[go: up one dir, main page]

CN112434909B - A batch production satellite AIT process generation method based on element relationships - Google Patents

A batch production satellite AIT process generation method based on element relationships Download PDF

Info

Publication number
CN112434909B
CN112434909B CN202011192021.XA CN202011192021A CN112434909B CN 112434909 B CN112434909 B CN 112434909B CN 202011192021 A CN202011192021 A CN 202011192021A CN 112434909 B CN112434909 B CN 112434909B
Authority
CN
China
Prior art keywords
satellite
ait
work
project
flow
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Active
Application number
CN202011192021.XA
Other languages
Chinese (zh)
Other versions
CN112434909A (en
Inventor
张旭
迟军
吴振宇
郝文宇
周耀华
王东
王金刚
丛飞
柴智渊
朱位
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
China Academy of Space Technology CAST
Original Assignee
China Academy of Space Technology CAST
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by China Academy of Space Technology CAST filed Critical China Academy of Space Technology CAST
Priority to CN202011192021.XA priority Critical patent/CN112434909B/en
Publication of CN112434909A publication Critical patent/CN112434909A/en
Application granted granted Critical
Publication of CN112434909B publication Critical patent/CN112434909B/en
Active legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Classifications

    • GPHYSICS
    • G06COMPUTING OR CALCULATING; COUNTING
    • G06QINFORMATION AND COMMUNICATION TECHNOLOGY [ICT] SPECIALLY ADAPTED FOR ADMINISTRATIVE, COMMERCIAL, FINANCIAL, MANAGERIAL OR SUPERVISORY PURPOSES; SYSTEMS OR METHODS SPECIALLY ADAPTED FOR ADMINISTRATIVE, COMMERCIAL, FINANCIAL, MANAGERIAL OR SUPERVISORY PURPOSES, NOT OTHERWISE PROVIDED FOR
    • G06Q10/00Administration; Management
    • G06Q10/10Office automation; Time management
    • G06Q10/103Workflow collaboration or project management
    • GPHYSICS
    • G06COMPUTING OR CALCULATING; COUNTING
    • G06QINFORMATION AND COMMUNICATION TECHNOLOGY [ICT] SPECIALLY ADAPTED FOR ADMINISTRATIVE, COMMERCIAL, FINANCIAL, MANAGERIAL OR SUPERVISORY PURPOSES; SYSTEMS OR METHODS SPECIALLY ADAPTED FOR ADMINISTRATIVE, COMMERCIAL, FINANCIAL, MANAGERIAL OR SUPERVISORY PURPOSES, NOT OTHERWISE PROVIDED FOR
    • G06Q10/00Administration; Management
    • G06Q10/06Resources, workflows, human or project management; Enterprise or organisation planning; Enterprise or organisation modelling
    • G06Q10/063Operations research, analysis or management
    • G06Q10/0633Workflow analysis
    • YGENERAL TAGGING OF NEW TECHNOLOGICAL DEVELOPMENTS; GENERAL TAGGING OF CROSS-SECTIONAL TECHNOLOGIES SPANNING OVER SEVERAL SECTIONS OF THE IPC; TECHNICAL SUBJECTS COVERED BY FORMER USPC CROSS-REFERENCE ART COLLECTIONS [XRACs] AND DIGESTS
    • Y02TECHNOLOGIES OR APPLICATIONS FOR MITIGATION OR ADAPTATION AGAINST CLIMATE CHANGE
    • Y02PCLIMATE CHANGE MITIGATION TECHNOLOGIES IN THE PRODUCTION OR PROCESSING OF GOODS
    • Y02P90/00Enabling technologies with a potential contribution to greenhouse gas [GHG] emissions mitigation
    • Y02P90/30Computing systems specially adapted for manufacturing

Landscapes

  • Business, Economics & Management (AREA)
  • Human Resources & Organizations (AREA)
  • Engineering & Computer Science (AREA)
  • Strategic Management (AREA)
  • Entrepreneurship & Innovation (AREA)
  • Economics (AREA)
  • General Business, Economics & Management (AREA)
  • Marketing (AREA)
  • Operations Research (AREA)
  • Quality & Reliability (AREA)
  • Tourism & Hospitality (AREA)
  • Physics & Mathematics (AREA)
  • General Physics & Mathematics (AREA)
  • Theoretical Computer Science (AREA)
  • Data Mining & Analysis (AREA)
  • Development Economics (AREA)
  • Educational Administration (AREA)
  • Game Theory and Decision Science (AREA)
  • Management, Administration, Business Operations System, And Electronic Commerce (AREA)

Abstract

Under the condition of meeting the requirement of the whole project of the satellite, a single-star skeleton flow formed by each flow module is established based on the matching relation among elements of working projects of the satellite AIT stage, the matching condition based on the element relation among the flow modules in the skeleton flow is obtained, a single-star possible solution flow set is obtained by calculation according to the matching condition based on the element relation among the flow modules in the skeleton flow, the possible solution flow set of the batch satellite is obtained according to the delivery time of the satellite and the limiting requirement of element resource guarantee conditions, and the optimal batch production flow of a target range is obtained by comparison; in the process of executing the flow, the rest items after the flow is interrupted are used as new target ranges, and the same calculation and comparison methods are adopted to obtain the dynamically optimized batch satellite AIT flow. The invention greatly improves the development progress of the batch production satellite, greatly saves resources, reduces the development cost and improves the utilization rate of production resources and the working efficiency.

Description

一种基于要素关系的批产卫星AIT流程生成方法A batch production satellite AIT process generation method based on element relationships

技术领域Technical field

本发明涉及一种基于要素关系的批产卫星AIT流程生成方法,应用于卫星尤其是批产卫星研制的AIT流程设计领域。The invention relates to a method for generating AIT process for batch production satellites based on element relationships, which is applied to satellites, especially the field of AIT process design for batch production satellite development.

背景技术Background technique

在卫星研制过程中,部组件产品研制完成后,需要把部组件产品进行集成、总装形成整星后,完成整星级的测试和试验,确认整星符合设计和用户要求后,对按照进入发射场的状态完成卫星出厂前的总装和测试工作,将卫星运抵发射场开展发射场的发射工作。对部组件产品进行整星的集成、总装、测试(含试验)即AIT,对应AIT的卫星研制阶段即卫星AIT阶段,对应AIT的卫星研制流程即卫星AIT流程。In the satellite development process, after the development of component products is completed, the component products need to be integrated and assembled to form a complete satellite. After completing the testing and testing of the entire star, it is confirmed that the entire satellite meets the design and user requirements, and then the launch is carried out according to the requirements. The state of the field completes the final assembly and testing of the satellite before leaving the factory, and transports the satellite to the launch site to carry out launch work at the launch site. The integration, final assembly, and testing (including testing) of the entire satellite for component products is AIT. The satellite development stage corresponding to AIT is the satellite AIT stage. The satellite development process corresponding to AIT is the satellite AIT process.

卫星AIT流程中,一般需要进行各个阶段的总装、测试,并根据要求完成力学试验、热试验、磁试验、EMC试验,以及与运载、用户等系统的系统级对接等试验。国内传统的卫星AIT流程以几个大的试验项目为基准,采用传统的项目顺序固定不变,当某个项目意外中断时,或者等待该项目重启,或者忍受具备条件风险的情况下继续后续项目。In the satellite AIT process, it is generally necessary to conduct final assembly and testing at various stages, and complete mechanical tests, thermal tests, magnetic tests, EMC tests, and system-level docking with carrier, user and other systems as required. The traditional domestic satellite AIT process is based on several large test projects, and the traditional project sequence is fixed. When a project is unexpectedly interrupted, one has to wait for the project to restart, or continue with subsequent projects while enduring the necessary risks. .

近年来,随着卫星研制数量的增加和星座系统的建设需求,出现相同或相近状态的一系列卫星按照组批方式进行研制的模式。为充分利用人员、试验场地等各种研制资源,并保证研制的进度,批产卫星研制的模式逐渐区别于单星的模式,相应的批产卫星AIT流程也与单星AIT流程有所区别。这方面国内比较典型的批产卫星研制的项目是北斗导航卫星系统。适应我国北斗全球组网的批产卫星研制,满足快速组网的工程建设需求,需要越来越短的卫星研制发射周期,最关键的就是在保证质量标准的条件下对卫星AIT流程的优化,在北斗全球组网批产卫星研制中采用了一种优化的方法,实现了单星进度优化3个月的效果,批产卫星也提前完成北斗组网计划。In recent years, with the increase in the number of satellites developed and the construction needs of constellation systems, a series of satellites in the same or similar status have been developed in batches. In order to make full use of various development resources such as personnel and test sites and ensure the progress of development, the batch production satellite development model is gradually different from the single-satellite model, and the corresponding batch production satellite AIT process is also different from the single-satellite AIT process. In this regard, a typical domestic mass-produced satellite development project is the Beidou navigation satellite system. To adapt to the batch production satellite development of my country's Beidou global network and meet the engineering construction needs of rapid network, shorter and shorter satellite development and launch cycles are required. The most critical thing is to optimize the satellite AIT process while ensuring quality standards. An optimization method was adopted in the development of Beidou global network batch production satellites, which achieved the effect of optimizing the progress of a single satellite for 3 months. The batch production satellites also completed the Beidou network plan ahead of schedule.

发明内容Contents of the invention

本发明解决的问题是:克服传统卫星AIT流程设计的不足,提供了一种基于要素关系的批产卫星AIT流程生成方法。本发明的方法基于卫星AIT阶段工作项目衔接的核心关系——要素间的匹配关系,在满足卫星整体项目要求的情况下,能够设计获得最优(即周期最短)的批产卫星AIT流程,并能够在执行流程的过程中实现动态优化,大大提高了批产卫星的研制进度;大大减少了项目间的人员交接次数,节约人力和设备等资源,从而降低研制成本,提高了生产资源利用率和工作效率,并可简化应用于单颗卫星的AIT流程优化。The problem solved by the present invention is to overcome the shortcomings of traditional satellite AIT process design and provide a batch satellite AIT process generation method based on element relationships. The method of the present invention is based on the matching relationship between elements, which is the core relationship of the work project connection in the satellite AIT stage. Under the condition of meeting the requirements of the overall satellite project, the optimal (ie, the shortest cycle) batch production satellite AIT process can be designed, and It can achieve dynamic optimization during the execution process, greatly improving the development progress of batch production satellites; greatly reducing the number of personnel handovers between projects, saving resources such as manpower and equipment, thereby reducing development costs, improving production resource utilization and work efficiency, and can simplify the AIT process optimization applied to a single satellite.

本发明的技术解决方案是:The technical solution of the present invention is:

一种基于要素关系的批产卫星AIT流程生成方法,包括步骤如下:A batch production satellite AIT process generation method based on element relationships includes the following steps:

1)确定多颗卫星在AIT阶段需要开展的工作内容,将工作内容逐级分解直至不可再分为止,获得不可再分解的工作项目并作为基本单元的单星AIT阶段的工作项目集合;1) Determine the work content that multiple satellites need to carry out in the AIT phase, decompose the work content step by step until it cannot be divided anymore, obtain the work items that cannot be further divided, and use them as the basic unit of the work item set for the single-satellite AIT stage;

2)确定开展卫星AIT阶段各工作项目的核心要素,组成需要的颗粒度的AIT工作要素集;确定步骤1)所述工作项目集合中每个工作项目对应核心要素的具体内容;所述核心要素由星方面的要素、人方面的要素、机方面的要素、料方面的要素和环境方面的要素中的几个或全部组成;2) Determine the core elements of each work item in the satellite AIT stage to form an AIT work element set with the required granularity; determine the specific content of the core elements corresponding to each work item in the work item set in step 1); the core elements It is composed of several or all of the star elements, human elements, machine elements, material elements and environmental elements;

3)针对每个单星,分析确定必须按先后固定顺序开展的工作项目,形成单星存在紧耦合关系的项目关系清单;其余相互间无先后固定顺序要求的工作项目作为松耦合项目;3) For each single satellite, analyze and determine the work projects that must be carried out in a fixed order, and form a list of project relationships with a tight coupling relationship for the single satellite; the remaining work projects that have no fixed order requirements are regarded as loosely coupled projects;

4)对每颗单星,分别将紧耦合项目关系清单中的工作项目按先后固定顺序排列形成流程模块,同时,每个松耦合项目也作为一个流程模块,形成由各个流程模块组成的单星骨架流程;4) For each single star, the work items in the tightly coupled project relationship list are arranged in a fixed order to form a process module. At the same time, each loosely coupled project is also used as a process module to form a single star composed of various process modules. skeleton process;

5)将流程模块中的第一个项目作为该流程模块的输入项目,将流程模块中的最后一个项目作为该流程模块的输出项目,根据流程模块间要素关系匹配条件,遍历所有流程模块,分析两两流程模块间是否匹配;5) Use the first item in the process module as the input item of the process module, and use the last item in the process module as the output item of the process module. According to the matching conditions of the element relationships between process modules, traverse all process modules and analyze Whether there is a match between the two process modules;

6)排列组合,给出所有流程模块可能的排列方案,每个方案作为一个可能解流程集,获得多个可能解流程集;即,形成包含卫星AIT阶段全部工作项目的全流程的可能解的流程集;6) Permutation and combination, giving the possible arrangement schemes of all process modules, each scheme is regarded as a possible solution process set, and multiple possible solution process sets are obtained; that is, a possible solution is formed that includes the entire process of all work items in the satellite AIT stage process set;

7)根据卫星发射时间要求确定的出厂先后顺序,以及每个工作项目对应核心要素的资源保障条件的限制要求,筛选获得满足限制要求的可能解流程集;7) Based on the factory order determined by the satellite launch time requirements and the restriction requirements of the resource guarantee conditions corresponding to the core elements of each work project, screen out a set of possible solution processes that meet the restriction requirements;

8)根据用户对卫星发射时间的细化限制要求和权重原则,从步骤7)筛选获得的可能解流程集中比较获得最优的可能解流程集作为批量生产流程,执行投产任务。8) According to the user's detailed restriction requirements and weighting principles for satellite launch time, the possible solution processes obtained from step 7) are intensively compared to obtain the optimal set of possible solution processes as a mass production process to execute the production task.

在执行批量生产流程中,如批量生产流程发生流程执行中断,以各卫星剩余未完成的工作项目组成新的流程模块,再次进行步骤6)~8),获得剩余未完成项目的最优批产流程,即为批产卫星AIT流程执行过程中的动态优化。During the execution of the mass production process, if the process execution of the mass production process is interrupted, a new process module is formed with the remaining unfinished work items of each satellite, and steps 6) to 8) are performed again to obtain the optimal batch production of the remaining unfinished items. The process is the dynamic optimization during the execution of the batch production satellite AIT process.

当批产卫星数量设置为1时,即为单星AIT流程的生成方法。When the number of batch-produced satellites is set to 1, it is the generation method of the single-satellite AIT process.

本发明与现有技术相比的优点在于:The advantages of the present invention compared with the prior art are:

1)本发明给出了实现批产卫星AIT流程生成方法的步骤,能够在满足卫星整体项目要求的情况下,获得研制周期最短的批产卫星AIT流程。1) The present invention provides steps for realizing a batch production satellite AIT process generation method, which can obtain the batch production satellite AIT process with the shortest development cycle while meeting the overall satellite project requirements.

2)本发明的方法除适用于卫星开展AIT工作之前的AIT流程设计之外,还适用于执行AIT流程中的动态优化。2) The method of the present invention is not only suitable for the AIT process design before the satellite carries out AIT work, but also suitable for dynamic optimization in the execution of the AIT process.

3)本发明的方法除了适用于批产卫星研制外,还可以将批产卫星数量设定为1,从而适用于单星研制。3) In addition to being suitable for the development of batch-produced satellites, the method of the present invention can also set the number of batch-produced satellites to 1, thereby being suitable for the development of single-satellites.

附图说明Description of the drawings

图1为本发明的基于要素关系的批产卫星AIT流程生成方法示意图。Figure 1 is a schematic diagram of the batch production satellite AIT process generation method based on element relationships of the present invention.

图2为采用本发明前的单星AIT阶段流程示意图。Figure 2 is a schematic flow chart of the single-star AIT stage before the present invention is adopted.

图3为采用本发明前的双星AIT阶段流程示意图。Figure 3 is a schematic flow diagram of the dual-star AIT stage before the present invention is adopted.

图4为采用本发明后的单星骨架流程示意图。Figure 4 is a schematic flow diagram of a single satellite skeleton after adopting the present invention.

图5为采用本发明优化后的双星AIT阶段流程示意图。Figure 5 is a schematic flow diagram of the dual-star AIT stage after optimization using the present invention.

具体实施方式Detailed ways

本方法能够获得研制周期最短的批产卫星AIT流程;并能在执行流程过程中实现动态优化;除了适用于批产卫星外,也适用于单星研制,并能够在执行流程的过程中实现动态优化。This method can obtain the batch-production satellite AIT process with the shortest development cycle; and can achieve dynamic optimization during the execution of the process; in addition to being suitable for batch-production satellites, it is also suitable for single-satellite development, and can achieve dynamic optimization during the execution of the process. optimization.

如图1所示为本发明的基于要素关系的批产卫星AIT流程生成方法示意图,包括步骤如下:Figure 1 shows a schematic diagram of the batch production satellite AIT process generation method based on element relationships of the present invention, which includes the following steps:

1)确定多颗卫星在AIT阶段需要开展的工作内容,将工作内容逐级分解直至不可再分为止,获得不可再分解的工作项目并作为基本单元的单星AIT阶段的工作项目集合;1) Determine the work content that multiple satellites need to carry out in the AIT phase, decompose the work content step by step until it cannot be divided anymore, obtain the work items that cannot be further divided, and use them as the basic unit of the work item set for the single-satellite AIT stage;

2)确定开展卫星AIT阶段各工作项目的核心要素,组成需要的颗粒度的AIT工作要素集;确定步骤1)所述工作项目集合中每个工作项目对应核心要素的具体内容;所述核心要素由星方面的要素、人方面的要素、机方面的要素、料方面的要素和环境方面的要素中的几个或全部组成;2) Determine the core elements of each work item in the satellite AIT stage to form an AIT work element set with the required granularity; determine the specific content of the core elements corresponding to each work item in the work item set in step 1); the core elements It is composed of several or all of the star elements, human elements, machine elements, material elements and environmental elements;

3)针对每个单星,分析确定必须按先后固定顺序开展的工作项目,形成单星存在紧耦合关系的项目关系清单;其余相互间无先后固定顺序要求的工作项目作为松耦合项目;3) For each single satellite, analyze and determine the work projects that must be carried out in a fixed order, and form a list of project relationships with a tight coupling relationship for the single satellite; the remaining work projects that have no fixed order requirements are regarded as loosely coupled projects;

4)对每颗单星,分别将紧耦合项目关系清单中的工作项目按先后固定顺序排列形成流程模块,同时,每个松耦合项目也作为一个流程模块,形成由各个流程模块组成的单星骨架流程;4) For each single star, the work items in the tightly coupled project relationship list are arranged in a fixed order to form a process module. At the same time, each loosely coupled project is also used as a process module to form a single star composed of various process modules. skeleton process;

5)将流程模块中的第一个项目作为该流程模块的输入项目,将流程模块中的最后一个项目作为该流程模块的输出项目,根据流程模块间要素关系匹配条件,遍历所有流程模块,分析两两流程模块间是否匹配;5) Use the first item in the process module as the input item of the process module, and use the last item in the process module as the output item of the process module. According to the matching conditions of the element relationships between process modules, traverse all process modules and analyze Whether there is a match between the two process modules;

6)排列组合,给出所有流程模块可能的排列方案,每个方案作为一个可能解流程集,获得多个可能解流程集;即,形成包含卫星AIT阶段全部工作项目的全流程的可能解的流程集.6) Permutation and combination, giving the possible arrangement schemes of all process modules, each scheme is regarded as a possible solution process set, and multiple possible solution process sets are obtained; that is, a possible solution is formed that includes the entire process of all work items in the satellite AIT stage Process set.

7)根据卫星发射时间要求确定的出厂时间先后顺序,以及每个工作项目对应核心要素的资源保障条件的限制要求,筛选获得满足限制要求的可能解流程集;7) Based on the factory time sequence determined by the satellite launch time requirements and the restriction requirements of the resource guarantee conditions corresponding to the core elements of each work project, screen out a set of possible solution processes that meet the restriction requirements;

8)根据用户对卫星发射时间的细化限制要求和权重原则,从步骤7)筛选获得的可能解流程集中比较获得最优的可能解流程集作为批量生产流程,执行投产任务。8) According to the user's detailed restriction requirements and weighting principles for satellite launch time, the possible solution processes obtained from step 7) are intensively compared to obtain the optimal set of possible solution processes as a mass production process to execute the production task.

在执行批量生产流程中,如批量生产流程发生流程执行中断,以各卫星剩余未完成的工作项目组成新的流程模块,再次进行步骤6)~8),获得剩余未完成项目的最优批产流程,即为批产卫星AIT流程执行过程中的动态优化。During the execution of the mass production process, if the process execution of the mass production process is interrupted, a new process module is formed with the remaining unfinished work items of each satellite, and steps 6) to 8) are performed again to obtain the optimal batch production of the remaining unfinished items. The process is the dynamic optimization during the execution of the batch production satellite AIT process.

当批产卫星数量设置为1时,即为单星AIT流程的生成方法。When the number of batch-produced satellites is set to 1, it is the generation method of the single-satellite AIT process.

具体步骤如下:Specific steps are as follows:

(1)分解工作内容,确定单颗卫星在AIT阶段的工作项目集合。根据卫星研制需要,确定卫星在AIT阶段需要开展的工作内容,对工作内容进行逐级分解至不可再分解的项目为止,获得不可再分解的工作项目并作为基本单元的单星AIT阶段的工作项目集合。确定项目是否不可再分解的原则是:该项目的颗粒度在时间上不可再分割,及一旦项目开始,到项目结束之前不可分割或中断,如果再分割或中断,只能重新开始并完成整个项目。如整星测试工作内容可分为各个不同阶段、不同状态的测试项目,热试验工作内容一般为不可再分解项目。(1) Decompose the work content and determine the set of work items for a single satellite in the AIT stage. According to the needs of satellite development, determine the work content that needs to be carried out by the satellite in the AIT stage, decompose the work content step by step until it can no longer be decomposed, and obtain the work items that cannot be decomposed again and serve as the basic unit of the work items in the single-satellite AIT stage. gather. The principle for determining whether a project cannot be further divided is: the granularity of the project cannot be divided again in time, and once the project starts, it cannot be divided or interrupted until the end of the project. If it is divided or interrupted again, the entire project can only be restarted and completed. . For example, the entire satellite test work content can be divided into test items in different stages and different states, and the thermal test work content is generally non-decomposable items.

(2)确定开展卫星AIT阶段各工作项目的核心要素和各工作项目核心要素的具体内容。根据确定的单颗卫星在AIT阶段的工作项目集合,确定卫星AIT阶段各项工作项目的核心要素,组成AIT工作要素集;对单颗卫星在AIT阶段的各工作项目,确定其要素的具体内容。各所述要素是指:一个项目衔接另一个项目时的匹配条件。(2) Determine the core elements of each work project in the satellite AIT stage and the specific content of the core elements of each work project. Based on the determined set of work items for a single satellite in the AIT stage, determine the core elements of each work item in the AIT stage of the satellite to form an AIT work element set; for each work item of a single satellite in the AIT stage, determine the specific content of its elements . Each of the mentioned factors refers to the matching conditions when one project is connected to another project.

一般可以从“星、人、机、料、环”五个方面要素形成要素集,对应五方面要素的内容如下:Generally, an element set can be formed from the five elements of "star, people, machine, material, and environment". The content corresponding to the five elements is as follows:

①“星”方面的要素,即该项目相关的卫星状态,是硬件状态、软件状态、整星组合状态三方面的集合。每个项目有输入状态、输出状态两种“星”方面的要素,分别对应开展该项目需要的卫星状态、开展该项目后的卫星状态。硬件状态指组成卫星需要装星齐套的对应设备;软件状态指设备中装载的对应软件;整星组合状态指卫星整体的总装状态,包括整星放置状态和各舱段状态,整星放置状态一般有水平放置、垂直放置两种状态,各舱段状态一般有平台开舱/合舱、载荷舱开舱/合舱等状态,不同卫星的整星组合状态定义和分类会根据卫星特点而不同。硬件状态、软件状态、整星组合状态三方面要素按照相互独立处理。① The "star" element, that is, the status of the satellite related to the project, is a collection of three aspects: hardware status, software status, and overall satellite combination status. Each project has two "star" elements, input status and output status, which respectively correspond to the satellite status required to carry out the project and the satellite status after the project is carried out. The hardware status refers to the corresponding equipment that composes the satellite and needs to be installed in a complete set of satellites; the software status refers to the corresponding software loaded in the equipment; the entire satellite combination status refers to the overall assembly status of the satellite, including the entire satellite placement status and the status of each module. The entire satellite placement status Generally, there are two states: horizontal placement and vertical placement. The state of each compartment generally includes platform open/closed, load bay open/closed, etc. The definition and classification of the entire satellite combination state of different satellites will be different according to the characteristics of the satellite. . The three elements of hardware status, software status, and overall star combination status are treated independently of each other.

根据方法的颗粒度,可以在较粗的层次实现,给出组成卫星的总的硬件状态、组成卫星的总的软件状态、总的整星组合状态的集合,如硬件,软件,整星组合状态;也可以在较细的层次实现,给出各设备、各软件、总的整星组合状态的集合,如硬件1,硬件5,…,软件1,软件3,…,整星水平放置、平台开舱、载荷舱合舱;即表示硬件1和硬件5等硬件设备齐备,软件1和软件3等软件齐备,且卫星处于整星水平放置、平台开舱、载荷舱合舱的状态。其中的每一项称为一项“星”要素。Depending on the granularity of the method, it can be implemented at a coarser level, giving the total hardware status of the satellite, the total software status of the satellite, and the total satellite combination status, such as hardware, software, and the entire satellite combination status. ; It can also be implemented at a finer level, giving a collection of each device, each software, and the overall star combination status, such as hardware 1, hardware 5,..., software 1, software 3,..., the entire star is placed horizontally, and the platform Open and load bay closed; this means that the hardware equipment such as Hardware 1 and Hardware 5 are complete, the software such as Software 1 and Software 3 are complete, and the satellite is in a state where the entire satellite is placed horizontally, the platform is open, and the load bay is closed. Each of these is called a "star" element.

②“人”方面的要素,即开展该项目需要的人员条件,是总装人员、测试人员、试验人员、总体人员四方面的集合。总装人员、测试人员、试验人员、总体人员分别是负责总装操作的各类人员、整星测试的各类人员、整星试验的各类人员、整星总体工作的各类人员。总装人员、测试人员、试验人员、总体人员四方面要素相互独立处理。②The "people" element, that is, the personnel conditions required to carry out the project, is a collection of four aspects: assembly personnel, testers, test personnel, and overall personnel. The general assembly personnel, testers, test personnel, and general personnel are respectively the various personnel responsible for the final assembly operation, the various personnel for the entire satellite test, the various personnel for the entire satellite test, and the various personnel for the overall work of the entire satellite. The four elements of assembly personnel, testers, testing personnel, and overall personnel are handled independently of each other.

根据方法的颗粒度,可以在较粗的层次实现,给出总的总装人员、总的测试人员、总的试验人员、总的总体人员的集合,如总装人员,测试人员,试验人员、总体人员;也可以在较细的层次实现,给出细化的四方面人员的集合,如总装钳工人员,总装电装人员,…,测试指挥,测试电源人员,…,热试验指挥,热试验控制人员,…,卫星总体人员,电源总体人员,…,即表示总装钳工人员和总装电装人员等总装人员、测试指挥和测试电源人员等测试人员,热试验指挥和热试验控制人员等试验人员、卫星总体人员和电源总体人员等总体人员齐备的状态。其中的每一项称为一项“人”要素。Depending on the granularity of the method, it can be implemented at a coarser level, giving a collection of total assembly personnel, total testing personnel, total testing personnel, and total overall personnel, such as assembly personnel, testing personnel, testing personnel, and overall personnel. ; It can also be implemented at a finer level, giving a detailed set of personnel from four aspects, such as final assembly fitters, final assembly electrical installation personnel,..., test directors, test power supply personnel,..., thermal test directors, thermal test control personnel ,..., the overall personnel of the satellite, the overall personnel of the power supply,..., which means the general assembly personnel such as the general assembly fitters and the general assembly electrical installation personnel, the test personnel such as the test commander and the test power supply personnel, the thermal test commander and the thermal test controller and other test personnel, satellite The state that all personnel including general personnel and power supply personnel are fully prepared. Each of these is called a "human" element.

③“机”方面的要素,即开展该项目需要的地面设备保障条件,是卫星的地面工装设备、地面测试设备两方面的集合。地面工装设备、地面测试设备分别是用于对卫星总装操作、整星测试的各类地面设备。地面工装设备、地面测试设备两方面要素相互独立处理。③The "machine" element, that is, the ground equipment support conditions required to carry out the project, is a collection of satellite ground tooling equipment and ground test equipment. Ground tooling equipment and ground test equipment are various types of ground equipment used for satellite assembly operations and complete satellite testing respectively. The two elements of ground tooling equipment and ground testing equipment are handled independently of each other.

根据方法的颗粒度,可以在较粗的层次实现,给出总的总装人员、总的测试人员、总的试验人员、总的总体人员的集合,如地面工装设备,地面测试设备;也可以在较细的层次实现,给出细化的两方面地面设备的集合,如地面支架车,太阳翼展开支架,…,总控测试设备,电源测试设备,…;即表示地面支架车和太阳翼展开支架等地面工装设备、总控测试设备和电源测试设备等地面测试设备齐备的状态。其中的每一项称为一项“机”要素。Depending on the granularity of the method, it can be implemented at a coarser level, giving a collection of total assembly personnel, total testing personnel, total testing personnel, and total overall personnel, such as ground tooling equipment and ground testing equipment; it can also be implemented at a coarser level. Implementation at a finer level provides a detailed set of two aspects of ground equipment, such as ground support vehicles, solar wing deployment supports,..., general control test equipment, power supply test equipment,...; that is, ground support vehicles and solar wing deployment Ground tooling equipment such as brackets, general control test equipment, power supply test equipment and other ground test equipment are in complete condition. Each of these items is called a "machine" element.

④“料”,即开展该项目需要的辅助物料条件,尤其是稀缺的物料资源条件,是紧固件、支架、辅材三方面物料的集合。紧固件、支架、辅材分别是用于紧固、支撑、其它辅助操作的各类辅助物料。紧固件、支架、辅材三方面要素相互独立处理。④ "Materials" refers to the auxiliary material conditions required to carry out the project, especially the scarce material resource conditions. It is a collection of fasteners, brackets and auxiliary materials. Fasteners, brackets, and auxiliary materials are various types of auxiliary materials used for fastening, support, and other auxiliary operations. The three elements of fasteners, brackets and auxiliary materials are processed independently of each other.

根据方法的颗粒度,可以在较粗的层次实现,给出总的紧固件、总的支架、总的辅材的集合,如紧固件、支架、辅材;也可以在较细的层次实现,给出细化的三方面辅助物料的集合,如螺钉,垫片,…,相机支架,电池支架,…,尼龙扎带,硅橡胶,…;即表示螺钉和垫片等紧固件、相机支架和电池支架等支架、尼龙扎带和硅橡胶等辅材齐备的状态。其中的每一项称为一项“料”要素。Depending on the granularity of the method, it can be implemented at a coarser level, giving a collection of total fasteners, total brackets, and total auxiliary materials, such as fasteners, brackets, and auxiliary materials; it can also be implemented at a finer level. Realization, giving a detailed set of three auxiliary materials, such as screws, gaskets,..., camera brackets, battery brackets,..., nylon ties, silicone rubber,...; that is, fasteners such as screws and gaskets, The camera holder, battery holder and other brackets, as well as auxiliary materials such as nylon ties and silicone rubber are fully prepared. Each of these items is called a "material" element.

⑤“环”,即开展该项目需要的环境条件,是卫星总装或测试需要的地面环境条件的集合,通常环境条件包括电测工位、噪声试验间,随机振动力学试验间,热真空罐,EMC试验间,检漏间等;特殊情况下在外场试验时可能将天气、地质等外部条件纳入。⑤ "Ring" refers to the environmental conditions required to carry out the project. It is a collection of ground environmental conditions required for satellite assembly or testing. Usually the environmental conditions include electrical measurement stations, noise test rooms, random vibration dynamics test rooms, and thermal vacuum tanks. EMC test room, leak detection room, etc.; under special circumstances, external conditions such as weather and geology may be included in field tests.

根据方法的颗粒度,可以在较粗的层次实现,给出总的环境条件的集合,如环境条件;也可以在较细的层次实现,给出细化的环境条件的集合,如测试试验工位,温度;即表示测试试验工位、环境温度两方面的环境条件状态。其中的每一项称为一项“环”要素。Depending on the granularity of the method, it can be implemented at a coarser level, giving a set of total environmental conditions, such as environmental conditions; it can also be implemented at a finer level, giving a set of refined environmental conditions, such as testing and testing work. Position, temperature; that is, it represents the environmental conditions of the test station and ambient temperature. Each of these items is called a "ring" element.

AIT工作要素集可以采用粗颗粒度的方法,表示为{硬件,软件,整星组合状态};{硬件,软件,整星组合状态};{总装人员,测试人员,试验人员,总体人员},{地面工装设备,地面测试设备},{紧固件,支架,辅材},{环境条件},或进一步细化表示。其中先后两次出现的“{硬件,软件,整星组合状态}”分别对应输入状态、输出状态两种状态的“星”方面要素。The AIT work element set can use a coarse-grained method, expressed as {hardware, software, whole star combination status}; {hardware, software, whole star combination status}; {general assembly personnel, testers, test personnel, overall personnel}, {Ground tooling equipment, ground testing equipment}, {fasteners, brackets, auxiliary materials}, {environmental conditions}, or further refinement. Among them, "{hardware, software, whole star combination state}" that appears twice corresponds to the "star" aspects of the input state and output state respectively.

采用粗颗粒度的方法,直接用“星、人、机、料、环”五个方面的要素组成AIT工作要素集,则后续求解单星或批产卫星最优流程的复杂度低,但精细化不够,细节可能被忽略而影响实际流程执行;采用细颗粒度的方法,可以将这五个方面要素细化成要素子集后组成AIT工作要素集,则后续求解单星或批产卫星最优流程的细节周到,但复杂度高。可以根据卫星型号优化的程度要求,选择对应颗粒度的AIT工作要素集。Adopting a coarse-grained method and directly using the five elements of "satellites, people, machines, materials, and environment" to form the AIT work element set, the subsequent solution of the optimal process for single satellites or batch production satellites will be low-complexity, but precise. If not refined enough, details may be ignored and affect the actual process execution; using a fine-grained method, these five aspects can be refined into element subsets to form an AIT work element set, and then the optimal single-satellite or batch-production satellite can be subsequently solved. The details of the process are thoughtful, but the complexity is high. The AIT work factor set corresponding to the granularity can be selected according to the degree of optimization requirements of the satellite model.

在确定AIT工作要素集的基础上,确定各项目的要素的具体内容。如某项的要素表示为:{蓄电池组,卫星水平放置};{蓄电池组,应答机,卫星水平放置};{总装电装人员},{整星支架车},{螺钉,垫片},{电测工位},即表示该项目需要蓄电池组装星条件、卫星水平放置下开展,完成后蓄电池组、应答机均装星、卫星水平放置;需要总装电装人员操作,需要整星支架车设备,需要螺钉、垫片两种辅材,在电测工位实施。On the basis of determining the set of AIT work elements, determine the specific content of the elements of each project. For example, the elements of a certain item are expressed as: {battery pack, satellite placed horizontally}; {battery pack, transponder, satellite placed horizontally}; {general assembly and electrical installation personnel}, {whole satellite support vehicle}, {screws, washers}, {Electrical test station} means that the project needs to be carried out under battery assembly conditions and the satellite is placed horizontally. After completion, the battery pack and transponder are installed and the satellite is placed horizontally; it requires the operation of the general assembly and electrical installation personnel, and the entire satellite support vehicle is required The equipment requires two auxiliary materials, screws and gaskets, which are implemented at the electrical measurement station.

(3)确定单星紧耦合项目关系清单。按照卫星研制的标准、规范、特定工作要求,分析明确必须先后衔接开展的项目,其项目间的关系即为紧耦合项目关系,给出其清单。其它项目即为松耦合的项目。(3) Determine the single-satellite tightly coupled project relationship list. According to the standards, specifications, and specific work requirements of satellite development, the projects that must be carried out successively are analyzed and clarified. The relationship between the projects is a tightly coupled project relationship, and a list is given. Other projects are loosely coupled projects.

(4)建立单星骨架流程。即将紧耦合项目关系清单中涉及的项目按照紧耦合项目关系,相同项目进行合并,建立各项目组成的流程模块,各松耦合的项目也作为一个流程模块看待,形成各流程模块组成的单星骨架流程。所述骨架流程是指由各流程模块组成的松散的流程。骨架流程不一定衔接全部项目,即流程模块间不一定衔接,在下面两个步骤中调整获得衔接全部项目的流程。(4) Establish a single-star skeleton process. That is, the projects involved in the tightly coupled project relationship list are merged according to the tightly coupled project relationship, and the same projects are merged to establish process modules composed of each project. Each loosely coupled project is also treated as a process module to form a single star skeleton composed of each process module. process. The skeleton process refers to a loose process composed of various process modules. The skeleton process may not necessarily connect all projects, that is, the process modules may not necessarily connect. Adjust the process in the following two steps to obtain a process that connects all projects.

(5)获得骨架流程中各流程模块间基于要素关系的匹配情况。按照如下方法判定两个流程模块间的要素关系是否匹配:(5) Obtain the matching situation based on element relationships between each process module in the skeleton process. Use the following method to determine whether the element relationships between two process modules match:

①将流程模块中的第一个项目、最后一个项目分别作为该流程模块的输入项目、输出项目。① Use the first project and the last project in the process module as the input project and output project of the process module respectively.

②分析两个流程模块间是否匹配。如果一个流程模块B的输入项目与另一个流程模块A的输出项目满足如下的匹配条件,则认为流程模块B匹配流程模块A:②Analyze whether there is a match between the two process modules. If the input items of one process module B and the output items of another process module A meet the following matching conditions, then process module B is considered to match process module A:

a.流程模块B的输入项目的输入状态、流程模块A的输出项目的输出状态的所有“星”要素项的状态完全相同。a. The status of all "star" element items of the input status of the input item of process module B and the output status of the output item of process module A are exactly the same.

b.流程模块A输出项目完成并释放人力资源后,流程模块B的输入项目的的所有“人”要素项可以满足项目需求,即开展流程模块B输入项目的人力资源可以保证。b. After the output project of process module A is completed and human resources are released, all "people" element items of the input project of process module B can meet the project requirements, that is, the human resources for carrying out the input project of process module B can be guaranteed.

c.流程模块A输出项目完成并释放地面设备资源后,流程模块B的输入项目的所有“机”要素项可以满足项目需求,即开展流程模块B输入项目的地面设备资源可以保证。c. After the output project of process module A is completed and the ground equipment resources are released, all the "machine" element items of the input project of process module B can meet the project requirements, that is, the ground equipment resources for the input project of process module B can be guaranteed.

d.流程模块A输出项目完成后,流程模块B的输入项目的所有“料”要素项可以满足项目需求,即开展流程模块B输入项目的材料资源充足。d. After the output project of process module A is completed, all the "material" elements of the input project of process module B can meet the project requirements, that is, there are sufficient material resources to carry out the input project of process module B.

e.流程模块A输出项目完成并释放环境资源后,流程模块B的输入项目的所有“环”要素项可以满足项目需求,即开展流程模块B输入项目的环境资源可以保证。e. After the output project of process module A is completed and environmental resources are released, all "ring" element items of the input project of process module B can meet the project requirements, that is, the environmental resources of the input project of process module B can be guaranteed.

(6)计算获得单星可能解的流程集。根据骨架流程中各流程模块间基于要素关系的匹配情况,人工或利用计算机分析,排列给出所有流程模块排列的所有方案,形成包含卫星AIT阶段全部工作项目的全流程的方案组合,即可能解的流程集。如流程模块B匹配流程模块A,则可以在AIT流程中将流程模块B紧邻排列在流程模块A后。利用计算机分析时,可以将两个流程模块间匹配、不匹配的情况分别用值1、0表示,以支持计算机软件算法。(6) Calculate the set of processes to obtain possible solutions for a single star. According to the matching between the process modules in the skeleton process based on the element relationship, manual or computer analysis is performed to arrange all the solutions for the arrangement of all process modules, forming a full-process solution combination that includes all work items in the satellite AIT stage, that is, possible solutions process set. If process module B matches process module A, process module B can be arranged immediately after process module A in the AIT process. When using computer analysis, the matching and mismatching situations between the two process modules can be represented by values 1 and 0 respectively to support computer software algorithms.

在计算机分析资源不具备,或人工分析工作量大的情况下,也可以采取简化方式获得相对较优的可能解的流程集,简化方式一般包括:When computer analysis resources are not available or manual analysis workload is heavy, simplified methods can also be used to obtain a relatively better set of possible solutions. Simplified methods generally include:

①传统顺序法。按传统的顺序,将松耦合项目排入骨架流程中。①Traditional sequential method. Sequence loosely coupled projects into a skeleton process in a traditional order.

②简单对换法。针对少量、主要的松耦合项目,进行人工工作量可接受的简单的兑换项目顺序的调整。②Simple swap method. For a small number of major loosely coupled projects, make simple adjustments to the order of redemption projects with acceptable manual workload.

③它星要素借用法。借用批产其它星的要素资源,优先满足该目标卫星的AIT工作,即调换改变批产卫星不同卫星的要素资源保障条件。③ Borrowing method of other star elements. Borrow the element resources of other satellites in batch production to give priority to the AIT work of the target satellite, that is, exchange and change the element resource guarantee conditions of different satellites in batch production.

(7)比较获得目标范围的批产卫星最优流程。根据卫星发射时间要求的出厂时间先后顺序,以及“星”的关键资源保障条件(如某关键国产化单机无法在10月之前交付装星)、“人”的关键资源保障条件(如同一人员无法同时开展两颗卫星的工作)、“机”的关键资源保障条件(如只有一辆支架车)、“料”的关键资源保障条件(如硅橡胶在10月之后才能到位)、“环”的资源保障条件(如热真空罐在5月~12月用于其它宇航型号而不可用于本型号)等资源保障条件的限制要求,将批产各卫星可能解的流程集进行组合,获得满足限制条件的各星流程的组合,即批产卫星可能解的流程集。根据用户对批产卫星首发发射时间、收官发射时间、是否按阶段分批发射和批次发射时间的限制要求,按照用户给出的权重原则,从批产卫星可能解的流程集比较获得最优的批产流程。(7) Compare and obtain the optimal process for batch production of satellites within the target range. According to the order of delivery time required by the satellite launch time, as well as the key resource guarantee conditions of the "star" (such as a key domestically produced single machine cannot be delivered and installed on the satellite before October), the key resource guarantee conditions of "people" (such as the same person cannot be Carry out work on two satellites at the same time), the key resource guarantee conditions for "machine" (such as only one bracket truck), the key resource guarantee conditions for "materials" (such as silicone rubber will not be available until after October), and the conditions for "environment" In order to meet the restriction requirements of resource guarantee conditions (such as the thermal vacuum tank being used for other aerospace models from May to December but not for this model), the possible process sets for batch production of each satellite are combined to meet the constraints. The combination of the processes of each satellite based on the conditions, that is, the set of processes that can be solved by batch production satellites. According to the user's requirements for the first launch time, final launch time, whether to launch in batches according to stages and the batch launch time limit requirements of the batch satellite, and in accordance with the weighting principle given by the user, the best solution is obtained from the process set comparison of the batch satellite. Excellent batch production process.

当卫星数量为1时,直接比较该卫星的多个可能流程的周期,最短周期的流程即是单颗卫星的最优流程。When the number of satellites is 1, the periods of multiple possible processes for the satellite are directly compared, and the process with the shortest period is the optimal process for a single satellite.

(8)在执行最优批产流程过程中,如顺利将完成批产卫星AIT工作,如发生某个项目问题引起流程中断,以各卫星剩余未完成的项目作为新的流程设计目标范围(即工作项目集合),根据对中断项目的处置策略(与其它项目调整、暂停等策略),重新计算获得剩余项目的可能的流程集,比较获得剩余项目的最优批产流程,并执行新的最优批产流程,实现批产流程执行过程中的动态优化。(8) During the execution of the optimal batch production process, if the batch production satellite AIT work will be completed smoothly, if a project problem occurs and the process is interrupted, the remaining unfinished projects of each satellite will be used as the new process design target range (i.e. Work item set), according to the disposal strategy for interrupted projects (adjustment, suspension, etc. strategies with other projects), recalculate the possible process set for obtaining the remaining projects, compare the optimal batch production process for obtaining the remaining projects, and execute the new best Optimize the batch production process and realize dynamic optimization during the execution of the batch production process.

实施例Example

以某批产卫星型号项目为例,为提高批产研制进度,对优化前的单星、双星流程,基于要素关系的批产卫星AIT流程生成方法,识别可以优化的流程环节,形成了优化后的新的双星研制流程,开展了一系列流程优措施,大幅提高了研制效率:Taking a certain batch-production satellite model project as an example, in order to improve the progress of batch-production development, a batch-production satellite AIT process generation method based on factor relationships was used to identify the process links that can be optimized for the single-satellite and double-satellite processes before optimization, and formed the optimized process. In the new double-star development process, a series of process optimization measures have been carried out to greatly improve the development efficiency:

(1)图2所示为优化前的单星流程,图3所示为优化前的双星流程。单星流程的工作内容包括卫星部装、舱段总装、卫星总装有线测试、卫星总装无线测试、整星力学试验、与运载对接、整星热试验、综合对接、出厂前总装测试、出厂总装,分解工作内容,确定单颗卫星在AIT阶段的工作项目集合:卫星部装、与运载对接、综合对接不可再分解,舱段总装分为平台总装、载荷舱总装、三舱对接,卫星总装有线测试分为单机交付、软件落焊、平台总装、平台测试、载荷舱总装、载荷舱测试、B状态测试,卫星总装无线测试/EMC试验分为无线状态总装、C状态测试/EMC试验、无线状态后总装,整星力学试验分为无线状态总装、振动试验及噪声试验、无线状态后总装,热试验分为星表热试验改造、舱内热试验改造、热真空试验、热试验后总装,出厂前总装电测分解为出厂前总装、出厂前电测。(1) Figure 2 shows the single-star process before optimization, and Figure 3 shows the double-star process before optimization. The work content of the single-satellite process includes satellite assembly, cabin assembly, satellite assembly wire test, satellite assembly wireless test, whole-satellite mechanical test, docking with the carrier, whole-satellite thermal test, comprehensive docking, pre-factory assembly test, and factory final assembly. Decompose the work content and determine the set of work items for a single satellite in the AIT stage: satellite assembly, docking with the carrier, and comprehensive docking cannot be further decomposed. The final assembly of the cabin is divided into platform final assembly, load bay final assembly, three-cabin docking, and satellite final assembly line testing. It is divided into stand-alone delivery, software drop welding, platform assembly, platform testing, load bay assembly, load bay test, and B state test. The satellite assembly wireless test/EMC test is divided into wireless state final assembly, C state test/EMC test, and wireless state post-processing. Final assembly, the whole satellite mechanical test is divided into wireless state final assembly, vibration test and noise test, and wireless state post-final assembly. The thermal test is divided into satellite thermal test modification, cabin thermal test modification, thermal vacuum test, final assembly after thermal test, and final assembly before leaving the factory. Electrical testing is divided into pre-factory assembly and pre-factory electrical testing.

特别的是,可基于ECRS方法在覆盖卫星AIT总目标的情况下,获得整个项目在不同阶段的项目分解结果。In particular, the project decomposition results of the entire project at different stages can be obtained based on the ECRS method while covering the overall goal of satellite AIT.

(2)根据以上单颗卫星在AIT阶段的工作项目集合,确定AIT工作要素集和各项目的要素的具体内容,本实施例对{星,人,机,料,环}五方面要素,为降低本发明描述的复杂度,只对“星”要素的“硬件状态”、“环”要素细化,对应AIT工作要素集示意表示为{平台单机,载荷舱单机,星表热控部件,星表大型部件},软件状态,整星组合状态};{平台单机,载荷舱单机,星表热控部件,星表大型部件},软件状态,整星组合状态};{总装人员,测试人员,试验人员,总体人员};{地面工装设备,地面测试设备};{紧固件,支架,辅材};{测试试验工位,外部无线干扰}。(2) Based on the above work project set of a single satellite in the AIT stage, determine the AIT work element set and the specific content of the elements of each project. In this embodiment, the five elements of {satellites, people, machines, materials, and environment} are: To reduce the complexity of the description of the present invention, only the "hardware status" and "ring" elements of the "star" element are refined. The corresponding AIT work element set is schematically represented as {platform single machine, load bay single machine, star table thermal control component, star table Table large components}, software status, whole satellite combination status}; {platform single machine, load bay single machine, star watch thermal control parts, star watch large components}, software status, whole star combination status}; {general assembly personnel, testers, Test personnel, general personnel}; {ground tooling equipment, ground testing equipment}; {fasteners, brackets, auxiliary materials}; {test test station, external wireless interference}.

(3)按照卫星研制标准、规范、特定工作要求,确定以下项目间存在紧耦合项目关系:软件落焊、单机交付;卫星部装/单机交付、载荷舱总装/平台总装;载荷舱总装/平台总装、三舱对接;舱内热试验改装/星表热试验改装、热试验、热试验后总装;无线测试试验前总装、C状态测试/EMC试验;无线测试试验前总装,振动试验及噪声试验、与运载对接。所述“载荷舱总装/平台总装、三舱对接”表示载荷舱总装、平台总装并行开展,然后紧密衔接三舱对接,其它表述类似。(3) In accordance with satellite development standards, specifications, and specific work requirements, it is determined that there is a tightly coupled project relationship between the following projects: software drop welding, stand-alone delivery; satellite assembly/stand-alone delivery, load bay final assembly/platform final assembly; load bay final assembly/platform Final assembly, three-cabin docking; in-cabin thermal test modification/star table thermal test modification, thermal test, final assembly after thermal test; wireless test test before final assembly, C status test/EMC test; wireless test test before final assembly, vibration test and noise test, Connect with the carrier. The mentioned "load bay final assembly/platform final assembly, three-cabin docking" means that the load bay final assembly and platform final assembly are carried out in parallel, and then closely connected to the three-cabin docking, and other expressions are similar.

可见,热真空试验、振动试验及噪声试验没有严格的先后关系,C状态测试/EMC试验、振动试验及噪声试验都需要无线状态总装、无线状态后总装,未优化前的流程没有更好地调整松耦合项目与其它项目间的衔接关系。It can be seen that there is no strict sequence relationship between thermal vacuum test, vibration test and noise test. C-state test/EMC test, vibration test and noise test all require wireless state final assembly and wireless state post-assembly. The process before optimization has not been better adjusted. The connection between loosely coupled projects and other projects.

(4)按照紧耦合项目关系清单建立各项目组成的流程模块,各松耦合的项目也作为一个流程模块看待,建立各流程模块组成的单星骨架流程如图4所示,其中流程模块包括开始流程模块、结束流程模块、其它流程模块,其它流程模块包括无线流程模块(无线测试试验前总装至无线测试试验前总装的流程模块)、热试验流程模块(星表热试验改装、舱内热试验改装至热试验后改装的流程模块)、综合对接流程模块。(4) Establish process modules composed of each project according to the tightly coupled project relationship list. Each loosely coupled project is also treated as a process module. The single-star skeleton process composed of each process module is established as shown in Figure 4. The process module includes the start Process module, end process module, other process modules, other process modules include wireless process module (process module from wireless test pre-test assembly to wireless test pre-test assembly), thermal test process module (star table thermal test modification, cabin thermal test modification Process module modified after thermal testing) and comprehensive docking process module.

(5)获得骨架流程中各流程模块间基于要素关系的匹配情况,如表1所示为表中第一列各流程模块匹配第一行各流程模块的情况,“1”表示匹配,“0”表示不匹配,以用于计算机分析。如,无线流程模块不匹配开始流程模块(无线流程模块的卫星状态需要安排太阳翼,与开始流程模块输出状态“星”方面要素的未安装太阳翼状态不同),而热试验模块可以匹配开始流程模块(因为各方面要素匹配)。(5) Obtain the matching between each process module in the skeleton process based on element relationships. As shown in Table 1, the matching of each process module in the first column of the table with each process module in the first row, "1" means matching, "0" ” indicates a mismatch for purposes of computer analysis. For example, the wireless process module does not match the start process module (the satellite status of the wireless process module requires the solar wing to be arranged, which is different from the uninstalled solar wing status of the "star" aspect element of the output status of the start process module), while the thermal test module can match the start process Module (because all aspects of the elements match).

表1各流程模块间基于要素关系的匹配情况示例Table 1 Examples of matching between each process module based on element relationships

注:表中,“1”表示匹配,“0”表示不匹配,以用于计算机分析。Note: In the table, "1" means matching and "0" means not matching, for computer analysis.

(6)计算获得单星可能解的流程集。在流程模块数量少、复杂度小的情况下,可以人工给出各流程模块的排列组合,即可能解的流程集,有{开始流程模块、综合对接模块、热试验模块、无线流程模块、结束流程模块},以及{开始流程模块、热试验模块、综合对接模块、无线流程模块、结束流程模块}共2个解。这两个解比较进度无差异,因此均是单星的最优流程。(6) Calculate the set of processes to obtain possible solutions for a single star. When the number of process modules is small and the complexity is small, the permutation and combination of each process module can be manually given, that is, the process set of possible solutions, including {start process module, comprehensive docking module, thermal test module, wireless process module, end Process module}, and {start process module, thermal test module, comprehensive docking module, wireless process module, end process module}, a total of 2 solutions. There is no difference in progress between these two solutions, so they are both optimal processes for a single star.

(7)比较获得双星的批产卫星最优流程。命名为M1、M2的两颗卫星要求同时启动AIT工作、同时出厂发射,单星流程为解A({开始流程模块、综合对接模块、热试验模块、无线流程模块、结束流程模块}),或解B({开始流程模块、热试验模块、综合对接模块、无线流程模块、结束流程模块})这两个解,则组合得到双星卫星可能解的流程集,有三个解,分别为AA、BB、AB(与BA实际效果一致,与BA作为同一解),即两颗星均使用流程A,均使用流程B,分别使用流程A、流程B三种组合流程。根据用户尽快完成研制的要求,两颗星选择不一样的流程,以避免相同流程模块的资源冲突,保证并行研制进度。在实际工程中,由于两颗星共用热真空罐,对流程A、流程B批产流程中热试验相关的部分进行局部优化,将热真空试验合并,将两颗星的综合对接、星表热试验改装、舱内热试验改装进行交叉。最终得到的双星批产卫星最优流程如图5所示。(7) Compare the optimal process for mass production of dual satellites. The two satellites named M1 and M2 are required to start AIT work and launch from the factory at the same time. The single-satellite process is solution A ({start process module, comprehensive docking module, thermal test module, wireless process module, end process module}), or Solution B ({Start Process Module, Thermal Test Module, Comprehensive Docking Module, Wireless Process Module, End Process Module}) can be combined to obtain the process set of possible solutions for the double satellite satellite. There are three solutions, namely AA and BB. , AB (consistent with the actual effect of BA, and the same solution as BA), that is, both stars use process A, both use process B, and use three combined processes of process A and process B respectively. According to the user's requirement to complete development as soon as possible, the two stars choose different processes to avoid resource conflicts in the same process modules and ensure parallel development progress. In the actual project, since the two satellites share a thermal vacuum tank, the thermal test-related parts of the batch production process of process A and process B were partially optimized, the thermal vacuum test was merged, and the comprehensive docking of the two satellites and the satellite thermal test were combined. The test modification and the cabin thermal test modification are crossed. The final optimal process for batch production of dual-satellite satellites is shown in Figure 5.

本发明说明书中未作详细描述的内容属本领域专业技术人员的公知技术。Contents not described in detail in the specification of the present invention belong to the well-known techniques of those skilled in the art.

Claims (5)

1.一种基于要素关系的批产卫星AIT流程生成方法,其特征在于,包括步骤如下:1. A batch production satellite AIT process generation method based on element relationships, which is characterized by including the following steps: 1)确定多颗卫星在AIT阶段需要开展的工作内容,将工作内容逐级分解直至不可再分为止,获得不可再分解的工作项目并作为基本单元的单星AIT阶段的工作项目集合;1) Determine the work content that multiple satellites need to carry out in the AIT phase, decompose the work content step by step until it cannot be divided anymore, obtain the work items that cannot be further divided, and use them as the basic unit of the work item set for the single-satellite AIT stage; 2)确定开展卫星AIT阶段各工作项目的核心要素,组成需要的颗粒度的AIT工作要素集;确定步骤1)所述工作项目集合中每个工作项目对应核心要素的具体内容;2) Determine the core elements of each work item in the satellite AIT stage to form an AIT work element set with the required granularity; determine the specific content of the core elements corresponding to each work item in the work item set described in step 1); 3)针对每个单星,分析确定必须按先后固定顺序开展的工作项目,形成单星存在紧耦合关系的项目关系清单;其余相互间无先后固定顺序要求的工作项目作为松耦合项目;3) For each single satellite, analyze and determine the work projects that must be carried out in a fixed order, and form a list of project relationships with a tight coupling relationship for the single satellite; the remaining work projects that have no fixed order requirements are regarded as loosely coupled projects; 4)对每颗单星,分别将紧耦合项目关系清单中的工作项目按先后固定顺序排列形成流程模块,同时,每个松耦合项目也作为一个流程模块,形成由各个流程模块组成的单星骨架流程;4) For each single star, the work items in the tightly coupled project relationship list are arranged in a fixed order to form a process module. At the same time, each loosely coupled project is also used as a process module to form a single star composed of various process modules. skeleton process; 5)将流程模块中的第一个项目作为该流程模块的输入项目,将流程模块中的最后一个项目作为该流程模块的输出项目,根据流程模块间要素关系匹配条件,遍历所有流程模块,分析两两流程模块间是否匹配,获得不同流程模块间的匹配关系;5) Use the first item in the process module as the input item of the process module, and use the last item in the process module as the output item of the process module. According to the matching conditions of the element relationships between process modules, traverse all process modules and analyze Check whether there is a match between two process modules, and obtain the matching relationship between different process modules; 6)排列组合,根据步骤5)获得的匹配关系,给出所有流程模块可能的排列方案,每个方案作为一个可能解流程集,获得多个可能解流程集;6) Permutation and combination. Based on the matching relationship obtained in step 5), possible arrangement schemes of all process modules are given. Each scheme is used as a possible solution process set to obtain multiple possible solution process sets; 7)根据卫星发射时间要求确定的出厂先后顺序,以及每个工作项目对应核心要素的资源保障条件的限制要求,筛选获得满足限制要求的可能解流程集;7) Based on the factory order determined by the satellite launch time requirements and the restriction requirements of the resource guarantee conditions corresponding to the core elements of each work project, screen out a set of possible solution processes that meet the restriction requirements; 8)根据用户对卫星发射时间的细化限制要求和权重原则,从步骤7)筛选获得的可能解流程集中比较获得最优的可能解流程集作为批量生产流程,执行投产任务。8) According to the user's detailed restriction requirements and weighting principles for satellite launch time, the possible solution processes obtained from step 7) are intensively compared to obtain the optimal set of possible solution processes as a mass production process to execute the production task. 2.根据权利要求1所述的一种基于要素关系的批产卫星AIT流程生成方法,其特征在于:在执行批量生产流程中,如批量生产流程发生流程执行中断,则以各卫星剩余未完成的工作项目组成新的流程模块,再次进行步骤6)~8),获得剩余未完成项目的最优批产流程,即为批产卫星AIT流程执行过程中的动态优化。2. A method for generating AIT process for batch production of satellites based on element relationships according to claim 1, characterized in that: during the execution of the mass production process, if the process execution of the mass production process is interrupted, the remaining unfinished process of each satellite will be The work items form a new process module, and steps 6) to 8) are performed again to obtain the optimal batch production process for the remaining unfinished projects, which is the dynamic optimization during the execution of the batch production satellite AIT process. 3.根据权利要求1所述的一种基于要素关系的批产卫星AIT流程生成方法,其特征在于:当批量生产卫星数量设置为1时,即为单星AIT流程的生成方法。3. A method for generating a batch-production satellite AIT process based on element relationships according to claim 1, characterized in that: when the number of batch-produced satellites is set to 1, it is a method for generating a single-satellite AIT process. 4.根据权利要求1~3任意之一所述的一种基于要素关系的批产卫星AIT流程生成方法,其特征在于:步骤2)所述核心要素由星方面的要素、人方面的要素、机方面的要素、料方面的要素和环境方面的要素中的几个或全部组成。4. A batch production satellite AIT process generation method based on element relationships according to any one of claims 1 to 3, characterized in that: the core elements in step 2) are composed of satellite-related elements, human-related elements, It consists of several or all of the mechanical factors, material factors and environmental factors. 5.根据权利要求4所述的一种基于要素关系的批产卫星AIT流程生成方法,其特征在于:步骤6)所述可能解流程集包含卫星AIT阶段全部工作项目的全流程。5. A method for generating batch satellite AIT processes based on element relationships according to claim 4, characterized in that: the set of possible solution processes in step 6) includes the entire process of all work items in the satellite AIT stage.
CN202011192021.XA 2020-10-30 2020-10-30 A batch production satellite AIT process generation method based on element relationships Active CN112434909B (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN202011192021.XA CN112434909B (en) 2020-10-30 2020-10-30 A batch production satellite AIT process generation method based on element relationships

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN202011192021.XA CN112434909B (en) 2020-10-30 2020-10-30 A batch production satellite AIT process generation method based on element relationships

Publications (2)

Publication Number Publication Date
CN112434909A CN112434909A (en) 2021-03-02
CN112434909B true CN112434909B (en) 2023-11-10

Family

ID=74694875

Family Applications (1)

Application Number Title Priority Date Filing Date
CN202011192021.XA Active CN112434909B (en) 2020-10-30 2020-10-30 A batch production satellite AIT process generation method based on element relationships

Country Status (1)

Country Link
CN (1) CN112434909B (en)

Families Citing this family (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN120238179B (en) * 2025-06-03 2025-07-29 中国科学院微小卫星创新研究院 Satellite mass production testing method, satellite mass production testing equipment and computer storage medium

Citations (2)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN105574178A (en) * 2015-12-21 2016-05-11 莱诺斯科技(北京)有限公司 Basic database for satellite testing as well as device and method for batch satellite testing
CN111651837A (en) * 2020-06-03 2020-09-11 中国科学院微小卫星创新研究院 Satellite thermal control management system and method

Family Cites Families (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
US7225981B2 (en) * 2004-01-10 2007-06-05 Kenneth Jongebloed, Inc. Adaptive network-centric online autonomic supply chain management system

Patent Citations (2)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN105574178A (en) * 2015-12-21 2016-05-11 莱诺斯科技(北京)有限公司 Basic database for satellite testing as well as device and method for batch satellite testing
CN111651837A (en) * 2020-06-03 2020-09-11 中国科学院微小卫星创新研究院 Satellite thermal control management system and method

Also Published As

Publication number Publication date
CN112434909A (en) 2021-03-02

Similar Documents

Publication Publication Date Title
Wang Application and development prospect of digital twin technology in aerospace
US9056685B2 (en) Method and system for mounting interior components in an aircraft
CN112434909B (en) A batch production satellite AIT process generation method based on element relationships
CN111651837B (en) Satellite thermal control management system and method
CN106844846B (en) Method for verifying multi-failure-mode damage mechanism of high-temperature-resistant composite material structure
CN103336194A (en) Integrated automatic test system of on-board computer of civilian airliner
CN105302718A (en) Design method of multiplexing software-oriented test model
CN105701294B (en) Realize the method and system of chip complex engineering modification
CN102539097B (en) Forecasting system for high-magnitude test condition of sinusoidal vibration test for spacecraft
CN105629960A (en) Electric vehicle controller model in-the-loop test system and method
CN101342946A (en) Airbus series aircraft audio management component automatic test device and method
CN108334428B (en) Parallel testing method for system functions
CN107862145A (en) A kind of re-entry space vehicle flight time sequence and Energy Sources Equilibrium Coupling Design System and method for
CN103699939A (en) Component application validation process establishment method for space navigation
Ma et al. Efficient and effective dimension control in automotive applications
CN110716861A (en) A server testing system, method and device
CN114219108A (en) Vehicle diagnosis method, system, terminal and storage medium
CN202195949U (en) Direct-current converter external characteristic hardware-in-the-loop simulation testing bench
CN106919760B (en) A kind of body section torsion stiffness distribution character calculation method
CN102297765A (en) Hardware-in-loop simulation test bed for external characteristics of direct current converter
CN113919048B (en) A modular configuration layout method to adapt to satellite incremental payload changes
CN105022864A (en) System test point selecting method based on extended dependence matrix
Krammer et al. Advanced manufacturing technologies for general assembly
Colledani et al. Multi-objective early-stage design of automotive hybrid assembly lines
CN120670292A (en) Automatic generation and auxiliary verification system for satellite test design

Legal Events

Date Code Title Description
PB01 Publication
PB01 Publication
SE01 Entry into force of request for substantive examination
SE01 Entry into force of request for substantive examination
GR01 Patent grant
GR01 Patent grant