[go: up one dir, main page]

JPH0352812Y2 - - Google Patents

Info

Publication number
JPH0352812Y2
JPH0352812Y2 JP14304086U JP14304086U JPH0352812Y2 JP H0352812 Y2 JPH0352812 Y2 JP H0352812Y2 JP 14304086 U JP14304086 U JP 14304086U JP 14304086 U JP14304086 U JP 14304086U JP H0352812 Y2 JPH0352812 Y2 JP H0352812Y2
Authority
JP
Japan
Prior art keywords
truss
support surface
shoring
nuts
bolts
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Expired
Application number
JP14304086U
Other languages
Japanese (ja)
Other versions
JPS6350908U (en
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed filed Critical
Priority to JP14304086U priority Critical patent/JPH0352812Y2/ja
Publication of JPS6350908U publication Critical patent/JPS6350908U/ja
Application granted granted Critical
Publication of JPH0352812Y2 publication Critical patent/JPH0352812Y2/ja
Expired legal-status Critical Current

Links

Landscapes

  • Bridges Or Land Bridges (AREA)
  • Forms Removed On Construction Sites Or Auxiliary Members Thereof (AREA)

Description

【考案の詳細な説明】 〔産業上の利用分野〕 この考案は、支保工用トラス、更に詳しくは、
比較的長スパンの橋梁等を構築する場合に使用す
る支保工用のトラスに関するものである。
[Detailed explanation of the invention] [Industrial application field] This invention is applicable to shoring trusses, more specifically,
This relates to shoring trusses used when constructing relatively long span bridges.

〔従来の技術と問題点〕[Conventional technology and problems]

例えば、コンクリート橋梁を構築する場合、橋
脚間に配置したスラブ型枠を支持する支保工が必
要になる。
For example, when constructing a concrete bridge, shoring is required to support the slab formwork placed between the piers.

従来、上記のような支保工の一般的な構造は、
地上に多数の仮設枠やパイプサポート群を立設す
ることによつて構成していたため、多数の資材が
必要になり、設備経費が高くつくと共に、組立及
び解体に多くの労力と時間を必要とし、作業能率
が悪く施工コストを高騰させるという欠点があ
る。
Conventionally, the general structure of shoring as described above is
Because it was constructed by erecting a large number of temporary frames and pipe support groups on the ground, a large number of materials were required, equipment costs were high, and assembly and disassembly required a lot of labor and time. However, there are drawbacks such as poor work efficiency and increased construction costs.

また、前記のような仮設枠やパイプサポートを
用いた支保工の欠点を解消するため、橋脚間に架
設するトラスによつて支保工を構成し、工場で製
作したトラスを現場に輸送し、これを橋脚間に架
設することにより仮設枠やパイプサポート類の使
用を省くことが考えられている。
In addition, in order to eliminate the disadvantages of shoring using temporary frames and pipe supports as described above, shoring is constructed from trusses installed between bridge piers, and the truss manufactured in a factory is transported to the site. It is considered that the use of temporary frames and pipe supports can be eliminated by constructing the bridge between the piers.

上記のようなトラスの支保工は、橋脚間に現場
で架設するだけであるため、作業の省力化と短縮
化を可能にし、設備経費の削減を図ることができ
るという利点がある反面、交通事情や輸送手段の
制約から長いスパンのトラスを作業現場に輸送す
るのが極めて困難であるという問題がある。
The above-mentioned truss shoring simply needs to be erected on-site between the piers, so it has the advantage of saving labor and shortening the work period, and reducing equipment costs. There is a problem in that it is extremely difficult to transport long-span trusses to work sites due to constraints on transport methods.

この考案は、上記のようなトラス式支保工の問
題点を解決するためになされたものであり、作業
現場への輸送が手軽に行なえ、トラスの採用が容
易に実施できる支保工用トラスを提供することが
目的である。
This idea was made to solve the above-mentioned problems with truss-type shoring, and provides a shoring truss that can be easily transported to the work site and can be easily adopted. The purpose is to

〔問題点を解決するための手段〕 上記のような問題点を解決するためにこの考案
は、複数の梁部材の組合せによつて構成され、互
に接続せんとする梁部材の接続側端部に、剪断支
持面と引張圧縮支持面を組合せたジヨイント部を
両梁部材において互に接合し合う段状に形成し、
両梁部材をジヨイント部の引張圧縮支持面でボル
ト、ナツトにより着脱自在に結合するようにした
ものである。
[Means for Solving the Problems] In order to solve the above-mentioned problems, this invention consists of a combination of a plurality of beam members, and the connection side ends of the beam members that are to be connected to each other are A joint portion combining a shear support surface and a tension compression support surface is formed in a step shape that joins each other in both beam members,
Both beam members are removably connected by bolts and nuts at the tensile compression support surface of the joint portion.

〔作用〕[Effect]

トラスを構成する複数の梁部材を分割した状態
で作業現場に輸送し、現場において互に接続せん
とする梁部材のジヨイント部を接合し、その引張
圧縮支持面をボルト、ナツトで結合することによ
りトラスを組立てる。
By transporting the multiple beam members that make up the truss in a divided state to the work site, joining the joints of the beam members that are to be connected to each other at the site, and connecting their tension and compression support surfaces with bolts and nuts. Assemble the truss.

組上つたトラスを橋脚間に架設すればスラブ型
枠の支保工が完成し、コンクリート打設時におい
てトラスのジヨイント部にかかる荷重は、剪断支
持面で剪断荷重を支持し、引張り及び圧縮荷重を
引張圧縮支持面で支持する。
By installing the assembled truss between the piers, the support for the slab formwork is completed, and during concrete pouring, the load applied to the joint of the truss is supported by the shear support surface, and the tension and compression loads are supported by the shear support surface. Support with tension compression support surface.

〔実施例〕〔Example〕

以下、この考案の実施例を添付図面に基づいて
説明する。
Hereinafter, embodiments of this invention will be described based on the accompanying drawings.

第1図のように、支保工用のトラス1は、中央
梁2とその両端に結合した端部梁3,3と、両端
部梁3,3に取付けた調整梁4,4の組合せによ
つて、橋脚5と5間に架設する長さに構成され、
中央梁2と両端部梁3,3の結合部分に結合と分
離が自在となるジヨイント部6が設けられてい
る。
As shown in Figure 1, a truss 1 for shoring is made up of a combination of a central beam 2, end beams 3, 3 connected to both ends of the central beam 2, and adjustment beams 4, 4 attached to both end beams 3, 3. It is configured with a length to be constructed between piers 5 and 5,
A joint portion 6 that can be freely connected and separated is provided at the connecting portion between the center beam 2 and both end beams 3, 3.

前記中央梁2は、各々二本のチヤンネル材を背
中合せ状態で平行させた上弦材7と下弦材8を垂
直材9と傾斜材10で結合して形成され、両端部
梁3,3も同じく上弦材7aと下弦材8aを垂直
材9aと傾斜材10aで、中央梁2と同様の断面
構造に形成されている。(第4図参照) 上記中央梁2と端部梁3を結合するジヨイント
部6は、第2図乃至第4図に示す第1の例の場
合、中央梁2の端部及び端部梁3の結合側端部の
各々に、水平プレート11と、この水平プレート
11の一端に上部垂直プレート12と水平プレー
ト11の他端に下部垂直プレート13とを、中央
梁2と端部梁3で互に接合し合う段状に設けて構
成され、水平プレート11の接合面が剪断支持面
14となり、上下垂直プレート12,13の各接
合面が引張圧縮支持面15,16となる。
The central beam 2 is formed by connecting an upper chord member 7 and a lower chord member 8, each of which is made of two parallel channel members back to back, with a vertical member 9 and an inclined member 10, and both end beams 3, 3 are also formed by connecting the upper chord member 7 and the lower chord member 8, which are parallel to each other, back to back. The member 7a and the lower chord member 8a are made of a vertical member 9a and an inclined member 10a, and are formed to have the same cross-sectional structure as the central beam 2. (See Fig. 4) In the case of the first example shown in Figs. 2 to 4, the joint portion 6 connecting the central beam 2 and the end beams 3 A horizontal plate 11 is attached to each of the joining side ends of the horizontal plate 11, an upper vertical plate 12 is attached to one end of the horizontal plate 11, and a lower vertical plate 13 is attached to the other end of the horizontal plate 11. The joint surface of the horizontal plate 11 serves as a shear support surface 14, and the joint surfaces of the upper and lower vertical plates 12, 13 serve as tension and compression support surfaces 15, 16.

上記ジヨイント部6は、中央梁2の水平プレー
ト11が端部梁3の水平プレート11上に載り、
中央梁2の両端が端部梁3,3によつて支持され
るよう、中央梁2は水平プレート11の下部が凹
入し、逆に端部梁3,3は水平プレート11の下
部が突出するように形成されている。
In the joint portion 6, the horizontal plate 11 of the center beam 2 rests on the horizontal plate 11 of the end beam 3,
The lower part of the horizontal plate 11 of the central beam 2 is recessed so that both ends of the central beam 2 are supported by the end beams 3, 3, and conversely, the lower part of the horizontal plate 11 of the end beams 3, 3 protrudes. It is formed to do so.

ジヨイント部6において、上下の垂直プレート
12,13には、ボルト、ナツト17で着脱自在
で結合するためのボルト孔18,19が穿設さ
れ、中央梁2と端部梁3の結合時において、両水
平プレート11,11の剪断支持面14がトラス
1の剪断荷重を支持し、上部垂直プレート12,
12の支持面15が圧縮荷重を支持する。
In the joint part 6, bolt holes 18 and 19 are drilled in the upper and lower vertical plates 12 and 13 for removably connecting them with bolts and nuts 17, and when the center beam 2 and the end beams 3 are connected, The shear support surfaces 14 of both horizontal plates 11, 11 support the shear loads of the truss 1, and the upper vertical plates 12,
Twelve support surfaces 15 support compressive loads.

従つて、上部垂直プレート12,12を結合す
るボルト、ナツト17は、中央梁2と端部梁3の
横ずれを防止する役目をする。
Therefore, the bolts and nuts 17 that connect the upper vertical plates 12, 12 serve to prevent the central beam 2 and the end beams 3 from shifting laterally.

また、下部垂直プレート13,13の支持面1
6には引張り荷重が作用し、これをボルト、ナツ
ト17によつて支持する。このため、下部垂直プ
レート13,13の結合は上部垂直プレート1
2,12の結合よりボルト、ナツト17の数を多
くし、引張荷重の支持強度を向上させている。
In addition, the support surface 1 of the lower vertical plates 13, 13
A tensile load acts on 6, which is supported by bolts and nuts 17. Therefore, the lower vertical plates 13, 13 are connected to the upper vertical plate 1.
The number of bolts and nuts 17 is increased compared to the combination of 2 and 12 to improve the tensile load support strength.

前記調整梁4,4は、端部梁3,3にトラス1
の長手方向に位置調整が自在となるようボルト、
ナツトで結合され、橋脚5,5の間隔に合わせて
トラス1の長さを調整することができるようにし
ている。
The adjustment beams 4, 4 have a truss 1 on the end beams 3, 3.
bolts so that the position can be freely adjusted in the longitudinal direction.
They are connected with nuts so that the length of the truss 1 can be adjusted according to the spacing between the piers 5, 5.

次に第5図は中央梁2と端部梁3の結合を行な
うジヨイント部6の第2の例を示しており、第1
図乃至第4図と同一部分は同一符号を付すことに
よつて説明に代える。
Next, FIG. 5 shows a second example of the joint part 6 that connects the center beam 2 and the end beams 3, and the first
Components that are the same as those in FIGS. 4 to 4 are designated by the same reference numerals and will not be described further.

この第2の例のジヨイント部6は、第2図の水
平プレート11,11に代えて傾斜プレート11
a,11aを用い、剪断支持面14aを傾斜させ
ることにより、この支持面14aで引張力も支持
することができるようにしている。
The joint portion 6 of this second example has an inclined plate 11 instead of the horizontal plates 11, 11 in FIG.
a, 11a and by slanting the shear support surface 14a, this support surface 14a can also support tensile force.

なお、図示省略したが、一定長さの中央梁2に
対して、長さの異なる複数種類の端部梁を用意
し、使用する端部梁を選択することにより、トラ
スの全長を橋脚の間隔に合わせて選択することが
できるようにしてもよく、また、中央梁2にムク
リをつけてもよい。
Although not shown in the figure, by preparing multiple types of end beams with different lengths for the central beam 2 of a constant length and selecting the end beam to be used, the total length of the truss can be adjusted to the spacing between the piers. Alternatively, the central beam 2 may be provided with a blank.

この考案のトラスは上記のような構成であり中
央梁2と端部梁3,3及び調整梁4,4は分解し
た状態で作業現場に輸送し、現場において各梁を
順次ボルト、ナツトで結合することにより、所定
長さのトラス1を組立て、このトラス1を橋脚5
と5間に架設する。
The truss of this invention has the above-mentioned configuration, and the center beam 2, end beams 3, 3, and adjustment beams 4, 4 are transported to the work site in a disassembled state, and each beam is sequentially connected with bolts and nuts at the site. By doing so, a truss 1 of a predetermined length is assembled, and this truss 1 is attached to the piers 5.
It will be constructed between 5 and 5.

トラス1の架設は、第1図のように、橋脚5,
5の上部にアンカーを用いてブラケツト21,2
1を突設し、ブラケツト21,21上にジヤツキ
22を設置し、このジヤツキ22上にトラス1の
両端に位置する調整梁4の端部を載置すればよ
く、このようにして複数のトラス1を橋脚5,5
間に平行状態で架設し、この後、トラス1上に根
太23を介してスラブ型枠24を敷設し、型枠2
4上へのコンクリートの打設により、スラブを形
成する。
The construction of the truss 1 is as shown in Fig. 1.
Attach the brackets 21, 2 using anchors at the top of 5.
1 is provided protrudingly, a jack 22 is installed on the brackets 21, 21, and the ends of the adjustment beams 4 located at both ends of the truss 1 are placed on the jacks 22. In this way, a plurality of truss 1 to pier 5,5
After that, the slab formwork 24 is laid on the truss 1 via the joists 23, and the formwork 2
4. Form a slab by pouring concrete on top.

コンクリート打設時の荷重をトラス1によつて
支持すると共に、トラス1自身は中央梁2と端部
梁3の結合によつてそのジヨイント部6に荷重が
集中することになるが、剪断支持面14と引張圧
縮支持面15,16及びボルト、ナツト17によ
りジヨイント部6に大きな耐荷重支持力があり、
トラス1は大きな荷重に耐えることができる。
The load during concrete pouring is supported by the truss 1, and the load is concentrated on the joint 6 of the truss 1 itself due to the connection between the center beam 2 and the end beams 3, but the shear support surface 14, tension and compression support surfaces 15 and 16, and bolts and nuts 17, the joint portion 6 has a large load-bearing capacity.
The truss 1 can withstand large loads.

〔効果〕 以上のように、この考案によると、複数の梁
部材をジヨイント部でボルト、ナツトにより結合
してトラスを組立てるようにしたので、嵩低い短
尺の状態で作業現場に輸送することができ長スパ
ン支保工のトラス化が実現できる。
[Effects] As described above, according to this invention, a truss is assembled by connecting multiple beam members at the joint with bolts and nuts, so it can be transported to the work site in a short, low-bulk state. Long span shoring can be made into a truss.

また、ジヨイント部を剪断支持面と引張圧縮支
持面の組合せによる段状に形成し、ボルト、ナツ
トで結合したので、ジヨイント部の耐荷重支持強
度が向上し、短尺梁部材を結合して長尺トラスを
構成したにもかかわらず十分な強度が得られ、重
量構造物の構築が可能になる。
In addition, the joint part is formed into a stepped shape with a combination of shear support surfaces and tension/compression support surfaces, which are connected using bolts and nuts, which improves the load-bearing strength of the joint part. Even though it is constructed as a truss, sufficient strength can be obtained, making it possible to construct heavy structures.

【図面の簡単な説明】[Brief explanation of the drawing]

第1図はこの考案に係るトラスの使用状態を示
す縦断正面図、第2図は同上の要部を拡大した縦
断正面図、第3図は同じく要部の縦断側面図、第
4図は同要部の分解斜視図、第5図はジヨイント
部の第2の例を示す正面図である。 1……トラス、2……中央梁、3……端部梁、
6……ジヨイント部、11……水平プレート、1
2……上部垂直プレート、13……下部垂直プレ
ート、14……剪断支持面、15,16……引張
圧縮支持面、17……ボルト、ナツト、18,1
9……ボルト孔。
Fig. 1 is a longitudinal sectional front view showing the state of use of the truss according to this invention, Fig. 2 is an enlarged longitudinal sectional front view of the main parts of the above, Fig. 3 is a longitudinal sectional side view of the same main parts, and Fig. 4 is the same. FIG. 5 is an exploded perspective view of the main parts and a front view showing a second example of the joint part. 1...Truss, 2...Central beam, 3...End beam,
6...Joint part, 11...Horizontal plate, 1
2... Upper vertical plate, 13... Lower vertical plate, 14... Shearing support surface, 15, 16... Tension compression supporting surface, 17... Bolt, nut, 18, 1
9...Bolt hole.

Claims (1)

【実用新案登録請求の範囲】 1 複数の梁部材の組合せによつて構成され、互
に接続せんとする梁部材の接続側端部に、剪断
支持面と引張圧縮支持面を組合せたジヨイント
部を両梁部材において互に接合し合う段状に形
成し、両梁部材をジヨイント部の引張圧縮支持
面でボルト、ナツトにより着脱自在に結合する
ようにした支保工用トラス。 2 ジヨイント部の剪断支持面が水平に形成され
ている実用新案登録請求の範囲第1項に記載の
支保工用トラス。 3 ジヨイント部の剪断支持面が傾斜面に形成さ
れている実用新案登録請求の範囲第1項に記載
の支保工用トラス。
[Claims for Utility Model Registration] 1. Consisting of a combination of a plurality of beam members, a joint portion that combines a shear support surface and a tension compression support surface is provided at the connecting end of the beam members that are to be connected to each other. A shoring truss in which both beam members are formed in a step shape that joins each other, and both beam members are removably connected with bolts and nuts at the tensile compression support surface of the joint part. 2. The shoring truss according to claim 1 of the utility model registration claim, wherein the shear support surface of the joint portion is formed horizontally. 3. The shoring truss according to claim 1, wherein the shear support surface of the joint portion is formed as an inclined surface.
JP14304086U 1986-09-16 1986-09-16 Expired JPH0352812Y2 (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
JP14304086U JPH0352812Y2 (en) 1986-09-16 1986-09-16

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
JP14304086U JPH0352812Y2 (en) 1986-09-16 1986-09-16

Publications (2)

Publication Number Publication Date
JPS6350908U JPS6350908U (en) 1988-04-06
JPH0352812Y2 true JPH0352812Y2 (en) 1991-11-18

Family

ID=31052349

Family Applications (1)

Application Number Title Priority Date Filing Date
JP14304086U Expired JPH0352812Y2 (en) 1986-09-16 1986-09-16

Country Status (1)

Country Link
JP (1) JPH0352812Y2 (en)

Families Citing this family (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JP4985540B2 (en) * 2008-05-19 2012-07-25 鹿島建設株式会社 Vertical beam system for mobile work vehicles for cantilever installation

Also Published As

Publication number Publication date
JPS6350908U (en) 1988-04-06

Similar Documents

Publication Publication Date Title
US5079890A (en) Space frame structure and method of constructing a space frame structure
KR102187993B1 (en) Prefabricated Bridge Structure and Construction Method
CA2358747C (en) Ring beam/lintel system
US4646495A (en) Composite load-bearing system for modular buildings
US4648216A (en) Prefabricated building
US20040134152A1 (en) Method and apparatus for precast and framed block element construction
US3952472A (en) Joint for transferring bending moments
CN111411721A (en) A prefabricated prefabricated sub-beam composite member
EP0418216B1 (en) Frame-work for structural walls in multy-storey buildings
CN102140850B (en) Frame with floors of composite grid structure and construction method thereof
US4294052A (en) Prefabricated load bearing structure
US4173102A (en) Building construction
US3374592A (en) Precast column with shear-head sections
JPH0352812Y2 (en)
US20040211146A1 (en) Truss
JP2003049407A (en) Bridge and its construction method
EP0393091B1 (en) A load-bearing horizontal structural system for a building
CN212926452U (en) Joint connecting device for assembly type building frame
KR102750635B1 (en) Joint structure of girder and column and method therefor
CN218815194U (en) Assembled light-duty bearing structure
KR102624021B1 (en) Partial preflexion composite girder and column connection structure construction method and girder and column connection structure constructed thereby
CN210288076U (en) A prefabricated steel truss composite girder bridge
WO2007134073A2 (en) Construction method using precast planar frame elements
JP3070703U (en) Steel building
JPS58185838A (en) Construction of building by precast concrete member