JP2631864B2 - Construction method of flat tunnel - Google Patents
Construction method of flat tunnelInfo
- Publication number
- JP2631864B2 JP2631864B2 JP63143583A JP14358388A JP2631864B2 JP 2631864 B2 JP2631864 B2 JP 2631864B2 JP 63143583 A JP63143583 A JP 63143583A JP 14358388 A JP14358388 A JP 14358388A JP 2631864 B2 JP2631864 B2 JP 2631864B2
- Authority
- JP
- Japan
- Prior art keywords
- ring
- segment
- prestress
- tunnel
- temporary support
- Prior art date
- Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
- Expired - Lifetime
Links
- 238000010276 construction Methods 0.000 title description 3
- 238000000034 method Methods 0.000 claims description 8
- 238000009412 basement excavation Methods 0.000 description 7
- 238000009434 installation Methods 0.000 description 4
- 230000000694 effects Effects 0.000 description 2
- 238000005516 engineering process Methods 0.000 description 2
- 239000004809 Teflon Substances 0.000 description 1
- 229920006362 Teflon® Polymers 0.000 description 1
- 230000002159 abnormal effect Effects 0.000 description 1
- 238000007796 conventional method Methods 0.000 description 1
- 239000002783 friction material Substances 0.000 description 1
- 230000002093 peripheral effect Effects 0.000 description 1
- 238000003908 quality control method Methods 0.000 description 1
Landscapes
- Lining And Supports For Tunnels (AREA)
Description
【発明の詳細な説明】 <産業上の利用分野> 本発明は偏平断面形状のシールドトンネルの施工方法
に関するものである。The present invention relates to a method for constructing a shield tunnel having a flat cross section.
<従来の技術> 従来から、偏平断面形状のシールドトンネル内でセグ
メントを組み立て、リングを形成した後にプレストレス
を導入し、セグメントのリング強度を得るタイプの偏平
トンネルの施工方法が存在する。<Prior Art> Conventionally, there is a method of constructing a flat tunnel of a type in which segments are assembled in a shield tunnel having a flat cross-sectional shape, a ring is formed, and then prestress is introduced to obtain ring strength of the segment.
<本発明が解決しようとする問題点> 通常の円形断面形状のトンネルと比較すると、偏平断
面形状のトンネルは、周囲の地山圧力の影響を受けてリ
ング形状が変形しやすいという欠点を有する。<Problems to be Solved by the Present Invention> Compared with a tunnel having a normal circular cross section, a tunnel having a flat cross section has a disadvantage that the ring shape is easily deformed under the influence of surrounding ground pressure.
上記の従来技術の場合、プレストレスを導入するまで
のセグメントのリング強度は、ボルト接合等によるため
継手部の強度が低い。In the case of the above-described conventional technology, the ring strength of the segment until the introduction of the prestress is low due to the bolt connection or the like, so that the strength of the joint is low.
この状態で地山圧力が作用すれば、セグメントは所定
のリング形状を保持できない。If ground pressure acts in this state, the segment cannot maintain a predetermined ring shape.
従って、地山圧力の作用しないシールドテール内でプ
レストレスを導入し、セグメントのリング強度が発現
し、地山圧力に抵抗できる状態になった後でなければシ
ールド機は前進できない。Therefore, a prestress is introduced in the shield tail where the ground pressure does not act, the ring strength of the segment is developed, and the shield machine can move forward only after the state where the ground pressure can be resisted.
その結果、セグメントのプレストレス導入が、シール
ドの掘進能率を低下させる原因となっている。As a result, the introduction of the prestress of the segment causes a decrease in the efficiency of shield excavation.
<本発明の目的> 本発明は上記のような問題点を解決するためになされ
たもので、シールドの掘進作業と、セグメントのプレス
トレス導入作業を独立して行い、セグメントのプレスト
レス導入作業に影響されることなく、シールドの掘進能
率を向上させることができる偏平トンネルの施工方法を
提供することを目的とする。<Object of the present invention> The present invention has been made in order to solve the above-described problems. The shield excavation work and the segment prestress introduction work are independently performed, and the segment prestress introduction work is performed. An object of the present invention is to provide a method of constructing a flat tunnel capable of improving the shield excavation efficiency without being affected.
<本発明の構成> 以下、図面を参照しながら本発明の一実施例について
説明する。Hereinafter, an embodiment of the present invention will be described with reference to the drawings.
なお、本実施例においては第1図に示すように、リン
グ内に鉛直方向に、3本の仮支柱2をほぼ等間隔で設置
した場合について説明する。In this embodiment, as shown in FIG. 1, a case will be described in which three temporary columns 2 are installed at substantially equal intervals in the vertical direction in the ring.
<イ>セグメントの組み立て 先ず従来の方法と同様に、シールド機で偏平断面形状
のトンネルの掘進を行いながら、シールドテール部内に
セグメント1のリングを組み立てる。<A> Segment assembly First, as in the conventional method, a ring of the segment 1 is assembled in the shield tail portion while excavating a tunnel having a flat cross-sectional shape with a shield machine.
このとき、後述の仮支柱2を設置するセグメント1の
内面には、テーパーシュー11が予め突設されている。At this time, a tapered shoe 11 is previously provided on the inner surface of the segment 1 on which the temporary support 2 to be described later is installed.
このテーパーシュー11は、トンネル軸と平行に設けら
れた突起体であり、テーパーシュー11の突出方向の長さ
をトンネルの切羽側に向かって次第に増加させ、テーパ
ー状に形成したものである。The tapered shoe 11 is a protrusion provided in parallel with the tunnel axis, and is formed in a tapered shape by gradually increasing the length of the tapered shoe 11 in the protruding direction toward the face of the tunnel.
また、テーパーシュー11のテーパー面は、テフロン等
の低摩擦材によって加工し、仮支柱2が摺動しやすく形
成してある。The tapered surface of the tapered shoe 11 is processed with a low-friction material such as Teflon, so that the temporary support column 2 is easily slid.
<ロ>仮支柱の設置 セグメント1のリングを組み立てた後、プレストレス
を導入する前に、仮支柱2をリング内に設置する。<B> Installation of temporary strut After assembling the ring of segment 1, before introducing prestress, temporary strut 2 is installed in the ring.
仮支柱2の設置数は、リングに作用する周囲の地山圧
力に十分抵抗できるように、計算によって求められた必
要数を設置する。The required number of temporary columns 2 is determined by calculation so as to sufficiently resist the surrounding ground pressure acting on the ring.
この仮支柱2は、第2図に示すように、板状体等の上
下両端面に、前述のテーパーシュー11と同じテーパー角
を有する溝21を刻設した構造である。As shown in FIG. 2, the temporary support 2 has a structure in which grooves 21 having the same taper angle as the above-described taper shoe 11 are formed on both upper and lower end surfaces of a plate-like body or the like.
そして、仮支柱2を設置する上下両端部近傍のセグメ
ント1に設けたテーパーシュー11に、仮支柱2の溝を嵌
合し、第2図に示すように切羽側に摺動させて所定の位
置で係止させる。Then, the groove of the temporary support 2 is fitted to the taper shoe 11 provided on the segment 1 near the upper and lower ends of the temporary support 2 and is slid toward the face as shown in FIG. To lock.
なお、仮支柱2の摺動用としてジャッキ(図示せず)
等を取り付け、また仮支柱2の固定設置用としてストッ
パ(図示せず)等を設けるとよい。A jack (not shown) for sliding the temporary support 2
And the like, and a stopper (not shown) or the like may be provided for fixedly installing the temporary support 2.
さらに、仮支柱2には、圧力センサ22や沈下量センサ
23を取り付けておくとよい。Further, the temporary support 2 has a pressure sensor 22 and a sink amount sensor.
It is good to attach 23.
<ハ>プレストレスの導入 全仮支柱2の設置が終了した後、シールド機を掘進さ
せ、上記と同様の手順でセグメント1の組み立て及び仮
支柱2の設置作業を進める。<C> Introduction of Prestress After the installation of all the temporary columns 2 is completed, the shield machine is excavated, and the assembly of the segment 1 and the installation of the temporary columns 2 are advanced in the same procedure as described above.
そしてシールド機の掘進と同時に、シールド機の後方
のセグメント1のリングにおいては、公知の方法でプレ
ストレスの導入作業を行う。At the same time as the excavation of the shield machine, a prestress introduction operation is performed in a ring of the segment 1 behind the shield machine by a known method.
<ニ>仮支柱の撤去 プレストレスを導入し、セグメント1のリングが所定
の強度を発現した後、全仮支柱2をテーパーシュー11を
切羽と反対側に摺動させて撤去する。<D> Removal of Temporary Props After prestress is introduced and the ring of the segment 1 exhibits a predetermined strength, all the temporary supports 2 are removed by sliding the tapered shoe 11 to the side opposite to the face.
以上の作業を繰り返し行い、偏平トンネルの施工を完
了する。The above operation is repeated to complete the construction of the flat tunnel.
<作用> 本発明は、リング内に設置した仮支柱2の支持力によ
って、リングに作用する周囲の地山圧力に十分抵抗する
ことができる。<Operation> The present invention can sufficiently resist the surrounding ground pressure acting on the ring by the supporting force of the temporary support column 2 installed in the ring.
そのため、リングにプレストレスを導入する以前にシ
ールド機を掘進させ、リングをシールド機後方の地山内
に残しておいても、リングの所要の断面形状を確保でき
るという作用を有する。Therefore, even if the shield machine is dug before the prestress is introduced into the ring and the ring is left in the ground behind the shield machine, the required cross-sectional shape of the ring can be secured.
<その他の実施例> 以上の実施例の他に、第3図に示すような小口径のト
ンネルの場合には、仮支柱2を中央部の一ケ所に設置す
れば足りる場合もあり、また、第4図に示すような縦長
の偏平トンネルにおいても、上記と同様の方法で良好な
施工を行うことができる。<Other Embodiments> In addition to the above embodiments, in the case of a small-diameter tunnel as shown in FIG. 3, it may be sufficient to install the temporary strut 2 at one location in the center. In a vertically long flat tunnel as shown in FIG. 4, good construction can be performed in the same manner as described above.
また、仮支柱2はリングの内周面間を支持し、周囲の
地山圧力に抵抗するためのものであるから、水平方向に
設置することも当然考えられる。In addition, since the temporary support 2 is provided to support the space between the inner peripheral surfaces of the ring and resist the surrounding ground pressure, it is naturally conceivable to install the temporary support 2 in the horizontal direction.
例えば第5図に示すように、縦横方向に仮支柱2を設
置する場合も考えられる。For example, as shown in FIG. 5, there may be a case where temporary columns 2 are installed in the vertical and horizontal directions.
さらに、仮支柱2のその他の構造としては、上下方向
の長さをジャッキ等で伸縮可能に構成し、仮支柱2の設
置、撤去作業が容易に行える構造も考えられる。Further, as another structure of the temporary support 2, a structure in which the length of the temporary support 2 can be extended and contracted by a jack or the like so that the provisional support 2 can be easily installed and removed can be considered.
<本発明の効果> 本発明は以上説明したようになるので、次のような効
果を期待することができる。<Effects of the Present Invention> Since the present invention has been described above, the following effects can be expected.
<イ>従来技術の場合、地山圧力の作用しないシールド
テール内でプレストレスを導入し、セグメントのリング
強度が発現し、地山圧力に抵抗できる状態になった後で
なければシールド機は前進できないため、セグメントの
プレストレス導入が、シールドの掘進能率を低下させる
原因となっている。<B> In the case of the conventional technology, the pre-stress is introduced into the shield tail where the ground pressure does not act, the ring strength of the segment is developed, and the shield machine moves forward only after it is in a state where it can resist the ground pressure. Because of this, the introduction of prestressing of the segments has reduced the efficiency of shield excavation.
それに対して本発明は、セグメントの組み立て後プレ
ストレスの導入前に、リング内周間を仮支柱によって支
持する方法である。On the other hand, the present invention is a method of supporting the inner circumference of the ring with a temporary support after assembling the segments and before introducing the prestress.
そのため、シールドテール後方にセグメントを組み立
てた場合においても、仮支柱の支持力によって周囲の地
山圧力に十分抵抗でき、リングの所要の断面形状を確保
しながらプレストレスを行うことができる。Therefore, even when the segments are assembled behind the shield tail, it is possible to sufficiently resist the surrounding ground pressure by the supporting force of the temporary support, and to perform the prestress while securing the required cross-sectional shape of the ring.
従って、シールドの掘進作業と、セグメントのプレス
トレス導入作業を独立して行うことができ、セグメント
のプレストレス導入作業に影響されることなく、シール
ドの掘進能率を向上させることができる。Therefore, the shield excavation work and the segment prestress introduction work can be performed independently, and the shield excavation efficiency can be improved without being affected by the segment prestress introduction work.
<ロ>セグメントのプレストレス導入作業を、シールド
機の後方で独立して行うことができるため、プレストレ
スの導入作業に十分な作業時間をとることができる。<B> Since the pre-stress introduction work of the segment can be performed independently behind the shield machine, sufficient work time can be taken for the pre-stress introduction work.
そのため、セグメントのリングの品質管理または、作
業の安全上従来と比較すると有利である。For this reason, it is advantageous in terms of quality control of the ring of the segment or work safety as compared with the related art.
<ハ>仮支柱によりセグメントのリングの所要の断面形
状を保持しながら、プレストレスを導入することができ
る。<C> Prestress can be introduced while the required cross-sectional shape of the segment ring is maintained by the temporary support.
そのため、変形のない断面形状のトンネルを構築する
ことができる。Therefore, it is possible to construct a tunnel having a sectional shape without deformation.
<ニ>プレストレスの導入時以外にセグメントリングに
異常荷重が作用した場合でも、仮支柱によって荷重を支
持することができるため、リングの変形を防止すること
ができる。<D> Even if an abnormal load is applied to the segment ring other than when the prestress is introduced, the load can be supported by the temporary support, so that deformation of the ring can be prevented.
第1図:本発明の一実施例の説明図 第2図:仮支柱の設置説明図 第3〜5図:その他の実施例の説明図 Fig. 1: Explanatory drawing of one embodiment of the present invention Fig. 2: Explanatory drawing of installation of temporary supports Fig. 3-5: Explanatory drawing of other embodiments
Claims (1)
メントを組み立て、リングを形成した後にプレストレス
を導入して行う偏平トンネルの施工方法において、 セグメント内周面にはテーパーシューを設けておき、セ
グメントを組み立てた後に、前記テーパーシューと嵌合
する溝を設けた仮支柱を、その溝をテーパーシューと嵌
合させて配置し、 次にプレストレスを導入し、所定のリング強度が生じた
後に仮支柱を撤去して行うことを特徴とする、 偏平トンネルの施工方法。1. A method for constructing a flat tunnel in which a segment is assembled in a shield tunnel having a flat cross-sectional shape, a ring is formed, and then a prestress is introduced. After assembling, a temporary support provided with a groove to be fitted with the tapered shoe is arranged by fitting the groove to the tapered shoe, and then a prestress is introduced, and after a predetermined ring strength is generated, the temporary support is temporarily provided. A method for constructing a flat tunnel, comprising removing a support post.
Priority Applications (1)
| Application Number | Priority Date | Filing Date | Title |
|---|---|---|---|
| JP63143583A JP2631864B2 (en) | 1988-06-13 | 1988-06-13 | Construction method of flat tunnel |
Applications Claiming Priority (1)
| Application Number | Priority Date | Filing Date | Title |
|---|---|---|---|
| JP63143583A JP2631864B2 (en) | 1988-06-13 | 1988-06-13 | Construction method of flat tunnel |
Publications (2)
| Publication Number | Publication Date |
|---|---|
| JPH01312196A JPH01312196A (en) | 1989-12-15 |
| JP2631864B2 true JP2631864B2 (en) | 1997-07-16 |
Family
ID=15342112
Family Applications (1)
| Application Number | Title | Priority Date | Filing Date |
|---|---|---|---|
| JP63143583A Expired - Lifetime JP2631864B2 (en) | 1988-06-13 | 1988-06-13 | Construction method of flat tunnel |
Country Status (1)
| Country | Link |
|---|---|
| JP (1) | JP2631864B2 (en) |
Families Citing this family (4)
| Publication number | Priority date | Publication date | Assignee | Title |
|---|---|---|---|---|
| US9589565B2 (en) | 2013-06-21 | 2017-03-07 | Microsoft Technology Licensing, Llc | Environmentally aware dialog policies and response generation |
| US9311298B2 (en) | 2013-06-21 | 2016-04-12 | Microsoft Technology Licensing, Llc | Building conversational understanding systems using a toolset |
| US9529794B2 (en) | 2014-03-27 | 2016-12-27 | Microsoft Technology Licensing, Llc | Flexible schema for language model customization |
| CN106089267A (en) * | 2016-06-30 | 2016-11-09 | 中交航局第四工程有限公司 | Excavator auxiliary steel arch-shelf mounting process |
Family Cites Families (1)
| Publication number | Priority date | Publication date | Assignee | Title |
|---|---|---|---|---|
| JPH0791957B2 (en) * | 1988-05-16 | 1995-10-09 | 前田建設工業株式会社 | Construction method of separated pillars in shield tunnel with composite section |
-
1988
- 1988-06-13 JP JP63143583A patent/JP2631864B2/en not_active Expired - Lifetime
Also Published As
| Publication number | Publication date |
|---|---|
| JPH01312196A (en) | 1989-12-15 |
Similar Documents
| Publication | Publication Date | Title |
|---|---|---|
| JP3285261B2 (en) | Precast formwork for tunnel lining | |
| JP2631864B2 (en) | Construction method of flat tunnel | |
| JP3793955B2 (en) | Multiple support construction method | |
| JPS6314997A (en) | Method of constructing tunnel | |
| CN221857751U (en) | A pipe jacking correction device | |
| JPH07119549B2 (en) | Twin tunnel | |
| JP3270660B2 (en) | Column structure in underground structure | |
| JPH10121576A (en) | Fixing structure of pedestal | |
| JPH05179647A (en) | Supporting structure for earth retaining wall | |
| JP3780847B2 (en) | Tie rod method | |
| JP3772246B2 (en) | Seismic isolation method for existing buildings | |
| JPH07119548B2 (en) | Reinforcement structure of eyeglass type tunnel | |
| JP2597298B2 (en) | Preceding method for the ground in front of the tunnel face | |
| JPH08291700A (en) | Shield segment | |
| CN220621888U (en) | Guiding positioning and supporting structure for construction pipe shed in tunnel hole | |
| JP3227959B2 (en) | Anchor frame | |
| JP4647396B2 (en) | Bending strength strengthening method for upper end of foundation pile or upper and lower ends of pillar of existing structure | |
| JPH05133194A (en) | Construction method of split vertical elliptical shield tunnel | |
| JPH10252068A (en) | How to install a retaining shoring | |
| JPH0742155A (en) | Construction method of girder and length adjustment mechanism of girder in girder dam stop method | |
| JPS60148993A (en) | Tunnel drilling construction method | |
| JP3680952B2 (en) | Cast-in-place concrete pile | |
| JP3335453B2 (en) | Tunnel wall | |
| JP2838091B2 (en) | Double section shield tunnel lining structure | |
| JPS59141695A (en) | Contstruction of tunnel in ground inferior place |