piles, and the steps are as follows:
步骤一、根据场地条件和计算分析,确定钢板支护排桩的倾斜角度α在0°到30°,但不包括0°,并选择钢板桩的长度和桩身强度;
步骤二、开挖沟槽;Step 2: Dig trenches;
步骤三、倾斜排桩施工,采用单桩逐根打入法施打钢板桩,包括:Step 3: In the construction of inclined piles, the steel sheet piles are driven by the single pile driving method one by one, including:
1)钢板桩在打入前将桩尖处的凹槽口封闭,锁口处涂以黄油或其它油脂;1) Before driving the steel sheet pile, close the groove at the tip of the pile, and coat the lock with butter or other grease;
2)测量定位放线:放出钢板桩围护的轴线,并间隔的设置导向桩,导向桩直接使用钢板桩充当,然后挂绳线作为导线,打桩时利用导线控制钢板桩的轴线;2) Measuring and positioning the line: release the axis of the steel sheet pile enclosure, and set up guide piles at intervals. The guide pile is directly used as the steel sheet pile, and then the lanyard line is used as the wire, and the wire is used to control the axis of the steel sheet pile during piling;
3)送桩:采用斜桩静压机吊起钢板桩,人工扶正就位,定位误差<20mm;按照步骤一确定的倾斜角度对桩身进行控制;根据步骤一确定的倾斜角度α并结合下返深度及设备高度分别计算桩位线、入土线及对位线;桩位复核无误后,利用斜桩静压机顺序施工;在打桩过程中,用两台经纬仪监测并控制以保证钢板桩的倾斜角度α;3) Feeding the piles: Use the inclined pile static press to lift the steel sheet piles, manually straighten them into place, and the positioning error is less than 20mm; control the pile body according to the inclination angle determined in
4)单桩逐根连续施打,在打设第一块钢板桩和第二块钢板桩过程中,每打入1m测量一次位置和方向,以便起到导向样板作用,打至预定深度后立即用钢筋或钢板与围檩支架电焊作临时固定;4) The single piles are continuously driven one by one. During the process of driving the first steel sheet pile and the second steel sheet pile, the position and direction are measured once every 1m of driving, so as to play the role of a guiding model. Immediately after driving to the predetermined depth Use steel bars or steel plates and electric welding of purlin brackets for temporary fixation;
步骤四、隔水帷幕施工;Step 4. Waterproof curtain construction;
步骤五、冠梁施工;Step 5. Crown beam construction;
步骤六、对基坑坑底进行清理、整平,并进行下一步的施工作业;Step 6. Clean and level the bottom of the foundation pit, and carry out the next construction operation;
步骤七、采用履带拨桩机配合振动锤拔桩;基础施工完成、回填后即可拔桩。Step 7. Use the crawler pile pulling machine to cooperate with the vibrating hammer to pull out the pile; the pile can be pulled out after the foundation construction is completed and the backfilling is completed.
进一步讲,对于分层开挖的基坑,针对不同的排桩支护形式,在冠梁施工后,重复步骤一至步骤五的施工过程,直至开挖至基坑的底部;然后,进行步骤六和步骤七。Further, for the layered excavation foundation pit, for different pile support forms, after the crown beam is constructed, repeat the construction process from
与现有技术相比,本发明的有益效果是:Compared with the prior art, the beneficial effects of the present invention are:
采用本发明所述的利用可回收倾斜钢板桩的基坑支护结构进行基坑支护,可以改善基坑支护效果。例如可以更好的适用于软土地区超深、超大基坑的支护。且本发明施工简单,工期缩短;使用钢板桩能提供必要的安全性。而且对于建设任务而言,能降低对空间的要求;使用钢板桩可以不受天气条件的制约;在使用钢板桩的过程中,能简化检查材料或系统性能的复杂程序保证其适应性、互换性良好。最重要的是,钢板桩可以回收重复利用,节约资金。Using the foundation pit supporting structure utilizing the recyclable inclined steel sheet pile according to the present invention for foundation pit support can improve the foundation pit supporting effect. For example, it can be better applied to the support of super-deep and super-large foundation pits in soft soil areas. In addition, the present invention has simple construction and shortened construction period; the use of steel sheet piles can provide necessary safety. And for construction tasks, it can reduce the space requirements; the use of steel sheet piles can not be restricted by weather conditions; in the process of using steel sheet piles, it can simplify the complex procedures for checking the performance of materials or systems to ensure their adaptability and interchangeability. Sex is good. Most importantly, sheet piles can be recycled and reused, saving money.
附图说明Description of drawings
图1为现有技术基坑支护方法的示意图;Fig. 1 is the schematic diagram of prior art foundation pit support method;
图2为本发明实例采用的倾斜钢板支护桩进行基坑支护方法的示意图;Fig. 2 is the schematic diagram of the method for supporting foundation pit with inclined steel plate support piles adopted in the example of the present invention;
图3是钢板桩锁口及其锁口咬合连接示意图。Fig. 3 is a schematic diagram of a steel sheet pile lock and its snap connection.
具体实施方式Detailed ways
下面结合附图及具体实施例对本发明做进一步的说明,但下述实施例绝非对本发明有任何限制。The present invention will be further described below with reference to the accompanying drawings and specific embodiments, but the following embodiments do not limit the present invention by any means.
在开挖基坑前,通常需要使用支护桩对基坑进行支护,以避免基坑发生侧面坍塌,影响基坑的施工。图1为一种常用的基坑支护方法的示意图。参见图1,支护桩结构包括三根竖直的支护桩,支护桩为钢板桩1,三根示意的钢板桩1可以采用逐个压入的方式进入土体。图1中钢板桩1深入基坑底部3以下,以获得较高的支撑强度,钢板桩1位于基坑底部之下的部分占钢板桩1长度的1倍-3倍,以确保对基坑的有效支撑。在将钢板桩1(图中示意了三根)压入土体后,可以将冠梁2与三个钢板桩1的外侧固定连接。该冠梁2的侧面可以支撑基坑侧面。上述结构形成的排桩均为竖直桩,其在进行基坑支护时有诸多缺点,例如:相同开挖深度的桩顶位移大,内力大,使桩后地面产生较大变形,危及周围环境;当桩的强度不够时容易导致护坡桩折断而使基坑失稳;采用竖直排桩使基坑可能开挖的深度较小,在开挖深度较大时,排桩很容易发生倾覆破坏,因此支护结构需要更大截面和插入深度。不适用于软土地区超深、超大基坑的支护,影响了排桩的应用。Before excavating the foundation pit, it is usually necessary to use supporting piles to support the foundation pit to avoid side collapse of the foundation pit and affect the construction of the foundation pit. Figure 1 is a schematic diagram of a commonly used foundation pit support method. Referring to FIG. 1 , the supporting pile structure includes three vertical supporting piles, the supporting piles are
为了改善基坑支护效果,更好的适用于软土地区超深、超大基坑的支护,本发明提出的一种利用倾斜钢板桩的可回收基坑支护结构,如图2所示,该基坑支护结构包括钢板支护排桩,所述钢板支护排桩包括多个插入土体的钢板桩1,所述钢板桩1包括桩体11,所述钢板桩1上在桩体11位于插入土体的一端为桩尖12,另一端为桩尾13,所述钢板桩1由梯形槽钢构成,在所述钢板桩1宽度方向的两侧均设有锁口14,相邻钢板桩1之间通过锁口14咬合连接;所有钢板桩1的桩尾13均与冠梁2固定;其特征在于,所有钢板桩1呈与重力方向倾斜的插入土体中,倾斜角度为α,α在0°到30°,但不包括0°,优选的倾斜角度α=15°~20°。从而使所述钢板桩支护排桩向基坑内侧倾斜。In order to improve the support effect of foundation pits and be more suitable for the support of ultra-deep and super-large foundation pits in soft soil areas, a recyclable foundation pit support structure using inclined steel sheet piles proposed by the present invention is shown in Figure 2 , the foundation pit supporting structure includes a steel sheet support row pile, the steel sheet support row pile includes a plurality of steel sheet piles 1 inserted into the soil, the
本发明中,所述钢板桩1沿待挖基坑边沿方向的长度为L,所述钢板桩1沿待挖基坑边沿方向的桩间距为H,H=2~2.5L。In the present invention, the length of the
所述冠梁2的横截面可以是方形或是矩形,若是方形,其边长为A,且A>0.6L。若是矩形,该矩形的长边为B、短边为C,短边C的走向与重力方向重合,且B>0.6L。The cross section of the
本发明提供的基坑支护结构,使用钢板桩能提供必要的安全性,使用钢板桩可以不受天气条件的制约;通过将钢板支护排桩倾斜地设置,可以改善支撑效果。另外,由于钢板支护排桩是向基坑内侧倾斜,可以降低施工难度,并使对基坑的支护更加均匀。In the foundation pit supporting structure provided by the present invention, the use of steel sheet piles can provide necessary safety, and the use of steel sheet piles can not be restricted by weather conditions; the supporting effect can be improved by arranging the steel sheet support piles in an inclined manner. In addition, because the steel plate support piles are inclined to the inside of the foundation pit, the construction difficulty can be reduced, and the support of the foundation pit can be more uniform.
利用本发明提供的上述基坑支护结构的基坑支护方法,步骤如下:Utilize the foundation pit support method of the above-mentioned foundation pit support structure provided by the present invention, and the steps are as follows:
步骤一、根据场地条件和计算分析,在倾斜角度α(0°到30°)范围内,确定最优的钢板排桩倾斜角度,对桩长与桩身强度进行选择。
步骤二、开挖沟槽:根据基坑围护边线用挖机开挖沟槽,并清除地下障碍物,开挖沟槽土体应及时处理,以保证冠梁、连梁的正常施工。
步骤三、倾斜排桩施工,倾斜排桩使用钢板桩进行作业。采用单桩逐根打入法施打钢板桩。其过程如下:Step 3: Construction of inclined piles, and steel sheet piles are used for inclined piles. The steel sheet piles are driven by the single pile driving method one by one. The process is as follows:
1)施工准备工作:钢板桩在打入前将桩尖处的凹槽口封闭,避免泥土挤入,锁口处涂以黄油或其它油脂;对于年久失修,锁口变形,锈蚀严重的钢板桩,应进行整修矫正,对于弯曲变形的钢板桩,用油压千斤顶顶压或火烘等方法进行矫正。1) Construction preparations: Before driving the steel sheet pile, close the groove at the tip of the pile to avoid the intrusion of soil, and coat the lock with butter or other grease; The piles should be repaired and corrected. For the steel sheet piles that are bent and deformed, they should be corrected by methods such as hydraulic jack pressing or fire drying.
2)测量定位放线:由测量员放出钢板桩围护的轴线,每隔一定距离设置导向桩,导向桩直接使用钢板桩充当,然后挂绳线作为导线,打桩时利用导线控制钢板桩的轴线。2) Measuring and positioning the line: The surveyor releases the axis of the steel sheet pile enclosure, and sets up guide piles at certain distances. The guide piles are directly used as the steel sheet piles, and then the lanyard line is used as the wire, and the wire is used to control the axis of the steel sheet pile during piling. .
3)送桩:采用斜桩静压机吊起钢板桩,人工扶正就位,定位误差控制在<20mm;按照步骤一确定的倾斜角度0~30°、且向基坑内侧倾斜,斜桩应根据设计倾斜角度并结合下返深度及设备高度分别计算桩位线、入土线及对位线。桩位复核无误后,斜桩静压机方可按顺序施工。在打桩过程中。为保证钢板桩的角度。用两台经纬仪在两个方向加以控制。3) Feeding the piles: Use the inclined pile static press to lift the steel sheet piles, artificially straighten them in place, and control the positioning error to be less than 20mm; the inclined angle determined in
4)单桩逐根连续施打,注意桩顶高程不宜相差太大。在开始打设第一块钢板桩和第二块钢板桩过程中,为了确保位置和方向精确,以便起到导向样板作用,故每打入1m测量一次位置和方向,打至预定深度后立即用钢筋或钢板与围檩支架电焊作临时固定;4) The single piles are continuously driven one by one, and it should be noted that the heights of the pile tops should not be too different. In the process of driving the first sheet pile and the second sheet pile, in order to ensure the accurate position and direction, so as to play the role of a guide model, the position and direction are measured every time 1m is driven, and the position and direction are measured immediately after driving to the predetermined depth. Temporary fixing by electric welding of steel bars or steel plates and purlin brackets;
步骤四、隔水帷幕施工:在倾斜排桩施工的同时进行隔水帷幕的施工,位置沿基坑边外侧距离倾斜排桩桩顶0.5~1m处,且隔水帷幕的搅拌桩桩底标高与倾斜排桩桩底标高相同。Step 4. Construction of the water-proof curtain: The construction of the water-proof curtain is carried out at the same time as the construction of the inclined piles. The bottom elevations of the inclined piles are the same.
过程如下:The process is as follows:
1)定位:深层搅拌机到达指定桩位,对中。1) Positioning: The deep mixer reaches the designated pile position and aligns.
2)预搅下沉:待深层搅拌机的冷却水循环正常后,启动搅拌机电机,放松搅拌机吊索使搅拌机沿导向架搅拌切土下沉。2) Pre-mixing and sinking: After the cooling water circulation of the deep mixer is normal, start the motor of the mixer, loosen the sling of the mixer, and let the mixer stir and cut the soil along the guide frame and sink.
3)制备水泥浆:待深层搅拌机下沉到一定深度时,即开始按设计确定的配合比搅拌水泥浆,待压浆前将水泥浆倒入集料斗中。3) Preparation of cement slurry: When the deep mixer sinks to a certain depth, it starts to mix the cement slurry according to the mixing ratio determined by the design, and pours the cement slurry into the collecting hopper before grouting.
4)提升喷浆搅拌:深层搅拌机下沉到设计深度后,开启灰浆泵将水泥浆压入地基中,且边喷浆、边旋转,同时严格按照设计确定的提升速度提升深层搅拌机。4) Lifting and mixing: After the deep mixer sinks to the design depth, turn on the mortar pump to press the cement slurry into the foundation, and rotate while spraying, and at the same time lift the deep mixer in strict accordance with the lifting speed determined by the design.
5)重复上、下搅拌:深层搅拌机提升至设计深度的顶面标高时,集料斗中的水泥浆应正好排空。为时软土和水泥浆搅拌均匀,可再次将搅拌机边旋转边沉入土中,至设计加固深度后在将搅拌机提升出地面。5) Repeat up and down mixing: When the deep mixer is lifted to the top elevation of the design depth, the cement slurry in the hopper should be just emptied. In order to mix the soft soil and the cement slurry evenly, the mixer can be sunk into the soil while rotating again, and the mixer can be lifted out of the ground after reaching the designed reinforcement depth.
6)清洗:清洗全部管路中残存的水泥浆,并将粘附在搅拌头的软土清洗干净。6) Cleaning: Clean the remaining cement slurry in all pipelines, and clean the soft soil adhering to the mixing head.
7)移位:将深层搅拌机移至下一桩位,重复上述步骤。7) Shift: Move the deep mixer to the next pile position and repeat the above steps.
步骤五、冠梁施工:过程如下:Step 5. Crown beam construction: The process is as follows:
1)冠梁土方采用机械分区开挖,先开挖第一层土方至支护桩设计桩顶标高,清除余土后开始破除桩头浮浆至设计标高,桩芯顶面的混凝土要凿毛处理,清除桩顶浮渣,如设计标高桩头砼强度达不到设计要求,须继续破除直至砼质量达到设计要求,不足标高段冠梁砼时一同浇筑成型。1) The crown beam earthwork shall be excavated by mechanical partitions. First, the first layer of earthwork shall be excavated to the design pile top elevation of the supporting pile. After removing the remaining soil, the pile head floating slurry shall be removed to the design elevation. The concrete on the top surface of the pile core shall be chiseled. Treatment and removal of scum at the top of the pile. If the strength of the pile head concrete at the design elevation fails to meet the design requirements, it must continue to be demolished until the quality of the concrete meets the design requirements, and it is poured together when the concrete of the crown beam at the elevation section is insufficient.
2)桩间土人工整平至冠梁底标高,并夯填实密实。2) The soil between the piles is artificially leveled to the bottom elevation of the crown beam, and compacted and compacted.
3)桩头破除后即可按冠梁剖面配筋进行钢筋制作。钢筋下料、绑扎误差确保满足设计及施工规范要求。对冠梁分段浇筑的结合部位应预留钢筋。3) After the pile head is broken, the reinforcement can be made according to the section reinforcement of the crown beam. Rebar cutting and binding errors ensure that the design and construction specifications are met. Reinforcing bars should be reserved for the joint part of the crown beam segmented pouring.
4)对冠梁标高进行校核并安装模板。模板支护时须确保模板稳定、牢固,以防浇筑砼时模板变形,模板截面尺寸按冠梁剖面制作。4) Check the elevation of the crown beam and install the formwork. When the formwork is supported, it is necessary to ensure that the formwork is stable and firm to prevent the formwork from being deformed when the concrete is poured. The size of the formwork section is made according to the crown beam section.
5)完成钢筋工程。纵筋最好采用HRB335级或HRB400级钢筋,箍筋及拉结筋应采用HPB300级和HRB335级钢筋。侧面纵筋直径不应小于20mm,间距不应大于200mm;顶底面纵筋直径不应小于20mm,间距不应大于300mm;箍筋直径不应小于8mm,间距不应大于250mm;拉结筋直径应采用6~12mm,间距不应大于500mm。5) Complete the reinforcement works. Longitudinal reinforcement is best to use HRB335 or HRB400 steel, stirrups and tie bars should use HPB300 and HRB335 steel. The diameter of the side longitudinal bars should not be less than 20mm, and the spacing should not be greater than 200mm; the diameter of the top and bottom longitudinal bars should not be less than 20mm, and the spacing should not be greater than 300mm; the diameter of the stirrups should not be less than 8mm, and the spacing should not be greater than 250mm; the diameter of the tie bars should be Use 6 to 12mm, and the spacing should not be greater than 500mm.
6)完成混凝土浇筑及养护。混凝土强度等级不应低于C25,排桩主筋锚入冠梁不应小于35d(d为钢筋直径)。6) Complete the concrete pouring and curing. The concrete strength grade should not be lower than C25, and the anchoring of the main reinforcement of the row piles into the crown beam should not be less than 35d (d is the diameter of the reinforcement).
对于分层开挖的基坑,针对不同的排桩支护形式,重复上述步骤施工直至开挖至基坑的底部。For the foundation pit excavated in layers, for different pile support forms, repeat the above steps until the excavation reaches the bottom of the foundation pit.
步骤六、对基坑坑底进行清理、整平,并进行下一步的施工作业;Step 6. Clean and level the bottom of the foundation pit, and carry out the next construction operation;
步骤七、采用履带拨桩机配合振动锤拔桩;基础施工完成、回填后即可拔桩,过程如下:Step 7. Use the crawler pile pulling machine to cooperate with the vibrating hammer to pull out the pile; after the foundation construction is completed and the backfilling is completed, the pile can be pulled out. The process is as follows:
1)拆除冠梁。1) Remove the crown beam.
2)震动。先用打桩机夹住钢板桩头部振动1min~2min,使钢板桩周围的土松动,产生“液化”减少土对桩的摩擦力。2) Vibration. First, clamp the head of the steel sheet pile with a pile driver and vibrate it for 1 min to 2 min to loosen the soil around the steel sheet pile and produce "liquefaction" to reduce the friction force of the soil on the pile.
3)振拔。拔桩时注意桩机的负荷情况,发现上拔困难或拔不出来时,应停止拔桩,先振动1min~2min后再往下锤0.5~1.0m再往上振拔,如此反复可将桩拔出来。3) Vibrate. When pulling out the pile, pay attention to the load of the pile driver. When it is found that it is difficult to pull up or cannot be pulled out, the pile should be stopped. First vibrate for 1min-2min, then hammer down 0.5-1.0m and then vibrate upwards. Repeatedly, the pile can be pulled out. Pull out.
利用本发明提供的基坑支护方法,对于建设任务而言,能降低对空间的要求;在使用钢板桩的过程中,能简化检查材料系统性能的复杂程序保证其适应性、互换性良好。最重要的是,钢板桩可以回收重复利用,节约资金。The foundation pit support method provided by the invention can reduce the space requirements for construction tasks; in the process of using steel sheet piles, it can simplify the complex procedures for checking the performance of the material system to ensure good adaptability and interchangeability. . Most importantly, sheet piles can be recycled and reused, saving money.
尽管上面结合附图对本发明进行了描述,但是本发明并不局限于上述的具体实施方式,上述的具体实施方式仅仅是示意性的,而不是限制性的,本领域的普通技术人员在本发明的启示下,在不脱离本发明宗旨的情况下,还可以做出很多变形,这些均属于本发明的保护之内。Although the present invention has been described above in conjunction with the accompanying drawings, the present invention is not limited to the above-mentioned specific embodiments, which are merely illustrative rather than restrictive. Under the inspiration of the present invention, many modifications can be made without departing from the spirit of the present invention, which all belong to the protection of the present invention.
Claims (7)
Priority Applications (1)
| Application Number | Priority Date | Filing Date | Title |
|---|---|---|---|
| CN202010102565.6A CN111287194A (en) | 2020-02-19 | 2020-02-19 | Recyclable foundation pit support structure using inclined steel sheet piles and its support method |
Applications Claiming Priority (1)
| Application Number | Priority Date | Filing Date | Title |
|---|---|---|---|
| CN202010102565.6A CN111287194A (en) | 2020-02-19 | 2020-02-19 | Recyclable foundation pit support structure using inclined steel sheet piles and its support method |
Publications (1)
| Publication Number | Publication Date |
|---|---|
| CN111287194A true CN111287194A (en) | 2020-06-16 |
Family
ID=71023134
Family Applications (1)
| Application Number | Title | Priority Date | Filing Date |
|---|---|---|---|
| CN202010102565.6A Pending CN111287194A (en) | 2020-02-19 | 2020-02-19 | Recyclable foundation pit support structure using inclined steel sheet piles and its support method |
Country Status (1)
| Country | Link |
|---|---|
| CN (1) | CN111287194A (en) |
Cited By (3)
| Publication number | Priority date | Publication date | Assignee | Title |
|---|---|---|---|---|
| CN113309071A (en) * | 2021-05-31 | 2021-08-27 | 中南大学 | A hat-shaped steel sheet pile with stable connection and installation method |
| CN113756321A (en) * | 2021-08-31 | 2021-12-07 | 山东大学 | Full-recovery supporting system for temporary foundation pit components of subway station and construction method |
| CN117286827A (en) * | 2023-08-09 | 2023-12-26 | 哈尔滨工程大学 | River separation water-blocking structure and construction method |
Citations (7)
| Publication number | Priority date | Publication date | Assignee | Title |
|---|---|---|---|---|
| JP2006057253A (en) * | 2004-08-17 | 2006-03-02 | Railway Technical Res Inst | Steel sheet pile combined direct foundation method and steel sheet pile combined direct foundation |
| CN104912082A (en) * | 2014-03-14 | 2015-09-16 | 江苏东合南岩土工程技术研究有限公司 | Inclined assembled double-row steel sheet pile foundation pit supporting structure and construction method thereof |
| CN107513993A (en) * | 2017-08-22 | 2017-12-26 | 中交第四公路工程局有限公司 | Overlength Straight Combination steel sheet pile construction method |
| CN107620309A (en) * | 2017-07-27 | 2018-01-23 | 天津大学 | Foundation pit supporting method |
| CN107740419A (en) * | 2017-07-27 | 2018-02-27 | 天津大学 | Foundation pit supporting method and raked pile |
| CN109440780A (en) * | 2018-11-24 | 2019-03-08 | 天津大学 | Active inclination Single row pillars foundation pit supporting method |
| CN212248262U (en) * | 2020-02-19 | 2020-12-29 | 天津大学 | Recyclable foundation pit support structure using inclined steel sheet piles |
-
2020
- 2020-02-19 CN CN202010102565.6A patent/CN111287194A/en active Pending
Patent Citations (7)
| Publication number | Priority date | Publication date | Assignee | Title |
|---|---|---|---|---|
| JP2006057253A (en) * | 2004-08-17 | 2006-03-02 | Railway Technical Res Inst | Steel sheet pile combined direct foundation method and steel sheet pile combined direct foundation |
| CN104912082A (en) * | 2014-03-14 | 2015-09-16 | 江苏东合南岩土工程技术研究有限公司 | Inclined assembled double-row steel sheet pile foundation pit supporting structure and construction method thereof |
| CN107620309A (en) * | 2017-07-27 | 2018-01-23 | 天津大学 | Foundation pit supporting method |
| CN107740419A (en) * | 2017-07-27 | 2018-02-27 | 天津大学 | Foundation pit supporting method and raked pile |
| CN107513993A (en) * | 2017-08-22 | 2017-12-26 | 中交第四公路工程局有限公司 | Overlength Straight Combination steel sheet pile construction method |
| CN109440780A (en) * | 2018-11-24 | 2019-03-08 | 天津大学 | Active inclination Single row pillars foundation pit supporting method |
| CN212248262U (en) * | 2020-02-19 | 2020-12-29 | 天津大学 | Recyclable foundation pit support structure using inclined steel sheet piles |
Cited By (3)
| Publication number | Priority date | Publication date | Assignee | Title |
|---|---|---|---|---|
| CN113309071A (en) * | 2021-05-31 | 2021-08-27 | 中南大学 | A hat-shaped steel sheet pile with stable connection and installation method |
| CN113756321A (en) * | 2021-08-31 | 2021-12-07 | 山东大学 | Full-recovery supporting system for temporary foundation pit components of subway station and construction method |
| CN117286827A (en) * | 2023-08-09 | 2023-12-26 | 哈尔滨工程大学 | River separation water-blocking structure and construction method |
Similar Documents
| Publication | Publication Date | Title |
|---|---|---|
| CN111287193A (en) | Foundation pit support structure using steel sheet piles and precast concrete piles and its support method | |
| WO2023077552A1 (en) | Construction method for foundation pit enclosure and earth excavation | |
| CN105951711A (en) | Enclosing construction method of underground continuous wall of seashore power station | |
| CN109440778A (en) | Active two-way inclined pile foundation pit support method | |
| CN111560962A (en) | Backfill area foundation pit supporting structure and construction method thereof | |
| CN111287194A (en) | Recyclable foundation pit support structure using inclined steel sheet piles and its support method | |
| CN107366290A (en) | Foundation pit supporting method and raked pile | |
| CN111119198A (en) | A reinforced structure that is used for SMW worker method stake to strut system | |
| CN111851543A (en) | Cofferdam structure for narrow, long and deep foundation pit construction and its use method | |
| CN110055973B (en) | Foundation pit enclosure structure under high-speed railway bridge with limited construction space and water stopping method | |
| CN108978680B (en) | Mucky soil elevator foundation pit supporting construction device and method | |
| CN113266392B (en) | A construction method of pipe jacking through existing anchor cable groups | |
| CN110344394A (en) | A kind of surrounding deep foundation pit shallow embedding structure base ruggedized construction and construction method | |
| CN118110193A (en) | The whole process construction method of large diameter caisson in complex geological conditions | |
| CN113431097A (en) | Protection structure of shallow foundation building next to deep foundation pit engineering and construction method | |
| CN110258600B (en) | Vertical cofferdam construction method suitable for deepwater area | |
| CN115897600A (en) | Construction method for newly-built foundation pit close to existing subway station deep foundation pit proximity area | |
| CN213448506U (en) | Plugging structure arranged between foundation pit fender posts | |
| CN212248262U (en) | Recyclable foundation pit support structure using inclined steel sheet piles | |
| CN212248261U (en) | Foundation pit support structure using steel sheet piles and precast concrete piles | |
| CN111962522A (en) | A combined support structure of inclined wedge piles and vertical pipe piles and construction method thereof | |
| CN113266019B (en) | Construction method of foundation pit steel pipe support system | |
| CN116335086A (en) | Gravity type shore protection wall construction process | |
| CN212506314U (en) | A kind of pile-anchor support foundation pit deepening reinforcement support structure | |
| CN209816867U (en) | A supporting construction for peripheral foundation ditch of existing building |
Legal Events
| Date | Code | Title | Description |
|---|---|---|---|
| PB01 | Publication | ||
| PB01 | Publication | ||
| SE01 | Entry into force of request for substantive examination | ||
| SE01 | Entry into force of request for substantive examination | ||
| WD01 | Invention patent application deemed withdrawn after publication |
Application publication date: 20200616 |
|
| WD01 | Invention patent application deemed withdrawn after publication |