CN215516328U - Long thin wall equipment hoist and mount frock - Google Patents
Long thin wall equipment hoist and mount frock Download PDFInfo
- Publication number
- CN215516328U CN215516328U CN202121648516.9U CN202121648516U CN215516328U CN 215516328 U CN215516328 U CN 215516328U CN 202121648516 U CN202121648516 U CN 202121648516U CN 215516328 U CN215516328 U CN 215516328U
- Authority
- CN
- China
- Prior art keywords
- equipment
- long thin
- hoisting
- lifting
- balance beam
- Prior art date
- Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
- Active
Links
- 229910000831 Steel Inorganic materials 0.000 claims abstract description 17
- 239000010959 steel Substances 0.000 claims abstract description 17
- 238000000034 method Methods 0.000 description 3
- 238000010008 shearing Methods 0.000 description 2
- 230000009286 beneficial effect Effects 0.000 description 1
- 230000007547 defect Effects 0.000 description 1
- 238000010586 diagram Methods 0.000 description 1
- 238000009434 installation Methods 0.000 description 1
- 238000012986 modification Methods 0.000 description 1
- 230000004048 modification Effects 0.000 description 1
Images
Landscapes
- Load-Engaging Elements For Cranes (AREA)
Abstract
The utility model relates to a long thin-wall equipment hoisting tool, which comprises a balance beam and a fixed support, wherein the length of the balance beam is greater than the radial width of the equipment, the balance beam is arranged above the equipment, one end of a steel wire rope is connected with a hoisting point at the bottom of the equipment, the other end of the steel wire rope is sequentially connected with the balance beam and a crane hook, and the fixed support is arranged between the two hoisting points. The utility model has the advantages of ingenious design, simple, practical and safe design, can meet the hoisting requirement by the mutual matching of the balance beam and the fixed support.
Description
Technical Field
The utility model relates to a hoisting tool device, in particular to a hoisting tool for long, thin and thin-walled equipment.
Background
In the field of industrial equipment installation, because a slender thin-wall workpiece has the characteristics of small rigidity, narrow width and large weight, the operability of the hoisting operation of the whole slender thin-wall workpiece is extremely poor, and particularly, when the slender thin-wall workpiece is hoisted in a large span, the safety and reliability of a hoisting load and the stress damage of an equipment body are always ensured, so that the slender thin-wall workpiece is difficult to hoist, and further the operation efficiency is low.
Under the traditional assembly process conditions, I-shaped steel beam lifting appliances and cross beam lifting appliances are generally adopted for lifting. Firstly, when a slender thin-wall workpiece is hoisted, axial shearing force is easily generated, and the device body is damaged with a certain probability; secondly, the multi-directional stress of the lifting appliance is completely acted on the lifting appliance, so that the adopted lifting appliance is relatively complex and heavy in structure for ensuring the lifting safety, and the lifting load is increased; the hoisting cost is increased, and the potential safety hazard of hoisting personnel during operation is increased.
SUMMERY OF THE UTILITY MODEL
Aiming at the defects of the prior art, the utility model provides a long thin-wall equipment hoisting tool.
The technical scheme adopted by the utility model for solving the technical problems is as follows: the utility model provides a long thin wall equipment hoist and mount frock includes compensating beam, fixed stay, compensating beam length is greater than the radial width of equipment to set up in the equipment top, the hoisting point of wire rope one end jointing equipment bottom, the other end connects gradually compensating beam and crane lifting hook, the fixed stay sets up between two hoisting points.
In a preferred embodiment of the hoisting tool for long and thin-wall equipment provided by the utility model, guide arcs are arranged at two ends of the balance beam, and the steel wire rope is clamped into the guide arcs and covered by the lock catches.
In a preferred embodiment of the hoisting tool for the long and thin wall equipment provided by the utility model, a plurality of first lifting lugs are arranged at the top of the balance beam and are connected with a crane lifting hook through a steel wire rope.
In a preferred embodiment of the hoisting tool for long, thin and thin wall equipment provided by the utility model, two second lifting lugs are arranged at the bottom of the balance beam, and are connected with third lifting lugs arranged on the fixed support through steel wire ropes.
In a preferred embodiment of the hoisting tool for long and thin-wall equipment provided by the utility model, grooves for accommodating hoisting points are arranged at two ends of the fixed support.
In a preferred embodiment of the long thin-wall equipment hoisting tool provided by the utility model, an inclined wedge is welded on the hoisting point and is clamped in the groove.
Compared with the prior art, the hoisting tool for the long thin-wall equipment, provided by the utility model, has the beneficial effects that: the utility model has the advantages of ingenious design, simple, practical and safe design, can meet the hoisting requirement by the mutual matching of the balance beam and the fixed support.
Drawings
In order to more clearly illustrate the technical solutions in the embodiments of the present invention, the drawings needed to be used in the description of the embodiments are briefly introduced below, it is obvious that the drawings in the following description are only some embodiments of the present invention, and other drawings can be obtained by those skilled in the art without inventive efforts, wherein:
fig. 1 is a schematic lifting diagram of a long thin-wall equipment lifting tool.
Fig. 2 is a hoisting side view of a long thin-wall equipment hoisting tool.
Fig. 3 is a partial schematic view I of a long thin-wall equipment hoisting tool.
FIG. 4 is a partial schematic view II of a long thin-wall equipment hoisting tool.
In the figure: 1. a balance beam; 2. fixing and supporting; 3. hoisting points; 4. a pilot arc; 5. locking; 6. a first lifting lug; 7. a second lifting lug; 8. a third lifting lug; 9. a groove; 10. and a slanting wedge.
Detailed Description
The technical solutions in the embodiments of the present invention will be clearly and completely described below with reference to the drawings in the embodiments of the present invention, and it is obvious that the described embodiments are only a part of the embodiments of the present invention, and not all of the embodiments. All other embodiments, which can be derived by a person skilled in the art from the embodiments given herein without making any creative effort, shall fall within the protection scope of the present invention.
In the description of the present invention, it should be noted that the terms "center", "upper", "lower", "left", "right", "vertical", "horizontal", "inner", "outer", etc., indicate orientations or positional relationships based on the orientations or positional relationships shown in the drawings, and are only for convenience of description and simplicity of description, but do not indicate or imply that the device or element being referred to must have a particular orientation, be constructed and operated in a particular orientation, and thus, should not be construed as limiting the present invention; the terms "first," "second," and "third" are used for descriptive purposes only and are not to be construed as indicating or implying relative importance; furthermore, unless expressly stated or limited otherwise, the terms "mounted," "connected," and "connected" are to be construed broadly, as they may be fixedly connected, detachably connected, or integrally connected, for example; can be mechanically or electrically connected; they may be connected directly or indirectly through intervening media, or they may be interconnected between two elements. The specific meanings of the above terms in the present invention can be understood in specific cases to those skilled in the art.
Referring to fig. 1 to 4, the long and thin-wall equipment hoisting tool comprises a balance beam 1 and a fixed support 2, wherein the balance beam 1 is arranged above the equipment, one end of a steel wire rope is connected with a hoisting point 3 at the bottom of the equipment, the other end of the steel wire rope is sequentially connected with the balance beam 1 and a crane hook, the length of the balance beam 1 is greater than the radial width of the equipment, the steel wire rope is prevented from extruding an equipment shell during hoisting, the fixed support 2 is arranged between the two hoisting points 3, the axial direction of the long and thin-wall equipment is reinforced, the two hoisting points 3 are supported firmly, and the shearing force of the axial tension on the equipment is counteracted.
Preferably, the two ends of the balance beam 1 are provided with guide arcs 4, the guide arcs 4 are divided into two parts by fixed pulleys and are respectively welded to the two ends of the balance beam 1, the steel wire rope is clamped in the guide arcs 4, friction between the steel wire rope and the balance beam 1 in the lifting process is reduced, and meanwhile, the guide arcs 4 are covered by the lock catches 5, so that the steel wire rope is limited on the guide arcs 4, and slipping is prevented.
Preferably, the top of the balance beam 1 is provided with a plurality of first lifting lugs 6, and the first lifting lugs are connected with a crane lifting hook through a steel wire rope to disperse stress points.
Preferably, two second lifting lugs 7 are arranged at the bottom of the balance beam 1 and connected with a third lifting lug 8 arranged on the fixed support 2 through a steel wire rope, so that stress points are dispersed.
Preferably, the two ends of the fixed support 2 are provided with grooves 9 for accommodating the hanging points 3, and the fixed support 2 is clamped between the two hanging points 3 through the grooves 9 to prevent shaking.
Preferably, the lifting point 3 is welded with an inclined wedge 10 and clamped in the groove 9, so that the fixed support 2 is tightly abutted against the inclined wedge 10 and cannot slide when being stressed upwards.
The above description is only an embodiment of the present invention, and not intended to limit the scope of the present invention, and all modifications of equivalent structures and equivalent processes, which are made by the present specification, or directly or indirectly applied to other related technical fields, are included in the scope of the present invention.
Claims (6)
1. The utility model provides a long thin wall equipment hoist and mount frock which characterized in that: including compensating beam, fixed stay, compensating beam length is greater than the radial width of equipment to set up in the equipment top, the hoisting point of wire rope one end jointing equipment bottom, the other end connects gradually compensating beam and crane hook, the fixed stay sets up between two hoisting points.
2. The long thin-wall equipment hoisting tool according to claim 1, characterized in that: and guide arcs are arranged at two ends of the balance beam, and the steel wire rope is clamped into the guide arcs and is covered by the lock catch.
3. The long thin-wall equipment hoisting tool according to claim 1, characterized in that: a plurality of first lifting lugs are arranged at the top of the balance beam and are connected with a crane lifting hook through a steel wire rope.
4. The long thin-wall equipment hoisting tool according to claim 1, characterized in that: and two second lifting lugs are arranged at the bottom of the balance beam and are connected with third lifting lugs arranged on the fixed support through steel wire ropes.
5. The long thin-wall equipment hoisting tool according to claim 1, characterized in that: and grooves for accommodating lifting points are arranged at two ends of the fixed support.
6. The long thin-wall equipment hoisting tool according to claim 5, characterized in that: the lifting point is welded with an inclined wedge and clamped in the groove.
Priority Applications (1)
| Application Number | Priority Date | Filing Date | Title |
|---|---|---|---|
| CN202121648516.9U CN215516328U (en) | 2021-07-20 | 2021-07-20 | Long thin wall equipment hoist and mount frock |
Applications Claiming Priority (1)
| Application Number | Priority Date | Filing Date | Title |
|---|---|---|---|
| CN202121648516.9U CN215516328U (en) | 2021-07-20 | 2021-07-20 | Long thin wall equipment hoist and mount frock |
Publications (1)
| Publication Number | Publication Date |
|---|---|
| CN215516328U true CN215516328U (en) | 2022-01-14 |
Family
ID=79814032
Family Applications (1)
| Application Number | Title | Priority Date | Filing Date |
|---|---|---|---|
| CN202121648516.9U Active CN215516328U (en) | 2021-07-20 | 2021-07-20 | Long thin wall equipment hoist and mount frock |
Country Status (1)
| Country | Link |
|---|---|
| CN (1) | CN215516328U (en) |
-
2021
- 2021-07-20 CN CN202121648516.9U patent/CN215516328U/en active Active
Similar Documents
| Publication | Publication Date | Title |
|---|---|---|
| CN101258095B (en) | Combined double lower pulley mechanism | |
| CN214167082U (en) | Special lifting device for pressure vessel | |
| CN215516328U (en) | Long thin wall equipment hoist and mount frock | |
| CN216662188U (en) | Wall bushing hoisting balance tool | |
| CN108373098A (en) | Power cable lifting device | |
| CN211776321U (en) | Wire clamping device for steel wire rope and tower stay cable device | |
| CN219990886U (en) | Container hoisting structure | |
| CN218507357U (en) | Lifting appliance | |
| CN215854592U (en) | Large-diameter sling connection protection sling | |
| CN214935260U (en) | Lifting appliance | |
| CN216971705U (en) | Steel box girder sling | |
| CN113998605B (en) | A wall casing lifting balancing tool | |
| CN215208053U (en) | Fuel cell hangs gets frock | |
| CN218860130U (en) | Lifting appliance | |
| CN223397292U (en) | Nuclear power reactor outer dome lifting tools | |
| CN219469421U (en) | Prefabricated component lifting device | |
| CN209890074U (en) | Stator hoisting device of water turbine | |
| CN219217239U (en) | Wire rope separator | |
| CN112125122A (en) | Hoisting method of wind power generation equipment | |
| CN220011847U (en) | Steel reinforcement cage hoist mechanism | |
| CN223280453U (en) | A hoisting frame for a platform structure | |
| CN222374131U (en) | Battery pack lifting hook | |
| CN220283305U (en) | Lifting appliance for lifting eccentric heliostat | |
| CN215479268U (en) | Bridge crane fixed pulley wire rope goes out groove fault handling device | |
| CN217708511U (en) | Generator stator hoisting system |
Legal Events
| Date | Code | Title | Description |
|---|---|---|---|
| GR01 | Patent grant | ||
| GR01 | Patent grant |