Equipment for joining steel pipe piles and foundation beamsInfo
- Publication number
- JP3142685B2 JP3142685B2 JP05143266A JP14326693A JP3142685B2 JP 3142685 B2 JP3142685 B2 JP 3142685B2 JP 05143266 A JP05143266 A JP 05143266A JP 14326693 A JP14326693 A JP 14326693A JP 3142685 B2 JP3142685 B2 JP 3142685B2
- Authority
- JP
- Japan
- Prior art keywords
- steel pipe
- pile
- bundle
- pipe pile
- pile head
- Prior art date
- Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
- Expired - Fee Related
Links
Landscapes
- Foundations (AREA)
Description
【0001】[0001]
【産業上の利用分野】この発明は鋼管杭に対して位置決
めした状態で基礎梁を接合する、鋼管杭と基礎梁の接合
装置に関するものである。BACKGROUND OF THE INVENTION 1. Field of the Invention The present invention relates to an apparatus for joining a steel pipe pile and a foundation beam in a state of being positioned with respect to the steel pipe pile.
【0002】[0002]
【従来技術及び発明が解決しようとする課題】独立基礎
を杭に支持させる杭基礎において、設置済みの鋼管杭に
対して基礎梁を接合する場合、従来は図10に示すように
杭頭回りに鉄筋コンクリート造の独立基礎を構築し、そ
の天端に基礎梁を載せ、下端をアンカーボルトに接続す
ることによって鋼管杭に接合している。2. Description of the Related Art In a pile foundation for supporting an independent foundation on a pile, when a foundation beam is joined to an installed steel pipe pile, conventionally, as shown in FIG. An independent foundation made of reinforced concrete is constructed, a foundation beam is placed on the top, and the lower end is connected to an anchor bolt by connecting it to a steel pipe pile.
【0003】この、基礎梁をコンクリート造の独立基礎
上に載せる方法では杭芯に対して束の位置をずらすこと
により鋼管杭の平面上の施工誤差を吸収することはでき
るが、基礎梁が独立基礎の構築後にその上に載せられる
ため基礎梁のレベルを調整することが難しく、また独立
基礎のコンクリートが硬化するまでは作業を進めること
ができない。In this method of placing the foundation beam on a concrete independent foundation, it is possible to absorb the construction error on the plane of the steel pipe pile by shifting the position of the bundle with respect to the pile core, but the foundation beam is independent. It is difficult to adjust the level of the foundation beam because it is placed on it after the foundation has been built, and work cannot proceed until the concrete of the independent foundation has hardened.
【0004】この発明は従来の鋼管杭と基礎梁の接合方
法に着目してなされたもので、基礎梁のレベル調整が行
え、作業の中断を要しない接合装置を提案しようとする
ものである。The present invention has been made by paying attention to a conventional method of joining a steel pipe pile and a foundation beam, and an object of the invention is to propose a joining apparatus which can adjust the level of the foundation beam and does not require interruption of work.
【0005】[0005]
【課題を解決するための手段】本発明では独立基礎を構
成し、下端にベースプレートが一体化した束材に基礎梁
を接続すると同時に、鋼管杭の頭部に杭頭金物を接続
し、杭頭金物にベースプレートを支持するレベル調整ボ
ルトを螺合することにより基礎梁のレベル調整を行い、
また基礎梁の接合が終了するまでの間の基礎梁の荷重を
レベル調整ボルトに負担させることにより作業の中断を
回避する。According to the present invention, an independent foundation is constructed, a foundation beam is connected to a bundle member having an integrated base plate at a lower end, and a pile head metal is connected to a head of a steel pipe pile. Adjust the level of the foundation beam by screwing the level adjustment bolt that supports the base plate to the object,
In addition, by suspending the load of the foundation beam to the level adjustment bolt until the joining of the foundation beam is completed, interruption of the work is avoided.
【0006】束材の下端にはベースプレートと共に、こ
れに外接する環状部材が一体化し、束材、すなわち基礎
梁は環状部材内に充填されるグラウト材によって鋼管杭
に接合される。環状部材はレベル調整ボルトを包囲し、
レベル調整ボルトに対して水平面内で位置決めされるこ
とにより鋼管杭に対する束材の平面上の施工誤差を吸収
する。At the lower end of the bundle, a base plate and an annular member circumscribing the base plate are integrated, and the bundle, that is, the foundation beam, is joined to the steel pipe pile by a grout material filled in the annular member. An annular member surrounds the level adjustment bolt,
Positioning the level adjusting bolts in the horizontal plane absorbs construction errors of the bundles on the steel pipe pile on the plane.
【0007】レベル調整ボルトは杭頭金物に軸を鉛直に
向けて螺合し、束材下端のベースプレートを支持するこ
とによりそのレベルを鋼管杭に対して調整し、また基礎
梁を鋼管杭に接合するグラウト材が硬化するまでの基礎
梁の鉛直荷重と水平荷重を負担し、鋼管杭に伝達する。
レベル調整ボルトが施工時の基礎梁と束材の荷重を鋼管
杭に伝達することにより仮支持用の部材を要することな
く、束材と鋼管杭の接合後の、基礎梁とその上載荷重を
鋼管杭に伝達するグラウト材の充填が行え、作業の中断
が回避され、工期の短縮化が図られる。The level adjusting bolt is screwed into the pile head metal so that the shaft is oriented vertically, and the level is adjusted with respect to the steel pipe pile by supporting the base plate at the lower end of the bundle, and the foundation beam is joined to the steel pipe pile. The vertical load and horizontal load of the foundation beam until the grout hardens are transferred and transmitted to the steel pipe pile.
The level adjustment bolt transfers the load of the foundation beam and the bundle at the time of construction to the steel pipe pile, so that the temporary beam and the overburden after joining the bundle and the steel pipe pile can be transferred to the steel pipe without the need for temporary support members. The grout material transmitted to the pile can be filled, work interruption can be avoided, and the construction period can be shortened.
【0008】[0008]
【実施例】以下本発明を一実施例を示す図面に基づいて
説明する。DESCRIPTION OF THE PREFERRED EMBODIMENTS The present invention will be described below with reference to the drawings showing one embodiment.
【0009】この発明の接合装置1は図1に示すように
下端にベースプレート21とこれに外接する環状部材22が
一体化し、基礎梁6が接続する束材2と、鋼管杭7の頭
部に上に載り、これに接続される杭頭金物3と、杭頭金
物3に軸を鉛直に向けて螺合し、束材2のベースプレー
ト21を支持し、束材2のレベルを調整するレベル調整ボ
ルト4と、環状部材22内に充填され、束材2を鋼管杭7
に接合するグラウト材5とから構成され、基礎梁6の水
平面内の位置とレベルを鋼管杭7に対して調整しながら
両者を接合するものである。As shown in FIG. 1, the joining device 1 of the present invention has a base plate 21 and an annular member 22 circumscribing the base plate 21 integrated at the lower end, and a bundle 2 to which the foundation beam 6 is connected, and a head of the steel pipe pile 7. A pile head metal piece 3 to be mounted on and connected to the pile head metal piece 3 and screwed in such a manner that the shaft is vertically oriented to the pile head metal piece 3 to support the base plate 21 of the bundle material 2 and adjust the level of the bundle material 2. Bolt 4 and ring member 22 filled in annular member 22 and bundle 2
And a grout material 5 joined to the steel pipe pile 7 while adjusting the position and level of the foundation beam 6 in the horizontal plane with respect to the steel pipe pile 7.
【0010】杭頭金物3は鋼管杭7の頭部を適当な高さ
で切断し、杭頭回りの地盤を掘削し、ドライモルタル8
で均した後に設置され、杭頭金物3に螺合したレベル調
整ボルト4を回し、その頭部のレベルを所定の高さに調
整した後に、基礎梁6が接続した束材2がレベル調整さ
れた状態で設置される。束材2のベースプレート21はレ
ベル調整ボルト4上に載置され、環状部材22がレベル調
整ボルト4に外接する範囲内で、束材2のレベル調整ボ
ルト4に対する平面上の位置決めが行われる。The pile head metal 3 cuts the head of the steel pipe pile 7 at an appropriate height, excavates the ground around the pile head, and
After the level adjustment bolt 4 screwed to the pile head metal 3 is turned to adjust the level of the head to a predetermined height, the level of the bundle 2 to which the foundation beam 6 is connected is adjusted. It is installed in the state where it was set. The base plate 21 of the bundle 2 is placed on the level adjusting bolts 4, and positioning of the bundle 2 with respect to the level adjusting bolts 4 is performed within a range where the annular member 22 circumscribes the level adjusting bolts 4.
【0011】レベル調整ボルト4はまた、鋼管杭7に接
続した杭頭金物3に螺合することによりグラウト材5の
充填までの基礎梁6の鉛直荷重を鋼管杭7に伝達し、グ
ラウト材5の硬化後には頭部がグラウト材5中に定着さ
れることにより基礎梁6からの鉛直上向きの力(引き抜
き力)を鋼管杭8に伝達する働きをする。The level adjusting bolt 4 also transfers the vertical load of the foundation beam 6 up to the filling of the grout material 5 to the steel pipe pile 7 by being screwed into the pile head metal 3 connected to the steel pipe pile 7. After hardening, the head is fixed in the grout material 5 so as to transmit a vertically upward force (pulling force) from the foundation beam 6 to the steel pipe pile 8.
【0012】レベル調整ボルト4上への束材2の設置と
その位置の調整後、環状部材22の下端と、先行して充填
されたドライモルタル8間の隙間をドライモルタル9で
目止めし、環状部材22内にその一部に明けられた開口か
らコンクリートやモルタル等のグラウト材5を充填し、
その硬化によって基礎梁6と鋼管杭7の接合が完了す
る。After the installation of the bundle 2 on the level adjusting bolt 4 and the adjustment of its position, the gap between the lower end of the annular member 22 and the previously filled dry mortar 8 is filled with dry mortar 9, A grout material 5 such as concrete or mortar is filled into the annular member 22 through an opening made in a part thereof,
By the hardening, the joining of the foundation beam 6 and the steel pipe pile 7 is completed.
【0013】図1,図2は杭頭金物3に、下端にアンカ
ープレート11が接続したアンカー筋10を接続し、アンカ
ー筋10とアンカープレート11を鋼管杭7の頭部内に充填
されるグラウト材12中に定着させることによって杭頭金
物3を鋼管杭7に接続した場合の実施例を示したもので
ある。FIG. 1 and FIG. 2 show an example in which an anchor bar 10 having an anchor plate 11 connected to a lower end thereof is connected to a pile head metal 3, and the anchor bar 10 and the anchor plate 11 are filled in the head of the steel pipe pile 7. This shows an embodiment in which the pile head metal 3 is connected to the steel pipe pile 7 by being fixed in the material 12.
【0014】この実施例では基礎梁6や束材2が受ける
鉛直荷重はベースプレート21からグラウト材5に伝達さ
れ、グラウト材5の圧縮力によって杭頭金物3に伝達さ
れ、鋼管杭7に伝達される。グラウト材5の強度発現ま
での鉛直荷重は基礎梁6と束材2のみであることから、
上記の通り、レベル調整ボルト4の圧縮力によって鋼管
杭7に伝達される。In this embodiment, the vertical load applied to the foundation beam 6 and the bundle 2 is transmitted from the base plate 21 to the grout 5, transmitted to the pile head metal 3 by the compressive force of the grout 5, and transmitted to the steel pipe pile 7. You. Since the vertical load until the strength development of the grout material 5 is only the foundation beam 6 and the bundle material 2,
As described above, the power is transmitted to the steel pipe pile 7 by the compression force of the level adjustment bolt 4.
【0015】基礎梁6や束材2からの引き抜き力は環状
部材22の内周に接合されたシアリブ23からグラウト材5
に伝達され、グラウト材5のせん断力によってレベル調
整ボルト4に伝達され、その引張力によって杭頭金物3
に伝達される。更に杭頭金物3のアンカー筋10とグラウ
ト材12間の付着力によって鋼管杭7へ伝達される。この
実施例では引き抜き力はレベル調整ボルト4の頭部の下
面に作用する支圧力によって引張力に変換されるためレ
ベル調整ボルト4は図3〜図6に示す実施例より大型に
なっている。The pulling force from the foundation beam 6 and the bundle 2 is controlled by the shear rib 23 joined to the inner periphery of the annular member 22 from the grout 5.
Is transmitted to the level adjusting bolt 4 by the shearing force of the grout material 5, and the pile head metal 3 is transmitted by the tensile force.
Is transmitted to Further, it is transmitted to the steel pipe pile 7 by the adhesive force between the anchor bar 10 of the pile head metal 3 and the grout material 12. In this embodiment, the pull-out force is converted into a tensile force by the supporting force acting on the lower surface of the head of the level adjusting bolt 4, so that the level adjusting bolt 4 is larger than the embodiments shown in FIGS.
【0016】また基礎梁6や束材2からの水平力は環状
部材22からグラウト材5に伝達され、グラウト材5の圧
縮力によってレベル調整ボルト4から杭頭金物3へ、更
にアンカー筋10から鋼管杭7へ伝達される。グラウト材
5が硬化するまではベースプレート21とレベル調整ボル
ト4間の摩擦力によって杭頭金物3へ伝達され、杭頭金
物3からはその下面に突設され、鋼管杭7に内接する突
起31によって鋼管杭7へ伝達される。The horizontal force from the foundation beam 6 and the bundle 2 is transmitted from the annular member 22 to the grout 5, and the compressive force of the grout 5 causes the level adjusting bolt 4 to move to the pile head metal 3 and further from the anchor bar 10. It is transmitted to the steel pipe pile 7. Until the grout material 5 is hardened, the frictional force between the base plate 21 and the level adjustment bolt 4 is transmitted to the pile head metal 3, and from the pile head metal 3, a projection 31 is provided on the lower surface thereof and is inscribed in the steel pipe pile 7. It is transmitted to the steel pipe pile 7.
【0017】図3,図4は上記実施例の環状部材22の径
を杭頭金物3を包囲する大きさにし、杭頭金物3をグラ
ウト材5中に埋設して定着させることにより束材2と杭
頭金物3を接合した場合の実施例である。ここでは杭頭
金物3がグラウト材5中に定着されることから、杭頭金
物3の平面積を鋼管杭7の外径より大きくし、外周を鋼
管杭7の外周より突出させることにより図1の実施例に
おけるレベル調整ボルト4に代わり、杭頭金物3自身の
定着強度が期待できるためレベル調整ボルト4は小型化
されている。基礎梁6や束材2からの引き抜き力は杭頭
金物3の、鋼管杭7から外周に張り出した部分の支圧力
によって鋼管杭7に伝達される。FIG. 3 and FIG. 4 show that the diameter of the annular member 22 of the above embodiment is set to a size surrounding the pile head metal 3 and the pile head metal 3 is buried in the grout material 5 to be fixed. This is an embodiment in the case where the pile head metal 3 is joined to the pile head. Here, since the pile head metal 3 is fixed in the grout material 5, the plane area of the pile head metal 3 is made larger than the outer diameter of the steel pipe pile 7 and the outer periphery is projected from the outer periphery of the steel pipe pile 7 as shown in FIG. Instead of the level adjusting bolt 4 in the embodiment, the fixing strength of the pile head metal 3 itself can be expected, so that the level adjusting bolt 4 is downsized. The pulling force from the foundation beam 6 and the bundle 2 is transmitted to the steel pipe pile 7 by the bearing force of the portion of the pile head metal 3 projecting from the steel pipe pile 7 to the outer periphery.
【0018】図5は図3の実施例と同様に環状部材22に
よって杭頭金物3を包囲し、杭頭金物3の上方にアンカ
ー筋32を突出させ、アンカー筋32をグラウト材5中に定
着させることにより束材2と杭頭金物3を接合した場合
である。束材2と杭頭金物3間の引き抜き力は杭頭金物
3の上方に突出したアンカー筋32の引張力とその回りの
付着力によって伝達される。FIG. 5 shows a similar manner to the embodiment of FIG. 3 in which the pile head metal 3 is surrounded by the annular member 22, the anchor bar 32 is projected above the pile head metal 3, and the anchor bar 32 is fixed in the grout material 5. This is the case where the bundle 2 and the pile head metal 3 are joined together. The pull-out force between the bundle 2 and the pile head 3 is transmitted by the tensile force of the anchor bar 32 protruding above the pile head 3 and the adhesive force therearound.
【0019】図6は基礎梁6や束材2からの引き抜き力
を鋼管杭7に伝達する必要がない部位に適用される杭頭
金物3を用いた場合の実施例であり、杭頭金物3にはレ
ベル調整ボルト4のみが付属する。FIG. 6 shows an embodiment in which a pile fitting 3 is applied to a portion where it is not necessary to transmit the pulling force from the foundation beam 6 or the bundle 2 to the steel pipe pile 7. Comes with only a level adjustment bolt 4.
【0020】図7〜図9は図1に示す実施例と同様に環
状部材22を杭頭金物3の上方に位置させた場合に、杭頭
金物3を、杭頭の内周面との間にクリアランスを持ちな
がら、杭頭上に載る形状に形成し、杭頭の外周を包囲す
るリング33からボルト34を締め付け、鋼管杭7の頭部を
かしめ、杭頭金物3に密着させることにより杭頭金物3
を鋼管杭7に接続した場合の実施例である。この実施例
では鋼管杭7の頭部がかしめられて杭頭金物3に一体化
することによりグラウト材5からの鉛直荷重や、レベル
調整ボルト4からの引き抜き力及び水平力は杭頭金物3
から直接鋼管杭7に伝達される。FIGS. 7 to 9 show the case where the annular member 22 is located above the pile head metal 3 as in the embodiment shown in FIG. With a clearance, the bolt is formed from a ring 33 surrounding the periphery of the pile head, and bolts 34 are tightened. Thing 3
This is an embodiment in which is connected to the steel pipe pile 7. In this embodiment, the head of the steel pipe pile 7 is caulked and integrated with the pile head metal 3, so that the vertical load from the grout material 5, the pulling force and the horizontal force from the level adjustment bolt 4, and the pile head metal 3
From the steel pipe pile 7 directly.
【0021】[0021]
【発明の効果】この発明は以上の通りであり、独立基礎
を構成し、下端にベースプレートが一体化した束材に基
礎梁を接続すると同時に、鋼管杭の頭部に杭頭金物を接
続し、杭頭金物にベースプレートを支持するレベル調整
ボルトを螺合したものであるため、基礎梁のレベル調整
を行うことができ、また基礎梁の接合が終了するまでの
間の基礎梁の荷重はレベル調整ボルトが負担するため仮
支持用の部材を要することなく、束材と鋼管杭の接合後
の、基礎梁とその上載荷重を鋼管杭に伝達するグラウト
材の充填が行え、作業の中断が回避され、工期の短縮化
を図ることができる。As described above, the present invention constitutes an independent foundation. At the same time, the foundation beam is connected to the bundle member having the base plate integrated at the lower end, and the pile head metal is connected to the head of the steel pipe pile. Since the level adjustment bolts that support the base plate are screwed to the pile head hardware, the level adjustment of the foundation beam can be performed, and the load on the foundation beam until the joining of the foundation beam is completed is adjusted. Since the bolts bear, there is no need for temporary support members, and after joining the bundle and the steel pipe pile, the foundation beam and the grout material that transmits the loading load to the steel pipe pile can be filled, and work interruption is avoided. In addition, the construction period can be shortened.
【図1】環状部材を杭頭金物上に配置した場合の実施例
を示した縦断面図である。FIG. 1 is a longitudinal sectional view showing an embodiment when an annular member is arranged on a pile head metal.
【図2】図1の平面図である。FIG. 2 is a plan view of FIG.
【図3】環状部材を杭頭金物を包囲して配置した場合の
実施例を示した縦断面図である。FIG. 3 is a longitudinal sectional view showing an embodiment in which an annular member is arranged so as to surround a pile head metal.
【図4】図3の平面図である。FIG. 4 is a plan view of FIG. 3;
【図5】環状部材を杭頭金物を包囲して配置した場合の
他の実施例を示した縦断面図である。FIG. 5 is a longitudinal sectional view showing another embodiment in which an annular member is arranged so as to surround a pile head metal.
【図6】図3に示す実施例において引き抜き力を伝達さ
せない場合の実施例を示した縦断面図である。FIG. 6 is a longitudinal sectional view showing an embodiment in a case where a pull-out force is not transmitted in the embodiment shown in FIG. 3;
【図7】環状部材を杭頭金物上に配置した場合の他の実
施例を示した縦断面図である。FIG. 7 is a longitudinal sectional view showing another embodiment when an annular member is arranged on a pile head metal.
【図8】図7の一部拡大図である。FIG. 8 is a partially enlarged view of FIG. 7;
【図9】図8の杭頭金物部分の平面図である。FIG. 9 is a plan view of a pile head metal part in FIG. 8;
【図10】従来構造を示した縦断面図である。FIG. 10 is a longitudinal sectional view showing a conventional structure.
1……接合装置、2……束材、21……ベースプレート、
22……環状部材、23……シアリブ、3……杭頭金物、31
……突起、32……アンカー筋、33……リング、34……ボ
ルト、4……レベル調整ボルト、5……グラウト材、6
……基礎梁、7……鋼管杭、8,9……ドライモルタ
ル、10……アンカー筋、11……アンカープレート、12…
…グラウト材。1 ... joining device, 2 ... bundle material, 21 ... base plate,
22 ... annular member, 23 ... shear rib, 3 ... pile head hardware, 31
... Projection, 32 ... Anchor bar, 33 ... Ring, 34 ... Bolt, 4 ... Level adjustment bolt, 5 ... Grout material, 6
…… Foundation beam, 7… Pipe pile, 8,9… Dry mortar, 10… Anchor bar, 11… Anchor plate, 12…
... grouting material.
フロントページの続き (58)調査した分野(Int.Cl.7,DB名) E02D 27/12 E02D 27/00 Continuation of the front page (58) Field surveyed (Int. Cl. 7 , DB name) E02D 27/12 E02D 27/00
Claims (1)
環状部材が一体化し、基礎梁が接続する束材と、鋼管杭
の頭部上に載り、これに接続される杭頭金物と、杭頭金
物に軸を鉛直に向けて螺合し、束材のベースプレートを
支持し、束材のレベルを調整するレベル調整ボルトと、
環状部材内に充填され、束材の脚部を鋼管杭に対して接
合するグラウト材とから構成される鋼管杭と独立基礎の
接合装置。1. A base plate and an annular member circumscribing the base plate are integrated at a lower end thereof, a bundle connected to a foundation beam, a pile head mounted on a steel pipe pile head and connected thereto, and a pile head hardware A level adjustment bolt that screwes the shaft vertically to support the base plate of the bundle, and adjusts the level of the bundle,
A joining device for a steel pipe pile and an independent foundation, which is filled in an annular member and is composed of a grout material for joining a leg portion of a bundle to a steel pipe pile.
Priority Applications (1)
| Application Number | Priority Date | Filing Date | Title |
|---|---|---|---|
| JP05143266A JP3142685B2 (en) | 1993-06-15 | 1993-06-15 | Equipment for joining steel pipe piles and foundation beams |
Applications Claiming Priority (1)
| Application Number | Priority Date | Filing Date | Title |
|---|---|---|---|
| JP05143266A JP3142685B2 (en) | 1993-06-15 | 1993-06-15 | Equipment for joining steel pipe piles and foundation beams |
Publications (2)
| Publication Number | Publication Date |
|---|---|
| JPH073817A JPH073817A (en) | 1995-01-06 |
| JP3142685B2 true JP3142685B2 (en) | 2001-03-07 |
Family
ID=15334753
Family Applications (1)
| Application Number | Title | Priority Date | Filing Date |
|---|---|---|---|
| JP05143266A Expired - Fee Related JP3142685B2 (en) | 1993-06-15 | 1993-06-15 | Equipment for joining steel pipe piles and foundation beams |
Country Status (1)
| Country | Link |
|---|---|
| JP (1) | JP3142685B2 (en) |
Cited By (1)
| Publication number | Priority date | Publication date | Assignee | Title |
|---|---|---|---|---|
| US6275601B1 (en) | 1997-03-05 | 2001-08-14 | Fujitsu Denso Ltd. | Fingerprinting judging method |
Families Citing this family (2)
| Publication number | Priority date | Publication date | Assignee | Title |
|---|---|---|---|---|
| JP2006265999A (en) * | 2005-03-25 | 2006-10-05 | Koyama Kosakusho:Kk | Basic structure of independent pile without basic beam |
| CN106703033B (en) * | 2015-11-13 | 2019-06-14 | 五冶集团上海有限公司 | A kind of support with adjustable of PHC pipe pile cutter |
-
1993
- 1993-06-15 JP JP05143266A patent/JP3142685B2/en not_active Expired - Fee Related
Cited By (1)
| Publication number | Priority date | Publication date | Assignee | Title |
|---|---|---|---|---|
| US6275601B1 (en) | 1997-03-05 | 2001-08-14 | Fujitsu Denso Ltd. | Fingerprinting judging method |
Also Published As
| Publication number | Publication date |
|---|---|
| JPH073817A (en) | 1995-01-06 |
Similar Documents
| Publication | Publication Date | Title |
|---|---|---|
| JP4693299B2 (en) | Column base connection structure | |
| JP3179677B2 (en) | Crane fixing structure, method of fixing the same, and method of removing the fixed structure | |
| JP3142685B2 (en) | Equipment for joining steel pipe piles and foundation beams | |
| JPH10121576A (en) | Fixing structure of pedestal | |
| JP2014037722A (en) | Installation structure and construction method for solar panel trestle | |
| JP4657028B2 (en) | Joining structure and joining method of pile and superstructure | |
| JP2002285564A (en) | STRUCTURE FOUNDATION SUPPORT STRUCTURE AND ITS CONSTRUCTION METHOD | |
| JPH02164931A (en) | Building foundation construction method | |
| JP2005320720A (en) | Column base structure | |
| JP3278823B2 (en) | Column base fixing device and column base fixing method | |
| JPH04285211A (en) | Foundation structure of building | |
| JP3290636B2 (en) | Joint structure between steel column base and foundation concrete | |
| JP2002194748A (en) | Construction method of foundation and foundation structure of building | |
| JP3838165B2 (en) | Joining structure and joining method of steel pipe column and steel pipe pile | |
| JP3233260B2 (en) | Anchoring structure of anchor material on steel column base | |
| JP2006257710A (en) | Joint structure between cast-in-place concrete pile and foundation | |
| JPH1025759A (en) | Adjustable column base | |
| JP3682504B2 (en) | Building foundations and construction methods | |
| JPH05287763A (en) | Joining construction of pile top with beam | |
| JP2024073886A (en) | Pile foundation structure | |
| JPH0118215B2 (en) | ||
| JP4296537B2 (en) | Joining structure and joining method of ready-made pile and superstructure | |
| JP2024126220A (en) | Precast spandrel wall installation method and precast spandrel wall support structure | |
| JP2024179748A (en) | Seismic isolation structure for steel pipe pile head and construction method thereof | |
| JPH08226132A (en) | Anchor bolt erection structure |
Legal Events
| Date | Code | Title | Description |
|---|---|---|---|
| A01 | Written decision to grant a patent or to grant a registration (utility model) |
Free format text: JAPANESE INTERMEDIATE CODE: A01 Effective date: 20001212 |
|
| FPAY | Renewal fee payment (event date is renewal date of database) |
Free format text: PAYMENT UNTIL: 20081222 Year of fee payment: 8 |
|
| FPAY | Renewal fee payment (event date is renewal date of database) |
Free format text: PAYMENT UNTIL: 20081222 Year of fee payment: 8 |
|
| FPAY | Renewal fee payment (event date is renewal date of database) |
Free format text: PAYMENT UNTIL: 20091222 Year of fee payment: 9 |
|
| FPAY | Renewal fee payment (event date is renewal date of database) |
Free format text: PAYMENT UNTIL: 20101222 Year of fee payment: 10 |
|
| FPAY | Renewal fee payment (event date is renewal date of database) |
Free format text: PAYMENT UNTIL: 20101222 Year of fee payment: 10 |
|
| FPAY | Renewal fee payment (event date is renewal date of database) |
Free format text: PAYMENT UNTIL: 20111222 Year of fee payment: 11 |
|
| FPAY | Renewal fee payment (event date is renewal date of database) |
Free format text: PAYMENT UNTIL: 20111222 Year of fee payment: 11 |
|
| S531 | Written request for registration of change of domicile |
Free format text: JAPANESE INTERMEDIATE CODE: R313531 |
|
| FPAY | Renewal fee payment (event date is renewal date of database) |
Free format text: PAYMENT UNTIL: 20111222 Year of fee payment: 11 |
|
| R350 | Written notification of registration of transfer |
Free format text: JAPANESE INTERMEDIATE CODE: R350 |
|
| LAPS | Cancellation because of no payment of annual fees |