[go: up one dir, main page]

JP2002070498A - Method and device for placing concrete for tunnel - Google Patents

Method and device for placing concrete for tunnel

Info

Publication number
JP2002070498A
JP2002070498A JP2000257043A JP2000257043A JP2002070498A JP 2002070498 A JP2002070498 A JP 2002070498A JP 2000257043 A JP2000257043 A JP 2000257043A JP 2000257043 A JP2000257043 A JP 2000257043A JP 2002070498 A JP2002070498 A JP 2002070498A
Authority
JP
Japan
Prior art keywords
concrete
pipe
transport
pipes
tunnel
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Pending
Application number
JP2000257043A
Other languages
Japanese (ja)
Inventor
Tsutomu Kitagawa
勉 北川
Takeshi Aizaki
毅 相崎
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Gifu Industry Co Ltd
Original Assignee
Gifu Industry Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Gifu Industry Co Ltd filed Critical Gifu Industry Co Ltd
Priority to JP2000257043A priority Critical patent/JP2002070498A/en
Publication of JP2002070498A publication Critical patent/JP2002070498A/en
Pending legal-status Critical Current

Links

Landscapes

  • Lining And Supports For Tunnels (AREA)

Abstract

PROBLEM TO BE SOLVED: To eliminate the need for the rearrangement piping work of a concrete transport pipe, easily rearrange concrete transport, drastically reduce a construction period, and to place concrete uniformly with improved quality. SOLUTION: In the method and device for placing concrete 14 for secondary lining by using a traveling form 16 in a tunnel 12, a concrete transport pipe 20 to be used out of a plurality of concrete transport pipes 20 arranged at the traveling form 16 is connected to a concrete supply pipe 22 arranged at the traveling form 16, and then the concrete 14 is placed between the traveling form 16 and a wall surface 48 in the tunnel successively or simultaneously from a concrete carry-out pipe 24 being provided at several locations of the concrete transport pipe 20 to be used.

Description

【発明の詳細な説明】DETAILED DESCRIPTION OF THE INVENTION

【0001】[0001]

【発明の属する技術分野】本発明は、トンネル内に二次
覆工用のコンクリートを打設する方法および装置に関す
るものである。なお、本明細書中、「打設」とは、養生
硬化させていない泥状のコンクリートを型枠とトンネル
内壁面との間に充填させることをいう。
BACKGROUND OF THE INVENTION 1. Field of the Invention The present invention relates to a method and an apparatus for placing concrete for secondary lining in a tunnel. In addition, in this specification, "casting" refers to filling mud-like concrete that has not been cured and hardened between the formwork and the inner wall surface of the tunnel.

【0002】[0002]

【従来の技術】元来、トンネル内への二次覆工用のコン
クリートの打設は、コンクリート打設するための移動式
型枠を、コンクリート打設終了後、前方に折畳んで搬送
し、展開させて再び設置し、その個所でコンクリートを
打設する形式の移動式型枠により行われていた。
2. Description of the Related Art Originally, for concrete placement for secondary lining in a tunnel, a movable formwork for placing concrete is folded forward and transported after completion of concrete placement. It was developed using a movable formwork that was deployed, installed again, and cast concrete at that location.

【0003】また、移動式型枠とトンネル内壁面との間
へのコンクリート打設は、ラップ側(トンネル掘削側と
反対側)の下部、妻側(トンネル掘削側)の下部、ラッ
プ側の上部、妻側の上部へと順次打設するのが常であ
る。
In addition, concrete is placed between the movable formwork and the inner wall surface of the tunnel by a lower part on the lap side (opposite to the tunnel excavation side), a lower part on the wife side (tunnel excavation side), and an upper part on the lap side. , And is usually placed sequentially on the upper part of the wife's side.

【0004】このため、まずコンクリートの打設は、移
動式型枠の所定位置の検査窓を開放させてコンクリート
搬出口とし、コンクリート供給管に連結されたコンクリ
ート搬送管の先端をこの検査窓から突出させ、このコン
クリート搬送管の先端から移動式型枠とトンネル内壁面
との間に、コンクリートを充填する。
[0004] For this purpose, concrete is cast first by opening an inspection window at a predetermined position of a movable formwork to serve as a concrete carry-out port, and projecting a tip of a concrete transport pipe connected to a concrete supply pipe from the inspection window. Then, concrete is filled between the movable formwork and the inner wall surface of the tunnel from the tip of the concrete transport pipe.

【0005】次に、作業員がコンクリート充填位置より
下方の検査窓からコンクリート充填量を目視し、規定量
のコンクリートが充填された後、この検査窓を閉塞し、
別の検査窓へ移動し、検査窓の開放、コンクリート充填
量の目視、検査窓の閉塞、を行う。
Next, a worker visually checks the amount of concrete filling from an inspection window below the concrete filling position, and after a specified amount of concrete is filled, closes the inspection window.
Move to another inspection window, open the inspection window, visually check the concrete filling amount, and close the inspection window.

【0006】次に、所定個所でのコンクリート打設完了
後、別個所へコンクリートを打設するため、打設完了個
所の検査窓からコンクリート搬送管を収納し、別の位置
の検査窓をコンクリート搬出口として使用し、再び前記
同様作業によりコンクリートを打設する。
[0006] Next, after the concrete placement at a predetermined location is completed, the concrete transport pipe is stored from the inspection window at the location where the casting has been completed, and the inspection window at another position is transported to the concrete. It is used as an outlet, and concrete is cast again by the same operation as described above.

【0007】このコンクリートの搬送切替えは、コンク
リート搬送管を多数に分割し、別個所へ組替え配管させ
ることにより行っていた。
[0007] The concrete transport switching has been performed by dividing the concrete transport pipe into a large number and reassembling the concrete transport pipes to separate locations.

【0008】また、図10〜図12に示すように、コン
クリート打設個所は、移動式型枠の長さ方向の上下二個
所の計4個所のみから行っていた。
Further, as shown in FIGS. 10 to 12, concrete is cast from only four places, that is, two upper and lower places in the longitudinal direction of the movable formwork.

【0009】このため、移動式型枠の各個所(4個所)
におけるコンクリート打設時に、通常は打設したコンク
リートの締固め、およびコンクリート内に混在する気泡
の除去に使用する振動具の振動により、打設したコンク
リートを移動式型枠とトンネル内壁面との間へ均して充
填させていた。
For this reason, each part (four places) of the movable formwork
When placing concrete, the concrete placed between the movable formwork and the inner wall of the tunnel is usually compressed by compaction of the poured concrete and vibration of the vibrator used to remove air bubbles mixed in the concrete. To fill.

【0010】なお、図10〜図12中50は移動式型
枠、52はコンクリート供給管、54はコンクリート搬
送管、56は検査窓、58は振動具、60はコンクリー
ト、62はトンネル内壁面を示す。
In FIGS. 10 to 12, reference numeral 50 denotes a movable formwork, 52 denotes a concrete supply pipe, 54 denotes a concrete transport pipe, 56 denotes an inspection window, 58 denotes a vibrator, 60 denotes concrete, and 62 denotes an inner wall surface of the tunnel. Show.

【0011】[0011]

【発明が解決しようとする課題】従来、移動式型枠によ
るトンネル内壁面との間へのコンクリート打設におい
て、ラップ側の下部、妻側の下部、ラップ側の上部、妻
側の上部の計4個所へと順次、コンクリート搬送管を組
替え配管する作業が必要となり、その作業が非常に煩雑
であるばかりか、工期遅延の要因となっていた。
Conventionally, in placing concrete between a movable formwork and an inner wall surface of a tunnel, a total of a lower part on a lap side, a lower part on a wife side, an upper part on a lap side, and an upper part on a wife side. The work of rearranging the concrete transport pipes in order to four places was required, which was not only very complicated but also caused a delay in the construction period.

【0012】また、移動式型枠の4個所のみからコンク
リートを打設していたため、移動式型枠とトンネル内壁
面との間への充填するコンクリートが不均一となり、打
設コンクリートの品質が著しく低下することが問題とな
っていた。
Further, since concrete is cast from only four locations of the movable formwork, the concrete to be filled between the movable formwork and the inner wall surface of the tunnel becomes uneven, and the quality of the cast concrete is remarkable. It was a problem that it decreased.

【0013】本発明は、このような欠点に鑑み、コンク
リート搬送管の組替え配管作業を皆無とし、容易にコン
クリート搬送切替えが行え、工期を大幅に短縮すること
ができ、コンクリートを均一に、しかも高品質に打設す
ることができるトンネル用コンクリート打設方法および
その装置を提供することを目的とするものである。
In view of the above drawbacks, the present invention eliminates the need for any work to replace concrete transfer pipes, facilitates concrete transfer switching, greatly shortens the construction period, and makes concrete concrete uniform and high-priced. It is an object of the present invention to provide a method and an apparatus for placing concrete for a tunnel, which can be cast with high quality.

【0014】[0014]

【課題を解決するための手段】本発明は、トンネル内に
移動式型枠を使用して二次覆工用のコンクリートを打設
する方法および装置において、移動式型枠内に複数配設
されたコンクリート搬送管のうち使用するコンクリート
搬送管と、移動式型枠内に配設されたコンクリート供給
管とを、連結させた後、使用するコンクリート搬送管の
長さ方向の数個所に設けられた各コンクリート搬出管か
ら、コンクリート供給管から供給されたコンクリート
を、順次または同時に移動式型枠とトンネル内壁面との
間に打設することを特徴とするもの、または各コンクリ
ート搬送管の連結部分、およびコンクリート搬送管とコ
ンクリート搬出管との連結部分において、コンクリート
搬送管を三重構造とし、中部搬送管を内外部搬送管に対
して回動自在とし、各搬送管に穿孔させた各通孔を合致
させることによりコンクリートの搬送を可能とし、内外
部搬送管の各通孔を中部搬送管により通孔以外の個所に
て閉塞させることにより、コンクリートの搬送を閉止
し、各コンクリート搬送管および各コンクリート搬出管
へのコンクリートの搬送を制御することを特徴とするも
のである。
SUMMARY OF THE INVENTION The present invention relates to a method and an apparatus for placing concrete for secondary lining using a movable form in a tunnel. After connecting the concrete transfer pipe to be used among the concrete transfer pipes to be used and the concrete supply pipe disposed in the movable formwork, the concrete transfer pipe to be used was provided at several places in the length direction of the concrete transfer pipe to be used. From each concrete discharge pipe, concrete supplied from a concrete supply pipe is sequentially or simultaneously poured between a movable formwork and a tunnel inner wall surface, or a connection portion of each concrete transport pipe, And at the connecting portion between the concrete transfer pipe and the concrete discharge pipe, the concrete transfer pipe has a triple structure, and the middle transfer pipe is rotatable with respect to the inner and outer transfer pipes, The concrete can be transported by matching the through holes drilled in the transport pipe, and the concrete transport is closed by closing each through hole of the inner and outer transport pipes at locations other than the through holes by the middle transport pipe. It is characterized in that it is closed and controls the transfer of concrete to each concrete transfer pipe and each concrete discharge pipe.

【0015】[0015]

【発明の実施の形態】本発明に係るトンネル用コンクリ
ート打設装置は、トンネル12内に二次覆工用のコンク
リート14を打設するための移動式型枠16に装着され
るものであり、図1〜図9に示すように、以下の構成か
らなるものである。
DESCRIPTION OF THE PREFERRED EMBODIMENTS A concrete casting device for a tunnel according to the present invention is mounted on a movable formwork 16 for placing concrete 14 for secondary lining in a tunnel 12. As shown in FIGS. 1 to 9, it has the following configuration.

【0016】移動式型枠16のガントリー18上に複数
のコンクリート搬送管20、およびコンクリート供給管
22が、それぞれ配設されている。
A plurality of concrete transfer pipes 20 and concrete supply pipes 22 are provided on the gantry 18 of the movable formwork 16, respectively.

【0017】本例において、コンクリート搬送管20
は、移動式型枠16の上段に一個、移動式型枠16の両
側の中段、下段に各一個、の合計5個配設され、コンク
リート供給管22は移動式型枠16のラップ側(トンネ
ル掘削側と反対側)に一個配設されている。
In this embodiment, the concrete transport pipe 20
The concrete supply pipe 22 is provided on the lap side (tunnel) of the movable formwork 16, one at the upper stage of the movable formwork 16, and one each at the middle stage and the lower stage on both sides of the movable formwork 16. One on the side opposite to the excavation side).

【0018】各コンクリート搬送管20の長さ方向の数
個所にコンクリート搬出管24が設けられている。
Concrete discharge pipes 24 are provided at several points in the length direction of each concrete transfer pipe 20.

【0019】本例において、コンクリート搬出管24
は、各コンクリート搬送管20にそれぞれ五個ずつ設け
られている。
In this embodiment, the concrete discharge pipe 24
Are provided in each of the concrete transport pipes 20.

【0020】各コンクリート搬送管20とコンクリート
搬出管24との連結部分において、コンクリート搬送管
20を三重構造とし、中部搬送管26を内外部搬送管2
7,28に対して回動自在とし、各管26,27,28
にそれぞれコンクリート14を搬送するための通孔30
を穿孔させ、中部搬送管26により各通孔30を合致さ
せることにより、コンクリート14の搬送を可能とし、
また通孔30を合致させた内外部搬送管27,28の各
通孔30を中部搬送管26により通孔30以外の個所に
て閉塞させることにより、コンクリート14の搬送を閉
止し、コンクリート14の搬送を制御させてある。
At the connecting portion between each concrete transfer pipe 20 and the concrete discharge pipe 24, the concrete transfer pipe 20 has a triple structure, and the middle transfer pipe 26 is connected to the inner and outer transfer pipes 2.
7 and 28, and each pipe 26, 27, 28
Holes 30 for transporting concrete 14 respectively
And by allowing each of the through holes 30 to coincide with each other with the central transport pipe 26, the concrete 14 can be transported.
Further, by closing each of the through holes 30 of the inner and outer transfer pipes 27 and 28 in which the through holes 30 are matched with each other at positions other than the through holes 30 by the middle transfer pipe 26, the transfer of the concrete 14 is closed, and The transport is controlled.

【0021】この構造は、移動式型枠16の両側の中段
および下段の各コンクリート搬送管20の連結部分にも
採用されている。
This structure is also employed in the connecting portions of the concrete conveying pipes 20 in the middle and lower stages on both sides of the movable formwork 16.

【0022】また、中段および下段の各コンクリート搬
送管20の連結部分、およびコンクリート搬送管20と
コンクリート搬出管24との連結部分、の使用しないコ
ンクリート搬送管20内に、コンクリート14の搬送を
閉止するための閉止板32が挿脱自在にそれぞれ配設さ
れている。
In addition, the transport of the concrete 14 is closed in the concrete transport pipes 20 which are not used in the connecting portions of the concrete transport pipes 20 in the middle and lower stages and the connecting portion between the concrete transport pipes 20 and the concrete discharge pipes 24. Closing plates 32 are provided so that they can be inserted and removed.

【0023】この各閉止板32を各コンクリート搬送管
20内に挿入させ、コンクリート14の搬送を閉止する
ことにより、他のコンクリート搬送管20およびコンク
リート搬出管24へのコンクリート14の搬送を制御す
ることができる。
The transport of the concrete 14 to the other concrete transport pipes 20 and the concrete discharge pipe 24 is controlled by inserting the respective closing plates 32 into the respective concrete transport pipes 20 and closing the transport of the concrete 14. Can be.

【0024】また、コンクリート搬送管20およびコン
クリート供給管22の連結近部には、両管20,22内
に残留するコンクリート14を排出するための排出バル
ブ(図示略)が設けられている。
A discharge valve (not shown) for discharging the concrete 14 remaining in the two pipes 20 and 22 is provided near the connection between the concrete transport pipe 20 and the concrete supply pipe 22.

【0025】各コンクリート搬送管20とコンクリート
供給管22との間にコンクリート分流機34が配設され
ている。
A concrete diverter 34 is provided between each concrete transport pipe 20 and the concrete supply pipe 22.

【0026】本例において、コンクリート分流機34
は、基枠36の一側に複数のコンクリート搬送用連結管
38が並列に配設され、基枠36の他側にコンクリート
供給用連結管40が移動機構(図示略)等を介して移動
自在に配設されてなるものである。
In this embodiment, the concrete diverter 34
A plurality of concrete transport connecting pipes 38 are arranged in parallel on one side of the base frame 36, and a concrete supply connecting pipe 40 is movable on the other side of the base frame 36 via a moving mechanism (not shown) or the like. It is arranged in.

【0027】このコンクリート分流機34への各コンク
リート搬送管20およびコンクリート供給管22の連結
は、各コンクリート搬送管20をコンクリート搬送用連
結管38に、コンクリート供給管22をコンクリート供
給用連結管40に、ジョイント42を介してそれぞれ連
結させることにより行う。
The concrete transfer pipes 20 and the concrete supply pipes 22 are connected to the concrete diverter 34 by connecting the concrete transfer pipes 20 to the concrete transfer connection pipes 38 and the concrete supply pipes 22 to the concrete supply connection pipes 40. , Through a joint 42.

【0028】さらに、コンクリート供給管22の先端部
分をU字型に回動自在に二点支持させ、コンクリート供
給用連結管40との連結部分を含めて三点支持させるこ
とにより、各コンクリート搬送管20の連結切替え時
に、コンクリート供給管22の先端部分を上下左右動さ
せ、スムーズにコンクリート供給管22を移動させる配
慮がなされている。
Furthermore, the concrete supply pipe 22 is rotatably supported at two points in a U-shape at two points, and the concrete supply pipe 22 is supported at three points including the connection with the concrete supply connection pipe 40, so that each concrete transfer pipe is supported. At the time of connection switching of 20, the concrete supply pipe 22 is moved up and down and left and right so that the concrete supply pipe 22 is smoothly moved.

【0029】移動式型枠16には多数の検査窓44が設
けられており、この検査窓44はコンクリート打設口と
して使用され、または打設コンクリートの打設状況を確
認するために使用されるものである。
The movable formwork 16 is provided with a large number of inspection windows 44, and these inspection windows 44 are used as a concrete pouring port or used to check the state of the concrete being poured. Things.

【0030】なお、図中46は既二次覆工部、48は掘
削され、または一次覆工用のコンクリートが吹付けられ
たトンネル内壁面を示す。
In the drawing, reference numeral 46 denotes an existing secondary lining portion, and reference numeral 48 denotes an inner wall surface of a tunnel to which excavated or concrete for primary lining has been sprayed.

【0031】本装置を使用してトンネル12内に二次覆
工用のコンクリート14を打設する方法を以下に詳述す
る。
The method of placing the concrete 14 for secondary lining in the tunnel 12 using the present apparatus will be described in detail below.

【0032】まず、移動式型枠16をトンネル12の所
定位置まで移動させる。
First, the movable formwork 16 is moved to a predetermined position of the tunnel 12.

【0033】この際、移動式型枠16のラップ側(トン
ネル掘削側と反対側)は既二次覆工部46に重合させる
必要がある。
At this time, the wrap side (the side opposite to the tunnel excavation side) of the movable formwork 16 needs to be overlapped with the existing secondary lining portion 46.

【0034】次に、コンクリート搬送管20をコンクリ
ート分流機34により、移動式型枠16のラップ側の下
部へコンクリート14が充填されるように切替連結す
る。
Next, the concrete conveying pipe 20 is switched and connected by the concrete diverter 34 so that the concrete 14 is filled in the lower part of the movable formwork 16 on the wrap side.

【0035】本例においては、まず移動式型枠16の幅
方向の一側(図1において右側、図2において下側)の
下段に配設されたコンクリート搬送管20へコンクリー
ト14を搬送させ、次いで移動式型枠16の幅方向の他
側(図1において左側、図2において上側)の下段のコ
ンクリート搬送管20、次いで移動式型枠16の中段の
コンクリート搬送管20、次いで移動式型枠16の上段
のコンクリート搬送管20へと、順次コンクリート14
を搬送させる。
In this embodiment, first, concrete 14 is transported to a concrete transport pipe 20 arranged at a lower side of one side in the width direction of the movable formwork 16 (right side in FIG. 1, lower side in FIG. 2). Next, the lower concrete transport pipe 20 on the other side of the movable form 16 in the width direction (the left side in FIG. 1 and the upper side in FIG. 2), the middle concrete transport pipe 20 on the movable form 16 and then the movable form 16 to the concrete transport pipe 20 at the upper stage,
Is transported.

【0036】次に、コンクリート分流機34により切替
連結されたコンクリート搬送管20の各コンクリート搬
出管24のうち使用するコンクリート搬出管24との連
結部分において、コンクリート搬送管20の内外部搬送
管26,28の両通孔30を合致させることにより、コ
ンクリート14の搬送を可能とすると共に、コンクリー
ト搬送管20と使用するコンクリート搬出管24との連
結近部に閉止板32を挿入させ、他のコンクリート搬出
管24へのコンクリート14の搬送を閉止させ、コンク
リート14の搬送を制御する。
Next, at the portion of each concrete discharge pipe 24 of the concrete transport pipe 20 switched and connected by the concrete diverter 34 connected to the concrete discharge pipe 24 to be used, the inner and outer transport pipes 26, 28, the concrete 14 can be transported, and the closing plate 32 is inserted into the vicinity of the connection between the concrete transport pipe 20 and the concrete discharge pipe 24 to be used to carry out another concrete discharge. The transfer of the concrete 14 to the pipe 24 is closed, and the transfer of the concrete 14 is controlled.

【0037】次に、移動式型枠16の妻側周縁を確実に
被覆(妻止め)し、所定の検査窓44をコンクリート打
設口とし、この検査窓44から使用するコンクリート搬
出管24を突出させ、移動式型枠16とトンネル内壁面
48との間にコンクリート14を打設する。
Next, the periphery of the movable side of the movable formwork 16 is securely covered (stopped), and a predetermined inspection window 44 is used as a concrete pouring port. The concrete discharge pipe 24 to be used is projected from the inspection window 44. Then, the concrete 14 is cast between the movable formwork 16 and the inner wall surface 48 of the tunnel.

【0038】この際、コンクリート打設量に応じて、振
動具(図示略)を介して打設コンクリート14を振動さ
せ、締固めることにより、養生硬化後のコンクリートの
強度、耐久性を向上させることが望ましい。
At this time, the strength and durability of the concrete after curing and curing are improved by vibrating and compacting the poured concrete 14 via a vibrator (not shown) according to the amount of concrete poured. Is desirable.

【0039】次に、所定量のコンクリート14の打設完
了後、別の検査窓16から突出させた別のコンクリート
搬出管24からコンクリート14を打設する。
Next, after the concrete 14 is poured, the concrete 14 is poured from another concrete discharge pipe 24 protruding from another inspection window 16.

【0040】この際、コンクリート搬送管20と使用す
るコンクリート搬出管24との連結部分において、コン
クリート搬送管20の中部搬送管26を回動させ、中部
搬送管26および内外部搬送管27,28の各通孔30
を合致させることにより、コンクリート14の搬送を可
能とし、コンクリート搬送管20と使用するコンクリー
ト搬出管24との連結近部に閉止板32を挿入させ、他
のコンクリート搬出管24へのコンクリート14の搬送
を閉止させると共に、既打設済コンクリート搬出管24
とコンクリート搬送管20との連結部分において、コン
クリート搬送管20の内外部搬送管27,28の各通孔
30を中部搬送管26を回動させ、中部搬送管26の通
孔30以外の個所にて閉塞させることにより、コンクリ
ート14の搬送を閉止し、コンクリート14の搬送を制
御する。
At this time, at the connecting portion between the concrete transfer pipe 20 and the concrete discharge pipe 24 to be used, the middle transfer pipe 26 of the concrete transfer pipe 20 is rotated, and the middle transfer pipe 26 and the inner and outer transfer pipes 27 and 28 are rotated. Each through hole 30
And the concrete plate 14 can be transported, the closing plate 32 is inserted near the connection between the concrete transport pipe 20 and the concrete discharge pipe 24 to be used, and the concrete 14 is transported to another concrete discharge pipe 24. And the concrete discharge pipe 24
In the connection portion between the concrete transfer pipe 20 and the concrete transfer pipe 20, the through holes 30 of the inner and outer transfer pipes 27, 28 of the concrete transfer pipe 20 are rotated to the central transfer pipe 26, and are moved to locations other than the through holes 30 of the middle transfer pipe 26. The transport of the concrete 14 is closed by closing it, and the transport of the concrete 14 is controlled.

【0041】次に、このコンクリート搬送管20におけ
るコンクリート14の打設完了後、コンクリート分流機
34によりこのコンクリート搬送管20とコンクリート
供給管22との連結を解除し、他のコンクリート搬送管
20とを切替連結させ、順次コンクリート14を移動式
型枠16とトンネル内壁面48との間に打設する。
Next, after the concrete 14 is poured into the concrete transfer pipe 20, the connection between the concrete transfer pipe 20 and the concrete supply pipe 22 is released by the concrete diverter 34, and the other concrete transfer pipe 20 is connected. The concrete connection 14 is sequentially switched between the movable formwork 16 and the inner wall surface 48 of the tunnel.

【0042】次に、移動式型枠16が設置された個所の
コンクリート打設完了後、打設コンクリートの養生硬化
させ、移動式型枠16を脱型する。
Next, after the concrete casting at the location where the movable formwork 16 is installed is completed, the cast concrete is cured and hardened, and the movable formwork 16 is released.

【0043】この移動式型枠16の脱型により、トンネ
ル12内に二次覆工用のコンクリート14の打設が完了
する。
The removal of the movable formwork 16 completes the placement of the concrete 14 for secondary lining in the tunnel 12.

【0044】次に、移動式型枠16を前方へ移動させ、
コンクリート供給管22と使用するコンクリート搬送管
20の切替連結、使用するコンクリート搬出管24の切
替え、コンクリート14の打設、コンクリート14の養
生硬化、移動式型枠16の脱型、をトンネル12の全長
にわたり連続して行う。
Next, the movable formwork 16 is moved forward,
Switching the concrete supply pipe 22 and the concrete transport pipe 20 to be used, switching the concrete discharge pipe 24 to be used, placing the concrete 14, curing and curing the concrete 14, and removing the movable formwork 16 from the entire length of the tunnel 12. And continuously.

【0045】このように、コンクリート供給管22と使
用するコンクリート搬送管20との切替連結、およびコ
ンクリート搬送管20の使用するコンクリート搬出管2
4の切替え、が極めて容易に行うとこができ、従来のよ
うにコンクリート搬送管の組替え配管作業を行う必要が
なく、工期を大幅に短縮することが可能となる。
As described above, the switching connection between the concrete supply pipe 22 and the concrete transport pipe 20 to be used, and the concrete discharge pipe 2 used by the concrete transport pipe 20
4 can be switched very easily, and it is not necessary to perform the work of replacing the concrete transport pipe as in the conventional case, and it is possible to greatly shorten the construction period.

【0046】また、移動式型枠16の長さ方向におい
て、各コンクリート搬送管20に設けられた数個所のコ
ンクリート搬出管24からコンクリート14を打設する
ことができ、また使用するコンクリート搬送管20の各
コンクリート搬出管24から同時にコンクリート打設す
ることにより、工期をさらに短縮できると共に、移動式
型枠16とトンネル内壁面48との間にコンクリート1
4が均一に充填されるため、品質、特に強度を向上させ
ることができる。
In the lengthwise direction of the movable formwork 16, the concrete 14 can be poured from the concrete discharge pipes 24 provided at each concrete transfer pipe 20, and the concrete transfer pipe 20 to be used can be cast. By simultaneously placing the concrete from each of the concrete discharge pipes 24, the construction period can be further shortened, and the concrete 1 is placed between the movable formwork 16 and the inner wall surface 48 of the tunnel.
Since 4 is uniformly filled, the quality, particularly the strength, can be improved.

【0047】なお、本例において、各コンクリート搬送
管20の連結部分およびコンクリート搬送管20とコン
クリート搬出管24との連結部分において、コンクリー
ト搬送管20を三重構造とし、中部搬送管26および内
外部搬送管27,28の各通孔30を合致させることに
よりコンクリート14の搬送を可能とし、内外部搬送管
27,28の各通孔30を中部搬送管26により通孔3
0以外の個所にて閉塞させることにより、コンクリート
14の搬送を閉止するものであるが、コンクリート搬送
管20を三重構造とすることなく、使用しないコンクリ
ート搬送管20およびコンクリート搬出管24側に閉鎖
板(図示略)を挿入させてコンクリート14の搬送を制
御させてもよく、コンクリート14の搬送を制御できる
他の構造を採用することは自由である。
In this embodiment, the concrete transfer pipe 20 has a triple structure at the connection between the concrete transfer pipes 20 and the connection between the concrete transfer pipe 20 and the concrete discharge pipe 24. The concrete 14 can be transported by matching the through holes 30 of the pipes 27 and 28, and the through holes 30 of the inner and outer transport pipes 27 and 28 are connected to the through holes 3 by the middle transport pipe 26.
The transport of the concrete 14 is closed by closing at a location other than 0. However, the concrete transport pipe 20 is not formed in a triple structure, and the unused concrete transport pipe 20 and the concrete discharge pipe 24 are closed plates. (Not shown) may be inserted to control the transport of the concrete 14, and other structures capable of controlling the transport of the concrete 14 may be freely used.

【0048】また、コンクリート搬送管20および各コ
ンクリート搬送管20に設けられたコンクリート搬出管
24の個数は本例に限定されることはなく、取扱い易い
個数とすることは自由である。
Further, the number of the concrete transfer pipes 20 and the concrete discharge pipes 24 provided in each concrete transfer pipe 20 are not limited to the present embodiment, and may be freely set to a number that is easy to handle.

【0049】また、コンクリート分流機34は、基枠3
6の一側に複数のコンクリート搬送用連結管38が並列
に配設され、基枠36の他側にコンクリート供給用連結
管40が移動自在に配設されてなるものであるが、コン
クリート供給管22を使用するコンクリート搬送管20
へ連結させる構造のものであればよい。
Further, the concrete shunting machine 34 is
6, a plurality of connecting pipes 38 for transporting concrete are arranged in parallel on one side, and a connecting pipe 40 for supplying concrete is movably provided on the other side of the base frame 36. Concrete transfer pipe 20 using 22
Any structure may be used as long as it is connected to

【0050】また、コンクリート分流機34は移動式型
枠16上に一個のみ配設されているが、二個以上配設さ
せることにより、移動式型枠16とトンネル内壁面48
との間に複数個所、例えば移動式型枠16の両側の下
段、中段から同時にコンクリート14を打設させること
は自明である。
Although only one concrete diverter 34 is provided on the movable formwork 16, two or more concrete diverters 34 are disposed on the movable formwork 16 and the inner wall surface 48 of the tunnel.
It is self-evident that the concrete 14 is simultaneously poured from a plurality of places, for example, the lower stage and the middle stage on both sides of the movable formwork 16.

【0051】また、コンクリート搬送管20と各コンク
リート供給管22との切替連結は、コンクリート分流機
34によるものであるが、作業員が人手により切替連結
させることは自明である。
The switching connection between the concrete transport pipe 20 and the concrete supply pipes 22 is performed by the concrete diverter 34, but it is obvious that the switching connection is manually performed by an operator.

【0052】また、移動式型枠16とトンネル内壁面4
8との間へのコンクリート14の打設は、各検査窓44
からによるものであるが、検査窓44とは別に移動式型
枠16に形成されたコンクリート打設口(図示略)を利
用してコンクリート14を打設することは自明である。
The movable formwork 16 and the inner wall surface 4 of the tunnel
The concrete 14 is placed between the inspection windows 44 and
However, it is obvious that the concrete 14 is cast using the concrete casting port (not shown) formed in the movable formwork 16 separately from the inspection window 44.

【0053】また、移動式型枠16とトンネル内壁面4
8との間へのコンクリート打設量を感知するコンクリー
トセンサー(図示略)を設置し、コンクリートセンサー
のコンクリート打設量の感知により、コンクリート供給
管22からのコンクリート供給、停止、コンクリート搬
出管24からのコンクリート打設、コンクリート搬送管
20およびコンクリート搬出管24の切替、等を連動さ
せることにより、作業の自動化を図り、作業性を向上さ
せることができる。
The movable form 16 and the inner wall 4 of the tunnel
8, a concrete sensor (not shown) for detecting the amount of concrete placed between the concrete supply pipe 22 and the concrete discharge pipe 24 is provided. By linking the concrete casting, switching of the concrete transport pipe 20 and the concrete discharge pipe 24, etc., the work can be automated and workability can be improved.

【0054】また、本発明の方法および装置は、略半円
形のトンネル円形のトンネル、例えば海中トンネル、下
水道等、特に用途は限定されない。
The method and apparatus of the present invention are not particularly limited for use, such as a substantially semicircular tunnel, a circular tunnel, for example, an underwater tunnel and a sewer.

【0055】[0055]

【発明の効果】本発明に係るトンネル用コンクリート打
設方法およびその装置によれば、複数のコンクリート搬
送管のうち使用するコンクリート搬送管と、コンクリー
ト供給管とを、連結させた後、使用するコンクリート搬
送管の各コンクリート搬出管から、コンクリート供給管
から供給されたコンクリートを、順次または同時に移動
式型枠とトンネル内壁面との間に打設するため、従来行
っていた型枠上でのコンクリート搬送管の組替え配管作
業を皆無とし、工期を大幅に短縮することができる。
According to the method and the apparatus for placing concrete for a tunnel according to the present invention, the concrete transfer pipe to be used after the concrete transfer pipe to be used among the plurality of concrete transfer pipes is connected to the concrete supply pipe. The concrete transport from the concrete supply pipe from each concrete discharge pipe of the transport pipe is sequentially or simultaneously poured between the movable formwork and the inner wall surface of the tunnel. There is no need to replace pipes, and the construction period can be greatly reduced.

【0056】また、移動式型枠の長さ方向において、各
コンクリート搬送管に設けられた数個所のコンクリート
搬出管からコンクリートを打設することができ、また各
コンクリート搬出管から同時にコンクリート打設するこ
とにより、工期をさらに短縮できると共に、移動式型枠
とトンネル内壁面との間にコンクリートが均一に充填さ
れるため、品質、特に強度を向上させることができる。
Further, in the length direction of the movable formwork, concrete can be poured from several concrete discharge pipes provided in each concrete transport pipe, and concrete is simultaneously poured from each concrete discharge pipe. Thereby, the construction period can be further shortened, and concrete can be uniformly filled between the movable formwork and the inner wall surface of the tunnel, so that the quality, particularly the strength, can be improved.

【0057】また、各コンクリート搬送管の連結部分、
およびコンクリート搬送管とコンクリート搬出管との連
結部分において、コンクリート搬送管を三重構造とし、
中部搬送管を内外部搬送管に対して回動自在とし、各管
にそれぞれ通孔を穿孔させ、各通孔を合致させることに
よりコンクリートの搬送を可能とし、内外部搬送管の各
通孔を中部搬送管により通孔以外の個所にて閉塞させる
ことにより、コンクリートの搬送を閉止し、コンクリー
トの搬送を制御することにより、コンクリート搬送管お
よびコンクリート搬出管によるコンクリート搬送切替え
を極めて容易に行うことができる。
Further, a connecting portion of each concrete conveying pipe,
And at the connection between the concrete transfer pipe and the concrete discharge pipe, the concrete transfer pipe has a triple structure,
The center transport pipe is made rotatable with respect to the internal and external transport pipes, through holes are drilled in each pipe, and concrete can be transported by matching each through hole. It is very easy to switch concrete transport by concrete transport pipe and concrete discharge pipe by closing concrete transport by closing the part other than through hole by the central transport pipe and controlling concrete transport. it can.

【図面の簡単な説明】[Brief description of the drawings]

【図1】本発明に係るトンネル用コンクリート打設装置
の正面図。
FIG. 1 is a front view of a concrete casting device for a tunnel according to the present invention.

【図2】同、平面図。FIG. 2 is a plan view of the same.

【図3】コンクリート搬送管とコンクリート搬出管との
連結部分を示す縦断面図。
FIG. 3 is a longitudinal sectional view showing a connection portion between a concrete transport pipe and a concrete discharge pipe.

【図4】同、正面図。FIG. 4 is a front view of the same.

【図5】内部搬送管を示す、(イ)は平面図、(ロ)は
正面図、(ハ)は側面図。
5 (a) is a plan view, FIG. 5 (b) is a front view, and FIG. 5 (c) is a side view showing the internal transfer pipe.

【図6】外部搬送管を示す正面図。FIG. 6 is a front view showing an external transfer pipe.

【図7】中部搬送管を示す、(イ)は平面図、(ロ)は
正面図、(ハ)は側面図。
7 (a) is a plan view, FIG. 7 (b) is a front view, and FIG.

【図8】閉止板を示す、(イ)は正面図、(ロ)は側面
図。
8 (a) is a front view and FIG. 8 (b) is a side view showing a closing plate.

【図9】本発明によるコンクリート打設状況を示す略線
側面図。
FIG. 9 is a schematic side view showing a concrete casting situation according to the present invention.

【図10】従来のトンネル用コンクリート打設装置を示
す正面図。
FIG. 10 is a front view showing a conventional concrete placing device for a tunnel.

【図11】同、側面図。FIG. 11 is a side view of the same.

【図12】同、コンクリート打設状況を示す略線側面
図。
FIG. 12 is a schematic side view showing the concrete casting situation.

【符号の説明】[Explanation of symbols]

12 トンネル 14 コンクリート 16 移動式型枠 20 コンクリート搬送管 22 コンクリート供給管 24 コンクリート搬出管 26 中部搬送管 27 内部搬送管 28 外部搬送管 30 通孔 34 コンクリート分流機 48 トンネル内壁面 DESCRIPTION OF SYMBOLS 12 Tunnel 14 Concrete 16 Movable formwork 20 Concrete transport pipe 22 Concrete supply pipe 24 Concrete discharge pipe 26 Central transport pipe 27 Internal transport pipe 28 External transport pipe 30 Through hole 34 Concrete diverter 48 Tunnel inner wall surface

Claims (4)

【特許請求の範囲】[Claims] 【請求項1】 トンネル(12)内に移動式型枠(16)を使用
して二次覆工用のコンクリート(14)を打設する方法にお
いて、移動式型枠(16)内に複数配設されたコンクリート
搬送管(20)のうち使用するコンクリート搬送管(20)と、
移動式型枠(16)内に配設されたコンクリート供給管(22)
とを、連結させた後、使用するコンクリート搬送管(20)
の長さ方向の数個所に設けられた各コンクリート搬出管
(24)から、コンクリート供給管(22)から供給されたコン
クリート(14)を、順次または同時に移動式型枠(16)とト
ンネル内壁面(48)との間に打設することを特徴とするト
ンネル用コンクリート打設方法。
1. A method of placing concrete (14) for secondary lining using a movable formwork (16) in a tunnel (12), wherein a plurality of concrete forms (14) are arranged in the movable formwork (16). Concrete transport pipe (20) to be used among the installed concrete transport pipes (20),
Concrete supply pipe (22) installed in movable formwork (16)
After being connected, concrete transport pipe (20) to be used
Concrete discharge pipes installed at several locations along the length of the
(24), concrete (14) supplied from a concrete supply pipe (22) is sequentially or simultaneously poured between a movable formwork (16) and a tunnel inner wall surface (48). Concrete placement method for tunnels.
【請求項2】 各コンクリート搬送管(20)の連結部分、
およびコンクリート搬送管(20)とコンクリート搬出管(2
4)との連結部分において、コンクリート搬送管(20)を三
重構造とし、中部搬送管(26)を内外部搬送管(27),(28)
に対して回動自在とし、各搬送管(26),(27),(28)に穿
孔させた各通孔(30)を合致させることによりコンクリー
ト(14)の搬送を可能とし、内外部搬送管(27),(28)の各
通孔(30)を中部搬送管(26)により通孔(30)以外の個所に
て閉塞させることにより、コンクリート(14)の搬送を閉
止し、各コンクリート搬送管(20)および各コンクリート
搬出管(24)へのコンクリート(14)の搬送を制御すること
を特徴とする請求項1記載のトンネル用コンクリート打
設方法。
2. A connecting portion of each concrete conveying pipe (20),
And concrete transfer pipe (20) and concrete discharge pipe (2
At the connection with 4), the concrete transport pipe (20) has a triple structure, and the central transport pipe (26) is the inner and outer transport pipes (27), (28)
The concrete (14) can be transported by matching the through holes (30) perforated in the transport pipes (26), (27), and (28). By closing the through holes (30) of the pipes (27) and (28) at locations other than the through holes (30) with the central transport pipe (26), the transport of the concrete (14) is closed and the concrete 2. The concrete casting method for a tunnel according to claim 1, wherein the control of the transport of the concrete (14) to the transport pipe (20) and each concrete discharge pipe (24) is controlled.
【請求項3】 トンネル(12)内に移動式型枠(16)を使用
して二次覆工用のコンクリート(14)を打設する装置にお
いて、移動式型枠(16)内に、長さ方向の数個所にコンク
リート搬出管(24)を備えた複数のコンクリート搬送管(2
0)およびコンクリート供給管(22)がそれぞれ配設されて
なり、コンクリート供給管(22)と使用する所定のコンク
リート搬送管(20)とを連結させた後、使用するコンクリ
ート搬送管(20)の各コンクリート搬出管(24)から、コン
クリート供給管(22)から供給されたコンクリート(14)
を、順次または同時に移動式型枠(16)とトンネル内壁面
(48)との間に打設するトンネル用コンクリート打設装
置。
3. An apparatus for placing concrete (14) for secondary lining using a movable formwork (16) in a tunnel (12). Concrete transport pipes (2) with concrete discharge pipes (24) at several locations
0) and a concrete supply pipe (22) are arranged, respectively, and after connecting the concrete supply pipe (22) and a predetermined concrete transfer pipe (20) to be used, the concrete transfer pipe (20) to be used is Concrete (14) supplied from concrete supply pipe (22) from each concrete discharge pipe (24)
Sequentially or simultaneously with the movable formwork (16) and the inner wall of the tunnel
A concrete casting device for tunnels to be cast between (48).
【請求項4】 各コンクリート搬送管(20)の連結部分、
およびコンクリート搬送管(20)とコンクリート搬出管(2
4)との連結部分において、コンクリート搬送管(20)を三
重構造とし、中部搬送管(26)を内外部搬送管(27),(28)
に対して回動自在とし、各搬送管(26),(27),(28)に穿
孔させた各通孔(30)を合致させることによりコンクリー
ト(14)の搬送を可能とし、内外部搬送管(27),(28)の各
通孔(30)を中部搬送管(26)により通孔(30)以外の個所に
て閉塞させることにより、コンクリート(14)の搬送を閉
止し、各コンクリート搬送管(20)および各コンクリート
搬出管(24)へのコンクリート(14)の搬送を制御すること
を特徴とする請求項3記載のトンネル用コンクリート打
設装置。
4. A connecting portion of each concrete conveying pipe (20),
And concrete transfer pipe (20) and concrete discharge pipe (2
At the connection with 4), the concrete transport pipe (20) has a triple structure, and the central transport pipe (26) is the inner and outer transport pipes (27), (28)
The concrete (14) can be transported by matching the through holes (30) perforated in the transport pipes (26), (27), and (28). By closing the through holes (30) of the pipes (27) and (28) at locations other than the through holes (30) with the central transport pipe (26), the transport of the concrete (14) is closed and the concrete 4. The concrete placing device for a tunnel according to claim 3, wherein the concrete is transported to the transport pipe and each concrete discharge pipe.
JP2000257043A 2000-08-28 2000-08-28 Method and device for placing concrete for tunnel Pending JP2002070498A (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
JP2000257043A JP2002070498A (en) 2000-08-28 2000-08-28 Method and device for placing concrete for tunnel

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
JP2000257043A JP2002070498A (en) 2000-08-28 2000-08-28 Method and device for placing concrete for tunnel

Publications (1)

Publication Number Publication Date
JP2002070498A true JP2002070498A (en) 2002-03-08

Family

ID=18745568

Family Applications (1)

Application Number Title Priority Date Filing Date
JP2000257043A Pending JP2002070498A (en) 2000-08-28 2000-08-28 Method and device for placing concrete for tunnel

Country Status (1)

Country Link
JP (1) JP2002070498A (en)

Cited By (4)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
WO2003075753A1 (en) 2002-03-14 2003-09-18 Olympus Corporation Endoscope image processing apparatus
CN102061926A (en) * 2009-11-11 2011-05-18 中铁十八局集团有限公司 TBM tunneling and secondary lining synchronous construction method at mucking of continuous belt conveyor and trolley
CN106640134A (en) * 2016-12-08 2017-05-10 熊鹏 Secondary lining window-chasing mould-entering system
JP2020023797A (en) * 2018-08-06 2020-02-13 株式会社奥村組 Method for placing concrete used for lining on upper end portion of tunnel

Cited By (5)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
WO2003075753A1 (en) 2002-03-14 2003-09-18 Olympus Corporation Endoscope image processing apparatus
CN102061926A (en) * 2009-11-11 2011-05-18 中铁十八局集团有限公司 TBM tunneling and secondary lining synchronous construction method at mucking of continuous belt conveyor and trolley
CN106640134A (en) * 2016-12-08 2017-05-10 熊鹏 Secondary lining window-chasing mould-entering system
JP2020023797A (en) * 2018-08-06 2020-02-13 株式会社奥村組 Method for placing concrete used for lining on upper end portion of tunnel
JP7018615B2 (en) 2018-08-06 2022-02-14 株式会社奥村組 How to place the top of tunnel lining concrete

Similar Documents

Publication Publication Date Title
JP7018615B2 (en) How to place the top of tunnel lining concrete
CN110043287A (en) The circumferential slip form construction device and method of wholecircle tunnel concrete liner
CN111622783B (en) A device and method for pouring thin-walled concrete for long-segment double-lining inverted arch of a small-diameter tunnel
JP2002070498A (en) Method and device for placing concrete for tunnel
JP6994895B2 (en) Lining concrete placing system
CN212376671U (en) A thin-walled concrete pouring device for a small-diameter tunnel long-segment second-lined inverted arch
JP7076363B2 (en) How to place tunnel lining concrete
KR20190081405A (en) Vibrator for lining concrete of tunnel and mold apparatus using the same
CN111119945A (en) Tunnel secondary lining concrete pumping extrusion type pouring construction method
JP3127329B2 (en) Secondary lining concrete placing equipment and its construction method
JP2698750B2 (en) Tunnel lining material mixing and casting device and method
JPH11210393A (en) Method and device for placing concrete in tunnel construction
JP2001262986A (en) Concrete compacting method and device therefor
KR102788445B1 (en) Mold apparatus for lining concrete having distributor and construction method for tunnel using the same
JP2001012196A (en) Compacting method for arch concrete and arch center for placing concrete
JP2021055355A (en) Concrete placement method at top end part of tunnel and formwork equipment for tunnel lining
JP4505351B2 (en) Concrete formwork
JP3076897U (en) Concrete casting equipment for tunnels
JPH05179894A (en) Sliding formwork
JP7678990B2 (en) Lining concrete pouring method
KR20040008615A (en) method for shoting ready mixed concrete to a mold for construct concrete roadbed in a railway tunnel
KR20230145796A (en) Mold apparatus for lining concrete and construction method for tunnel using the same
JP7738843B2 (en) Lining concrete pouring device and lining concrete pouring method
JPH07139297A (en) Method for lining with invert concrete, and corner form and lining device used therefor
JP7241335B2 (en) Method for removing residual concrete in pipes

Legal Events

Date Code Title Description
A621 Written request for application examination

Free format text: JAPANESE INTERMEDIATE CODE: A621

Effective date: 20070725

A977 Report on retrieval

Free format text: JAPANESE INTERMEDIATE CODE: A971007

Effective date: 20090629

A131 Notification of reasons for refusal

Free format text: JAPANESE INTERMEDIATE CODE: A131

Effective date: 20090714

A02 Decision of refusal

Free format text: JAPANESE INTERMEDIATE CODE: A02

Effective date: 20100302