[go: up one dir, main page]

JPH0317311A - Continuous underground wall method - Google Patents

Continuous underground wall method

Info

Publication number
JPH0317311A
JPH0317311A JP1150141A JP15014189A JPH0317311A JP H0317311 A JPH0317311 A JP H0317311A JP 1150141 A JP1150141 A JP 1150141A JP 15014189 A JP15014189 A JP 15014189A JP H0317311 A JPH0317311 A JP H0317311A
Authority
JP
Japan
Prior art keywords
continuous underground
internal
walls
underground walls
floor slab
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Granted
Application number
JP1150141A
Other languages
Japanese (ja)
Other versions
JP2757208B2 (en
Inventor
Toshimi Ino
伊野 敏美
Kenichi Kaneko
研一 金子
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Taisei Corp
Original Assignee
Taisei Corp
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Taisei Corp filed Critical Taisei Corp
Priority to JP1150141A priority Critical patent/JP2757208B2/en
Publication of JPH0317311A publication Critical patent/JPH0317311A/en
Application granted granted Critical
Publication of JP2757208B2 publication Critical patent/JP2757208B2/en
Anticipated expiration legal-status Critical
Expired - Lifetime legal-status Critical Current

Links

Landscapes

  • Bulkheads Adapted To Foundation Construction (AREA)
  • Underground Structures, Protecting, Testing And Restoring Foundations (AREA)

Abstract

PURPOSE:To ensure security and to reduce a construction period by constructing two cylindrical continuous underground walls opposed to each other at a certain interval so as to be closed in plane, and constructing a floor slab combined with the continuous underground walls to the bottom of the foundation formed by excavating between circumferential surfaces of them. CONSTITUTION:Cylindrical internal continuous underground wall 10 and external continuous underground wall 20 have different diameters with openings in the upper and lower ends, they are so constructed that their circumferential surfaces are closed in plane, and a circular bedrock held between the internal and exter nal continuous underground walls 10 and 20 is excavated in the shape of a spiral in the circumferential direction. Concrete is placed at the bottom, and a concrete floor slab 30 combined with the internal and external continuous underground walls 10 and 20 is formed to function as a strut. Then, after the excavation between the internal and external continuous underground walls 10 and 20 goes around, the lower part of the concrete floor slab 30 is excavated. According to the constitution, the concrete floor slab 30 functioning as the strut is extended to ensure security, to obtain many work places and to make it possible to reduce a construction period.

Description

【発明の詳細な説明】 〈産業上の利用分野〉 本発明は各種の山留工又は、地下貯蔵タンクや人工島等
の各種構造物の構成材に適用できる、連続地中壁工法に
関する。
DETAILED DESCRIPTION OF THE INVENTION <Industrial Application Field> The present invention relates to a continuous underground wall construction method that can be applied to various types of mountain retaining works or constituent materials of various structures such as underground storage tanks and artificial islands.

〈従来の技術〉 現在、地上側の土地利用に際し種々の制限を受けること
から、地下部の活用が注目されている。
<Conventional Technology> Currently, the use of underground areas is attracting attention because of various restrictions when using land above ground.

このような現状を背景に、最近は大深度に対応できる連
続地中壁の構築技術が種々提案されている。
Against this background, various construction techniques for continuous underground walls that can be constructed at great depths have recently been proposed.

従来のこの種の構築技術に関しては、回転掘削方式がパ
ケット掘削方式に比べ壁厚を大きく施工できることが知
られている。
Regarding conventional construction techniques of this type, it is known that the rotary excavation method allows construction of walls with greater thickness than the packet excavation method.

〈本発明が解決しようとする問題点〉 前述した従来の連続地中壁の構築技術には次のような問
題点がある。
<Problems to be Solved by the Present Invention> The conventional continuous underground wall construction techniques described above have the following problems.

〈イ〉深度が増すほど連続地中壁の強度確保に必要な壁
厚も増していく。
(a) As the depth increases, the wall thickness required to ensure the strength of the continuous underground wall also increases.

現在の構築技術にあっては、構築可能な最大壁厚が3m
程度である。
With current construction technology, the maximum wall thickness that can be constructed is 3m.
That's about it.

〈口〉設計壁厚が3mを越える場合は、一連の掘削工程
、コンクリート打設工を何度が繰り返して、連続地中壁
の内外面に補強壁を被覆する施工法が採用される。
<Explanation> When the designed wall thickness exceeds 3 m, a construction method is adopted in which a series of excavation processes and concrete pouring are repeated several times, and reinforcement walls are covered on the inner and outer surfaces of the continuous underground wall.

しかし、この施工法にあっては、補強工を含め施工コス
トが非常に高くつく。
However, with this construction method, the construction cost including reinforcement work is extremely high.

〈ハ〉設計壁厚が厚くなるほど産業廃棄物の発生量が増
すため、産業廃棄物の処理費が大きくなる。
<C> The thicker the design wall thickness, the more industrial waste will be generated, which will increase the cost of processing the industrial waste.

〈二〉以上の理由から、現行の施工法は益々高まる大深
度用の連続地中壁の要求に十分応えられない。
For the reasons mentioned above, the current construction methods cannot adequately meet the ever-increasing demand for continuous underground walls at great depths.

そのため、その改善技術の提案が望まれている。Therefore, proposals for improvement techniques are desired.

〈本発明の目的〉 本発明は以上の問題点を解決するために成されたもので
、その目的とすることろは施工性及び経済性に優れ、さ
らに工期の短縮を図れる連続地中壁工法を提供すること
にある。
<Object of the present invention> The present invention has been made to solve the above problems, and its purpose is to provide a continuous underground wall construction method that is excellent in construction efficiency and economy, and can shorten the construction period. Our goal is to provide the following.

〈本発明の構成〉 以下、図面を参照しながら本発明の一実施例である、円
筒形の連続地中壁を構築する場合について説明する。
<Configuration of the Present Invention> Hereinafter, a case of constructing a cylindrical continuous underground wall, which is an embodiment of the present invention, will be described with reference to the drawings.

尚、連続地中壁は円筒形に限定されるものではなく、こ
れ以外の形状に適用できることは勿論である。
Note that the continuous underground wall is not limited to a cylindrical shape, and can of course be applied to other shapes.

〈イ〉連続地中壁の構築 まず、第2、3図に示すように地中に一定の間隔を離し
て而対向する二重構造の連続地中壁を構築する。
<B> Construction of a continuous underground wall First, as shown in Figures 2 and 3, a continuous underground wall with a double structure facing each other at a certain distance is constructed underground.

この二重の連続地中壁は、内部連続地中壁10及び内部
連続地中壁10の外方に位置する外部連続地中壁20よ
りなり、両者とも上下端を開口する異径の筒状形を呈し
ている。
This double continuous underground wall consists of an internal continuous underground wall 10 and an external continuous underground wall 20 located outside of the internal continuous underground wall 10, both of which have a cylindrical shape with different diameters and open upper and lower ends. It has a shape.

即ち、内部連続地中壁10及び外部連続地中壁20は、
夫々の周面が平面的に閉合する関係にあるように構築す
る。
That is, the internal continuous underground wall 10 and the external continuous underground wall 20 are as follows:
It is constructed so that the respective circumferential surfaces are in a planar closed relationship.

内部及び外部連続地中壁10、20は公知の方法により
構築する。
The internal and external continuous underground walls 10, 20 are constructed by known methods.

〈口〉壁間掘削 つづいて第4図に示すように内部及び外部連続地中壁1
0、20間に挟まれた環状の他山を、円周方向に沿って
螺線状に掘削を続ける。
<Entrance> Continuing with wall-to-wall excavation, as shown in Figure 4, internal and external continuous underground walls 1
Excavating the annular ridge sandwiched between 0 and 20 in a spiral along the circumferential direction is continued.

〈ハ〉コンクリート床版の形成 同じく第4図に示すように内部及び外部連続地中壁10
、20間を掘削してできた他山の底面にコンクリートを
打設して、内部及び外部連続地中壁10、20と一体構
造のコンクリート床版30を形成する。
<C> Formation of concrete slab As shown in Figure 4, internal and external continuous underground walls 10
, 20 are excavated and concrete is placed on the bottom of the pile, thereby forming a concrete floor slab 30 having an integral structure with the internal and external continuous underground walls 10 and 20.

コンクリート床版30は内部及び外部連続地中壁10、
20の周面間で切梁として機能する。
The concrete slab 30 has internal and external continuous underground walls 10,
It functions as a strut between the 20 peripheral surfaces.

コンクリート床版3oを内部及び外部連続地中壁10、
20と一体化を図るには例えば、第5図に示すように内
部及び外部連続地中壁10、20を構築する際にコンク
リート床版30の接続予定箇所に鉄筋等の連結材40を
埋め込んでおくか、或は内部及び外部連続地中壁10、
20の該当箇所をはつって差し筋を接続したり、ねじや
アンカーを接続する等の連結構造を採用できる。
Concrete floor slab 3o is connected to internal and external continuous underground walls 10,
20, for example, as shown in FIG. 5, when constructing the internal and external continuous underground walls 10, 20, connecting materials 40 such as reinforcing bars are embedded in the planned connection points of the concrete slab 30. or internal and external continuous underground wall 10;
It is possible to employ a connection structure such as connecting the 20 corresponding points with reinforcing bars, or connecting screws or anchors.

次に打設したコンクリート床版30に強度が発現した段
階で、内部及び外部連続地中壁10、2O間の掘削を一
巡した後、さらにこのコンクリート床版30の下面を掘
削する。
Next, when the cast concrete slab 30 has developed strength, the lower surface of the concrete slab 30 is further excavated after one round of excavation between the internal and external continuous underground walls 10 and 2O.

以上の掘削工程及びコンクリート床版30の形成工程を
並行して繰り返し行うことで、内部及び外部連続地中壁
10、20間に螺線状のコンクリート床版30を形威す
る。
By repeating the above excavation process and the forming process of the concrete slab 30 in parallel, a spiral concrete slab 30 is formed between the internal and external continuous underground walls 10 and 20.

コンクリート床版30を螺線状に延長することで、内部
及び外部連続地中壁10、20の周面間に,螺線状に空
間が形威される。
By extending the concrete slab 30 in a spiral shape, a spiral space is formed between the circumferential surfaces of the internal and external continuous underground walls 10 and 20.

コンクリート床版30の螺線ピッチは、各連続地中壁1
0、20の壁厚や径や最終的な構造物の設計強度等によ
り定まる。
The spiral pitch of the concrete slab 30 is the same as that of each continuous underground wall 1.
It is determined by the wall thickness and diameter of 0 and 20, the design strength of the final structure, etc.

最終的に内部及び外部連続地中壁10、20の周面間に
は、゜コンクリート床版30で画威された螺線状の通路
が形威される。
Finally, a spiral passage defined by the concrete slab 30 is formed between the circumferential surfaces of the internal and external continuous underground walls 10, 20.

〈二〉内部掘削 第6図に示すようにコンクリート床版30により内部連
続地中壁10及び外部連続地中壁20の一体化を図った
後、内部連続地中壁10の内部を掘削する。
<2> Internal Excavation After the internal continuous underground wall 10 and the external continuous underground wall 20 are integrated with the concrete slab 30 as shown in FIG. 6, the inside of the internal continuous underground wall 10 is excavated.

使用目的に応じて内部連続地中壁10の内部に各種構造
物を構築する。
Various structures are constructed inside the internal continuous underground wall 10 depending on the purpose of use.

完成後の外力は、一体構造の外部連続地中壁20及びコ
ンクリート床版30及び内部連続地中壁10が分散して
支持することになる。
After completion, external forces will be dispersed and supported by the external continuous underground wall 20, concrete slab 30, and internal continuous underground wall 10, which are integrally constructed.

〈その他の実施例l〉 前記実施例は内部及び外部連続地中壁10、20の周面
間に螺線状のコンクリート床版30を一条施工する場合
について説明したが、上下に位置をずらして複数条のコ
ンクリート床版30を並行して施工することもできる。
<Other Embodiments 1> In the above embodiments, a case was explained in which a single spiral concrete slab 30 was constructed between the circumferential surfaces of the internal and external continuous underground walls 10 and 20. It is also possible to construct multiple concrete slabs 30 in parallel.

第7図は上下3段をグループとして掘削しながら施工す
る場合について示す。
Figure 7 shows the case where construction is carried out while excavating the upper and lower three stages as a group.

同図の場合、例えばグループの最上段Aで掘削を行って
いるとき、グループ中段Bではコンクリートの養生中で
あり、最下段Cでは掘削中である。
In the case of the figure, for example, when excavation is being carried out at the top A of the group, concrete is curing in the middle B of the group, and excavation is being carried out at the bottom C.

本実施例の場合、常に上位の段の作業は下位の段の作業
に先行して進められる。
In the case of this embodiment, the work at the higher stage is always carried out before the work at the lower stage.

又、作業箇所は上下2段或は4段以上に組み合わせてる
ことができる。
Further, the work areas can be combined into two levels (upper and lower) or four or more levels.

本実施例によれば、作業箇所が多くとれるので,工期の
大幅な短縮が可能である。
According to this embodiment, since there are many work areas, it is possible to significantly shorten the construction period.

くその他の実施例2〉 内部及び外部連続地中壁10.20の周面間の螺線状の
空間は通路として利用できる他に、コンクリートを充填
して一体の連続壁とすることも可能である。
Other Example 2> The spiral space between the circumferential surfaces of the internal and external continuous underground walls 10.20 can be used as a passageway, and can also be filled with concrete to form an integrated continuous wall. be.

〈その他の実施例3〉 連続地中壁を三重以上形成すると共に、各連続地中壁の
周面間にコンクリート床版を構築してもよい。
<Other Embodiment 3> Three or more continuous underground walls may be formed, and a concrete slab may be constructed between the peripheral surfaces of each continuous underground wall.

〈本発明の効果〉 本発明は以上説明したようになるから次の効果が得られ
る。
<Effects of the Present Invention> Since the present invention is as described above, the following effects can be obtained.

〈イ〉本発明では厚さが必要な場合、施工可能な薄手の
連続地中壁を複数条形成することで対処できる。
(A) In the present invention, if a thickness is required, this can be achieved by forming a plurality of thin continuous underground walls that can be constructed.

従って、従来の施工技術では限界とされていた3m以上
の壁厚の施工が可能となり、大深度で利用できる。
Therefore, it is now possible to construct walls with a wall thickness of 3 m or more, which was considered to be the limit with conventional construction techniques, and it can be used at great depths.

〈口〉連続地中壁を幾重にも形成するから、高い止水効
果が得られる。
<Entrance> Continuous underground walls are formed in multiple layers, resulting in a high water-stopping effect.

〈ハ〉連続地中壁の周面間を掘削しなから切梁機能を発
揮するコンクリート床版を延長していくから、すべての
掘削を完了した後に切梁をかける方法と比べて安全上有
利である。
〈C〉Since the concrete slab that functions as a strut is extended without excavating between the circumferential surfaces of the continuous underground wall, it is safer in comparison to the method of installing struts after all excavation is completed. It is.

〈二〉連続地中壁の周而間の螺線状の空間は通路として
活用できる。
(2) The spiral space between the continuous underground walls can be used as a passageway.

〈ホ〉連続地中壁間を施工する場合、作業箇所を多くと
れるので工期が短くて済む。
<E> When constructing between continuous underground walls, the construction period can be shortened because there are many work areas.

〈へ〉各連続地中壁の厚さを薄く設計できるので産業廃
棄物の処理費用が安くて済む。
(f) Since the thickness of each continuous underground wall can be designed to be thin, the cost of processing industrial waste can be reduced.

〈ト〉海洋プラットホーム等の海洋工事に適用すること
ら可能である。
<G> It is possible to apply it to offshore construction such as offshore platforms.

【図面の簡単な説明】[Brief explanation of drawings]

第1図二本発明に係る連続地中壁を用いて構築した地下
構造物の一部を破断した全体図 第2図:施工法の説明図であって内部及び外部連続地中
壁の構築時の断面図 第3図:第2図の平面図 第4図:内部及び外部連続地中壁の周面を掘削してコン
クリート床版を構築する時の断面図 第5図;コンクリート床版の定着構造例の説明図第6図
:内部連続地中壁内の掘削時の断面図第7図:その他の
実施例の説明図
Fig. 1 2 An overall partially cutaway view of an underground structure constructed using the continuous underground wall according to the present invention Fig. 2: An explanatory diagram of the construction method during construction of internal and external continuous underground walls Figure 3: Plan view of Figure 2 Figure 4: Cross-sectional view when constructing a concrete slab by excavating the circumference of the internal and external continuous underground walls Figure 5: Fixing of the concrete slab Explanatory diagram of structural example Figure 6: Cross-sectional view of internal continuous underground wall during excavation Figure 7: Explanatory diagram of other examples

Claims (1)

【特許請求の範囲】[Claims] (1)二つの連続地中壁を、一定の間隔を介して面対向
する筒形や角形等の平面的に閉合する関係を持たせて構
築し、 前記両連続地中壁の周面間を掘削し、 両連続地中壁の周面間を掘削してできた地盤の底面に両
連続地中壁と一体に床版を構築し、両連続地中壁の周面
間の掘削が一巡したら前記床版の下面に到達させ、 前記床版の下方を掘削しながら順次床版を延長して一体
構造の連続地中壁を構築する、 連続地中壁工法。
(1) Two continuous underground walls are constructed in a planar closed relationship such as cylindrical or square shapes that face each other with a certain distance between them, and the circumferential surfaces of the two continuous underground walls are After excavating between the circumferential surfaces of both continuous underground walls, a slab is constructed on the bottom of the ground created by excavating between the circumferential surfaces of both continuous underground walls, and a slab is constructed integrally with both continuous underground walls. A continuous underground wall construction method, in which the lower surface of the floor slab is reached, and the floor slab is successively extended while excavating below the floor slab to construct a continuous underground wall with an integrated structure.
JP1150141A 1989-06-13 1989-06-13 Continuous underground wall construction method Expired - Lifetime JP2757208B2 (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
JP1150141A JP2757208B2 (en) 1989-06-13 1989-06-13 Continuous underground wall construction method

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
JP1150141A JP2757208B2 (en) 1989-06-13 1989-06-13 Continuous underground wall construction method

Publications (2)

Publication Number Publication Date
JPH0317311A true JPH0317311A (en) 1991-01-25
JP2757208B2 JP2757208B2 (en) 1998-05-25

Family

ID=15490392

Family Applications (1)

Application Number Title Priority Date Filing Date
JP1150141A Expired - Lifetime JP2757208B2 (en) 1989-06-13 1989-06-13 Continuous underground wall construction method

Country Status (1)

Country Link
JP (1) JP2757208B2 (en)

Cited By (6)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JPH0527000A (en) * 1991-07-19 1993-02-05 Nec Corp Tracking receiver
US7025537B2 (en) * 2002-06-03 2006-04-11 Russell Matthew F Subterranean structures and methods for constructing subterranean structures
KR100776373B1 (en) * 2004-10-13 2007-11-16 코오롱건설주식회사 Two-column pile blocking method
KR100886445B1 (en) * 2006-12-12 2009-03-04 장지건 Soil tanks
JP2010106653A (en) * 2008-10-02 2010-05-13 Yotaro Kobayakawa Underground structure and composite structure
JP2015229822A (en) * 2014-06-03 2015-12-21 大成建設株式会社 Earth retaining structure and method for constructing earth retaining structure

Family Cites Families (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JP5231101B2 (en) 2008-06-27 2013-07-10 株式会社神戸製鋼所 Machine structural steel with excellent fatigue limit ratio and machinability

Cited By (6)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JPH0527000A (en) * 1991-07-19 1993-02-05 Nec Corp Tracking receiver
US7025537B2 (en) * 2002-06-03 2006-04-11 Russell Matthew F Subterranean structures and methods for constructing subterranean structures
KR100776373B1 (en) * 2004-10-13 2007-11-16 코오롱건설주식회사 Two-column pile blocking method
KR100886445B1 (en) * 2006-12-12 2009-03-04 장지건 Soil tanks
JP2010106653A (en) * 2008-10-02 2010-05-13 Yotaro Kobayakawa Underground structure and composite structure
JP2015229822A (en) * 2014-06-03 2015-12-21 大成建設株式会社 Earth retaining structure and method for constructing earth retaining structure

Also Published As

Publication number Publication date
JP2757208B2 (en) 1998-05-25

Similar Documents

Publication Publication Date Title
CN109944250B (en) Foundation pit forward and backward combined construction method of non-permanent vertical supporting system
CN112681376B (en) Construction method of shaft type underground stereo garage
JPH0317311A (en) Continuous underground wall method
JPS62288269A (en) How to extend the basement floor of a building
CN210507463U (en) Three-in-one structure of support system and basement structure system in foundation pit support
CN212671008U (en) Pile column structure for reverse construction method construction
JP3772915B2 (en) Foundation pile construction method and foundation pile
JPH0348292B2 (en)
JP2000192456A (en) Foundation pile structure in soft ground and foundation pile method
JPH0748833A (en) Foundation pile structure
CN210562273U (en) Foundation for bearing assembly type elevator
CN210177510U (en) Foundation pit protection structure and support structure
JPH03275816A (en) Building method for main slab in underground space
JPH0381422A (en) Caisson method
JPH0529239Y2 (en)
JPS63107612A (en) Cast-in-place concrete pile
JPS6343274Y2 (en)
JPH03103535A (en) Countermeasure structure for liquefaction of building
JP2000192472A (en) Method for immersing immersing body, and its immersing body
JPH0726569A (en) Pile foundation construction method for structures subjected to uneven earth pressure
JP2782263B2 (en) Underground structure and construction method
JPS61200222A (en) Large underground structure
SU1035137A1 (en) Pile foundation
JPH0326254B2 (en)
JPH06146308A (en) How to build an underground structure