CN216872860U - Doubly-fed asynchronous wind turbines and transmission systems for wind turbines - Google Patents
Doubly-fed asynchronous wind turbines and transmission systems for wind turbines Download PDFInfo
- Publication number
- CN216872860U CN216872860U CN202123443099.7U CN202123443099U CN216872860U CN 216872860 U CN216872860 U CN 216872860U CN 202123443099 U CN202123443099 U CN 202123443099U CN 216872860 U CN216872860 U CN 216872860U
- Authority
- CN
- China
- Prior art keywords
- converter
- frequency
- transformer
- electrically connected
- rotor
- Prior art date
- Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
- Active
Links
- 230000005540 biological transmission Effects 0.000 title claims abstract description 171
- 238000013461 design Methods 0.000 abstract description 20
- 230000005611 electricity Effects 0.000 abstract description 8
- 238000000034 method Methods 0.000 description 12
- 238000010248 power generation Methods 0.000 description 11
- 238000010586 diagram Methods 0.000 description 7
- 230000008569 process Effects 0.000 description 7
- 238000005516 engineering process Methods 0.000 description 4
- 238000006243 chemical reaction Methods 0.000 description 3
- 230000004048 modification Effects 0.000 description 3
- 238000012986 modification Methods 0.000 description 3
- 230000001360 synchronised effect Effects 0.000 description 3
- 238000004804 winding Methods 0.000 description 3
- 230000008901 benefit Effects 0.000 description 2
- 230000006698 induction Effects 0.000 description 2
- 238000009434 installation Methods 0.000 description 2
- 238000004519 manufacturing process Methods 0.000 description 2
- 238000011160 research Methods 0.000 description 2
- 238000007792 addition Methods 0.000 description 1
- 238000004458 analytical method Methods 0.000 description 1
- 230000009286 beneficial effect Effects 0.000 description 1
- 230000008859 change Effects 0.000 description 1
- 239000008358 core component Substances 0.000 description 1
- 230000001419 dependent effect Effects 0.000 description 1
- 238000011161 development Methods 0.000 description 1
- 230000000694 effects Effects 0.000 description 1
- 230000000750 progressive effect Effects 0.000 description 1
- 238000009420 retrofitting Methods 0.000 description 1
Images
Landscapes
- Control Of Eletrric Generators (AREA)
Abstract
Description
技术领域technical field
本申请属于风力发电技术领域,尤其涉及一种双馈异步风力发电机组和风力发电机组的输电系统。The application belongs to the technical field of wind power generation, and in particular relates to a doubly-fed asynchronous wind generator set and a power transmission system for the wind generator set.
背景技术Background technique
随着新能源技术的迅速发展,新能源的应用范围越来越广。其中,风力发电技术成为了重点关注的技术之一。With the rapid development of new energy technology, the application scope of new energy is getting wider and wider. Among them, wind power generation technology has become one of the key technologies.
在风力发电过程中,风力发电机组将风能转换成电能,再经输电线路将电能并入电网之中。然而,经本申请的发明人发现,目前的风力发电机组的输电成本和改装成本较为高昂。In the process of wind power generation, wind turbines convert wind energy into electrical energy, and then integrate the electrical energy into the power grid through transmission lines. However, the inventors of the present application have found that the cost of power transmission and modification of the current wind turbine is relatively high.
实用新型内容Utility model content
本申请实施例提供了一种双馈异步风力发电机组和风力发电机组的输电系统,至少能够解决风力发电机组的改装成本高昂的技术问题。The embodiments of the present application provide a doubly-fed asynchronous wind turbine generator set and a power transmission system for the wind turbine generator set, which can at least solve the technical problem of high retrofit cost of the wind turbine generator set.
第一方面,本申请实施例提供了一种双馈异步风力发电机组,双馈异步风力发电机组包括:发电机;转子侧变流器,转子侧变流器与发电机的转子电连接,用于将转子输出的交流电的频率调整至目标频率,目标频率小于50Hz;定子侧变流器,定子侧变流器与发电机的定子电连接,用于将定子输出的交流电的频率调整至目标频率。In the first aspect, the embodiments of the present application provide a doubly-fed asynchronous wind power generator set, which includes: a generator; a rotor-side converter, the rotor-side converter is electrically connected to the rotor of the generator, and the In order to adjust the frequency of the alternating current output by the rotor to the target frequency, the target frequency is less than 50Hz; the stator side converter, the stator side converter is electrically connected with the stator of the generator, and is used to adjust the frequency of the alternating current output by the stator to the target frequency .
第二方面,本申请实施例提供了一种风力发电机组的输电系统,风力发电机组的输电系统包括:双馈异步风力发电机组,双馈异步风力发电机组包括发电机和转子侧变流器,转子侧变流器与发电机的转子电连接,用于将转子输出的交流电的频率调整至目标频率,目标频率小于50Hz;第一升压变压器,第一升压变压器的低压侧分别与发电机的定子、转子侧变流器电连接,第一升压变压器的高压侧与电网电连接;第一变流器,第一变流器电连接于定子与电网之间,用于将定子输出的交流电的频率调整至目标频率。In a second aspect, an embodiment of the present application provides a power transmission system for a wind turbine. The power transmission system for a wind turbine includes: a doubly-fed asynchronous wind turbine, and the doubly-fed asynchronous wind turbine includes a generator and a rotor-side converter, The rotor-side converter is electrically connected to the rotor of the generator, and is used to adjust the frequency of the alternating current output by the rotor to the target frequency, and the target frequency is less than 50Hz; the first step-up transformer, the low-voltage side of the first step-up transformer is respectively connected to the generator. The stator and the rotor-side converter are electrically connected, and the high-voltage side of the first step-up transformer is electrically connected to the power grid; the first converter, the first converter is electrically connected between the stator and the power grid, and is used to convert the output voltage of the stator to the power grid. The frequency of the alternating current is adjusted to the target frequency.
这样,本申请实施例通过转子侧变流器和第一变流器将发电机输出的交流电的频率调整至小于50Hz,一方面可以提高风力发电机组的输电系统能够输送的最大功率,即提高风力发电机组的输电系统的输电能力;另一方面可以降低风力发电机组的输电系统中的输电线路的电压降,有助于维持输电系统的电压稳定性;又一方面可以减小输电电缆的损耗,延长输电电缆的寿命。In this way, in the embodiment of the present application, the frequency of the AC power output by the generator is adjusted to be less than 50 Hz through the rotor-side converter and the first converter. On the other hand, it can reduce the voltage drop of the transmission line in the power transmission system of the wind turbine, which helps to maintain the voltage stability of the power transmission system; on the other hand, it can reduce the loss of the transmission cable, Extend the life of transmission cables.
根据本申请第二方面的实施方式,第一变流器电连接于定子与第一升压变压器的低压侧之间。According to an embodiment of the second aspect of the present application, the first converter is electrically connected between the stator and the low voltage side of the first step-up transformer.
这样,通过发电机的定子与第一升压变压器的低压侧之间的第一变流器,可以将定子输出的交流电的频率调整至小于50Hz的目标频率,能够在无需对双馈异步风力发电机组中的发电机进行重新设计的情况下,使得双馈异步风力发电机组能够适用于频率小于50Hz的低频或分频输电场景,从而降低双馈异步风力发电机组的改装成本或设计成本。In this way, through the first converter between the stator of the generator and the low-voltage side of the first step-up transformer, the frequency of the alternating current output from the stator can be adjusted to a target frequency of less than 50 Hz, and it is possible to generate electricity without the need for double-fed asynchronous wind power generation. In the case of redesigning the generators in the unit, the DFIG asynchronous wind turbine can be applied to the low-frequency or sub-frequency transmission scenarios with a frequency less than 50Hz, thereby reducing the retrofit cost or design cost of the DFIG.
根据本申请第二方面前述任一实施方式,转子侧变流器的输入端与转子电连接,第一变流器的输入端与定子电连接,转子侧变流器的输出端和第一变流器的输出端均与第一升压变压器的低压侧电连接。According to any of the foregoing embodiments of the second aspect of the present application, the input end of the rotor-side converter is electrically connected to the rotor, the input end of the first converter is electrically connected to the stator, and the output end of the rotor-side converter is electrically connected to the first converter. The output ends of the current transformers are all electrically connected to the low voltage side of the first step-up transformer.
这样,通过设置在定子侧的第一变流器,可以将定子输出的交流电的频率调整至小于50Hz的目标频率,能够在无需对双馈异步风力发电机组中的发电机进行重新设计的情况下,使得双馈异步风力发电机组能够适用于频率小于50Hz的低频或分频输电场景,从而降低双馈异步风力发电机组的改装成本或设计成本。In this way, through the first converter provided on the stator side, the frequency of the alternating current output from the stator can be adjusted to a target frequency of less than 50 Hz, which can eliminate the need to redesign the generator in the doubly-fed asynchronous wind turbine. , so that the doubly-fed asynchronous wind turbine can be applied to low-frequency or sub-frequency transmission scenarios with a frequency less than 50Hz, thereby reducing the retrofit cost or design cost of the doubly-fed asynchronous wind turbine.
根据本申请第二方面前述任一实施方式,转子侧变流器的输入端与转子电连接,第一变流器的输入端分别与定子、转子侧变流器的输出端电连接,第一变流器的输出端与第一升压变压器的低压侧电连接。According to any of the foregoing embodiments of the second aspect of the present application, the input end of the rotor-side converter is electrically connected to the rotor, the input end of the first converter is electrically connected to the stator and the output end of the rotor-side converter, respectively, and the first The output end of the converter is electrically connected to the low voltage side of the first step-up transformer.
这样,通过设置在第一升压变压器的低压侧的第一变流器,可以将定子输出的交流电的频率调整至小于50Hz的目标频率,能够在无需对双馈异步风力发电机组中的发电机进行重新设计的情况下,使得双馈异步风力发电机组能够适用于频率小于50Hz的低频或分频输电场景,从而降低双馈异步风力发电机组的改装成本或设计成本。In this way, through the first converter arranged on the low voltage side of the first step-up transformer, the frequency of the alternating current output from the stator can be adjusted to a target frequency of less than 50 Hz, which can eliminate the need for the generator in the doubly-fed asynchronous wind turbine generator set. In the case of redesign, the doubly-fed asynchronous wind turbine can be applied to low-frequency or sub-frequency transmission scenarios with a frequency less than 50Hz, thereby reducing the retrofit cost or design cost of the doubly-fed asynchronous wind turbine.
根据本申请第二方面前述任一实施方式,第一变流器电连接于第一升压变压器的高压侧与电网之间。According to any of the foregoing embodiments of the second aspect of the present application, the first converter is electrically connected between the high voltage side of the first step-up transformer and the grid.
这样,通过设置在第一升压变压器的高压侧的第一变流器,可以将定子输出的交流电的频率调整至小于50Hz的目标频率,能够在无需对双馈异步风力发电机组中的发电机进行重新设计的情况下,使得双馈异步风力发电机组能够适用于频率小于50Hz的低频或分频输电场景,从而降低双馈异步风力发电机组的改装成本或设计成本。In this way, through the first converter arranged on the high voltage side of the first step-up transformer, the frequency of the alternating current output from the stator can be adjusted to a target frequency of less than 50 Hz, which can eliminate the need for the generator in the doubly-fed asynchronous wind turbine generator set. In the case of redesign, the doubly-fed asynchronous wind turbine can be applied to low-frequency or sub-frequency transmission scenarios with a frequency less than 50Hz, thereby reducing the retrofit cost or design cost of the doubly-fed asynchronous wind turbine.
根据本申请第二方面前述任一实施方式,目标频率为第一频率范围中的任意一个频率,第一频率范围包括8Hz~21Hz。According to any of the foregoing embodiments of the second aspect of the present application, the target frequency is any frequency in the first frequency range, and the first frequency range includes 8 Hz to 21 Hz.
这样,本申请实施例通过转子侧变流器和第一变流器将发电机输出的交流电的频率调整至8Hz~21Hz,使得风电发电机组输出8Hz~21Hz的低频交流电,一方面可以提高风力发电机组的输电系统能够输送的最大功率,即提高风力发电机组的输电系统的输电能力;另一方面可以降低风力发电机组的输电系统中的输电线路的电压降,有助于维持输电系统的电压稳定性;又一方面可以减小输电电缆的损耗,延长输电电缆的寿命。In this way, in the embodiment of the present application, the frequency of the alternating current output by the generator is adjusted to 8 Hz to 21 Hz through the rotor-side converter and the first converter, so that the wind power generator set outputs low frequency alternating current of 8 Hz to 21 Hz. On the one hand, wind power generation can be improved. The maximum power that the transmission system of the wind turbine can transmit, that is, to improve the transmission capacity of the transmission system of the wind turbine; on the other hand, it can reduce the voltage drop of the transmission line in the transmission system of the wind turbine, which helps to maintain the voltage stability of the transmission system On the other hand, it can reduce the loss of the transmission cable and prolong the life of the transmission cable.
根据本申请第二方面前述任一实施方式,目标频率包括50/3Hz。According to any of the preceding embodiments of the second aspect of the present application, the target frequency comprises 50/3 Hz.
这样,本申请实施例通过转子侧变流器和第一变流器将发电机输出的交流电的频率调整至50/3Hz,使得风电发电机组输出50/3Hz的低频交流电,一方面可以提高风力发电机组的输电系统能够输送的最大功率,即提高风力发电机组的输电系统的输电能力;另一方面可以降低风力发电机组的输电系统中的输电线路的电压降,有助于维持输电系统的电压稳定性;又一方面可以减小输电电缆的损耗,延长输电电缆的寿命。In this way, in the embodiment of the present application, the frequency of the alternating current output by the generator is adjusted to 50/3 Hz through the rotor-side converter and the first converter, so that the wind power generator set outputs low-frequency alternating current of 50/3 Hz. On the one hand, the wind power generation can be improved. The maximum power that the transmission system of the wind turbine can transmit, that is, to improve the transmission capacity of the transmission system of the wind turbine; on the other hand, it can reduce the voltage drop of the transmission line in the transmission system of the wind turbine, which helps to maintain the voltage stability of the transmission system On the other hand, it can reduce the loss of the transmission cable and prolong the life of the transmission cable.
根据本申请第二方面前述任一实施方式,输电系统还包括第二升压变压器和输电线缆,第二升压变压器的低压侧与至少一个第一升压变压器的高压侧电连接,第二升压变压器的高压侧通过输电线缆与电网电连接。According to any of the foregoing embodiments of the second aspect of the present application, the power transmission system further includes a second step-up transformer and a power transmission cable, the low-voltage side of the second step-up transformer is electrically connected to the high-voltage side of the at least one first step-up transformer, and the second step-up transformer is electrically connected to the high-voltage side of the at least one first step-up transformer. The high-voltage side of the step-up transformer is electrically connected to the grid through a power transmission cable.
这样,在风力发电机组输出的交流电通过输电线缆进行远距离传输之前,通过增设第二升压变压器将第一升压变压器的高压侧输出的交流电的电压值进一步升至更高的电压值,从而减小电能在远距离传输时的损耗,提高能源利用率。In this way, before the AC power output by the wind turbine is transmitted over a long distance through the power transmission cable, the voltage value of the AC power output from the high-voltage side of the first step-up transformer is further increased by adding a second step-up transformer to a higher voltage value, Therefore, the loss of electric energy during long-distance transmission is reduced, and the energy utilization rate is improved.
根据本申请第二方面前述任一实施方式,输电系统还包括第二变流器,第二变流器的输入端通过输电线缆与第二升压变压器的高压侧电连接,第二变流器的输出端与电网电连接,第二变流器被配置为将第二升压变压器输出的交流电的频率由目标频率调整至50Hz。According to any of the foregoing embodiments of the second aspect of the present application, the power transmission system further includes a second converter, the input end of the second converter is electrically connected to the high-voltage side of the second step-up transformer through a power transmission cable, and the second converter The output end of the converter is electrically connected to the grid, and the second converter is configured to adjust the frequency of the alternating current output by the second step-up transformer from the target frequency to 50 Hz.
这样,本申请实施例通过转子侧变流器和第一变流器将发电机输出的交流电的频率调整至小于50Hz的低频,使得风电发电机组输出低频交流电,从而提高风力发电机组的输电系统的输电能力,保持风力发电机组的输电系统的电压稳定性,提高风力发电机组的输电系统中的输电线路的寿命和降低输电成本。随后,第二变流器再将交流电的频率由小于50Hz的低频调整至50Hz,从而满足日常家用的交流电的频率要求。In this way, in the embodiment of the present application, the frequency of the alternating current output by the generator is adjusted to a low frequency of less than 50 Hz through the rotor-side converter and the first converter, so that the wind power generating set outputs low-frequency alternating current, thereby improving the power transmission system of the wind power generating set. Power transmission capacity, maintain the voltage stability of the power transmission system of the wind turbine, improve the life of the transmission line in the power transmission system of the wind turbine and reduce the cost of power transmission. Then, the second converter adjusts the frequency of the alternating current from a low frequency of less than 50 Hz to 50 Hz, so as to meet the frequency requirements of the alternating current for daily household use.
根据本申请第二方面前述任一实施方式,输电系统还包括第一降压变压器或者第三升压变压器,其中:第一降压变压器的高压侧通过输电线缆与第二升压变压器的高压侧电连接,第一降压变压器的低压侧与电网电连接;第三升压变压器的低压侧通过输电线缆与第二升压变压器的高压侧电连接,第三升压变压器的高压侧与电网电连接。According to any of the foregoing embodiments of the second aspect of the present application, the power transmission system further includes a first step-down transformer or a third step-up transformer, wherein: the high-voltage side of the first step-down transformer is connected to the high-voltage side of the second step-up transformer through a power transmission cable side is electrically connected, and the low-voltage side of the first step-down transformer is electrically connected to the grid; the low-voltage side of the third step-up transformer is electrically connected to the high-voltage side of the second step-up transformer through a power transmission cable, and the high-voltage side of the third step-up transformer is electrically connected to the power grid. Grid electrical connection.
这样,通过增设第一降压变压器或者第三升压变压器,可以将风力发电机组的输电系统输出的交流电转换为所期望的目标电压值的交流电,从而满足人们在生产或生活中的不同的用电需求。In this way, by adding the first step-down transformer or the third step-up transformer, the AC power output by the power transmission system of the wind turbine can be converted into the AC power with the desired target voltage value, so as to meet the different needs of people in production or life. electricity demand.
本申请实施例的双馈异步风力发电机组和风力发电机组的输电系统,双馈异步风力发电机组包括:发电机;转子侧变流器,转子侧变流器与发电机的转子电连接,用于将转子输出的交流电的频率调整至目标频率,目标频率小于50Hz;定子侧变流器,定子侧变流器与发电机的定子电连接,用于将定子输出的交流电的频率调整至目标频率。本申请实施例通过增设定子侧变流器将定子输出的交流电的频率调整至小于50Hz的目标频率,能够在无需对双馈异步风力发电机组中的发电机进行重新设计的情况下,使得双馈异步风力发电机组能够适用于频率小于50Hz的低频或分频输电场景,从而降低双馈异步风力发电机组的改装成本或设计成本。The doubly-fed asynchronous wind generator set and the power transmission system of the wind generator set in the embodiment of the present application, the doubly-fed asynchronous wind generator set includes: a generator; a rotor-side converter, the rotor-side converter is electrically connected to the rotor of the generator, and the In order to adjust the frequency of the alternating current output by the rotor to the target frequency, the target frequency is less than 50Hz; the stator side converter, the stator side converter is electrically connected with the stator of the generator, and is used to adjust the frequency of the alternating current output by the stator to the target frequency . In the embodiment of the present application, by adding a stator-side converter to adjust the frequency of the alternating current output from the stator to a target frequency of less than 50 Hz, it is possible to make The doubly-fed asynchronous wind turbine can be applied to low-frequency or divided-frequency transmission scenarios with a frequency less than 50Hz, thereby reducing the retrofit cost or design cost of the doubly-fed asynchronous wind turbine.
附图说明Description of drawings
为了更清楚地说明本申请实施例的技术方案,下面将对本申请实施例中所需要使用的附图作简单的介绍,对于本领域普通技术人员来讲,在不付出创造性劳动的前提下,还可以根据这些附图获得其他的附图。In order to illustrate the technical solutions of the embodiments of the present application more clearly, the following briefly introduces the accompanying drawings that need to be used in the embodiments of the present application. For those of ordinary skill in the art, without creative work, the Additional drawings can be obtained from these drawings.
图1为基于工频高压交流传输的输电方案的示意图;Fig. 1 is a schematic diagram of a power transmission scheme based on power frequency high voltage AC transmission;
图2为基于高压直流传输的输电方案的示意图;FIG. 2 is a schematic diagram of a power transmission scheme based on HVDC transmission;
图3为本申请实施例提供的双馈异步风力发电机组的一种结构示意图;3 is a schematic structural diagram of a doubly-fed asynchronous wind power generator set provided by an embodiment of the present application;
图4为本申请实施例提供的风力发电机组的输电系统的一种结构示意图;4 is a schematic structural diagram of a power transmission system of a wind turbine according to an embodiment of the application;
图5为本申请实施例提供的风力发电机组的输电系统的另一种结构示意图;5 is another schematic structural diagram of a power transmission system of a wind turbine according to an embodiment of the application;
图6为本申请实施例提供的风力发电机组的输电系统的又一种结构示意图;6 is another schematic structural diagram of a power transmission system of a wind turbine according to an embodiment of the present application;
图7为本申请实施例提供的风力发电机组的输电系统的又一种结构示意图。FIG. 7 is another schematic structural diagram of a power transmission system of a wind turbine according to an embodiment of the present application.
具体实施方式Detailed ways
下面将详细描述本申请的各个方面的特征和示例性实施例,为了使本申请的目的、技术方案及优点更加清楚明白,以下结合附图及具体实施例,对本申请进行进一步详细描述。应理解,此处所描述的具体实施例仅意在解释本申请,而不是限定本申请。对于本领域技术人员来说,本申请可以在不需要这些具体细节中的一些细节的情况下实施。下面对实施例的描述仅仅是为了通过示出本申请的示例来提供对本申请更好的理解。The features and exemplary embodiments of various aspects of the present application will be described in detail below. In order to make the purpose, technical solutions and advantages of the present application more clear, the present application will be further described in detail below with reference to the accompanying drawings and specific embodiments. It should be understood that the specific embodiments described herein are only intended to explain the present application, but not to limit the present application. It will be apparent to those skilled in the art that the present application may be practiced without some of these specific details. The following description of the embodiments is merely to provide a better understanding of the present application by illustrating examples of the present application.
需要说明的是,在本文中,诸如第一和第二等之类的关系术语仅仅用来将一个实体或者操作与另一个实体或操作区分开来,而不一定要求或者暗示这些实体或操作之间存在任何这种实际的关系或者顺序。而且,术语“包括”、“包含”或者其任何其他变体意在涵盖非排他性的包含,从而使得包括一系列要素的过程、方法、物品或者设备不仅包括那些要素,而且还包括没有明确列出的其他要素,或者是还包括为这种过程、方法、物品或者设备所固有的要素。在没有更多限制的情况下,由语句“包括……”限定的要素,并不排除在包括所述要素的过程、方法、物品或者设备中还存在另外的相同要素。It should be noted that, in this document, relational terms such as first and second are only used to distinguish one entity or operation from another entity or operation, and do not necessarily require or imply any relationship between these entities or operations. any such actual relationship or sequence exists. Moreover, the terms "comprising", "comprising" or any other variation thereof are intended to encompass a non-exclusive inclusion such that a process, method, article or device that includes a list of elements includes not only those elements, but also includes not explicitly listed or other elements inherent to such a process, method, article or apparatus. Without further limitation, an element defined by the phrase "comprises" does not preclude the presence of additional identical elements in a process, method, article, or device that includes the element.
应当理解,本文中使用的术语“和/或”仅仅是一种描述关联对象的关联关系,表示可以存在三种关系,例如,A和/或B,可以表示:单独存在A,同时存在A和B,单独存在B这三种情况。另外,本文中字符“/”,一般表示前后关联对象是一种“或”的关系。It should be understood that the term "and/or" used in this document is only an association relationship to describe the associated objects, indicating that there may be three kinds of relationships, for example, A and/or B, which may indicate that A exists alone, and A and B exist at the same time. B, there are three cases of B alone. In addition, the character "/" in this document generally indicates that the related objects are an "or" relationship.
在阐述本申请实施例所提供的技术方案之前,为了便于对本申请实施例理解,本申请首先对现有技术中存在的问题进行具体说明:Before describing the technical solutions provided by the embodiments of the present application, in order to facilitate the understanding of the embodiments of the present application, the present application first specifically describes the problems existing in the prior art:
如前所述,经本申请的发明人发现,相关技术中存在风力发电机组的输电成本和改装成本高昂的问题。As mentioned above, the inventors of the present application have found that the related art has problems of high cost of power transmission and retrofit of wind turbines.
为了解决风力发电机组的输电成本和改装成本高昂的问题,本申请的发明人首先对于相关技术中风力发电机组的输电线路和输电方式进行了研究,以确定导致上述技术问题的根因,具体的研究和分析过程如下:In order to solve the problems of high power transmission cost and retrofit cost of wind turbines, the inventor of the present application firstly studies the transmission lines and transmission methods of wind turbines in the related art to determine the root causes of the above technical problems. The research and analysis process is as follows:
图1为基于工频高压交流传输(简称HVAC)的输电方案。如图1所示,以海上风力发电机组的输电场景为例,海上风电场10’中可以包括多个风力发电机组100’。风力发电机组100’可以包括叶轮101’、发电机102’和变流器103’。示例性地,发电机102’可以是永磁同步发电机(Permanent Magnetic Synchronous Machine,简称PMSG)、双馈异步发电机(Doublyfed Induction Generator,简称DFIG)或者其他类型的发电机,图1中的发电机102’例如以永磁同步发电机PMSG示出。在风力的驱动下,叶轮101’开始转动并带动发电机102’中的转子相对于发电机102’中的定子开始旋转,进而开始发电。为了保证风力发电机组100’能够输出恒定的电能,通常需要变流器103’将发电机102’输出电能调整成电压幅值恒定和频率恒定(频率为工频50Hz)的电能。由于变流器103’输出的电压值较低,不利于电能的传输。因此,为了电能的高效传输,通常需要在变流器103’的输出端连接一个升压变压器200’,通过升压变压器200’将变流器103’输出的电压(即风力发电机组100’输出的电压)由较低电压值升压至较高电压值,如从690V(伏特)升压至35kV(千伏特),如得到电压值为35kV且频率为50Hz的交流电,即35kV/50Hz交流电。Figure 1 shows a power transmission scheme based on power frequency high voltage AC transmission (HVAC for short). As shown in FIG. 1 , taking a power transmission scenario of an offshore wind turbine as an example, the offshore wind farm 10' may include multiple wind turbines 100'. The wind turbine 100' may include an impeller 101', a generator 102' and a converter 103'. Exemplarily, the
接下来,每个升压变压器200’输出的升压后的电能(如35kV/50Hz交流电)再通过集电线路300’进行汇总,汇总后的电能再通过海上升压变电站中的升压变压器400’进一步升至更高的电压值(如110kV或220kV),如得到电压值为110kV或220kV且频率为50Hz的交流电,即110kV或220kV/50Hz交流电。再接下来,通过海上输电线缆500’将110kV或220kV/50Hz交流电传输至陆上变电站。最后,通过陆地变电站中的变压器600’将110kV或220kV/50Hz转换为目标电压值且频率为50Hz的交流电并入电网700’。Next, the boosted electric energy (such as 35kV/50Hz alternating current) output by each step-up transformer 200' is aggregated through the collector line 300', and the aggregated electric energy is then passed through the
经本申请的发明人发现,随着输电距离的增加,HVAC输电方案的输出成本也会增高,当海上风电场离岸距离超过一定距离(如约80km左右)时,HVAC输电方案的输电成本将会高于其他输电方案的输电成本。The inventors of the present application have found that with the increase of the transmission distance, the output cost of the HVAC power transmission scheme will also increase. Higher transmission costs than other transmission options.
图2为基于高压直流传输(简称VSC-HVAC)的输电方案。如图2所示,与图1所示的HVAC输电方案不同的是,图2所示的VSC-HVAC输电方案中还包括海上换流站800’和岸上换流站900’。容易理解的是,海上换流站800’设置在海上,岸上换流站900’设置在陆地上。海上换流站800’的作用是将海上升压变电站中的升压变压器400’输出的交流电(如110kV或220kV/50Hz交流电)转换为直流电。然后,通过海上输电线缆500’将海上换流站800’转换后的直流电传输至岸上换流站900’。岸上换流站900’再将直流电转换为交流电。即,图2所示的VSC-HVAC输电方案相比于图1所示的HVAC输电方案,增加了交流电转换为直流电、直流电再转换为交流电的过程。因此,VSC-HVAC输电方案需要配置海上换流站800’和岸上换流站900’,输电成本较高。Figure 2 shows a power transmission scheme based on high-voltage direct current transmission (VSC-HVAC for short). As shown in FIG. 2, different from the HVAC power transmission scheme shown in FIG. 1, the VSC-HVAC power transmission scheme shown in FIG. 2 also includes an offshore converter station 800' and an onshore converter station 900'. It is easy to understand that the offshore converter station 800' is arranged at sea, and the onshore converter station 900' is arranged on land. The role of the offshore converter station 800' is to convert the alternating current (such as 110kV or 220kV/50Hz alternating current) output by the step-up transformer 400' in the offshore step-up substation into direct current. Then, the DC power converted by the offshore converter station 800' is transmitted to the onshore converter station 900' through the offshore power transmission cable 500'. The onshore converter station 900' then converts the direct current to alternating current. That is, compared with the HVAC power transmission scheme shown in FIG. 1 , the VSC-HVAC power transmission scheme shown in FIG. 2 adds a process of converting alternating current to direct current, and then converting direct current to alternating current. Therefore, the VSC-HVAC power transmission scheme needs to configure the offshore converter station 800' and the onshore converter station 900', and the power transmission cost is relatively high.
为了降低风力发电机组的输电成本,本申请实施例提出了一种低频输电方案或称为分频输电方案,通过低频输电或分频输电可以降低风力发电机组的输电成本。但随之本申请的发明人又发现了相关技术中存在的另一个技术问题,那便是相关技术中双馈异步发电机的定子是按照输出50Hz的交流电设计的,无法适用于频率小于50Hz的低频或分频输电场景。若想要双馈异步发电机的定子适用于频率小于50Hz的低频或分频输电场景,则需要对双馈异步发电机进行重新设计,尤其是需要对双馈异步发电机的定子进行重新设计。发电机作为风力发电机组的核心部件,发电机重新设计也就意味着风力发电机组需要重新设计,这样一来,风力发电机组的改装成本或者说设计成本将会较为高昂。In order to reduce the power transmission cost of the wind turbine, the embodiment of the present application proposes a low-frequency power transmission scheme or a frequency division power transmission scheme. However, the inventor of the present application also discovered another technical problem in the related art, that is, the stator of the doubly-fed asynchronous generator in the related art is designed according to the AC output of 50Hz, and cannot be applied to the frequency less than 50Hz. Low-frequency or cross-frequency power transmission scenarios. If you want the stator of the DFIG to be suitable for low-frequency or divided-frequency power transmission scenarios with a frequency less than 50 Hz, the DFIG needs to be redesigned, especially the stator of the DFIG needs to be redesigned. As the core component of the wind turbine, the redesign of the generator means that the wind turbine needs to be redesigned. In this way, the retrofit cost or design cost of the wind turbine will be relatively high.
鉴于发明人的上述研究发现,本申请实施例提供了一种双馈异步风力发电机组,能够解决相关技术中存在的风力发电机组的改装成本高昂的技术问题。In view of the above research findings of the inventors, the embodiments of the present application provide a doubly-fed asynchronous wind power generator set, which can solve the technical problem of the high cost of retrofitting of wind power generator sets in the related art.
本申请实施例的技术构思在于:通过增设定子侧变流器将定子输出的交流电的频率由50Hz调整至小于50Hz,从而在无需对双馈异步风力发电机组中的发电机进行重新设计的情况下,使得双馈异步风力发电机组能够适用于频率小于50Hz的低频或分频输电场景,从而降低双馈异步风力发电机组的改装成本或设计成本。The technical idea of the embodiments of the present application is to adjust the frequency of the alternating current output from the stator from 50 Hz to less than 50 Hz by adding a stator-side converter, so that there is no need to redesign the generator in the doubly-fed asynchronous wind turbine. Under the circumstance, the DFIG asynchronous wind turbine can be applied to the low-frequency or sub-frequency transmission scenarios with a frequency less than 50Hz, thereby reducing the retrofit cost or design cost of the DFIG.
下面首先对本申请实施例所提供的双馈异步风力发电机组进行介绍。First, the doubly-fed asynchronous wind power generator set provided by the embodiment of the present application will be introduced below.
如图3所示,本申请实施例提供了一种双馈异步风力发电机组300。所谓的“双馈”即发电机的定子和转子都可以和电网进行功率交换。双馈异步发电机的定子或称定子绕组可以直接与电网相连,转子或称转子绕组可以通过变流器与电网连接。转子绕组电源的频率、电压、幅值和相位按运行要求可以由变流器自动调节,从而使得双馈异步风力发电机组可以在不同的转速下实现恒频发电,进而满足用电负载和并网的要求。本申请实施例提供的双馈异步风力发电机组300包括:发电机301、转子侧变流器302和定子侧变流器303。转子侧变流器302与发电机301的转子电连接,用于将转子输出的交流电的频率调整至目标频率。定子侧变流器303与发电机301的定子电连接,用于将定子输出的交流电的频率调整至目标频率。其中,目标频率小于50Hz。As shown in FIG. 3 , an embodiment of the present application provides a doubly-fed asynchronous wind generator set 300 . The so-called "double-fed" means that both the stator and the rotor of the generator can exchange power with the grid. The stator or stator winding of the doubly-fed asynchronous generator can be directly connected to the grid, and the rotor or rotor winding can be connected to the grid through a converter. The frequency, voltage, amplitude and phase of the rotor winding power supply can be automatically adjusted by the converter according to the operating requirements, so that the doubly-fed asynchronous wind turbine can achieve constant frequency power generation at different speeds, thereby satisfying the power load and grid connection. requirements. The doubly-fed asynchronous wind power generator set 300 provided in the embodiment of the present application includes: a
容易理解的是,转子侧变流器即可以理解为设置在转子侧且与发电机301的转子电连接的变流器,定子侧变流器即可以理解为设置在定子侧且与发电机301的定子电连接的变流器。在实际应用中,变流器也可以称作变频器或其他名称,如英文名称FrequencyConverter,即若将转子侧变流器和定子侧变流器替换成其他能够实现变频功能的电子器件,也处于本申请的保护范围之内。在本申请实施例中,转子侧变流器302和定子侧变流器303包括但不限于交-交变流器,即AC-AC变流器。It is easy to understand that the rotor-side converter can be understood as a converter provided on the rotor side and electrically connected to the rotor of the
下面对于本申请实施例的双馈异步风力发电机组300的工作过程进行简单介绍。The working process of the doubly-fed asynchronous wind power generating set 300 according to the embodiment of the present application will be briefly introduced below.
继续参见图3,根据本申请的一些实施例,双馈异步风力发电机组300还可以包括叶轮304和齿轮箱305。叶轮304带动齿轮箱305中的齿轮转动,实现风能对机械能的转换。齿轮箱305带动发电机301发电,实现机械能对电能的转换。转子侧变流器302将发电机301转子输出的交流电的频率调整至小于50Hz目标频率,定子侧变流器303将发电机301的定子输出的交流电的频率调整至小于50Hz目标频率。升压变压器200将转子侧变流器302和定子侧变流器303输出的交流电的电压由较低电压值升压至较高电压值,例如从690V升压至35kV,得到电压值为35kV且频率为小于50Hz的交流电,然后将电压值为35kV且频率为小于50Hz的交流电传输至电网500。Continuing to refer to FIG. 3 , according to some embodiments of the present application, the doubly-fed asynchronous
本申请实施例提供的双馈异步风力发电机组能够实现如下技术效果:由于目前的双馈异步发电机的定子是按照输出50Hz的交流电设计的,无法适用于频率小于50Hz的低频或分频输电场景。而本申请实施例通过增设定子侧变流器将定子输出的交流电的频率由50Hz调整至小于50Hz,从而在无需对双馈异步风力发电机组中的发电机进行重新设计的情况下,使得双馈异步风力发电机组能够适用于频率小于50Hz的低频或分频输电场景,从而降低双馈异步风力发电机组的改装成本或设计成本。The doubly-fed asynchronous wind power generator set provided by the embodiment of the present application can achieve the following technical effects: because the stator of the current doubly-fed asynchronous generator is designed according to the AC output of 50Hz, it cannot be applied to the low-frequency or divided-frequency power transmission scenarios with a frequency less than 50Hz. . However, in the embodiment of the present application, the frequency of the alternating current output from the stator is adjusted from 50 Hz to less than 50 Hz by adding a stator-side converter, so that the generator in the doubly-fed asynchronous wind turbine does not need to be redesigned. The doubly-fed asynchronous wind turbine can be applied to low-frequency or divided-frequency transmission scenarios with a frequency less than 50Hz, thereby reducing the retrofit cost or design cost of the doubly-fed asynchronous wind turbine.
针对风力发电机组的输电成本和改装成本高昂的问题,本申请实施例还提供了一种风力发电机组的输电系统。Aiming at the problems of high power transmission cost and modification cost of the wind power generating set, the embodiment of the present application also provides a power transmission system for the wind power generating set.
如图4所示,本申请实施例提供的风力发电机组的输电系统400包括:双馈异步风力发电机组410、第一变流器420和第一升压变压器430。双馈异步风力发电机组410包括发电机411和转子侧变流器412,转子侧变流器412与发电机411的转子电连接,用于将发电机411的转子输出的交流电的频率调整至目标频率,目标频率小于50Hz。第一变流器420电连接于发电机411的定子与电网500之间,用于将发电机411的定子输出的交流电的频率调整至小于50Hz的目标频率。第一升压变压器430的低压侧分别与发电机411的定子以及转子侧变流器412电连接,第一升压变压器430的高压侧与电网500电连接,第一升压变压器430用于将转子侧变流器302以及发电机411的定子或第一变流器420输出的交流电的电压由较低电压值升压至较高电压值,例如从690V升压至35kV。经过第一升压变压器430升压后的较高电压值且频率小于50Hz的交流电传输至电网500。As shown in FIG. 4 , the
本申请实施例提供的风力发电机组的输电系统400,增设第一变流器将定子输出的交流电的频率由50Hz调整至小于50Hz,从而在无需对双馈异步风力发电机组中的发电机进行重新设计的情况下,使得双馈异步风力发电机组能够适用于频率小于50Hz的低频或分频输电场景,从而降低双馈异步风力发电机组的改装成本或设计成本。In the
此外,本申请实施例提供的风力发电机组的输电系统400,通过转子侧变流器和第一变流器将发电机输出的交流电的频率调整至小于50Hz,一方面可以提高风力发电机组的输电系统能够输送的最大功率,即提高风力发电机组的输电系统的输电能力;另一方面可以降低风力发电机组的输电系统中的输电线路的电压降,有助于维持输电系统的电压稳定性;又一方面可以减小输电电缆的损耗,延长输电电缆的寿命。In addition, the
继续参见图4,根据本申请的一些实施例,可选地,第一变流器420可以电连接于发电机411的定子与第一升压变压器130的低压侧之间。即,第一变流器420将发电机411的定子输出的交流电的频率调整至小于50Hz的目标频率,然后第一升压变压器430对第一变流器420输出的交流电进行升压,得到较高电压值(如35kV)且频率小于50Hz的交流电。在本申请实施例中,转子侧变流器302和第一变流器420包括但不限于交-交变流器,即AC-AC变流器。Continuing to refer to FIG. 4 , according to some embodiments of the present application, optionally, the
这样,通过发电机的定子与第一升压变压器的低压侧之间的第一变流器,可以将定子输出的交流电的频率调整至小于50Hz的目标频率,能够在无需对双馈异步风力发电机组中的发电机进行重新设计的情况下,使得双馈异步风力发电机组能够适用于频率小于50Hz的低频或分频输电场景,从而降低双馈异步风力发电机组的改装成本或设计成本。In this way, through the first converter between the stator of the generator and the low-voltage side of the first step-up transformer, the frequency of the alternating current output from the stator can be adjusted to a target frequency of less than 50 Hz, and it is possible to generate electricity without the need for double-fed asynchronous wind power generation. In the case of redesigning the generators in the unit, the DFIG asynchronous wind turbine can be applied to the low-frequency or sub-frequency transmission scenarios with a frequency less than 50Hz, thereby reducing the retrofit cost or design cost of the DFIG.
继续参见图4,在一些具体的实施例中,可选地,第一变流器420可以设置在定子侧。具体地,转子侧变流器412的输入端与发电机411的转子电连接,第一变流器420的输入端与发电机411的定子电连接,转子侧变流器412的输出端和第一变流器420的输出端均与第一升压变压器430的低压侧电连接。转子侧变流器412将发电机411的转子输出的交流电的频率调整至目标频率,第一变流器420将发电机411的定子输出的交流电的频率调整至小于50Hz的目标频率。第一升压变压器430对转子侧变流器412和第一变流器420输出的交流电进行升压,得到较高电压值(如35kV)且频率小于50Hz的交流电。Continuing to refer to FIG. 4 , in some specific embodiments, optionally, the
这样,通过设置在定子侧的第一变流器,可以将定子输出的交流电的频率调整至小于50Hz的目标频率,能够在无需对双馈异步风力发电机组中的发电机进行重新设计的情况下,使得双馈异步风力发电机组能够适用于频率小于50Hz的低频或分频输电场景,从而降低双馈异步风力发电机组的改装成本或设计成本。In this way, through the first converter provided on the stator side, the frequency of the alternating current output from the stator can be adjusted to a target frequency of less than 50 Hz, which can eliminate the need to redesign the generator in the doubly-fed asynchronous wind turbine. , so that the doubly-fed asynchronous wind turbine can be applied to low-frequency or sub-frequency transmission scenarios with a frequency less than 50Hz, thereby reducing the retrofit cost or design cost of the doubly-fed asynchronous wind turbine.
如图5所示,在另一些具体的实施例中,可选地,第一变流器420还可以设置在第一升压变压器430的低压侧。具体地,转子侧变流器412的输入端与发电机411的转子电连接,第一变流器420的输入端分别与发电机411的定子以及转子侧变流器412的输出端电连接,第一变流器420的输出端与第一升压变压器430的低压侧电连接。转子侧变流器412将发电机411的转子输出的交流电的频率调整至目标频率,第一变流器420将发电机411的定子输出的交流电的频率调整至小于50Hz的目标频率。第一升压变压器430对转子侧变流器412和第一变流器420输出的交流电进行升压,得到较高电压值(如35kV)且频率小于50Hz的交流电。As shown in FIG. 5 , in other specific embodiments, optionally, the
这样,通过设置在第一升压变压器的低压侧的第一变压器,可以将定子输出的交流电的频率调整至小于50Hz的目标频率,能够在无需对双馈异步风力发电机组中的发电机进行重新设计的情况下,使得双馈异步风力发电机组能够适用于频率小于50Hz的低频或分频输电场景,从而降低双馈异步风力发电机组的改装成本或设计成本。In this way, through the first transformer arranged on the low voltage side of the first step-up transformer, the frequency of the alternating current output from the stator can be adjusted to a target frequency of less than 50 Hz, and the generators in the doubly-fed asynchronous wind turbines can be re-engineered without having to be rebuilt. In the case of design, the doubly-fed asynchronous wind turbine can be applied to low-frequency or sub-frequency transmission scenarios with a frequency less than 50Hz, thereby reducing the retrofit cost or design cost of the doubly-fed asynchronous wind turbine.
如图6所示,在另一些具体的实施例中,可选地,第一变流器420还可以设置在第一升压变压器430的高压侧。具体地,第一变流器420电连接于第一升压变压器430的高压侧与电网500之间。第一变流器420同样可以将发电机411的定子输出的交流电的频率调整至小于50Hz的目标频率。As shown in FIG. 6 , in some other specific embodiments, optionally, the
这样,通过设置在第一升压变压器的高压侧的第一变压器,可以将定子输出的交流电的频率调整至小于50Hz的目标频率,能够在无需对双馈异步风力发电机组中的发电机进行重新设计的情况下,使得双馈异步风力发电机组能够适用于频率小于50Hz的低频或分频输电场景,从而降低双馈异步风力发电机组的改装成本或设计成本。In this way, by means of the first transformer arranged on the high voltage side of the first step-up transformer, the frequency of the alternating current output from the stator can be adjusted to a target frequency of less than 50 Hz, and the generators in the doubly-fed asynchronous wind power generating set need not be reworked. In the case of design, the doubly-fed asynchronous wind turbine can be applied to low-frequency or sub-frequency transmission scenarios with a frequency less than 50Hz, thereby reducing the retrofit cost or design cost of the doubly-fed asynchronous wind turbine.
根据本申请的一些实施例,可选地,目标频率可以为第一频率范围中的任意一个频率,第一频率范围包括8Hz~21Hz。示例性地,例如目标频率可以为50/6Hz、15Hz、50/3Hz或21Hz等。According to some embodiments of the present application, optionally, the target frequency may be any frequency in a first frequency range, and the first frequency range includes 8 Hz to 21 Hz. Illustratively, for example, the target frequency may be 50/6 Hz, 15 Hz, 50/3 Hz, 21 Hz, or the like.
这样,本申请实施例通过转子侧变流器和第一变流器将发电机输出的交流电的频率调整至8Hz~21Hz,使得风电发电机组输出8Hz~21Hz的低频交流电,一方面可以提高风力发电机组的输电系统能够输送的最大功率,即提高风力发电机组的输电系统的输电能力;另一方面可以降低风力发电机组的输电系统中的输电线路的电压降,有助于维持输电系统的电压稳定性;又一方面可以减小输电电缆的损耗,延长输电电缆的寿命。In this way, in the embodiment of the present application, the frequency of the alternating current output by the generator is adjusted to 8 Hz to 21 Hz through the rotor-side converter and the first converter, so that the wind power generator set outputs low frequency alternating current of 8 Hz to 21 Hz. On the one hand, wind power generation can be improved. The maximum power that the transmission system of the wind turbine can transmit, that is, to improve the transmission capacity of the transmission system of the wind turbine; on the other hand, it can reduce the voltage drop of the transmission line in the transmission system of the wind turbine, which helps to maintain the voltage stability of the transmission system On the other hand, it can reduce the loss of the transmission cable and prolong the life of the transmission cable.
在一些具体的实施例中,可选地,目标频率可以包括50/3Hz。In some specific embodiments, the target frequency may optionally include 50/3 Hz.
这样,本申请实施例通过转子侧变流器和第一变流器将发电机输出的交流电的频率调整至50/3Hz,使得风电发电机组输出50/3Hz的低频交流电,一方面可以提高风力发电机组的输电系统能够输送的最大功率,即提高风力发电机组的输电系统的输电能力;另一方面可以降低风力发电机组的输电系统中的输电线路的电压降,有助于维持输电系统的电压稳定性;又一方面可以减小输电电缆的损耗,延长输电电缆的寿命。In this way, in the embodiment of the present application, the frequency of the alternating current output by the generator is adjusted to 50/3 Hz through the rotor-side converter and the first converter, so that the wind power generator set outputs low-frequency alternating current of 50/3 Hz. On the one hand, the wind power generation can be improved. The maximum power that the transmission system of the wind turbine can transmit, that is, to improve the transmission capacity of the transmission system of the wind turbine; on the other hand, it can reduce the voltage drop of the transmission line in the transmission system of the wind turbine, which helps to maintain the voltage stability of the transmission system On the other hand, it can reduce the loss of the transmission cable and prolong the life of the transmission cable.
如图7所示,根据本申请的一些实施例,可选地,风力发电机组的输电系统400还可以包括第二升压变压器710和输电线缆720,第二升压变压器710的低压侧与至少一个第一升压变压器430的高压侧电连接,第二升压变压器710的高压侧通过输电线缆720与电网500电连接。第二升压变压器710可以用于对至少一个第一升压变压器430输出的较高电压值(如35kV)且频率小于50Hz的交流电进行升压,如得到更高电压值(如110kV或220kV)且频率小于50Hz的交流电。输电线缆720将第二升压变压器710输出的更高电压值(如110kV或220kV)且频率小于50Hz的交流电传输至电网500。需要说明的是,在海上风力发电机组的输电场景中,第二升压变压器710可以设置在海上升压变电站之中,输电线缆720可以为海上输电线缆。As shown in FIG. 7 , according to some embodiments of the present application, optionally, the
这样,在风力发电机组输出的交流电通过输电线缆进行远距离传输之前,通过增设第二升压变压器将第一升压变压器的高压侧输出的交流电的电压值进一步升至更高的电压值,从而减小电能在远距离传输时的损耗,提高能源利用率。In this way, before the AC power output by the wind turbine is transmitted over a long distance through the power transmission cable, the voltage value of the AC power output from the high-voltage side of the first step-up transformer is further increased by adding a second step-up transformer to a higher voltage value, Therefore, the loss of electric energy during long-distance transmission is reduced, and the energy utilization rate is improved.
继续参见图7,根据本申请的一些实施例,可选地,风力发电机组的输电系统400还可以包括第二变流器730,第二变流器730的输入端通过输电线缆720与第二升压变压器710的高压侧电连接,第二变流器730的输出端与电网500电连接,第二变流器730被配置为将第二升压变压器710输出的交流电的频率由目标频率调整至50Hz。例如,第二升压变压器710输出的是110kV或220kV且频率小于50Hz的交流电,第二变流器730则可以将110kV或220kV且频率小于50Hz的交流电转换为110kV或220kV且频率等于50Hz的交流电。在本申请实施例中,第二变流器730包括但不限于交-交变流器,即AC-AC变流器。Continuing to refer to FIG. 7 , according to some embodiments of the present application, optionally, the
这样,本申请实施例通过转子侧变流器和第一变流器将发电机输出的交流电的频率调整至小于50Hz的低频,使得风电发电机组输出低频交流电,从而提高风力发电机组的输电系统的输电能力,保持风力发电机组的输电系统的电压稳定性,提高风力发电机组的输电系统中的输电线路的寿命和降低输电成本。随后,第二变流器再将交流电的频率由小于50Hz的低频调整至50Hz,从而满足日常家用的交流电的频率要求。In this way, in the embodiment of the present application, the frequency of the alternating current output by the generator is adjusted to a low frequency of less than 50 Hz through the rotor-side converter and the first converter, so that the wind power generating set outputs low-frequency alternating current, thereby improving the power transmission system of the wind power generating set. Power transmission capacity, maintain the voltage stability of the power transmission system of the wind turbine, improve the life of the transmission line in the power transmission system of the wind turbine and reduce the cost of power transmission. Then, the second converter adjusts the frequency of the alternating current from a low frequency of less than 50 Hz to 50 Hz, so as to meet the frequency requirements of the alternating current for daily household use.
需要说明的是,在海上风力发电机组的输电场景中,第二变流器730可以设置在陆地上,从而减少第二变流器的安装成本,提高第二变流器的安装效率。It should be noted that, in the power transmission scenario of the offshore wind turbine, the
根据本申请的一些实施例,可选地,风力发电机组的输电系统400还可以包括第一降压变压器740或者第三升压变压器750,其中:第一降压变压器740的高压侧通过输电线缆720与第二升压变压器710的高压侧电连接,第一降压变压器740的低压侧与电网500电连接。第三升压变压器750的低压侧通过输电线缆720与第二升压变压器710的高压侧电连接,第三升压变压器750的高压侧与电网500电连接。需要说明的是,在海上风力发电机组的输电场景中,第一降压变压器740或者第三升压变压器750可以设置在陆地上。According to some embodiments of the present application, optionally, the
容易理解的是,当需要对输电线缆720输送的交流电进行降压(例如将输电线缆720输送的交流电转换为日常生活用电)时,则可以设置第一降压变压器740,通过第一降压变压器740对输电线缆720输送的交流电进行降压,使得风力发电机组的输电系统400输出的交流电转换为所期望的目标电压值的交流电。当需要对输电线缆720输送的交流电进行升压(例如输电线缆720输送的交流电需要再次进行远距离传输)时,则可以设置第三升压变压器750,通过第三升压变压器750对输电线缆720输送的交流电进行升压,使得风力发电机组的输电系统400输出的交流电转换为所期望的目标电压值的交流电。It is easy to understand that when the AC power transmitted by the
这样,通过增设第一降压变压器或者第三升压变压器,可以将风力发电机组的输电系统输出的交流电转换为所期望的目标电压值的交流电,从而满足人们在生产或生活中的不同的用电需求。In this way, by adding the first step-down transformer or the third step-up transformer, the AC power output by the power transmission system of the wind turbine can be converted into the AC power with the desired target voltage value, so as to meet the different needs of people in production or life. electricity demand.
需要说明的是,第一升压变压器430、第二升压变压器710、第三升压变压器750和第一降压变压器740可以采用星-三角设计、星-星设计或其他类型设计,本申请实施例不作限定。It should be noted that, the first step-up
需要明确的是,本说明书中的各个实施例均采用递进的方式描述,各个实施例之间相同或相似的部分互相参见即可,每个实施例重点说明的都是与其他实施例的不同之处。对于输电系统实施例而言,相关之处可以参见风力发电机组实施例的说明部分。本申请并不局限于上文所描述并在图中示出的特定结构。本领域的技术人员可以在领会本申请的精神之后,作出各种改变、修改和添加。并且,为了简明起见,这里省略对已知技术的详细描述。It should be clear that each embodiment in this specification is described in a progressive manner, and the same or similar parts of each embodiment may be referred to each other, and each embodiment focuses on the differences from other embodiments. place. For the power transmission system embodiment, reference can be made to the description section of the wind turbine embodiment. The present application is not limited to the specific structures described above and shown in the drawings. Various changes, modifications and additions can be made by those skilled in the art after comprehending the spirit of the present application. Also, for the sake of brevity, detailed descriptions of known technologies are omitted here.
本领域技术人员应能理解,上述实施例均是示例性而非限制性的。在不同实施例中出现的不同技术特征可以进行组合,以取得有益效果。本领域技术人员在研究附图、说明书及权利要求书的基础上,应能理解并实现所揭示的实施例的其他变化的实施例。在权利要求书中,术语“包括”并不排除其他装置或步骤;数量词“一个”不排除多个;术语“第一”、“第二”用于标示名称而非用于表示任何特定的顺序。权利要求中的任何附图标记均不应被理解为对保护范围的限制。权利要求中出现的多个部分的功能可以由一个单独的硬件或软件模块来实现。某些技术特征出现在不同的从属权利要求中并不意味着不能将这些技术特征进行组合以取得有益效果。Those skilled in the art should understand that the above-mentioned embodiments are all illustrative and not restrictive. Different technical features appearing in different embodiments can be combined to achieve beneficial effects. Those skilled in the art should be able to understand and implement other variant embodiments of the disclosed embodiments on the basis of studying the drawings, the description and the claims. In the claims, the term "comprising" does not exclude other means or steps; the term "a" does not exclude a plurality; the terms "first" and "second" are used to denote names rather than any particular order . Any reference signs in the claims shall not be construed as limiting the scope. The functions of several parts presented in the claims can be implemented by a single hardware or software module. The mere presence of certain technical features in different dependent claims does not imply that these features cannot be combined to advantage.
Claims (8)
Priority Applications (1)
| Application Number | Priority Date | Filing Date | Title |
|---|---|---|---|
| CN202123443099.7U CN216872860U (en) | 2021-12-30 | 2021-12-30 | Doubly-fed asynchronous wind turbines and transmission systems for wind turbines |
Applications Claiming Priority (1)
| Application Number | Priority Date | Filing Date | Title |
|---|---|---|---|
| CN202123443099.7U CN216872860U (en) | 2021-12-30 | 2021-12-30 | Doubly-fed asynchronous wind turbines and transmission systems for wind turbines |
Publications (1)
| Publication Number | Publication Date |
|---|---|
| CN216872860U true CN216872860U (en) | 2022-07-01 |
Family
ID=82151011
Family Applications (1)
| Application Number | Title | Priority Date | Filing Date |
|---|---|---|---|
| CN202123443099.7U Active CN216872860U (en) | 2021-12-30 | 2021-12-30 | Doubly-fed asynchronous wind turbines and transmission systems for wind turbines |
Country Status (1)
| Country | Link |
|---|---|
| CN (1) | CN216872860U (en) |
-
2021
- 2021-12-30 CN CN202123443099.7U patent/CN216872860U/en active Active
Similar Documents
| Publication | Publication Date | Title |
|---|---|---|
| CN102694382B (en) | Method and arrangement for controlling an operation of an electric energy production facility during a disconnection to a utility grid | |
| US20150226185A1 (en) | Wind farm | |
| US10107264B2 (en) | Medium voltage wind power generation system and power generation method using the same | |
| CN110336326B (en) | Double-fed wind power/hydraulic power generation system with stator loop independently directly distributed to high-voltage power grid | |
| CN105207257A (en) | Offshore wind turbine grid connection method and system | |
| CN110080944B (en) | Wind power generation system and control method thereof | |
| CN107887924A (en) | Fan power transmission system | |
| US20140042818A1 (en) | Photovoltaic power plant | |
| CN217182965U (en) | Offshore wind farms and offshore wind power transmission systems | |
| Johnson et al. | Offshore wind farm with DC collection system | |
| CN103904639B (en) | For the Double-feed wind power unit converter control method of flexible direct current power transmission system | |
| CN115833243A (en) | A centralized inverter boost integrated offshore wind power generation system and method | |
| CN104362643A (en) | Method for calculating reactive compensation configured capacity for wind farm | |
| CN217882864U (en) | Wind power generation and transmission system | |
| CN201802563U (en) | Full-power squirrel-cage set wind power generation apparatus | |
| CN216872860U (en) | Doubly-fed asynchronous wind turbines and transmission systems for wind turbines | |
| CN201061153Y (en) | Full power grid-connected converter for megawatt wind power generation | |
| CN203406622U (en) | Direct drive wind power generation system based on common DC bus | |
| Verma et al. | Theoretical approach for comparison of various types of wind generator systems | |
| CN114498739A (en) | Offshore Wind Power System and Offshore Wind Power Transmission System | |
| CN216872861U (en) | Wind power transmission system | |
| CN207559583U (en) | The electric drive system and wind power generating set of wind power generating set | |
| CN207559584U (en) | The power generation-transmission system and wind power generating set of wind power generating set | |
| CN207542795U (en) | Wind turbine transmission system | |
| CN207801488U (en) | Current transformer, electric-control system and wind power plant transmission system |
Legal Events
| Date | Code | Title | Description |
|---|---|---|---|
| GR01 | Patent grant | ||
| GR01 | Patent grant | ||
| CP01 | Change in the name or title of a patent holder |
Address after: No.107 Shanghai Road, Urumqi Economic and Technological Development Zone, Urumqi City, Xinjiang Uygur Autonomous Region Patentee after: Jinfeng Technology Co.,Ltd. Address before: No.107 Shanghai Road, Urumqi Economic and Technological Development Zone, Urumqi City, Xinjiang Uygur Autonomous Region Patentee before: XINJIANG GOLDWIND SCIENCE & TECHNOLOGY Co.,Ltd. |
|
| CP01 | Change in the name or title of a patent holder |