[go: up one dir, main page]

JP2000001988A - Process management support device for building construction and computer-readable recording medium recording process management support program for building construction - Google Patents

Process management support device for building construction and computer-readable recording medium recording process management support program for building construction

Info

Publication number
JP2000001988A
JP2000001988A JP16967498A JP16967498A JP2000001988A JP 2000001988 A JP2000001988 A JP 2000001988A JP 16967498 A JP16967498 A JP 16967498A JP 16967498 A JP16967498 A JP 16967498A JP 2000001988 A JP2000001988 A JP 2000001988A
Authority
JP
Japan
Prior art keywords
construction
individual
delay
risk
work
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Withdrawn
Application number
JP16967498A
Other languages
Japanese (ja)
Inventor
Shigeaki Iwashita
繁昭 岩下
Yoshitaka Shitaya
嘉誉 下谷
Shuji Nishimura
修二 西村
Tomonori Sato
友紀 佐藤
Toshiyuki Konishi
俊行 小西
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Daiken Trade and Industry Co Ltd
Original Assignee
Daiken Trade and Industry Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Daiken Trade and Industry Co Ltd filed Critical Daiken Trade and Industry Co Ltd
Priority to JP16967498A priority Critical patent/JP2000001988A/en
Publication of JP2000001988A publication Critical patent/JP2000001988A/en
Withdrawn legal-status Critical Current

Links

Landscapes

  • Management, Administration, Business Operations System, And Electronic Commerce (AREA)

Abstract

(57)【要約】 (修正有) 【課題】 具体的な建築物施工の設定工期に対し種々の
遅延要因を加味して現実に実現可能で高い精度で施工を
完了し得る工程管理の支援を実現する。 【解決手段】 具体建築物に固有の情報として、施工地
域、着工・竣工予定日、工事別作業員数、CAD装置か
ら工事数量、現場環境に基づく第2工事遅延危険度等を
入力するS1〜S3。工事別の必要実働日数Diを集計
して全体必要実働日数Dtを求め、希望工期Dwtからこ
れを差し引いて全体余裕日数Drtを求めるS4。施工場
所・月に対応する降雨確率を第3工事遅延危険度として
設定し、敷地余裕度・前面道路リスク、降雨確率リス
ク、工程遅延リスクを集計して具体工事遅延危険度とす
るS5。S6でDrtをRiの値に応じて略比例配分によ
り各工事に割り振り、割り振られた余裕日数Driを必要
実働日数Diに加えて各工事毎の想定工期Dpiを決定す
る。
(57) [Summary] (Modifications required) [Problem] Support for process management that can be actually realized and completes construction with high accuracy by adding various delay factors to the concrete construction construction period. Realize. SOLUTION: As information unique to a specific building, S1 to S3 are input such as construction area, scheduled start of construction / completion date, number of workers by construction, construction quantity from CAD equipment, second construction delay risk based on site environment, and the like. . The required actual working days Di for each construction are totaled to obtain the total required working days Dt, and this is subtracted from the desired construction period Dwt to obtain the total spare days Drt S4. The rainfall probability corresponding to the construction site / month is set as the third construction delay risk, and the site margin, the front road risk, the rainfall probability risk, and the process delay risk are totaled and set as a specific construction delay risk S5. In S6, Drt is allocated to each construction in accordance with the value of Ri by substantially proportional distribution, and the allocated spare days Dri are added to the required actual working days Di to determine the estimated construction period Dpi for each construction.

Description

【発明の詳細な説明】DETAILED DESCRIPTION OF THE INVENTION

【0001】[0001]

【発明の属する技術分野】本発明は、住宅等の建築物施
工に伴う各種個別工事に対する工程管理を全体工期内で
高精度かつ正確に行うために用いられる建築物施工に対
する工程管理支援装置、及び、工程管理支援プログラム
を記録したコンピュータ読み取り可能な記録媒体に関す
る。
BACKGROUND OF THE INVENTION 1. Field of the Invention The present invention relates to a process management support device for a building construction used for performing a process management for various individual constructions accompanying a construction of a house or the like with high precision and accuracy within the entire construction period, and And a computer-readable recording medium on which a process management support program is recorded.

【0002】[0002]

【従来の技術】従来より、この種の建築物施工は、一般
に、施主からの依頼を受けた施工業者が多数の下請け業
者を使い、基礎工事,木工事,外装工事,内装工事,設
備工事等の各種個別工事を行わせるという形態が採られ
ている。そして、これらの場合の各種個別工事の工程管
理としては、個別工事の現実の進捗具合及び長年の経験
則に基づいて順に次工程のための資材納入,実行日等の
指示を出すという主に経験則に基づく工程管理が一般的
に採用されている。
2. Description of the Related Art Conventionally, in the construction of buildings of this type, construction companies receiving requests from the owner generally use a large number of subcontractors to perform foundation work, woodwork, exterior work, interior work, equipment work, and the like. In this form, various individual works are performed. In these cases, the process management of various individual works is mainly based on the experience of giving instructions on the delivery of materials for the next process, execution dates, etc. in order based on the actual progress of the individual works and many years of experience. Generally, process control based on rules is adopted.

【0003】また、大規模な土木工事等に対する工程管
理手法としてクリティカルパスメソッド(CPM:Crit
ical Path Method)を用いる手法も知られている。この
手法の場合には、各種の個別工事についてそれらの実行
順序等の制約条件に基づき、各種個別工事の直接費用と
その各種個別工事に要する時間(工期)とが比例すると
の仮定の下に費用が最小となる工程計画(工程表)、す
なわち、全体工期が最小となる工程表を矢線図により表
し、この工程表通りに各種個別工事が進行するようにそ
れらの工程管理が行われる。上記の矢線図による工程表
は、一般には机上で手作業により作成されるほか、コン
ピュータの表示装置を利用しその表示装置に対し操作者
が各種データを手入力により入力して描くことも行われ
ている。
[0003] A critical path method (CPM: Crit) is used as a process control method for large-scale civil engineering work.
ical Path Method) is also known. In the case of this method, the cost of various individual works is assumed to be proportional to the time required for each individual work (construction period) based on the constraints such as the order of execution. Is represented by an arrow diagram, that is, the process schedule in which the overall construction period is minimized, and the process management is performed so that various individual works proceed according to the process schedule. In general, the above-mentioned process chart based on the arrow diagram is manually created on a desk, and it is also possible to use a display device of a computer to draw various data on the display device by manually inputting various data. Have been done.

【0004】さらに、建築物施工に対する工程管理に用
いる工程表をコンピュータを利用して作成するプログラ
ムも存在する。このプログラムには、建築物施工に伴う
各種個別工事と、各工事の工期として予め定めた標準工
期と、各種個別工事の優先実行順位等の制約を定めた工
程順ルールとが予め記憶格納されており、このプログラ
ムがコンピュータに読み込まれることにより以下の処理
を実行するようになっている。すなわち、操作者がこの
コンピュータに対し、採用する下請け業者及びその下請
け業者の休日等の就業ルール等の初期データと、具体建
築物についての着工予定日、竣工予定日、建坪、部屋
数、屋根形状等に基づき期日データ及び各種個別工事毎
の工事数量とを入力することにより、上記の工程順ルー
ルに従い並べ替えた各種個別工事を上記標準工期を時間
軸方向に配列した工程表を表示装置等に出力するように
なっている。つまり、各種個別工事の標準工期は予め固
定的に定められているため、その各種個別工事種目を上
記着工日等の具体期日に沿って配置し直し、それに対し
各種個別工事の担当業者や工事数量等を表示したもので
ある。
[0004] Further, there is a program for creating a process chart used for process control for building construction using a computer. In this program, various individual works associated with building construction, a standard work period predetermined as a work period of each work, and a process order rule that defines constraints such as a priority execution order of various individual works are previously stored and stored. When the program is read by the computer, the following processing is executed. In other words, the operator uses this computer for initial data such as the subcontractor to be employed and the work rules of the subcontractor, such as holidays, and the scheduled start date, scheduled completion date, floor space, number of rooms, roof shape for concrete buildings. By inputting the due date data and the work quantity for each individual work based on the above, etc., the various individual works rearranged according to the above process order rules are displayed on a display device etc. with the above-mentioned standard work period arranged in the time axis direction. Output. In other words, since the standard construction period for various individual works is fixed beforehand, the various individual construction items are re-arranged along with the specific dates such as the above-mentioned start date, and the contractor and contractor Etc. are displayed.

【0005】[0005]

【発明が解決しようとする課題】ところが、上記従来の
経験則に基づく工程管理では、各種個別工事毎の個別対
応となり、最終的に建築物の施工完了日が何時になるか
の予測は全く不確かなものとなる。その上に、前工程の
遅延が次工程以降の各工程に必要な資材の発注・納入及
び下請け業者の着手の不確実さとなって現れ、施工完了
日が上記遅延以上に加速度的に後に延びることになる。
However, in the process control based on the conventional rule of thumb described above, each individual construction is individually dealt with, and it is completely uncertain what time the construction completion date will be finally. It becomes something. In addition, delays in the previous process appear as uncertainties in the ordering and delivery of materials necessary for each process after the next process, and the start of subcontractors, and the completion date of construction is accelerated later than the above delay. become.

【0006】また、上記CPMを用いて工程表を作成す
る場合には、机上にて作成するにしても、コンピュータ
を利用して作成するにしても、その作成を全て作成者の
手作業により行わなければならないという煩雑さを有す
る上に、途中段階での工程遅延発生に対し再度作成し直
すこともできるものの煩雑な作成作業を再度やり直す必
要がある。そして、このような矢線図では全体の工程の
流れを把握する上では便宜であるものの、建築物施工に
伴う多種多様な複雑な工程を全て盛り込んで工程管理を
行うには手間がかかり過ぎるという不都合がある。
When a process chart is created using the above-mentioned CPM, whether it is created on a desk or by using a computer, all of the creation is performed manually by the creator. In addition to the complexity of having to perform the process, it is necessary to re-create the process when the process delay occurs in the middle of the process, but it is necessary to perform the complicated process again. And while such arrow diagrams are convenient for grasping the flow of the entire process, it takes too much time to manage the process by incorporating all the various complicated processes involved in building construction. There are inconveniences.

【0007】さらに、上記のコンピュータプログラムを
利用して工程表を作成する場合には、各種個別工事の標
準工期が予め固定的に設定されているため、工程の変更
自体、及び、各個別工事の工期を個別の現場環境等に応
じてフレキシブルに変更することができないという不都
合がある。すなわち、建築物の施工場所が狭小地であ
る、資材搬入のための車両が進入不能である等の個別・
具体的な現場環境に基づく作業の難易に起因する工期の
遅延等の影響を工程表作成に加味し得ない上に、四季を
有する我が国特有の気象変動等に基づく工事の遅延要素
も上記工程表作成に加味し得ず、これらの現場環境もし
くは気象変動等の遅延要素に応じて工程管理をフレキシ
ブルに変更することができない。従って、このような遅
延要素をも加味した上で精度の高い工期予測、つまり、
確実な工期管理を行い得る高精度の工程管理を行い得な
いという不都合がある。
Furthermore, when the process schedule is created using the above-mentioned computer program, since the standard construction period of each individual work is fixedly set in advance, the change of the process itself and the individual work of each individual work are performed. There is an inconvenience that the construction period cannot be flexibly changed according to the individual site environment or the like. In other words, if the construction site of the building is on a narrow land, vehicles for carrying in materials cannot enter, etc.
In addition to the effects of delays in the construction period due to the difficulty of work based on the specific site environment, it is not possible to take into account the effects of the work schedule. The process management cannot be flexibly changed according to the delay factors such as the on-site environment and weather fluctuations. Therefore, taking into account such delay factors, highly accurate construction period prediction,
There is an inconvenience that it is not possible to carry out high-precision process management that can perform reliable construction period management.

【0008】本発明は、このような事情に鑑みてなされ
たものであり、その目的とするところは、具体的な建築
物施工についての設定工期に対し種々の要因を加味して
現実に実現可能で高い精度で建築物施工を完了し得る工
程管理を実現する工程管理支援装置及び工程管理支援プ
ログラムを記録したコンピュータ読み出し可能な記録媒
体を提供することにある。
The present invention has been made in view of such circumstances, and it is an object of the present invention to be able to actually realize it in consideration of various factors with respect to a concrete construction period for building construction. It is an object of the present invention to provide a process management support device for realizing process management capable of completing building construction with high accuracy and a computer-readable recording medium recording a process management support program.

【0009】[0009]

【課題を解決するための手段】上記目的を達成するため
に、本発明者は、希望設定工期と遅延要素を無視した理
論上の最短工期との差である余裕日数の各種個別工事に
対する配分を、具体的な建築物施工における個別・具体
的な遅延要素を加味してフレキシブルかつ最適化して工
程管理を行えばよいことに着目し、その手法として、気
象変動や施工現場の物理的環境等による各種遅延要素を
数値的に評価した工事遅延危険度として数値的に評価
し、この工事遅延危険度の値に応じて上記余裕日数を配
分することを考えだし、これをコンピュータ等のハード
ウェア資源を利用する工程管理支援装置等に適用したも
のである。
In order to achieve the above-mentioned object, the present inventor assigns the distribution of the extra days, which is the difference between the desired setting period and the theoretically shortest period ignoring delay elements, to various individual works. Focusing on the need to perform flexible and optimized process management by taking into account individual and specific delay factors in concrete building construction, as a method, it depends on weather fluctuations and the physical environment of the construction site etc. Various delay elements are evaluated numerically as the risk of construction delay evaluated numerically, and the above-mentioned extra days are devised to be allocated according to the value of the risk of construction delay. This is applied to a process management support device to be used.

【0010】具体的には、第1の発明は、請求項1記載
の如く、入力装置及び出力装置が接続されたコンピュー
タによって建築物の施工に対する工程管理を支援する建
築物施工に対する工程管理支援装置に係る。そして、こ
の第1の発明においては、以下の第1及び第2の各記憶
手段と、第1〜第4の各処理手段とを備えていることを
特定事項とする。すなわち、第1記憶手段を、降雨に関
する気象統計データと建築物の施工に必要な各種個別工
事別の標準歩掛かりデータと、上記各種個別工事の実行
順序についての制約を定めた工程順ルールと、上記各種
個別工事毎に遅延発生に対する危険性を経験則に基づい
て予め数値化した第1工事遅延危険度とからなる基礎情
報が予め記憶格納されたものとする。第2記憶手段とし
て、施工予定の具体建築物毎に入力される、施工地域
と、予定着工日及び希望竣工日と、上記各種個別工事別
に投入する予定の作業員数と、上記各種個別工事別の工
事対象数量と、上記具体建築物の現場環境に応じて数値
化された第2工事遅延危険度とからなる上記具体建築物
についての固有情報を更新可能に記憶保持するものとす
る。第1処理手段を、上記各種個別工事毎の予定作業員
数及び工事対象数量と、上記第1記憶手段から取り出し
た標準歩掛かりデータとに基づいて各種個別工事毎の必
要実働日数を演算し、その各必要実働日数の集計値を上
記予定着工日及び希望竣工日に基づく希望全体工期から
差し引いて全体余裕日数を決定するものとする。第2処
理手段を、上記第1記憶手段に記憶格納された気象統計
データの内から取り出した上記具体建築物の施工地域及
び施工期日に対応する気象統計データに基づいて気象変
動による第3工事遅延危険度を定め、この第3工事遅延
危険度及び上記第2工事遅延危険度を上記第1工事遅延
危険度に加味して各種個別工事毎の具体工事遅延危険度
を決定するものとする。第3処理手段を、上記全体余裕
日数を上記各種個別工事に対し上記具体工事遅延危険度
が高い程多くなるように個別に配分し、この配分された
個別余裕日数を上記必要実働日数に加えて各種個別工事
毎の想定個別工期を決定するものとする。そして、第4
処理手段を、一方の軸に上記希望全体工期の期日を、他
方の軸に上記工程順ルールの優先順に並べ替えた個別工
事種目をそれぞれ表示設定した直交テーブルに対し、各
種個別工事毎に対応する想定個別工期を線状記号もしく
は棒状記号により上記優先順の各種個別工事種目の各工
期が前後で連続するように表示した工程表を上記出力装
置に出力するものとする。
More specifically, a first aspect of the present invention provides a process management support apparatus for building construction in which a computer to which an input device and an output device are connected supports the process management for building construction. According to. In the first invention, it is a specific matter that the first invention includes the following first and second storage units and first to fourth processing units. That is, the first storage means stores weather statistics data relating to rainfall, standard stepping data for each individual construction necessary for construction of the building, and a process order rule that defines restrictions on the execution order of the various individual constructions, It is assumed that basic information including the first construction delay risk degree in which the risk of occurrence of delay is quantified in advance based on an empirical rule for each individual construction work is stored and stored in advance. As the second storage means, the construction area, the planned construction start date and the desired completion date, the number of workers to be put in each of the above individual works, and It is assumed that unique information on the specific building, which includes the construction target quantity and the second degree of construction delay risk quantified according to the site environment of the specific building, is stored and held in an updatable manner. The first processing means calculates the required number of actual working days for each individual construction based on the planned number of workers and the construction target quantity for each individual construction and the standard walking data taken out from the first storage means. The total number of required actual working days shall be subtracted from the desired overall construction period based on the planned start date and the desired completion date to determine the overall spare days. The second processing means performs third construction delay due to weather change based on weather statistics data corresponding to the construction area and construction date of the concrete building extracted from the weather statistics data stored and stored in the first storage means. The risk is determined, and the concrete work delay risk for each individual work is determined by adding the third work delay risk and the second work delay risk to the first work delay risk. The third processing means individually allocates the entire spare days to the various individual works so as to increase as the specific construction delay risk increases, and adds the allocated individual spare days to the required actual working days. The assumed individual construction period for each individual construction shall be determined. And the fourth
The processing means corresponds to each of the various types of individual work on the orthogonal table in which the axis of the desired overall work period is displayed on one axis and the individual work items rearranged in the order of priority of the process order rule are displayed and set on the other axis. A process chart in which the assumed individual construction periods are displayed by a linear symbol or a bar-shaped symbol so that the respective construction periods of the various individual construction types in the above-mentioned priority order are consecutive before and after is output to the output device.

【0011】上記の第1の発明に係る工程管理支援装置
の場合、例えばキーボード等の入力装置により具体建築
物についての固有情報、すなわち、その施工地域、予定
着工日もしくは着工可能日から希望竣工日までの期間で
ある希望全体工期、各種個別工事別の予定作業員数、各
種個別工事別の工事対象数量、及び、現場環境に基づく
作業難易度を入力して、第2記憶手段の記憶内容が工程
管理を行う対象の具体建築物についての固有情報に更新
される。これにより、まず、第1処理手段により全体余
裕日数が演算決定される一方、第2処理手段により各種
個別工事毎に定めた遅延発生予測の評価基準である第1
工事遅延危険度に対し現実の施工現場及び施工時期に基
づく遅延発生予測の評価基準である第2及び第3の両工
事遅延危険度を加味して各種個別工事毎の具体工事遅延
危険度が演算決定される。次に、第3処理手段により上
記全体余裕日数が上記具体工事遅延危険度の値に応じて
各種個別工事毎に配分され、この配分された個別余裕日
数に必要実働日数が加えられて各種個別工事毎の想定個
別工期が決定される。そして、第4処理手段により期日
と各種個別工事種目とを座標軸とする直交テーブルに対
し対応する想定個別工期が線状記号もしくは棒状記号に
より表示された工程表が例えばディスプレイもしくはプ
リンタ等の出力装置に出力され、この工程表に基づいて
より気象変動や具体建築物についての現場環境等の各種
遅延要素をも加味したフレキシブルかつ現実に実現可能
な工程管理を行うことが可能になり、希望全体工期に対
し正確な工期管理が可能になる。
In the case of the process management support device according to the first aspect of the present invention, the specific information on the concrete building, that is, the construction area, the scheduled start date or the possible start date from the start date of the construction is requested by an input device such as a keyboard. The desired total construction period, the number of workers scheduled for each individual construction, the number of works to be constructed for each individual construction, and the work difficulty based on the site environment are entered. The information is updated to the specific information on the concrete building to be managed. Thus, first, the first processing means calculates and determines the total number of spare days, while the second processing means sets the first criterion which is the evaluation criterion of the delay occurrence prediction set for each individual construction.
Calculate the concrete work delay risk for each individual work by taking into account both the second and third work delay risks, which are the evaluation criteria of the delay occurrence prediction based on the actual construction site and construction time, for the work delay risk It is determined. Next, the entire spare days are allocated by the third processing means for each individual construction in accordance with the value of the specific construction delay risk, and the required actual working days are added to the allocated individual spare days to obtain various individual construction days. The assumed individual construction period for each is determined. Then, a process chart in which the assumed individual construction period corresponding to the orthogonal table having the due date and various individual construction items as coordinate axes by the fourth processing means is displayed by a linear symbol or a bar symbol is output to an output device such as a display or a printer. Based on this process chart, it is possible to perform flexible and practically feasible process management that takes into account various delay factors such as weather fluctuations and the site environment of concrete buildings. On the other hand, accurate construction period management becomes possible.

【0012】ここで、上記第2記憶手段への具体建築部
についての各種個別工事別の工事対象数量の入力を、C
AD(Computer Aided Design)装置を接続し、このC
AD装置により上記各種個別工事別にCADデータに基
づき演算された工事対象数量、例えば基礎工事の対象面
積、屋根工事の屋根面積等を入力指令を受けて上記CA
D装置から自動的に取り込むようにしてもよい。これに
より、上記CAD装置により行われた設計データの有効
活用が図られると同時に、具体建築物についての固有情
報を操作者が個別に手入力する場合の手間を省力化させ
ることが可能になる。
Here, the input of the construction target quantity for each specific construction for the concrete building section into the second storage means is C
Connect an AD (Computer Aided Design) device and
The above-mentioned CA receives the input command for the construction target quantity calculated by the AD device based on the CAD data for each of the above individual constructions, for example, the target area for the foundation work, the roof area for the roof construction, etc.
You may make it take in automatically from D apparatus. This makes it possible to effectively utilize the design data performed by the CAD device, and at the same time, it is possible to save labor when the operator manually inputs individual information on the specific building individually.

【0013】また、上記第2処理手段における具体工事
遅延危険度の決定において、第1記憶手段に記憶格納さ
れた第1工事遅延危険度を、各種個別工事毎にその特有
要因、現場環境及び気象変動の各種遅延要因別に経験則
に基づいて予め定め、この遅延要因別の第1工事遅延危
険度に対し上記具体建築物についての第2及び第3の各
工事遅延危険度を乗じることにより行うようにしてもよ
い。上記特有要因としては例えば各種個別工事における
工事対象数量の見積もりと実際との差異が生じ易いか否
か、欠陥工事によるやり直し工事が生じ易いか否か等に
起因するものがあり、現場環境としては例えばその個別
工事が敷地の余裕度の影響を受け易いか否か、資材搬入
が直接行い得る前面道路の幅があるか否か等に起因する
ものがあり、また、気象変動としては個別工事が例えば
屋外工事である場合の如く降雨の影響を受け易いか否か
等に起因するものがある。これらの遅延要素別に各種個
別工事毎にその個別工事の特性に応じて影響を受け易い
か否かの度合いを予め何段階かの数値により第1工事遅
延危険度として定め、これに対し上記現場環境及び気象
変動等についての具体建築物施工に固有の遅延発生に対
する危険度である第2及び第3の各工事遅延危険度を乗
じたものを各種個別工事別に集計することにより、各種
個別工事毎に各種の遅延要素を全て加味した危険度合い
が具体工事遅延危険度として得られることになる。上記
第1工事遅延危険度の具体的な設定例としては、例えば
遅延発生の危険性が少ないもの、すなわち、各種遅延要
素の影響を受け難いものから順に「0」,「1」,
「2」というように3段階の数値を設定すればよい。
In the determination of the concrete construction delay risk in the second processing means, the first construction delay risk stored and stored in the first storage means is determined for each individual construction by its unique factors, site environment and weather. It is determined in advance based on an empirical rule for each of the various delay factors of the variation, and the first construction delay risk for each delay factor is multiplied by the second and third construction delay risks for the concrete building. It may be. The above-mentioned specific factors include, for example, whether or not a difference between the estimate of the number of works to be constructed in each individual construction and the actual construction is likely to occur, and whether or not rework due to defective construction is likely to occur. For example, there are factors such as whether the individual works are easily affected by the margin of the site, and whether there is a width of the front road where the materials can be directly carried in, etc. For example, as in the case of outdoor construction, there is a problem caused by whether or not it is easily affected by rainfall. For each of these delay elements, the degree of susceptibility to each individual construction according to the characteristics of the individual construction is determined in advance as a first construction delay risk by several numerical values. By multiplying each of the second and third construction delay risks, which are the risks to the occurrence of delays inherent in the construction of concrete buildings, such as weather fluctuations, etc., for each individual construction, The degree of danger taking into account all the various delay elements is obtained as the specific construction delay danger. As a specific example of the setting of the first construction delay risk, for example, those having a low risk of occurrence of delay, that is, “0”, “1”,
A three-step numerical value such as “2” may be set.

【0014】ここで、第1記憶手段に記憶格納される気
象統計データとして例えば各都道府県毎の月別の降雨確
率を予め入力しておき、第2処理手段においては、具体
建築物の施工地域に対応する都道府県の施工期日が属す
る月の降雨確率をそのまま第3工事遅延危険度として定
めるようにしてもよい。また、降雨確率以外にも、気象
統計データとして各道府県毎の月別の平均降雨量を予め
入力しておいてもよい。この場合には、その平均降雨量
の値の大小を例えば3段階の範囲に分け、降雨量の少な
い範囲から順に「0」,「1」,「2」という数値を第
3工事遅延危険度として設定すればよい。さらに、遅延
要素としての「現場環境」による第2工事遅延危険度と
しては、その現場環境に基づく作業難易度という観点か
ら数値化してもよい。つまり、資材納入を達成する上で
の難易度、作業を実行する上での難易度等を入力すれば
よい。上記資材納入を達成する上での難易度には、上記
の前面道路の幅に基づく資材搬入が容易か否かに加え、
例えば周辺道路の交通量が大であり資材納入や作業員の
現場到着に遅れが生じ易いか否か等がある。また、上記
作業実行上の難易度には、上記の敷地の余裕度に基づく
もの、例えば敷地面積が狭くて作業スペースが確保し難
いという敷地の余裕に起因するものや、その個別工事が
屋内作業であるか屋外作業であるかの相違、つまり、作
業が行い易いか否か等がある。そして、これらの作業の
難易度を上記と同様に容易であるものから順に「0」,
「1」,「2」というように例えば3段階の数値を第2
工事遅延危険度として設定するようにすればよい。この
ように設定した場合、上記具体工事遅延危険度の数値が
大であるほど工事が遅延する可能性が高いため、第3処
理手段において、その遅延の可能性が高いほど多くの余
裕日数を配分することにより、現実に実現可能な工程管
理が可能になる。
Here, for example, monthly rainfall probabilities for each prefecture are input in advance as weather statistical data stored and stored in the first storage means, and in the second processing means, a specific building construction area is determined. The rainfall probability of the month to which the corresponding construction date of the prefecture belongs may be directly determined as the third construction delay risk. In addition to the rainfall probability, a monthly average rainfall amount for each prefecture may be input in advance as weather statistical data. In this case, the magnitude of the average rainfall value is divided into, for example, three ranges, and the numerical values “0”, “1”, and “2” are set as the third construction delay risk in order from the range with the lowest rainfall. Just set it. Furthermore, the second construction delay risk due to the “site environment” as a delay element may be quantified from the viewpoint of the work difficulty based on the site environment. In other words, it is only necessary to input the degree of difficulty in achieving material delivery, the degree of difficulty in executing work, and the like. Difficulties in achieving the above material delivery include whether or not it is easy to carry in materials based on the width of the front road,
For example, it is determined whether there is a large traffic volume on the surrounding roads and delays occur in the delivery of materials and the arrival of workers at the site. In addition, the difficulty in performing the work is based on the above-mentioned site margin, for example, due to the site margin that the site area is small and it is difficult to secure a work space, or when individual works are performed indoors. And whether the work is an outdoor work, that is, whether the work is easy to perform or not. Then, the difficulty levels of these operations are set to “0”,
For example, numerical values in three stages such as “1” and “2”
What is necessary is just to set it as a construction delay risk. In such a case, the larger the numerical value of the concrete construction delay risk is, the higher the possibility of the construction delay is. Therefore, the third processing means allocates more spare days as the possibility of the delay is higher. By doing so, process management that can be actually realized becomes possible.

【0015】なお、上記の具体工事遅延危険度を決定す
る際に、さらに以下の遅延要素をそれぞれ数値化してこ
れらを加味して具体工事遅延危険度を決定するようにし
てもよい。すなわち、例えば資材入手の困難性(例えば
資材メーカーの在庫量の季節変動)、各種個別工事を発
注する下請け業者の技量の良否による影響、経験により
割り出される要素として設計変更もしくは施工不良が発
生し易い工事か否か(設計変更もしくは施工不良に伴う
やり直しによる遅延)、クレーンが必要な工事か否か
(クレーン到着遅れ・強風による作業不能等に起因する
遅延)、作業可能時間の季節変動による影響(日の出・
日の入り時間の季節変動)、あるいは、各種個別工事別
の重要度(基本工事か否か、次工程の工事と密接な関連
性を有する工事か否か)等の遅延要素を加味してもよ
い。
When determining the specific construction delay risk, the following delay elements may be digitized, and the specific construction delay risk may be determined in consideration of the numerical values. For example, difficulties in obtaining materials (for example, seasonal fluctuations in stocks of material manufacturers), the influence of the quality of skills of subcontractors ordering various individual works, design changes or poor construction as factors determined by experience occur. Whether the construction is easy (delay due to redo due to design change or construction failure), whether the construction requires a crane (delay due to crane arrival delay, inability to work due to strong wind, etc.), and the effect of seasonal fluctuations in workable time (sunrise·
A delay factor such as seasonal variation in sunset time) or the importance of each individual construction (whether the construction is a basic construction, or whether the construction is closely related to the construction of the next process) may be added.

【0016】さらに、上記第1記憶手段に予め記憶格納
された工程順ルールとしては、各種個別工事を実行する
ための優先順位、例えば木工事を行う前に基礎工事を終
了させておく必要がある等の制約に基づく実行順位であ
り、これに加えて、各種個別工事の内で同時実行可能か
否かのルールを含むようにしてもよい。同時実行可能な
個別工事がある場合には、上記第1処理手段での各必要
実働日数の集計値としては、それら同時実行可能な複数
の個別工事の内の最大の必要実働日数のみを集計するよ
うにすればよい。
Further, as a process order rule stored in advance in the first storage means, a priority order for executing various individual works, for example, it is necessary to finish a basic work before performing a wood work. And the like. In addition to this, a rule on whether or not simultaneous execution is possible in various individual works may be included. When there are individual works that can be executed simultaneously, only the maximum required actual work days of the plurality of individual work pieces that can be executed simultaneously is counted as the total value of the required actual work days in the first processing means. What should I do?

【0017】第2の発明は、コンピュータに実行させる
ための建築物施工に対する工程管理支援プログラムを記
録したコンピュータ読み取り可能な記録媒体に係り、こ
の記録媒体には、以下の記憶部を有し、第1〜第5ステ
ップの処理をコンピュータに実行させるための工程支援
管理支援プログラムが記録されていることを特定事項と
するものである。すなわち、上記記憶部には、降雨に関
する気象統計データ、建築物の施工に必要な各種個別工
事別の標準歩掛かりデータ、上記各種個別工事の実行順
序についての制約を定めた工程順ルール、及び、上記各
種個別工事毎に遅延発生に対する危険性を経験則に基づ
き予め数値化した第1工事遅延危険度からなる基礎情報
が記憶格納されている。そして、第1ステップの処理と
して、施工予定の具体建築物毎に、施工地域、予定着工
日及び希望竣工日、上記各種個別工事別に投入する予定
の作業員数、上記各種個別工事別の工事対象数量、並び
に、上記具体建築物の現場環境に応じて数値化された第
2工事遅延危険度からなる固有情報を入力させて記憶更
新する。第2ステップの処理として、入力された上記各
種個別工事毎の予定作業員数及び工事対象数量と、上記
記憶部から取り出した標準歩掛かりデータとに基づいて
各種個別工事毎の必要実働日数を演算し、その各必要実
働日数の集計値を上記予定着工日及び希望竣工日に基づ
く希望全体工期から差し引いて全体余裕日数を決定す
る。第3ステップの処理として、記憶部に記憶格納され
た気象統計データの内から第1ステップで入力された上
記具体建築物に対応する施工地域及び施工期日の気象統
計データを取り出し、この取り出した気象統計データに
基づいて気象変動による上記具体建築物施工の第3工事
遅延危険度を定め、この第3工事遅延危険度及び上記第
2工事遅延危険度を上記第1工事遅延危険度に加味して
各種個別工事毎の具体工事遅延危険度を決定する。第4
ステップの処理として、上記全体余裕日数を上記各種個
別工事に対し上記具体工事遅延危険度が高い程多くなる
ように個別に配分し、この配分された個別余裕日数を上
記必要実働日数に加えて各種個別工事毎の想定個別工期
を決定する。最後に、第5ステップの処理として、一方
の軸に上記希望全体工事の期日を、他方の軸に上記工程
順ルールの優先順に並べ替えた個別工事種目をそれぞれ
表示設定した直交テーブルに対し、各種個別工事毎に対
応する想定個別工期を線状記号もしくは棒状記号により
上記優先順の各種個別工事種目の各工期が前後で連続す
るように表示した工程表を出力装置に出力する。
A second invention relates to a computer-readable recording medium for recording a process management support program for building construction to be executed by a computer. The recording medium has the following storage unit. It is a specific matter that a process support management support program for causing a computer to execute the processes of the first to fifth steps is recorded. That is, in the storage unit, weather statistics data on rainfall, standard walk data for each individual construction required for building construction, a process order rule that defines restrictions on the execution order of the various individual constructions, and Basic information including the first construction delay risk degree in which the danger of occurrence of delay for each of the various individual works is quantified in advance based on an empirical rule is stored. Then, as the processing of the first step, for each concrete building to be constructed, the construction area, the planned start date and the desired completion date, the number of workers to be put into each of the above individual works, the number of works to be put into each of the above individual works In addition, unique information including the second construction delay risk quantified according to the site environment of the specific building is input and stored and updated. In the process of the second step, the required actual number of working days for each individual construction is calculated based on the input planned number of workers and construction target quantity for each individual construction and the standard walking data retrieved from the storage unit. Then, the total value of the required actual working days is subtracted from the desired overall construction period based on the planned start date and the desired completion date to determine the overall spare days. In the processing of the third step, the construction area and construction date corresponding to the specific building input in the first step are extracted from the weather statistics data stored in the storage unit, and the extracted weather data is extracted. The third construction delay risk of the concrete building construction due to weather fluctuation is determined based on the statistical data, and the third construction delay risk and the second construction delay risk are added to the first construction delay risk. Determine the specific construction delay risk for each individual construction. 4th
As the processing of the step, the total spare days are individually allocated to the various individual works so as to increase as the specific construction delay risk increases, and the allocated individual spare days are added to the required actual working days and various Determine the estimated individual construction period for each individual construction. Finally, as the process of the fifth step, the orthogonal table in which the date of the desired whole construction is displayed on one axis and the individual construction items rearranged in the order of the priority of the process order rule on the other axis are respectively set in the orthogonal table. A process chart is output to the output device, in which the assumed individual work period corresponding to each individual work is displayed by a linear symbol or a bar-shaped symbol such that the respective work periods of the various individual work items in the above-mentioned priority order are consecutive before and after.

【0018】この第2の発明の場合、上記記録媒体に記
録された工程管理支援プログラムをコンピュータに読み
取らせることにより、そのコンピュータにおいて上記第
1〜第5の各ステップに基づく処理を実行させることが
可能になる。すなわち、第1ステップにおいて、例えば
キーボード等の入力装置を介して具体建築物についての
上記と同様の固有情報が入力されると、まず、第2ステ
ップにおいて全体余裕日数が演算決定される一方、第3
ステップにおいて各種の遅延要素に基づき予め定めた遅
延発生予測の評価基準である第1工事遅延危険度に対し
現実の施工場所及び施工時期に基づく遅延発生予測の評
価基準である第2及び第3工事遅延危険度を加味した各
種個別工事毎の具体工事遅延危険度が演算決定されるこ
とになる。次に、第4ステップにおいて、上記全体余裕
日数が上記具体工事遅延危険度の値に応じて各種個別工
事毎に配分され、この配分された個別余裕日数に必要実
働日数が加えられて各種個別工事毎の想定個別工期が決
定される。そして、第5ステップにおいて、期日と各種
個別工事種目とを座標軸とする直交テーブルに対し対応
する想定個別工期が線状記号もしくは棒状記号により表
示された工程表が例えばディスプレイもしくはプリンタ
等の出力装置に出力され、この工程表に基づいて気象変
動や具体建築物についての現場環境等の各種遅延要素を
も加味したフレキシブルかつ現実に実現可能な工程管理
を行うことが可能になり、希望全体工期に対し正確な工
期管理が可能になる。
In the case of the second invention, by causing a computer to read the process management support program recorded on the recording medium, the computer can execute the processing based on the first to fifth steps. Will be possible. That is, in the first step, when the same specific information as described above about a specific building is input via an input device such as a keyboard, first, the total number of spare days is calculated and determined in the second step. 3
In the step, the second and third works are evaluation criteria of the delay occurrence prediction based on the actual construction place and the construction time with respect to the first construction delay risk which is the evaluation criteria of the delay occurrence prediction predetermined based on various delay elements. The specific construction delay risk for each individual construction taking into account the delay risk is calculated and determined. Next, in the fourth step, the total spare days are allocated to each individual construction in accordance with the value of the specific construction delay risk, and the required actual working days are added to the allocated individual spare days to obtain various individual construction works. The assumed individual construction period for each is determined. Then, in the fifth step, a process chart in which the assumed individual construction period corresponding to the orthogonal table having the date and various individual construction items as coordinate axes is displayed by a linear symbol or a bar symbol is output to an output device such as a display or a printer. Based on this process chart, it is possible to perform flexible and practically feasible process management that takes into account various delay factors such as weather fluctuations and the site environment of concrete buildings, based on this process schedule. Accurate construction period management becomes possible.

【0019】また、この第2の発明においても、上記第
1ステップにおける具体建築部についての固有情報の
内、各種個別工事別の工事対象数量の入力を、CAD
(Computer Aided Design)装置をコンピュータに接続
し、このCAD装置により上記各種個別工事別に演算さ
れた工事対象数量、例えば基礎工事の対象面積、屋根工
事の屋根面積等を上記第1ステップでの入力指令を受け
て上記CAD装置から自動的に取り込むようにしてもよ
い。これにより、上記CAD装置により行われた設計デ
ータの有効活用が図られると同時に、具体建築物につい
ての固有情報を操作者が個別に手入力する場合の手間を
省力化させることが可能になる。
Also in the second invention, the input of the construction target quantity for each individual construction in the specific information on the concrete building section in the first step is performed by CAD.
(Computer Aided Design) Connect the device to a computer, and input the work target quantity calculated for each of the above individual works by this CAD device, such as the target area for foundation work, the roof area for roof work, etc. in the first step. In response to this, the data may be automatically imported from the CAD device. This makes it possible to effectively utilize the design data performed by the CAD device, and at the same time, it is possible to save labor when the operator manually inputs individual information on the specific building individually.

【0020】また、記憶部に記憶格納する気象統計デー
タとして何を用いるか、それを用いて第3工事遅延危険
度を如何に定めるか、さらに、現場環境に応じた第2工
事遅延危険度の数値化を如何にするか、そして、第1〜
第3の各工事遅延危険度を用いて具体工事遅延危険度を
如何に演算するか、この具体工事遅延危険度に基づいて
全体余裕日数の配分を如何にするか等については、上記
の工程管理支援装置において説明したと同様の処理を行
うようにしてもよい。
Further, what is used as the weather statistical data stored and stored in the storage unit, how the third construction delay risk is determined using the data, and the second construction delay risk according to the site environment are determined. How to do the digitization, and
The above process management is used to determine how to calculate the concrete construction delay risk using each of the third construction delay risks, and how to allocate the total spare days based on the specific construction delay risk. The same processing as described in the support device may be performed.

【0021】さらに、上記記憶部に記憶格納された工程
順ルールとして、各種個別工事を実行するための優先順
位に加えて、各種個別工事の内で同時実行可能か否かの
ルールを含むようにした場合には、上記第2ステップで
の各必要実働日数の集計値として、同時実行可能な複数
の個別工事の内の最大の必要実働日数のみを集計するよ
うにすればよい。
Further, as the process order rules stored in the storage unit, in addition to the priority order for executing various individual works, a rule on whether or not simultaneous execution is possible among various individual works is included. In this case, only the maximum required actual working days of the plurality of individual works that can be executed simultaneously may be totaled as the total value of the required actual working days in the second step.

【0022】[0022]

【発明の実施の形態】以下、本発明の実施形態を図面に
基いて説明する。
Embodiments of the present invention will be described below with reference to the drawings.

【0023】図1は、本発明の実施形態に係る工程管理
支援装置を含む全体構成図を示し、1はマイクロプロフ
ェサーを内蔵したいわゆるパーソナルコンピュータ、2
は入力装置としてのキーボード、3は同じく入力装置と
してのマウス、4は出力装置としてのディスプレイ、5
は同じく出力装置としてのプリンタ、6は記録媒体とし
てのCD−ROM、7はマイクロプロセッサーを内蔵し
たパーソナルコンピュータ、8はそのパーソナルコンピ
ュータに接続されたディスプレイである。このパーソナ
ルコンピュータ7とディスプレイ8とによって建築物の
自動設計及び各部位の面積・数量等の工事対象数量を自
動計算するCAD装置の一部が構成されている。
FIG. 1 shows an overall configuration diagram including a process management support device according to an embodiment of the present invention, wherein 1 is a so-called personal computer having a built-in micro-processor,
Is a keyboard as an input device, 3 is a mouse also as an input device, 4 is a display as an output device, 5
Is a printer as an output device, 6 is a CD-ROM as a recording medium, 7 is a personal computer with a built-in microprocessor, and 8 is a display connected to the personal computer. The personal computer 7 and the display 8 constitute a part of a CAD apparatus for automatically calculating a building and automatically calculating a construction target quantity such as an area and quantity of each part.

【0024】上記パーソナルコンピュータ1は、図2に
示すように、記憶部10として第1記憶手段11及び第
2記憶手段12を備え、また、処理演算部13として第
1〜第4の各処理手段14〜17を備えている。この第
1〜第4の各処理手段14〜17は予めインストールさ
れた工程管理支援プログラムの各処理演算部により構成
される、もしくは、上記CD−ROM6からそれに記録
された工程管理支援プログラムを読み取ることにより構
成されるものである。なお、記録媒体としては、上記C
D−ROM6の他に、フロッピーディスク6′等の他の
媒体を用いることもできる。
As shown in FIG. 2, the personal computer 1 includes a first storage unit 11 and a second storage unit 12 as a storage unit 10, and first to fourth processing units as a processing operation unit 13. 14 to 17 are provided. Each of the first to fourth processing means 14 to 17 is constituted by a processing operation unit of a process management support program installed in advance, or reads the process management support program recorded therein from the CD-ROM 6. It consists of. In addition, as the recording medium, the above C
In addition to the D-ROM 6, other media such as a floppy disk 6 'may be used.

【0025】上記第1記憶手段11には予め種々の基礎
情報が入力されて記憶格納されている。基礎情報として
は以下のようなデータが記憶格納されている。
Various basic information is previously input and stored in the first storage means 11. The following data is stored and stored as basic information.

【0026】すなわち、気象統計データ、日の出・日の
入り時間についての統計データ、複数年(例えば10年
分)にわたる暦、建築物の施工に必要な全種類の個別工
事についての標準歩係りデータ、各種個別工事別の下請
け工事業者リスト、資材発注先リスト、各種個別工事の
実行順序についての工程順ルール、各種個別工事別に定
めた遅延発生に対する第1工事遅延危険度等が予め基礎
情報として記憶格納されている。
That is, weather statistical data, sunrise / sunset time statistical data, a calendar covering a plurality of years (for example, 10 years), standard step-by-step data for all types of individual works required for building construction, various individual A list of subcontractors for each work, a list of suppliers of materials, a process order rule for the execution order of various individual works, a first work delay danger to the occurrence of delay determined for each individual work, and the like are stored and stored in advance as basic information. I have.

【0027】ここで、上記気象データとしては、日本の
各地域(例えば各都市)毎に月別の降雨確率、例えば降
雨量10mm以上の降雨確率が記憶格納されている。こ
の気象データ及び日の出・日の入りについての統計デー
タは例えば「理科年表」(株式会社丸善発行)により得
られる。上記暦は全体工期の内の工事休止日(例えば日
曜日)の決定・設定を行うために用いられる。上記標準
歩係りデータは、各種個別工事についての過去の実績デ
ータに基づいて予め定められたものである。下請け工事
業者リストは、日本の各地域に存在する発注可能な業者
についての情報(名称,住所,連絡先等)である。同じ
く上記資材発注先リストは、各種個別工事に必要な資材
を納入し得る製造・販売元もしくは代理店についての情
報である。上記工程順ルールは各種個別工事を実行する
上でその実行順序についての制約、例えば先か後かの優
先順位や同時実行可能か否かのルールを定めたものであ
る。
Here, as the weather data, a monthly rain probability, for example, a rain probability of 10 mm or more, is stored and stored for each region (eg, each city) in Japan. The weather data and the statistical data on the sunrise and sunset are obtained from, for example, a “science chronology” (published by Maruzen Co., Ltd.). The calendar is used for determining and setting a construction suspension date (for example, Sunday) within the entire construction period. The standard gait data is determined in advance based on past performance data on various individual works. The subcontractor list is information (name, address, contact information, etc.) about contractable contractors existing in each region of Japan. Similarly, the material supplier list is information on manufacturers / distributors or distributors that can deliver materials necessary for various individual works. The above-mentioned process order rules define restrictions on the execution order in executing various individual works, for example, a priority order before or after and a rule as to whether or not simultaneous execution is possible.

【0028】また、上記第1工事遅延危険度は、各種個
別工事を行う上でその工事の特性に基づき遅れが生じ易
い工事か生じ難いかの度合いや、上記個別工事を遅延さ
せるような種々の遅延要素に対し影響を受け易いか受け
難いか、つまり、遅延が発生し易いか否かの度合いにつ
いて、経験則に基づいて予め数値化したものである。す
なわち、遅延発生に対する危険性についての基準を予め
定めたものである。具体的には、遅延要素として、上記
個別工事の特性に基づく工程遅延リスク、敷地の余裕度
に基づく敷地余裕度リスク、建築物の施工場所の前面道
路の幅に基づく前面道路リスク、及び、降雨の影響によ
る降雨影響リスクの4種類を設定し、この4種類の遅延
要素別に上記各種個別工事毎に評価したものである。例
えば、上記工程遅延リスクとして、遅れ難いものに
「0」を、やや遅れ易いものに「1」を、遅れ易いもの
(例えばクレーン作業を必要とする工事)に「2」をそ
れぞれ設定すればよい。同様に、敷地余裕度リスクとし
て、施工面積に対する敷地の余裕度が小さくてもそれに
影響されないものに「0」を、影響を受ける場合がある
ものに「1」を、影響を受けるものに「2」をそれぞれ
設定し、前面道路リスクとして、前面道路の広狭により
影響されないものに「0」を、影響を受ける場合がある
ものに「1」を、影響を受けるもの(例えば重量物の資
材搬入に支障がある工事)に「2」をそれぞれ設定し、
降雨影響リスクとして、降雨の影響を受けないもの(例
えば屋内工事)に「0」を、影響を受ける場合があるも
のに「1」を、影響を受けるものに「2」をそれぞれ設
定すれはよい。
The first construction delay risk may be determined based on the characteristics of each individual construction, whether the construction is likely to be delayed or not, and various factors such as delaying the individual construction. The degree of whether or not the delay element is easily affected, that is, whether or not the delay is likely to occur is quantified in advance based on an empirical rule. In other words, the criterion for the risk of occurrence of delay is determined in advance. Specifically, the delay factors include the process delay risk based on the characteristics of the individual works described above, the site margin risk based on the site margin, the front road risk based on the width of the front road at the construction site of the building, and rainfall. In this case, four types of rainfall impact risk due to the influence of the above are set, and the four types of delay elements are evaluated for each of the above-mentioned individual works. For example, the process delay risk may be set to “0” for those that are not easily delayed, “1” for those that are slightly delayed, and “2” for those that are easily delayed (for example, construction requiring crane work). . Similarly, as the site margin risk, “0” is given to those that are not affected even if the margin of the site with respect to the construction area is small, “1” is sometimes given, and “2” is given to those that are affected. ”Is set as the front road risk,“ 0 ”is set for those that are not affected by the width of the front road,“ 1 ”is set for those that may be affected, and those that are affected (for example, Work), set "2" for each
As the rainfall impact risk, it is good to set “0” to those not affected by rainfall (for example, indoor construction), “1” to those that may be affected, and “2” to those affected. .

【0029】なお、上記の各種個別工事とは、大分類と
しての開始工事、基礎工事、木工事、外装工事、内装工
事、設備工事、及び、終了工事があり、これら大分類の
各工事毎に細分類の個別工事がある。例えば、上記開始
工事に属するものとして看板・仮囲い設置、仮設トイレ
設置、仮設電気設置、及び、仮設水道設置等の各個別工
事があり、上記基礎工事に属するものとして整地〜ベー
スコンクリート打設、配管スリーブ、鉄筋組〜埋め戻
し、基礎配管、及び、仕上げの各個別工事があるという
ように多数の個別工事がある。
The above-mentioned various works include start work, foundation work, wood work, exterior work, interior work, equipment work, and end work, which are broadly classified. There are individual works of sub-classification. For example, signage and temporary enclosure installation, temporary toilet installation, temporary electric installation, and each individual work such as temporary water supply installation as belonging to the above-mentioned start work, leveling-base concrete casting as belonging to the above-mentioned foundation work, There are a number of individual works, such as individual works for piping sleeves, rebar sets-backfilling, foundation piping, and finishing.

【0030】次に、図3を用いて上記の第1〜第4の各
処理手段14〜17による各処理を説明する。
Next, each processing by the first to fourth processing means 14 to 17 will be described with reference to FIG.

【0031】(ステップS1〜S3)まず、上記の各処
理手段14〜17による各処理の開始の前提として施工
対象である具体建築物についての固有情報が入力された
ことが条件となる。このため、ステップS1で上記の固
有情報を入力するようにディスプレイ4に対し入力指示
を表示させる。これに基づいて操作者はステップS2で
上記各処理を行うために必要な固有情報をディスプレイ
4に入力すべきデータ毎に対話方式にて入力し、この入
力された固有情報が第2記憶手段12に記憶される。こ
の際、他の物件、もしくは、同じ具体建築物についての
固有情報が記憶格納されている場合には、新たに入力さ
れた固有情報に書き換えて更新する。
(Steps S1 to S3) First, as a prerequisite for the start of each processing by each of the above processing means 14 to 17, it is a condition that specific information on a concrete building to be constructed is input. Therefore, in step S1, an input instruction is displayed on the display 4 so as to input the unique information. Based on this, the operator inputs in a step S2 the unique information necessary for performing each of the above-mentioned processes in an interactive manner for each data to be input to the display 4, and the input unique information is stored in the second storage means 12 Is stored. At this time, if unique information about another property or the same specific building is stored, the information is rewritten and updated with newly input unique information.

【0032】ここで、上記固有情報とは、以下のような
各種データのことである。すなわち、具体建築物の施工
地域(例えば都市)、予定着工日及び希望竣工日、各種
個別工事別に採用する下請け工事業者、その下請け工事
業者の休日及び就業時間、その下請け工事業者に対する
各種個別工事の手配に必要な日数、採用する資材発注
先、その資材発注先に発注及び納入指定を行うために必
要な日数、各種個別工事別に投入する予定の作業員数、
各種個別工事別の工事対象数量(例えば面積等の標準歩
係りデータで用いられる単位の数量)、及び、上記具体
建築物の現場環境に応じて設定された第2工事遅延危険
度等の施工対象である具体建築物に固有の情報である。
Here, the above-mentioned unique information is various data as described below. In other words, the construction area (for example, a city) of the concrete building, the scheduled start date and the desired completion date, the subcontractor employed for each individual construction, the holidays and working hours of the subcontractor, and various individual works for the subcontractor The number of days required for the arrangement, the number of suppliers to be used for the materials, the number of days required for ordering and specifying delivery to the material suppliers, the number of workers to be entered for each individual construction,
The number of construction objects for each individual construction (for example, the number of units used in the standard walk-in data such as area) and the construction objects such as the second construction delay risk set according to the site environment of the above specific building Is information specific to the concrete building.

【0033】上記の採用する下請け工事業者の入力は、
個別に入力してもよいが、上記第1記憶手段11に予め
記憶格納された下請け工事業者リストをディスプレイ4
に表示させ、この表示された下請け工事業者リストから
採用する下請け工事業者を選択しその名称部分にカーソ
ルを位置させた状態でマウス3をクリックすることによ
り採用する下請け工事業者の入力を行うようにするのが
好ましい。上記の下請け工事業者への手配に必要な日数
は、後述の工程表が完成した後に作成される種々の管理
シートの作成に必要なデータであり、上記工程表に基づ
く工事開始日よりも何日前に手配をする必要があるかを
マイナス記号を付して入力する。同じく、上記資材発注
先に発注及び納入指定を行うために必要な日数も、上記
の種々の管理シートの作成に必要なデータであり、上記
工程表に基づく工事開始日よりも何日前に発注等をする
必要があるかをマイナス記号を付して入力する。
The input of the subcontractor employed above is
The subcontractor list stored in advance in the first storage means 11 may be input individually,
To select the subcontractor to be employed from the displayed subcontractor list, and click the mouse 3 with the cursor positioned at the name of the subcontractor to input the subcontractor to be employed. Is preferred. The number of days required for the arrangement to the subcontractor is the data required to create various management sheets created after the completion of the below-mentioned schedule, and several days before the construction start date based on the above-mentioned schedule. Enter with a minus sign if you need to make an arrangement. Similarly, the number of days required for ordering and specifying delivery to the above-mentioned material supplier is also data required to create the various management sheets described above. Enter with a minus sign if you need to

【0034】また、上記の各種個別工事別の投入予定の
作業員数は、例えば上記第1記憶手段11に記憶格納さ
れた標準歩係りデータを各種個別工事別に表としてディ
スプレイ4に表示させた状態でその表示画像の表に対し
対応する各種個別工事毎に入力していくようにすればよ
い。同様に、上記各種個別工事別の工事対象数量につい
ても、上記各種個別工事毎に標準歩係りデータと、投入
予定の作業員数とを表として表示されたディスプレイ4
の表示画像に対し併せて入力していくようにすればよ
い。このようにすることにより、次のステップS4で行
う各種個別工事別の必要実働日数の計算を表計算処理に
より自動的に行わすようにしてもよい。一方、上記の工
事対象数量の入力は操作者自身が入力するのではなく、
建築物の自動設計を行うCAD装置により自動計算され
たCADデータを取り込むことにより自動入力させるよ
うにするのが好ましい。このようなCAD装置では自動
設計の後に見積もりのために各部位毎の数量計算が自動
的に行われ、その数量計算結果が記憶保持されている。
この場合には、CAD装置のコンピュータ7を工程管理
支援装置のコンピュータ1に接続し、上記の表示画像に
領域設定されたデータ取り込みボタンをマウス3でクリ
ックすれば上記コンピュータ7から上記数量計算結果が
工事対象数量として上記表示画像に取り込まれて表示さ
れることになる。従って、上記の投入予定の作業員数を
操作者が入力すれば、上記標準歩係りデータと上記工事
対象数量とに基づいて後は自動的に各種個別工事毎の必
要実働日数の演算が行われることになる。
The number of workers scheduled to be put in for each of the individual works is calculated, for example, in a state where the standard attendance data stored in the first storage means 11 is displayed on the display 4 as a table for each of the various works. What is necessary is just to input into the table of the display image for every corresponding individual construction. Similarly, as for the construction target quantity for each of the above-mentioned individual works, a display 4 displaying a table of standard attendance data and the number of workers to be put in for each of the above-mentioned individual works.
What is necessary is just to input together with the display image of. By doing so, the calculation of the required actual working days for each individual construction performed in the next step S4 may be automatically performed by a spreadsheet process. On the other hand, the input of the above construction target quantity is not input by the operator himself,
It is preferable to input automatically by taking in CAD data automatically calculated by a CAD device for automatically designing a building. In such a CAD apparatus, the quantity calculation for each part is automatically performed for estimation after the automatic design, and the result of the quantity calculation is stored and held.
In this case, the computer 7 of the CAD device is connected to the computer 1 of the process management support device, and the data acquisition result set in the display image is clicked with the mouse 3. The number of works is taken in the display image and displayed. Therefore, if the operator inputs the number of workers to be put in, the necessary actual working days for each individual construction are automatically calculated based on the standard attendance data and the construction target quantity. become.

【0035】上記第2工事遅延危険度は、具体建築物の
現場環境の具体的状況に応じて予想される遅延発生に対
する危険度であり、第1工事遅延危険度の設定に用いた
遅延要素の内から現場環境に対応するものとして特に敷
地余裕度及び前面道路幅を2項目を選択し、これら敷地
余裕度及び前面道路幅についての具体建築物の具体状況
から予想される遅延危険度を数値化したものである。具
体的には、その具体建築物の現実の敷地余裕度条件とし
て敷地が広くて余裕がある場合には「0」を、敷地がや
や狭い場合には「1」を、敷地が狭くて問題がある場合
には「2」をそれぞれ設定し、現実の前面道路幅につい
ての前面道路条件として幅が広くて資材搬入等に余裕が
ある場合には「0」を、やや余裕がある程度の場合には
「1」を、余裕がなく問題がある場合には「2」をそれ
ぞれ設定する。これらはいずれも、数値が大きい程、工
事の遅延が発生する危険性が高いことを示している。こ
れらの第2工事遅延危険度の入力は、例えば敷地余裕度
の場合であれば、ディスプレイ4に表示させた入力画像
に敷地余裕度として「広い」、「やや狭い」、「狭くて
問題」の3種類の表示と、それぞれに対応する選択ボタ
ンを領域設定し、該当する選択ボタンをマウス3を用い
てクリックすることにより、それに対応する数値が入力
されるようにすればよい。
The second construction delay risk is the risk of occurrence of a delay expected according to the specific situation of the site environment of a concrete building, and is the delay element used for setting the first construction delay risk. Two items were selected for the site margin and front road width, especially those that correspond to the site environment from within, and the risk of delay expected from the concrete situation of the building with these site margin and front road width was quantified. It was done. Specifically, the actual site margin condition of the concrete building is “0” if the site is large and has room, “1” if the site is slightly narrow, and the site is narrow. In some cases, “2” is set, and “0” is set if the front road condition is wide and there is enough room for material loading, etc. "1" is set, and "2" is set when there is no margin and there is a problem. In each case, the larger the value, the higher the risk of delay in construction. If the input of the second construction delay risk is, for example, the site margin, the input image displayed on the display 4 indicates that the site margin is “wide”, “slightly narrow”, or “narrow and problematic”. The three types of display and the corresponding selection buttons may be set as areas, and the corresponding selection buttons may be clicked using the mouse 3 to input numerical values corresponding thereto.

【0036】以上の固有情報の全てが入力されたか否か
の確認をステップS3で行った後、ステップS4で全体
余裕日数Drtの演算を行う。この全体余裕日数Drtの演
算は以下のようにして行う。
After confirming whether or not all of the above specific information has been input in step S3, in step S4, the total spare days Drt is calculated. The calculation of the total spare days Drt is performed as follows.

【0037】(ステップS4)すなわち、まず、各種個
別工事別の必要実働日数Diを求め、次に、建築物施工
に要する全体必要実働日数Dtを求め、そして、ステッ
プS2で入力された希望竣工日と予定着工日との差であ
る希望全体工期Dwtから上記全体必要実働日数Dtを差
し引いて全体余裕日数Drtを求める。具体的には以下の
(1)〜(3)の各式による演算を行うことにより全体余裕日
数Drtが求められる。
(Step S4) That is, firstly, the required actual working days Di for each individual construction are obtained, then the total required actual working days Dt required for building construction are obtained, and the desired completion date input in step S2 is obtained. By subtracting the total required actual working days Dt from the desired total construction period Dwt, which is the difference between the scheduled start date and the scheduled start date, the overall spare days Drt is obtained. Specifically,
By performing the calculations according to the equations (1) to (3), the total spare days Drt is obtained.

【0038】 Di=Ni/(Mi×Si) …(1) Dt=D1+D2+…+Dn-1+Dn …(2) Drt=Dwt−Dt …(3) ここで、添字i=1〜n(nは各種個別工事の全体数)
であり、各種個別工事の種目に対応している。また、N
iは各種個別工事別の工事対象数量(単位m2)、Miは
各種個別工事別の投入予定の作業員数(単位は人)、S
iは各種個別工事別の標準歩係りデータ(単位は人・時
間/m2)である。
Di = Ni / (Mi × Si) (1) Dt = D1 + D2 +... + Dn-1 + Dn (2) Drt = Dwt−Dt (3) where subscripts i = 1 to n (n is various individual Total number of works)
And corresponds to various individual construction events. Also, N
i is the number of works to be constructed by each individual construction (unit: m 2 ), Mi is the number of workers to be put in by each individual construction (unit is person), S
i is standard attendance data (unit: person / hour / m 2 ) for each individual construction.

【0039】なお、上記(2)式での集計に際し、n種目
ある各種個別工事の内で第1記憶手段11に記憶格納さ
れた工程順ルールが加味されて特定の個別工事の必要実
働日数が集計から除かれるようになっている。すなわ
ち、上記工程順ルールにおいて、同時実行可能な複数の
個別工事の組み合わせがある場合には、その複数の個別
工事の各必要実働日数の内、最大の必要実働日数の値の
みが上記(2)式での集計に用いられ、他の必要実働日数
の値は上記集計から除かれる。つまり、全体必要実働日
数Dtとして真に必要な、あるいは、最短の日数が得ら
れるようになっている。
In addition, when counting in the above equation (2), the required actual working days of a specific individual construction are calculated by taking into account the process order rules stored in the first storage means 11 among the various types of individual constructions. It is now excluded from counting. That is, in the above-mentioned process order rule, when there is a combination of a plurality of individual works that can be executed simultaneously, only the value of the maximum required actual work days among the required actual work days of the plurality of individual works is the above (2). Used in the tally in the formula, other required working days values are excluded from the tally. In other words, it is possible to obtain a truly necessary or minimum number of days as the total required actual working days Dt.

【0040】また、上記(1)の演算は、上記ステップS
2の投入予定の作業員数や工事対象数量の入力の場合に
おいて説明したように自動表計算を用いて行うようにし
てもよい。
The calculation of (1) is performed in the step S
As described in the case of inputting the number of workers to be put in 2 and the number of construction objects, automatic table calculation may be used.

【0041】(ステップS5)次に、ステップS5で各
種個別工事別に現実の現場状況及び気象変動事情を考慮
した具体工事遅延危険度を決定する。この具体工事遅延
危険度の決定は以下のようにして行う。
(Step S5) Next, in step S5, a concrete construction delay risk is determined for each individual construction in consideration of the actual site situation and the weather fluctuation situation. This concrete construction delay risk is determined as follows.

【0042】すなわち、第1記憶手段11に記憶格納さ
れた気象統計データの内から、ステップS2で入力され
た具体建築物の施工場所(都市)及び施工期日(例えば
予定着工日から割り出した工期半ばの期日)の属する月
に対応する降雨確率を取り出し、この降雨確率を具体建
築物についての気象変動による第3工事遅延危険度R3
として設定する。例えば施工場所が大阪で、施工期日の
属する月が3月である場合には、上記気象統計データか
ら大阪の3月の降雨量10mm以上の降雨確率「0.1
3」を上記第3工事遅延危険度R3として設定する。そ
して、上記第1記憶手段11に記憶格納されている各種
個別工事別の第1工事遅延危険度の内の敷地余裕度リス
ク及び前面道路リスクのそれぞれに対し上記第2工事遅
延危険度を乗じ、上記第1工事遅延危険度の内の降雨確
率リスクに対し上記第3工事遅延危険度を乗じ、上記第
1工事遅延危険度の残りの工程遅延リスクに対しその個
別工事の重要度について3段階に設定した重要度条件R
4i(「0」,「1」,「2」)を乗じ、これら乗じた後
の値を集計して具体工事遅延危険度とする。
That is, from the weather statistics data stored in the first storage means 11, the construction site (city) and construction date (for example, the mid-construction period calculated from the scheduled construction start date) of the concrete building input in step S2 Of the third construction delay danger R3 due to weather fluctuations of the concrete building.
Set as For example, if the construction site is Osaka and the month to which the construction date belongs is March, the probability of rainfall with a rainfall of 10 mm or more in March in Osaka from "0.1
3 "is set as the third construction delay risk R3. Then, multiply each of the site margin risk and the front road risk among the first construction delay risks for each individual construction stored in the first storage means 11 by the second construction delay risk, The probability of rainfall in the first construction delay risk is multiplied by the third construction delay risk, and the remaining construction delay risk of the first construction delay risk is divided into three levels regarding the importance of the individual construction. Set importance condition R
4i (“0”, “1”, “2”), and the values after these multiplications are totaled as a concrete construction delay risk.

【0043】具体的には、第1工事遅延危険度R1-ij
(iは上記と同じで各種個別工事種目を表す添字であ
り、i=1〜n;jは各遅延要素種目を表す添字であ
り、j=1〜4)の内の工程遅延リスクをR1-i1(R1-
i1=0〜2)、敷地余裕度リスクをR1-i2(R1-i2=0
〜2)、前面道路リスクをR1-i3(R1-i3=0〜2)、
降雨影響リスクをR1-i4(R1-i4=0〜2)とし、第2
工事遅延危険度R2-im(mは現場環境種目を表す添字で
あり、m=1〜2)の内の敷地余裕度条件をR2-i1(R
2-i1=0〜2)、前面道路条件をR2-i2(R2-i2=0〜
2)、第3工事遅延危険度をR3とすると、ある個別工
事についての具体工事遅延危険度をRiは以下の(4)式
により求める。
Specifically, the first construction delay risk R1-ij
(I is the same as the above and is a suffix representing various individual construction items, i = 1 to n; j is a suffix representing each delay element item, and j = 1 to 4). i1 (R1-
i1 = 0-2), site margin risk is calculated as R1-i2 (R1-i2 = 0)
~ 2), the risk of the front road is R1-i3 (R1-i3 = 0-2),
The risk of rainfall impact is R1-i4 (R1-i4 = 0-2), and the second
The site margin condition within the construction delay risk R2-im (m is a subscript representing the site environment item, m = 1 to 2) is defined as R2-i1 (R
2-i1 = 0-2), and the front road condition is set to R2-i2 (R2-i2 = 0-
2) Assuming that the third construction delay risk is R3, the concrete construction delay risk for a certain individual construction is calculated by the following equation (4).

【0044】 Ri=R1-i1×R4i +R1-i2×R2-i1 +R1-i3×R2-i2 +R1-i4×R3 …(4) 例えば、個別工事として仮設トイレ設置工事を例に取っ
てある具体建築物についての具体工事遅延危険度Riを
求める場合について示すと、この仮設トイレ工事に対す
る第1工事遅延危険度R1-ijとして工程遅延リスクR1-
i1=0、敷地余裕度リスクR1-i2=1、前面道路リスク
R1-i3=1、降雨影響リスクR1-i4=1が予め評価され
て第1記憶手段11に記憶格納されており、具体建築物
の現場環境に基づく第2工事遅延危険度R2-imとして敷
地余裕度条件R2-i1=0、前面道路条件R2-i2=0が入
力されて第2記憶手段12に記憶されている一方、ステ
ップS5で降雨確率に基づく第3工事遅延危険度R3=
0.13が第1記憶手段11の気象統計データから取り
出され、これらの各数値が上記の(4)式に以下の如く
代入される。なお、重要度条件としてR4=2が入力設
定されているものとする。
Ri = R1-i1 × R4i + R1-i2 × R2-i1 + R1-i3 × R2-i2 + R1-i4 × R3 (4) For example, a concrete toilet installation work is taken as an example of individual work. In the case of calculating the concrete construction risk danger Ri of the building, the first construction delay danger R1-ij for this temporary toilet construction is referred to as a process delay risk R1-ij.
i1 = 0, site margin risk R1-i2 = 1, front road risk R1-i3 = 1, rainfall impact risk R1-i4 = 1 are pre-evaluated and stored in the first storage means 11, and the concrete building While the site margin condition R2-i1 = 0 and the front road condition R2-i2 = 0 are input and stored in the second storage means 12 as the second construction delay risk R2-im based on the site environment of the object, In step S5, the third construction delay risk R3 based on the rainfall probability is R3 =
0.13 is taken out from the weather statistics data in the first storage means 11, and these numerical values are substituted into the above-mentioned equation (4) as follows. It is assumed that R4 = 2 is input and set as the importance condition.

【0045】仮設トイレ工事の具体工事遅延危険度=0
×2+1×0+1×0+1×0.13=0.13 上記の(4)式では、第1工事遅延危険度としてある個
別工事について遅延発生の危険性が高いとして「2」が
予め記憶設定されていても、具体建築物の現場環境が各
遅延要素に対する余裕度が高ければ、つまり、影響を受
けないものであれば、第2工事遅延危険度として「0」
が入力設定されるため、上記の如く乗算される結果、そ
の遅延要素についての遅延発生に対する危険性は除かれ
ることになる。
Temporary toilet construction risk of construction delay = 0
× 2 + 1 × 0 + 1 × 0 + 1 × 0.13 = 0.13 In the above equation (4), “2” is stored and set in advance as the risk of occurrence of a delay is high for an individual work as the first work delay risk. However, if the site environment of the concrete building has a high margin for each delay element, that is, if it is not affected, the second construction delay risk is “0”.
Is set as an input, and as a result of the multiplication as described above, the risk of occurrence of delay for the delay element is eliminated.

【0046】(ステップS6)次に、ステップS6では
上記ステップS5で得られた各種個別工事別の具体工事
遅延危険度Riに基づいて各種個別工事毎の想定個別工
期Dpiの決定を行う。
(Step S6) Next, in step S6, the assumed individual construction period Dpi for each individual construction is determined based on the specific construction delay risk Ri for each individual construction obtained in step S5.

【0047】その基本的な方法は上記ステップS4で求
めた全体余裕日数Drtを上記ステップS5で求めた具体
工事遅延危険度Riの値に応じて各種個別工事に対し略
比例配分により割り振り、この割り振られた個別余裕日
数DriをステップS4で求めた各種個別工事別の必要実
働日数Diに追加することにより、各種個別工事毎の想
定個別工期Dpiの決定が行われる。ここで、上記全体余
裕日数Drtの割り振りは1日を単位として行うのが実用
上好ましい。
The basic method is to allocate the total spare days Drt obtained in the above step S4 to various individual works according to the value of the concrete construction risk danger Ri obtained in the above step S5 by substantially proportional distribution. By adding the obtained individual spare days Dri to the required actual working days Di for each individual construction obtained in step S4, the assumed individual construction period Dpi for each individual construction is determined. Here, it is practically preferable to allocate the total spare days Drt in units of one day.

【0048】また、簡略化した割り振り手法の一例とし
ては以下の如く行えばよい。すなわち、まず、上記のス
テップS5で得られた各種個別工事別の具体工事遅延危
険度Riを大きい値のものから順に並べ替え、最大値か
ら最小値までの範囲をいくつかに(例えば3つの範囲
に)区分けする。次に、上位の第1範囲に属する個別工
事に対し全体余裕日数Drtの内の例えば略50%分の日
数を、第2範囲に属する個別工事に対し例えば略30%
分の日数を、第3範囲に属する個別工事に対し略20%
分の日数をそれぞれ割り振る。そして、それぞれ割り振
られた日数を各範囲に属する個別工事の数で除した日数
(最小単位は1日)をその範囲に属する各個別工事に個
別余裕日数Driとして割り振ればよい。この場合、割り
振るための計算結果が1日未満の値になる場合には割り
振る日数を「0」とし、その分を具体工事遅延危険度が
より高い個別工事に割り振るようにすればよい。
An example of a simplified allocation method may be performed as follows. That is, first, the specific construction delay risk Ri for each individual construction obtained in step S5 is rearranged in ascending order of magnitude, and the range from the maximum value to the minimum value is reduced to some (for example, three ranges). To) Next, for the individual works belonging to the upper first range, the number of days equivalent to, for example, about 50% of the total spare days Drt is set to, for example, about 30% for the individual works belonging to the second range.
The number of days per minute is approximately 20% for individual works belonging to the third range.
Allocate minutes for each minute. Then, the number of days (the minimum unit is one day) obtained by dividing the allocated days by the number of individual works belonging to each range may be allocated as individual spare days Dri to each individual work belonging to the range. In this case, if the calculation result for the allocation is less than one day, the number of days to be allocated may be set to “0”, and that portion may be allocated to individual works with a higher risk of concrete work delay.

【0049】さらに、全体余裕日数Drtが比較的短日数
(例えば10日間)である場合には、上記の大値から順
に並べ替えたものの内の上位10位に属する個別工事に
対してのみ、Driとして1日ずつ画一的に割り振るよう
にすればよい。
Further, when the total number of spare days Drt is relatively short (for example, 10 days), only the individual works belonging to the top 10 out of those sorted in descending order of the above-mentioned values are converted into Dri. What is necessary is just to allocate uniformly one day at a time.

【0050】(ステップS7)上記ステップS6で得ら
れた想定個別工期Dpiに基づきステップS7でバーチャ
ート式の全体工程表を作成してディスプレイ4に表示す
る。すなわち、図4にこのステップS7で作成されてデ
ィスプレイ4に表示された工程表画像20を示すよう
に、横軸を施工期日欄21にして現実の施工期日を左か
ら右に経過順に並べ、縦軸を作業名欄22にして個別工
事種目を工程順ルールに基づく優先実行順に上から下に
並べて直交座標領域を設定して工程表を表示し、この工
程表の各個別工事と各施工期日とで規定される領域に対
し上記の想定個別工期Driが上記の優先順の先後の両個
別工事で連続するように棒状記号(バー)23,23,
…を表示する。
(Step S 7) Based on the assumed individual work period Dpi obtained in the above step S 6, a whole process chart of a bar chart type is created in step S 7 and displayed on the display 4. That is, as shown in FIG. 4, the horizontal axis is the construction date column 21, and the actual construction dates are arranged in order from left to right in the order of progress, as shown in the process chart image 20 created in step S 7 and displayed on the display 4. With the axis as the work name column 22, the individual construction items are arranged from top to bottom in the order of priority execution based on the process order rule, a rectangular coordinate area is set, a process chart is displayed, and each individual work and each construction date in the process chart are displayed. The bar-like symbols (bars) 23, 23, 23, 23, 23, 23
... is displayed.

【0051】詳細に説明すると、上記作業名欄22に細
分類の各個別工事を表示し、これに加え、その作業名欄
22の右隣の担当業者欄24にその個別工事を担当する
下請け工事業者(ステップS2で選択されたもの)の名
称を、さらにその右隣の日数欄25に各個別工事の想定
個別工期Driを、さらにその右隣の開始日欄及び終了日
欄26に上記想定個別工期Driに基づく現実の工事開始
日及び終了日をそれぞれ表示する。そして、バーチャー
ト表示欄27には、上記のバー23,23,…の内、必
要実働日数部23aが例えば特定色(例えば黒色)の塗
りつぶしにより、上記のステップS6で追加された具体
余裕日数Driに対応する日数の余裕日部23bが必要実
働日数部23aとは異なる態様(例えば水色もしくは濃
い網掛け)によりそれぞれ表示される一方、作業休止日
(日曜日)の休日表示28が上記各バー23とは異なる
態様(例えば灰色もしくは薄い網掛け)により表示され
る。
More specifically, the individual works of the sub-category are displayed in the work name column 22, and in addition, the subcontracting work in charge of the individual work is displayed in the contractor column 24 to the right of the work name column 22. The name of the contractor (the one selected in step S2), the estimated individual construction period Dri of each individual construction in the number of days column 25 on the right thereof, and the above-mentioned individual individual construction period Dri in the start date and end date columns 26 on the right thereof. The actual construction start date and end date based on the construction period Dri are displayed. In the bar chart display column 27, of the bars 23, 23,..., The required actual working days portion 23a is filled with, for example, a specific color (for example, black) by the specific margin days Dri added in step S6. Are displayed in a different form (for example, light blue or dark shaded) from the required actual working days section 23a, while the holiday display 28 of the work suspension day (Sunday) is Are displayed in different manners (eg, gray or light shaded).

【0052】図4においては、例えば個別工事の「看
板、仮囲い設置」、「仮設トイレ設置」、「仮設電気設
置」及び「仮設水道設置」の4つの個別工事が2月23
日の1日で同時実行され、次に、「土壌処理」及び基礎
工事(整地〜ベースコンクリート打設)」の両個別工事
が2月24日から同時実行され後者の個別工事が2月2
6日まで行われることを示している。これらの各個別工
事の各バー23は全て塗りつぶしの必要実働日数部23
aで表示され、これらには余裕日数の割り振りは行われ
ていない、つまり、遅延発生の危険性はないことを示し
ている。これに対し、上から14番目の「建て方・下地
パネル工事」のバー23は3月9日から始まる3日間の
必要実働日数部23aと、3月8日の1日間の余裕日数
部23bとからなり、また、上から23及び24番目の
「システムバス施工」と「屋根工事(ナチュール)」の
各工事の各バー23は3月16日及び17日の2日間の
余裕日数部23bを含んでおり、それぞれ余裕日数があ
ることを示している。
In FIG. 4, for example, four individual works of “signboard, temporary enclosure installation”, “temporary toilet installation”, “temporary electric installation” and “temporary water supply installation” of the individual works are performed on February 23.
The two individual works, "Soil treatment" and "Basic work (land leveling-base concrete placement)", were simultaneously carried out from February 24, and the latter work was carried out on February 2.
It shows that it will take place until the 6th. Each bar 23 of each of these individual works is required to be painted.
These are indicated by "a", and indicate that no spare days have been allocated, that is, there is no risk of occurrence of delay. On the other hand, the bar 14 of the 14th "building method / base panel construction" from the top has a required number of working days 23a for three days starting from March 9 and a marginal day part 23b for one day on March 8. In addition, each bar 23 of the 23rd and 24th "system bus construction" and "roofing construction (natural)" construction from the top includes a spare days part 23b for two days on March 16 and 17. , Which indicates that there are extra days for each.

【0053】なお、ステップS7で作成する工程表はバ
ーチャート式のものに限らず、ネットワーク式の工程表
でもよい。
The process chart created in step S7 is not limited to the bar chart type one, but may be a network type one.

【0054】(ステップS8)そして、ディスプレイ4
に表示された工程表画像20を検討して操作者がある特
定の個別工事の余裕日を増加・減少の変更を行いたい場
合には、その余裕日数部23bにカーソルを位置付けて
マウス3でクリックすることにより反転表示させた状態
で、上記工程表画像20の上側領域に領域設定された余
裕日変更ボタン31をマウス3でクリックすることによ
り、増加するか減少するかの設定するための図示省略の
画像が上記工程表画像20に重ねて表示される。この画
像により余裕日数の変更を行うことによりステップS7
に戻って工程表の再作成及びその再作成された工程表が
ディスプレイ4に表示される。
(Step S8) Then, the display 4
When the operator wants to change the increase / decrease of the spare days of a specific individual work by examining the process chart image 20 displayed in the above, the cursor is positioned on the spare days section 23b and clicked with the mouse 3 By clicking on the margin date change button 31 set in the upper area of the process chart image 20 with the mouse 3 in a state where the display is highlighted, the increase or decrease is not illustrated. Is superimposed on the process chart image 20 and displayed. The number of extra days is changed based on this image, thereby obtaining step S7.
Then, the process chart is re-created, and the re-created process chart is displayed on the display 4.

【0055】(ステップS9)ステップS8でディスプ
レイ4に表示された工程表画像20で不都合なければ、
その全体工程表に基づき各種の管理シートの作成が行わ
れる。すなわち、上記全体工程表の各種個別工事の開始
日から逆算した資材発注納入計画シート、諸手配計画シ
ート、各種の進捗管理シート、躯体部分の工程表シー
ト、下請け工事業者別の工程表シート、施主向けの工程
表シート等の各種の管理シートの作成を行う。
(Step S9) If the process chart image 20 displayed on the display 4 in step S8 is not inconvenient,
Various management sheets are created based on the overall process chart. In other words, the material order delivery plan sheet, various arrangement planning sheets, various progress management sheets, frame work schedule sheets, subordinate contractor work schedule sheets for each subcontractor, Create various management sheets such as process sheet sheets for customers.

【0056】例えば上記資材発注納入計画シートは図5
に示す資材発注納入計画画像41としてディスプレイ4
に表示される。これは、上記全体工程表(工程表画像2
0)の各種個別工事の開始日から、ステップS2で入力
された資材発注・納入に必要な日数分だけ逆算すること
により発注日及び納入日が演算され、これら発注日及び
納入日並びに発送元を各種個別工事別にかつ発注日の若
いものから順に表示させたものである。また、上記諸手
配計画シートは図6に示す諸手配計画画像42としてデ
ィスプレイ4に表示される。これは、上記と同じく全体
工程表の各種個別工事別の開始日から、ステップS2で
入力された手配に必要な日数分だけ逆算することにより
手配日が演算され、この手配日の期日を各種個別工事に
必要な手配種目と、手配元及び手配先と共に表示したも
のである。さらに、上記各種の進捗管理シートは、工事
進行過程において行われるべき各種の仕事(タスク)を
上記の各種入力データ及び演算結果に基づいて種類毎に
進捗管理シートとしてまとめたものである。その一例と
して 図7に工期の経過日毎にその日(図7では2月2
7日)に行うべきタスクについてまとめた担当者別タス
クリストシートが表示された担当者別タスクリスト画像
43を示す。このタスクリスト画像43には、「今日発
注すべき資材」欄44、「今日が納入日の現場配送部
材」欄45、「今日が手配日の諸手配」欄46、「今日
が作業日の工事」欄47、「今日から3日以内に始まる
工事」欄48、及び、「今日までで3日以内となる未完
了工事」欄49等の各欄が表示される。例えば上記の
「今日発注すべき資材」欄44は、資材(図7には「防
火軒天ボード」及び「不燃化粧胴差」が表示)について
の発注日及び納入日が表示され、今日が資材発注日であ
りその発注を行う必要のあることを操作者に示すもので
ある。
For example, the material order delivery planning sheet is shown in FIG.
Display 4 as material order delivery plan image 41 shown in
Will be displayed. This is the overall process chart (process chart image 2)
The order date and delivery date are calculated by calculating the number of days necessary for ordering and delivering the material input in step S2 from the start date of various individual works in step 0), and the order date, delivery date, and shipping source are calculated. These are displayed in order of various individual works and from the youngest one on the order date. The arrangement plan sheet is displayed on the display 4 as an arrangement plan image 42 shown in FIG. The arrangement date is calculated from the start date for each individual construction work in the overall process chart as described above by calculating the number of days required for the arrangement entered in step S2, and the date of the arrangement date is calculated for each individual. This is displayed together with the arrangement items required for construction, the arrangement source and the arrangement destination. Further, the various types of progress management sheets collect various types of tasks (tasks) to be performed in the course of the construction, based on the various types of input data and calculation results, as progress management sheets. As an example, FIG. 7 shows each day (e.g., February 2
The task list image 43 for each person on which the task list sheet for each person in charge of the task to be performed on the 7th) is displayed. In the task list image 43, a “material to be ordered today” column 44, a “today's delivery site on-site delivery member” column 45, a “today's arrangement date various arrangements” column 46, and a “today is a work day construction” Column 47, a "construction starting within three days from today" column 48, and an "uncompleted construction within three days from today" column 49 are displayed. For example, the above-mentioned "material to be ordered today" column 44 indicates the order date and delivery date of the material ("fireproof eaves sky board" and "non-combustible decorative body difference" are displayed in FIG. 7). This is an order date and indicates to the operator that it is necessary to place the order.

【0057】(ステップS10)最後に、上記の各画像
20,41,42,43の上側領域に領域設定された印
刷ボタン32をマウス3によりクリックすることにより
プリンタ5印刷指令が出力され、上記各画像20,4
1,42,43が印刷される。
(Step S10) Finally, by clicking with the mouse 3 the print button 32 set in the upper area of each of the images 20, 41, 42, and 43, a print command for the printer 5 is output. Images 20, 4
1, 42 and 43 are printed.

【0058】以上の処理により工程表が得られ、この工
程表に基づいて工程管理が行われることになる。また、
工事の途中で予期せぬ事態の発生により上記工程表と食
い違うことになった場合(遅れが生じた場合)には、上
記の工程表画像20において、上記事態発生以降の個別
工事の余裕日を上記のステップS8の処理において説明
したように減少変更して再計算させることにより、希望
竣工日までに建築物施工が全て終了するように余裕日数
が再配分された工程表を作成・表示することができる。
By the above process, a process chart is obtained, and process management is performed based on the process chart. Also,
In the case where an unexpected situation occurs during the construction to cause a discrepancy with the above process schedule (when a delay occurs), in the process schedule image 20, the allowance date of the individual construction work after the occurrence of the above situation is described. As described in the processing in step S8 above, by reducing and recalculating, a process chart is created and displayed in which the number of spare days is redistributed so that all building construction is completed by the desired completion date. Can be.

【0059】なお、上記の図3のフローチャートにおい
て、ステップS1〜S3により第1ステップが、ステッ
プS4により第2ステップもしくは第1処理手段14
が、ステップS5により第3ステップもしくは第2処理
手段15が、ステップS6により第4ステップもしくは
第3処理手段16が、ステップS7〜ステップS10に
より第5ステップもしくは第4処理手段17が構成され
ている。
In the flowchart of FIG. 3, the first step is performed by steps S1 to S3, and the second step or the first processing means 14 is performed by step S4.
However, step S5 constitutes the third step or second processing means 15, step S6 constitutes the fourth step or third processing means 16, and step S7 to step S10 constitutes the fifth step or fourth processing means 17. .

【0060】[0060]

【発明の効果】以上説明したように、請求項1〜請求項
3のいずれかに記載の発明における建築物施工に対する
工程管理支援装置、又は、請求項4〜請求項6のいずれ
かに記載の発明における建築物施工に対する工程管理支
援プログラムを記録したコンピュータ読み取り可能な記
録媒体によれば、工期の遅延発生に対する危険度合いを
加味して確実に希望工期内に建築物施工を完了し得る工
程表を自動的に得ることができる。この際、上記遅延発
生に対する危険度合いとして経験則及び統計資料等の基
礎情報に基づく各種個別工事別の第1工事遅延危険度に
対し、具体建築物についての現場環境及び気象変動等に
基づく第2及び第3工事遅延危険度を加味して上記具体
建築物についての具体工事遅延危険度を導出しているた
め、遅延発生予測、つまり、遅延発生に対する評価を種
々の要因の絡み合った現実の状況に即して行うことがで
きる。そして、このような具体工事遅延危険度に応じて
希望工期に対する余裕日数を各種個別工事毎に配分して
工程表が作成されるため、種々の遅延要素をも加味して
余裕日数を割り振った上記工程表に基づきフレキシブル
かつ現実に実現可能な工程管理を行うことができ、希望
全体工期内に確実に建築物施工が完了し得る工程管理を
行うことができるようになる。しかも、工期途中段階で
の変更が生じても変更後の工程表の作成をフレキシブル
かつ容易に行うことができる上に、その変更後の工程表
についても上記と同様に現実に実現可能な工程管理を行
い得るものが得られる。
As described above, the process management support apparatus for building construction according to any one of the first to third aspects of the present invention, or the fourth aspect of the present invention, relates to the fourth aspect of the present invention. According to the computer-readable recording medium on which the process management support program for building construction according to the present invention is recorded, a process schedule capable of completely completing building construction within a desired construction period by taking into account the degree of risk of delay in construction period is considered. You can get it automatically. At this time, as the degree of risk for the occurrence of the delay, the first degree of construction delay risk for each individual construction based on basic information such as empirical rules and statistical data is compared with the second degree based on the site environment and weather fluctuation of concrete buildings. And the third construction delay risk is taken into account to derive the concrete construction delay risk for the above-mentioned concrete building, so that the delay occurrence prediction, that is, the evaluation for the delay occurrence, is performed in the actual situation in which various factors are intertwined. It can be done according to. In addition, since the process schedule is created by allocating the spare days for the desired construction period for each individual construction according to the specific construction delay risk, the spare days are allocated in consideration of various delay elements. Flexible and practically feasible process management can be performed based on the process schedule, and it is possible to perform process management that can surely complete building construction within the desired overall construction period. Moreover, even if a change occurs in the middle of the construction period, the process chart after the change can be created flexibly and easily, and the process management after the change can be realized in the same manner as described above. Is obtained.

【図面の簡単な説明】[Brief description of the drawings]

【図1】本発明の工程管理支援装置の実施形態を示す装
置構成図である。
FIG. 1 is an apparatus configuration diagram showing an embodiment of a process management support apparatus according to the present invention.

【図2】図1の装置構成を詳細に示すブロック構成図で
ある。
FIG. 2 is a block diagram showing the configuration of the apparatus shown in FIG. 1 in detail.

【図3】工程管理支援プログラムによる処理を示すフロ
ーチャートである。
FIG. 3 is a flowchart showing processing by a process management support program.

【図4】ディスプレイにより全体工程表を表示した工程
表画像の例を示す一部省略正面図である。
FIG. 4 is a partially omitted front view showing an example of a process chart image displaying an entire process chart on a display.

【図5】ディスプレイにより資材発注納入計画シートを
表示した「資材発注納品計画」画像の一部省略正面図で
ある。
FIG. 5 is a partially omitted front view of a “material order delivery plan” image displaying a material order delivery plan sheet on a display.

【図6】ディスプレイにより諸手配計画シートを表示し
た「諸手配計画」画像の一部省略正面図である。
FIG. 6 is a partially omitted front view of an “arrangement plan” image displaying an arrangement plan sheet on a display;

【図7】進捗管理画像の一例としての担当者別タスクリ
ストをディスプレイに表示した「担当者別タスクリス
ト」画像の一部省略正面図である。
FIG. 7 is a partially omitted front view of a “person-in-charge task list” image displaying a person-in-charge task list as an example of a progress management image on a display;

【符号の説明】[Explanation of symbols]

1 パーソナルコンピュータ(コンピュー
タ) 2 キーボード(入力装置) 3 マウス(入力装置) 4 ディスプレイ(出力装置) 5 プリンタ(出力装置) 6 CD−ROM(記録媒体) 6′ フロッピーディスク(記録媒体) 7 パーソナルコンピュータ(CAD装置) 8 ディスプレイ(CAD装置) 10 記憶部 11 第1記憶手段 12 第2記憶手段 14 第1処理手段 15 第2処理手段 16 第3処理手段 17 第4処理手段 20 工程表画像(工程表) 21 施工期日欄 22 作業名欄(個別工事種目欄) 23 バー(棒状記号) 23a 実働日数部 23b 余裕日数部
Reference Signs List 1 personal computer (computer) 2 keyboard (input device) 3 mouse (input device) 4 display (output device) 5 printer (output device) 6 CD-ROM (recording medium) 6 ′ floppy disk (recording medium) 7 personal computer ( CAD device) 8 Display (CAD device) 10 Storage unit 11 First storage unit 12 Second storage unit 14 First processing unit 15 Second processing unit 16 Third processing unit 17 Fourth processing unit 20 Process schedule image (process schedule) 21 Construction date column 22 Work name column (individual construction item column) 23 Bar (bar-shaped symbol) 23a Actual working days 23b Extra days

───────────────────────────────────────────────────── フロントページの続き (72)発明者 佐藤 友紀 大阪府大阪市北区中之島2丁目3番18号 大建工業株式会社内 (72)発明者 小西 俊行 大阪府大阪市北区中之島2丁目3番18号 大建工業株式会社内 Fターム(参考) 5B049 BB05 CC21 CC32 EE33 EE34 EE37  ────────────────────────────────────────────────── ─── Continuing on the front page (72) Yuki Sato, Inventor 2-3-18 Nakanoshima, Kita-ku, Osaka, Osaka Inside Daiken Kogyo Co., Ltd. (72) Toshiyuki Konishi 2-3-3 Nakanoshima, Kita-ku, Osaka, Osaka No.18 Daiken Kogyo Co., Ltd. F term (reference) 5B049 BB05 CC21 CC32 EE33 EE34 EE37

Claims (6)

【特許請求の範囲】[Claims] 【請求項1】 入力装置及び出力装置が接続されたコン
ピュータによって建築物の施工に対する工程管理を支援
する建築物施工に対する工程管理支援装置であって、 降雨に関する気象統計データ、建築物の施工に必要な各
種個別工事別の標準歩掛かりデータ、上記各種個別工事
の実行順序についての制約を定めた工程順ルール、及
び、上記各種個別工事毎に遅延発生に対する危険性を経
験則に基づいて予め数値化した第1工事遅延危険度から
なる基礎情報が予め記憶格納された第1記憶手段と、 施工予定の具体建築物毎に入力される、施工地域、着工
予定日及び希望竣工日、上記各種個別工事別に投入する
予定の作業員数、上記各種個別工事別の工事対象数量、
並びに、上記具体建築物の現場環境に応じて数値化され
た第2工事遅延危険度からなる上記具体建築物について
の固有情報を更新可能に記憶保持する第2記憶手段と、 上記各種個別工事毎の予定作業員数及び工事対象数量
と、上記第1記憶手段から取り出した標準歩掛かりデー
タとに基づいて各種個別工事毎の必要実働日数を演算
し、その各必要実働日数の集計値を上記着工予定日及び
希望竣工日に基づく希望全体工期から差し引いて全体余
裕日数を決定する第1処理手段と、 上記第1記憶手段に記憶格納された気象統計データの内
から取り出した上記具体建築物の施工地域及び施工期日
に対応する気象統計データに基づいて気象変動による第
3工事遅延危険度を定め、この第3工事遅延危険度及び
第2工事遅延危険度を上記第1工事遅延危険度に加味し
て各種個別工事毎の具体工事遅延危険度を決定する第2
処理手段と、 上記全体余裕日数を上記各種個別工事に対し上記具体工
事遅延危険度が高い程多くなるように個別に配分し、こ
の配分された個別余裕日数を上記必要実働日数に加えて
各種個別工事毎の想定個別工期を決定する第3処理手段
と、 一方の軸に上記希望全体工期の期日を、他方の軸に上記
工程順ルールの優先順に並べ替えた個別工事種目をそれ
ぞれ表示設定した直交テーブルに対し、各種個別工事毎
に対応する想定個別工期を線状記号もしくは棒状記号に
より上記優先順の各種個別工事種目の各工期が前後で連
続するように表示した工程表を上記出力装置に出力する
第4処理手段とを備えていることを特徴とする建築物施
工に対する工程管理支援装置。
1. A process management support device for building construction, which supports a process management for building construction by a computer to which an input device and an output device are connected, and is required for meteorological statistical data relating to rainfall and building construction. Standard step-by-step data for each type of individual work, process order rules that set restrictions on the execution order of each type of individual work, and the risk of delays for each type of individual work are quantified in advance based on empirical rules The first storage means in which the basic information including the first construction delay risk is stored in advance, and the construction area, the scheduled construction start date and the desired completion date, and the various individual works described above, which are inputted for each concrete building to be constructed. The number of workers scheduled to be separately invested,
And second storage means for storing and updating the unique information about the concrete building, which is composed of a second construction delay risk quantified according to the site environment of the concrete building, in an updatable manner; The required number of actual working days for each individual construction is calculated based on the planned number of workers and the number of works to be constructed, and the standard walking data retrieved from the first storage means. First processing means for determining the total spare days by subtracting from the desired overall construction period based on the day and the desired completion date, and the construction area of the concrete building extracted from the weather statistical data stored in the first storage means And a third construction delay risk due to weather fluctuation is determined based on weather statistics data corresponding to the construction date, and the third construction delay risk and the second construction delay risk are determined by the first construction delay risk. By adding to the Kendo second to determine the specific construction delay risk of various individual work per
The processing means and the overall spare days are individually allocated to the various individual works so as to increase as the risk of the specific construction delay increases, and the allocated individual allowance days are added to the required actual working days in addition to the individual working days. A third processing means for determining an assumed individual work period for each work, and an orthogonal display in which one axis displays the date of the desired overall work period and the other axis displays individual work items rearranged in order of priority in the process order rule. Output to the output device a process chart that displays the expected individual work period corresponding to each individual work with a linear symbol or bar-shaped symbol so that each work period for each individual work type in the priority order is consecutive before and after the table. A process management support apparatus for building construction, comprising: a fourth processing unit that performs processing.
【請求項2】 請求項1において、 第1記憶手段に記憶格納された第1工事遅延危険度は、
各種個別工事毎にその特有要因、現場環境及び気象変動
の各種遅延要因別に予め定められており、 第2処理手段における具体工事遅延危険度の決定は、上
記遅延要因別の第1工事遅延危険度に対し具体建築物に
ついての第2及び第3の各工事遅延危険度を乗じること
により行うように構成されていることを特徴とする建築
物施工に対する工程管理支援装置。
2. The risk of the first construction delay stored in the first storage means according to claim 1,
The specific factor for each individual construction, the site environment and the various delay factors of weather change are predetermined in advance, and the determination of the concrete construction delay risk in the second processing means is based on the first construction delay risk for each of the above delay factors. A process management support apparatus for building construction, wherein the multiplication is performed by multiplying the second and third construction delay danger degrees of the concrete building.
【請求項3】 請求項1において、 具体建築物の設計を行うCAD装置と接続され、 入力指令を受けて、上記CAD装置により演算されたC
ADデータが各種個別工事別の工事対象数量として第2
記憶手段に対し入力されるように構成されていることを
特徴とする建築物施工に対する工程管理支援装置。
3. The computer system according to claim 1, which is connected to a CAD device for designing a concrete building, receives an input command, and calculates a C value calculated by said CAD device.
AD data is the second as the construction target quantity for each individual construction
A process management support apparatus for building construction, wherein the apparatus is configured to be input to a storage unit.
【請求項4】 降雨に関する気象統計データ、建築物の
施工に必要な各種個別工事別の標準歩掛かりデータ、上
記各種個別工事の実行順序についての制約を定めた工程
順ルール、及び、上記各種個別工事毎に遅延発生に対す
る危険性を経験則に基づいて予め数値化した第1工事遅
延危険度からなる基礎情報を記憶格納する記憶部を有
し、 施工予定の具体建築物毎に、施工地域、予定着工日及び
希望竣工日、上記各種個別工事別に投入する予定の作業
員数、上記各種個別工事別の工事対象数量、並びに、上
記具体建築物の現場環境に応じて数値化された第2工事
遅延危険度からなる固有情報を入力させて記憶更新する
第1ステップと、 入力された上記各種個別工事毎の予定作業員数及び工事
対象数量と、上記記憶部から取り出した標準歩掛かりデ
ータとに基づいて各種個別工事毎の必要実働日数を演算
し、その各必要実働日数の集計値を上記予定着工日及び
希望竣工日に基づく希望全体工期から差し引いて全体余
裕日数を決定する第2ステップと、 上記記憶部に記憶格納された気象統計データの内から第
1ステップで入力された上記具体建築物の施工地域及び
施工期日に対応する気象統計データを取り出し、この取
り出した気象統計データに基づいて気象変動による第3
工事遅延危険度を定め、この第3工事遅延危険度及び上
記第2工事遅延危険度を上記第1工事遅延危険度に加味
して各種個別工事毎の具体工事遅延危険度を決定する第
3ステップと、 上記全体余裕日数を上記各種個別工事に対し上記具体工
事遅延危険度が高い程多くなるように個別に配分し、こ
の配分された個別余裕日数を上記必要実働日数に加えて
各種個別工事毎の想定個別工期を決定する第4ステップ
と、 一方の軸に上記希望全体工事の期日を、他方の軸に上記
工程順ルールの優先順に並べ替えた個別工事種目をそれ
ぞれ表示設定した直交テーブルに対し、各種個別工事毎
に対応する想定個別工期を線状記号もしくは棒状記号に
より上記優先順の各種個別工事種目の各工期が前後で連
続するように表示した工程表を上記出力装置に出力する
第5ステップとをコンピュータに実行させる建築物施工
に対する工程管理支援プログラムを記録したコンピュー
タ読み取り可能な記録媒体。
4. Statistical data on rainfall, standard step data for each type of individual work required for construction of a building, a process order rule defining restrictions on the execution order of each type of individual work, It has a storage unit that stores the basic information consisting of the first construction delay risk, which quantifies the risk of occurrence of delay for each construction based on empirical rules in advance, and for each concrete building to be constructed, the construction area, The second construction delay quantified according to the scheduled start date and desired completion date, the number of workers scheduled to be entered for each of the above individual construction works, the number of construction works for each of the above individual construction works, and the site environment of the concrete building above The first step of inputting unique information including the degree of risk and storing and updating the information, the input planned number of workers and the number of works for each of the individual works, and the standard steps taken out of the storage unit Calculate the required number of actual working days for each individual construction based on the data, and subtract the total value of the required actual working days from the desired overall construction period based on the scheduled start date and the desired completion date to determine the total spare days. Two steps; extracting weather statistics data corresponding to the construction area and construction date of the concrete building input in the first step from the weather statistics data stored and stored in the storage unit; Based on climate change based on
A third step of determining the risk of construction delay and determining the concrete construction delay risk for each individual construction by adding the third construction delay risk and the second construction delay risk to the first construction delay risk. The above total spare days are individually allocated to the various individual works so as to increase as the risk of the specific work delay increases, and the allocated individual allowance days are added to the required actual working days and added to each individual work. The fourth step of determining the assumed individual construction period of the above, and the orthogonal table in which the axis of the desired overall construction is displayed on one axis, and the individual construction items rearranged in the order of the priority of the process order rule on the other axis are respectively set. Output to the output device a process chart in which the estimated individual work periods corresponding to each individual work are displayed using a linear symbol or a bar-shaped symbol so that the work periods for the various individual work items in the priority order are consecutive before and after. The fifth step and the process management support program the computer-readable recording medium for building construction to be executed by a computer that.
【請求項5】 請求項4において、 記憶部に記憶格納された第1工事遅延危険度は、各種個
別工事毎にその特有要因、現場環境及び気象変動の各種
遅延要因別に予め定められており、 第3ステップにおける具体工事遅延危険度の決定は、上
記遅延要因別の第1工事遅延危険度に対し具体建築物に
ついての第2及び第3の各工事遅延危険度を乗じること
により行うように構成されていることを特徴とするコン
ピュータ読み取り可能な記録媒体。
5. The first construction delay risk stored in the storage unit according to claim 4, wherein the first construction delay danger is predetermined for each individual construction, for each characteristic factor, site environment, and various delay factors of weather change, The determination of the specific construction delay risk in the third step is performed by multiplying the first construction delay risk for each of the above-mentioned delay factors by the second and third construction delay risks for the concrete building. A computer-readable recording medium characterized by being recorded.
【請求項6】 請求項4において、 第1ステップは、 各種個別工事別の工事対象数量として、入力指令を受け
て、具体建築物の設計を行うCAD装置により各種個別
工事別に演算されたCADデータを読み込むように構成
されていることを特徴とするコンピュータ読み取り可能
な記録媒体。
6. The CAD system according to claim 4, wherein the first step is a CAD data calculated for each individual construction by a CAD device which receives an input command and designs a concrete building as a construction target quantity for each individual construction. A computer-readable recording medium configured to read a computer program.
JP16967498A 1998-06-17 1998-06-17 Process management support device for building construction and computer-readable recording medium recording process management support program for building construction Withdrawn JP2000001988A (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
JP16967498A JP2000001988A (en) 1998-06-17 1998-06-17 Process management support device for building construction and computer-readable recording medium recording process management support program for building construction

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
JP16967498A JP2000001988A (en) 1998-06-17 1998-06-17 Process management support device for building construction and computer-readable recording medium recording process management support program for building construction

Publications (1)

Publication Number Publication Date
JP2000001988A true JP2000001988A (en) 2000-01-07

Family

ID=15890815

Family Applications (1)

Application Number Title Priority Date Filing Date
JP16967498A Withdrawn JP2000001988A (en) 1998-06-17 1998-06-17 Process management support device for building construction and computer-readable recording medium recording process management support program for building construction

Country Status (1)

Country Link
JP (1) JP2000001988A (en)

Cited By (22)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JP2002207786A (en) * 2001-01-10 2002-07-26 Hirai:Kk Method for constructing individually ordered house
JP2002297694A (en) * 2001-03-30 2002-10-11 Daiwa House Ind Co Ltd System, device, and method for additional construction adjustment, program, and data recording medium
JP2003022118A (en) * 2001-07-06 2003-01-24 Toyota Motor Corp Production process control device
JP2003064873A (en) * 2001-08-30 2003-03-05 Sumitomo Forestry Co Ltd Construction automatic analysis system
JP2006004430A (en) * 2004-06-15 2006-01-05 Microsoft Corp Method and system for restarting a project management system scheduling engine based on user input on a contractual start / end date
JP2007334639A (en) * 2006-06-15 2007-12-27 Ricoh Co Ltd Procurement support system, procurement support method and program
JP2008004075A (en) * 2006-05-26 2008-01-10 Asahi Kasei Homes Kk Construction information management system for building
JP2008158920A (en) * 2006-12-26 2008-07-10 Sumitomo Forestry Co Ltd Carrying-in management system of construction material to job site
JP2014044529A (en) * 2012-08-24 2014-03-13 Masuda Kensetsu:Kk Construction process management apparatus
JP2015020656A (en) * 2013-07-22 2015-02-02 株式会社デンソー Vehicle control device
JP2016062149A (en) * 2014-09-16 2016-04-25 株式会社日立パワーソリューションズ Information processing apparatus, process buffer calculation method, and program
JP2018193766A (en) * 2017-05-17 2018-12-06 大和ハウス工業株式会社 Concrete construction management system
CN109784691A (en) * 2018-12-28 2019-05-21 金螳螂家装电子商务(苏州)有限公司 A kind of integration system of house ornamentation construction workload data and price control data
KR20200036544A (en) * 2018-09-28 2020-04-07 진현미 A system for improving work environment of construction site and providing method thereof
CN111241704A (en) * 2020-01-21 2020-06-05 亚翔系统集成科技(苏州)股份有限公司 Method for treating pollutant outgassing in engineering construction period
JP2021039700A (en) * 2019-09-05 2021-03-11 株式会社日立ハイテクソリューションズ Support device, method, and program
CN112766757A (en) * 2021-01-25 2021-05-07 戴龙龙 Simple method for determining key process and calculating total construction period
JP2022047988A (en) * 2020-09-14 2022-03-25 西日本高速道路エンジニアリング四国株式会社 Work process determination device and work process determination program
KR20230026692A (en) * 2021-08-18 2023-02-27 (주) 디티솔루션 Method for managing process using deep learning and system of the same
JP2023105861A (en) * 2022-01-20 2023-08-01 株式会社リヨ・デ・ホーム Construction schedule preparation system and program
CN117093822A (en) * 2023-10-19 2023-11-21 西安艾派信息技术有限公司 Industrial brain data analysis platform based on industrial knowledge graph
JPWO2024034060A1 (en) * 2022-08-10 2024-02-15

Cited By (30)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JP2002207786A (en) * 2001-01-10 2002-07-26 Hirai:Kk Method for constructing individually ordered house
JP2002297694A (en) * 2001-03-30 2002-10-11 Daiwa House Ind Co Ltd System, device, and method for additional construction adjustment, program, and data recording medium
JP2003022118A (en) * 2001-07-06 2003-01-24 Toyota Motor Corp Production process control device
JP2003064873A (en) * 2001-08-30 2003-03-05 Sumitomo Forestry Co Ltd Construction automatic analysis system
JP2006004430A (en) * 2004-06-15 2006-01-05 Microsoft Corp Method and system for restarting a project management system scheduling engine based on user input on a contractual start / end date
JP2008004075A (en) * 2006-05-26 2008-01-10 Asahi Kasei Homes Kk Construction information management system for building
JP2007334639A (en) * 2006-06-15 2007-12-27 Ricoh Co Ltd Procurement support system, procurement support method and program
JP2008158920A (en) * 2006-12-26 2008-07-10 Sumitomo Forestry Co Ltd Carrying-in management system of construction material to job site
JP2014044529A (en) * 2012-08-24 2014-03-13 Masuda Kensetsu:Kk Construction process management apparatus
JP2015020656A (en) * 2013-07-22 2015-02-02 株式会社デンソー Vehicle control device
JP2016062149A (en) * 2014-09-16 2016-04-25 株式会社日立パワーソリューションズ Information processing apparatus, process buffer calculation method, and program
JP2018193766A (en) * 2017-05-17 2018-12-06 大和ハウス工業株式会社 Concrete construction management system
KR20200036544A (en) * 2018-09-28 2020-04-07 진현미 A system for improving work environment of construction site and providing method thereof
KR102190120B1 (en) * 2018-09-28 2020-12-11 진현미 A system for improving work environment of construction site and providing method thereof
CN109784691A (en) * 2018-12-28 2019-05-21 金螳螂家装电子商务(苏州)有限公司 A kind of integration system of house ornamentation construction workload data and price control data
JP7296283B2 (en) 2019-09-05 2023-06-22 株式会社日立ハイテクソリューションズ Support device, method and program
JP2021039700A (en) * 2019-09-05 2021-03-11 株式会社日立ハイテクソリューションズ Support device, method, and program
CN111241704A (en) * 2020-01-21 2020-06-05 亚翔系统集成科技(苏州)股份有限公司 Method for treating pollutant outgassing in engineering construction period
CN111241704B (en) * 2020-01-21 2024-04-26 亚翔系统集成科技(苏州)股份有限公司 Method for treating pollutant outgassing during engineering construction
JP2022047988A (en) * 2020-09-14 2022-03-25 西日本高速道路エンジニアリング四国株式会社 Work process determination device and work process determination program
CN112766757A (en) * 2021-01-25 2021-05-07 戴龙龙 Simple method for determining key process and calculating total construction period
CN112766757B (en) * 2021-01-25 2024-05-07 戴龙龙 Simple method for determining key working procedures and calculating total construction period
KR20230026692A (en) * 2021-08-18 2023-02-27 (주) 디티솔루션 Method for managing process using deep learning and system of the same
KR102802477B1 (en) * 2021-08-18 2025-05-07 (주) 디티솔루션 Method for managing process using deep learning and system of the same
JP2023105861A (en) * 2022-01-20 2023-08-01 株式会社リヨ・デ・ホーム Construction schedule preparation system and program
JPWO2024034060A1 (en) * 2022-08-10 2024-02-15
WO2024034060A1 (en) * 2022-08-10 2024-02-15 三菱電機ビルソリューションズ株式会社 Construction management system and construction management method
JP7676674B2 (en) 2022-08-10 2025-05-14 三菱電機ビルソリューションズ株式会社 Construction management system and construction management method
CN117093822A (en) * 2023-10-19 2023-11-21 西安艾派信息技术有限公司 Industrial brain data analysis platform based on industrial knowledge graph
CN117093822B (en) * 2023-10-19 2024-01-12 西安艾派信息技术有限公司 Industrial brain data analysis platform based on industrial knowledge graph

Similar Documents

Publication Publication Date Title
JP2000001988A (en) Process management support device for building construction and computer-readable recording medium recording process management support program for building construction
US5918219A (en) System and method for estimating construction project costs and schedules based on historical data
Navon Resource-based model for automatic cash-flow forecasting
Bansal et al. Potential of geographic information systems in building cost estimation and visualization
Mohamed et al. Knowledge based-system for alternative design, cost estimating and scheduling
JP2002304458A (en) Program, method and device for managing building
JP5414601B2 (en) Construction plan creation device and program
Yang et al. Management of daily progress in a construction project of multiple apartment buildings
US20070239410A1 (en) Location-based construction planning and scheduling system
Mohamed Knowledge based approach for productivity adjusted construction schedule
JP3164950B2 (en) Member determination device
Smailes A construction management approach to building the monumental adobe ciudadelas at Chan Chan, Peru
JP2000226937A (en) Schedule control table and preparation system therefor
Pathak Manpower planning, scheduling and tracking of a construction project using Microsoft Project software
Smailes Building Chan Chan: The application of construction project management to the analysis of ancient architecture
Thapa et al. BIM Orientation and Implementation
Attia Workflows for the automation of 4D & 5D BIM models: master thesis no.: 154/II. GR-BIM
Davis* Optimization of future manpower requirements in a multi-discipline consultancy
Adipratama et al. COMPARISON OF THE EFFECTIVENESS OF BUILDING INFORMATION MODELING BASED COST ESTIMATION AGAINST THE CONTRACTOR'S COST BUDGET PLAN IN DEVELOPMENT PROJECT OF BANJARBARU BAUNTUNG MARKET
JP2002230080A (en) System for automatically estimating price of building
Desai et al. MS project a better alternative for project resource management: A case of Surat city
Cheng et al. Automated master project schedule for construction incorporating building information model and IFC
Pisitpaibool et al. CONSTRUCTION DELAYS OF BUILDING REPAIR PROJECT AFTER THAILAND’S 2011 MAJOR FLOOD: CASE STUDY OF EDUCATIONAL GOVERNMENT SECTORS
JPH1166149A (en) Processor and method for information processing
Chakrabarty Integrated Computer-Aided Buildings and Housing Design by Optimization

Legal Events

Date Code Title Description
A300 Application deemed to be withdrawn because no request for examination was validly filed

Free format text: JAPANESE INTERMEDIATE CODE: A300

Effective date: 20050906