[go: up one dir, main page]

WO2018177307A1 - Fabricated underground building and construction method thereof - Google Patents

Fabricated underground building and construction method thereof Download PDF

Info

Publication number
WO2018177307A1
WO2018177307A1 PCT/CN2018/080791 CN2018080791W WO2018177307A1 WO 2018177307 A1 WO2018177307 A1 WO 2018177307A1 CN 2018080791 W CN2018080791 W CN 2018080791W WO 2018177307 A1 WO2018177307 A1 WO 2018177307A1
Authority
WO
WIPO (PCT)
Prior art keywords
wall
pile
chain
cutter
chain cutter
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Ceased
Application number
PCT/CN2018/080791
Other languages
French (fr)
Chinese (zh)
Inventor
王燏斌
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Individual
Original Assignee
Individual
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Individual filed Critical Individual
Publication of WO2018177307A1 publication Critical patent/WO2018177307A1/en
Anticipated expiration legal-status Critical
Ceased legal-status Critical Current

Links

Images

Classifications

    • EFIXED CONSTRUCTIONS
    • E02HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
    • E02DFOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
    • E02D29/00Independent underground or underwater structures; Retaining walls
    • E02D29/045Underground structures, e.g. tunnels or galleries, built in the open air or by methods involving disturbance of the ground surface all along the location line; Methods of making them

Definitions

  • the invention relates to a prefabricated underground building and a construction method thereof, and belongs to the technical field of civil engineering foundation construction.
  • the existing large-scale basic technology adopts the overall excavation construction method, with long construction period, high labor intensity and poor working environment safety.
  • the invention provides a fabricated underground building and a construction method thereof, the purpose of which is to overcome the defects of the prior art, and the main advantages thereof: the assembled underground building is composed of walls and piles, and the wall and the pile itself are excavated. Chain cutters at the bottom of the rock, prefabricated walls and piles of the factory, on-site block or overall drop, simple construction, short construction period and low cost.
  • the assembled underground building comprises a wall 1 and a pile 2, and the adjacent walls 1 are integrally connected by the pile 2, and the structure of the connection between the wall 1 and the pile 2 adopts a concave-convex embedded structure.
  • the joint of the wall 1 is a convex portion
  • the joint of the pile 2 is a concave portion
  • each concave portion is a groove having an opening in the middle of the cavity
  • the convex portion of the wall 1 is embedded in the concave portion of the pile 2, and the convex portion of the wall 1
  • the thickness of the joint between the end and the wall 1 is greater than or equal to the thickness of the wall 1.
  • the width of the groove portion of the pile 2 is greater than or equal to the thickness of the joint between the end of the wall 1 and the wall 1, and is smaller than the maximum of the convex portion at the interface of the wall 1. Thickness; wall 1 includes a wall 1-1, a wall 1-2 and a cross wall 1-3; the pile 2 is divided into two walls, three walls and four walls; during construction, the pile 2 is first After the depth is set, the wall 1 is re-constructed; the bottom and side of the wall 1 are provided with a track 4 running on the chain cutter 3, and the chain 4 is mounted on the track 4 during construction.
  • the width of the chain cutter 3 is smaller than the width of the groove of the pile 2.
  • the chain cutter 3 is composed of a chain 3-1 and a cutter 3-2 mounted on the chain 3-1.
  • the chain cutter 3 works, only the rock at the bottom of the wall 1 is excavated, and the chain cutter 3 runs from the bottom to the top. A bottom wall with excavated rock and soil to the top, and a bottom wall of a chain cutter 3 run down.
  • the bottom and the side of the pile 2 are provided with a track 4 on which the chain cutter 3 is operated.
  • the track 4 is provided with a chain cutter 3, and the chain cutter 3 is composed of a chain 3-1 and a cutter 3-2 mounted on the chain 3-1.
  • the invention has the advantages that the wall and the pile itself have a chain cutter for excavating the bottom rock, and the factory prefabrication, on-site block or overall descending construction method, the construction is simple, the construction period is short, and the cost is low.
  • FIG. 1 is a partial schematic view of a prefabricated underground building integrally formed by connecting the wall 1 and the pile 2, and is also a structural schematic view of the structure of the joint between the wall 1 and the pile 2 adopting a concave-convex embedded structure, and is also operated by the side chain cutter 3 of the wall 1
  • the schematic diagram of the structure of the track is also a structural diagram of the thickness t of the joint between the end of the boss and the wall 1;
  • FIG. 2 is a schematic view of the A direction of FIG. 1 , and is a structural schematic view of the construction wall 1 after the construction pile 2 is set to a depth, and is also composed of a driving power unit 5-1, a spoil processing unit 5-2 and a frame 5-3.
  • Figure 3 is a BB view of Figure 2 (with the chain cutter 3 removed), also a schematic view of the structure of the rail 4 running on the bottom chain cutter 3 of the wall 1-1, and also the mud nozzle 6 of the mud pipeline device 6 on the wall 1-1. 1 and a schematic view of the structure of the mud pipeline 6-2;
  • FIG. 5 is a schematic structural view of a chain cutter 3 capable of realizing space bending, and is also a schematic structural view of the chain 3-1 and the cutter 3-2;
  • FIG. 6 is a schematic structural view of the T-shaped wall 1-2, and is also a structural schematic view of the junction of the three end portions of the wall 1-2 being a convex portion, and is also a thickness t of the junction of the end of the wall 1-2 convex portion and the wall 1-2. a structural schematic view of the thickness greater than the middle of the wall 1-2;
  • FIG. 7 is a schematic structural view of the cross wall 1-3, and is also a structural schematic view of the joint of the wall 1-3 being a convex portion, and the thickness t of the connection between the end of the wall 1-3 and the wall 1-3 is greater than the wall 1- 3 structural schematic diagram of the thickness of the middle;
  • FIG. 8 is a schematic structural view of the chain cutter driving device 5 composed of the driving power device 5-1, the spoil processing device 5-2, and the frame 5-3, and is also a rocker driving the chain knife 3 to excavate the bottom of the pile 2A.
  • Figure 9 is a view of the A-A of Figure 8, and is also a schematic structural view of the construction state of the I-type tooling 2-1 in the pile 2A;
  • Figure 10 is a schematic view showing the structure of the pile 2A having two wall 1 interfaces, the joint being a concave portion, and the structure of the I-type tooling 2-1 provided with the chain cutter running track 4;
  • Figure 11 is a schematic structural view showing the construction state of the Type I tooling 2-1 and the Type II tooling 2-2 in the pile 2B;
  • FIG. 12 is a structural schematic view of the pile 2B having three recessed interfaces, and is also a schematic structural view of the type II tooling 2-2, which is also a structural schematic view of the rail 4 of the side chain cutter 3 of the pile 2B, and also the bottom edge of the rail 4.
  • Figure 13 is a schematic structural view showing the construction state of the Type I tooling 2-1 and the Type II tooling 2-2 in the pile 2C;
  • Figure 14 is a schematic view showing the structure of the pile 2C having four recessed interfaces
  • 15 is a schematic structural view showing a structure in which a joint between a wall 1 and a pile 2A adopts a concave-convex embedded structure
  • Figure 16 is a schematic view showing the structure in which the pile 2B is transported to the installation place, and the chain cutter 3 and the chain cutter driving device 5 are attached to the pile 2B;
  • Figure 17 is a structural schematic view showing that the chain cutter driving device 5 drives the chain cutter 3 to excavate the bottom of the pile 2B, and the pile 2B and the chain cutter 3 are lowered into position;
  • Figure 18 is a schematic view showing the structure after the pile 2B is lowered to a set depth and the chain cutter driving device 5 and the chain cutter 3 are removed;
  • Figure 19 is a schematic view showing the construction of two piles 2B according to the set requirements
  • Figure 20 is a schematic view showing the structure of the I-type tooling 2-1 after being taken out from the pile 2B;
  • Figure 21 is a structural view showing the attachment of the chain cutter 3 and the chain cutter driving device 5 to the wall 1-1, and embedding the convex portion of the wall 1-1 into the recessed groove of the pile 2B;
  • Figure 22 is a schematic view of the bottom of the wall 1-1 with the chain cutter 3 excavating the earth and soil, the side of the chain knife 3 running from the bottom up, the excavated geotechnical belt is brought to the top, and the wall 1-1 and the bottom chain knife 3 are lowered together. ;
  • Figure 23 is a schematic view showing the structure of the concrete in the cavity of the groove of the wall 1-1 and the pile 2B, and the concrete is poured; and the structure of the underground continuous wall composed of the wall 1-1 and the pile 2B;
  • Figure 24 is a view of the A-A of Figure 23, and is a structural schematic view of excavating the rock in the underground continuous wall composed of the wall 1-1 and the pile 2B for the construction of the basement;
  • Figure 25 is a schematic view showing the structure of the underground structure composed of the wall 1-1 and the pile 2A;
  • Figure 26 is a view taken along line A-A of Figure 25;
  • Figure 27 is a schematic view showing the structure of the underground structure composed of the T-shaped wall 1-2.
  • 1 in the figure is the wall of the assembled underground building, including a wall 1-1, a T-shaped wall 1-2 and a cross wall 1-3; 1-1 is a wall; 1-2 is a T-wall; 1-3 It is a cross wall; 2 is a pile of prefabricated underground building.
  • two-wall interface pile 2A three-wall interface pile 2B and four-wall interface pile 2C
  • 2A is a two-wall interface pile
  • 2B is a three-wall interface Pile
  • 2C is the pile of four-wall interface
  • 2-1 is the type I tooling with the chain knife 3 running track 4 when the pile 2 is constructed, the pile 2 needs to be extracted after the construction is completed
  • 2-2 is the pile II construction II Type tooling, pile 2 needs to be taken out after construction
  • 3 is a chain cutter for excavating rock and soil, consisting of chain 3-1 and cutter 3-2 installed on chain 3-1
  • 3-1 is chain constituting chain cutter 3.
  • 3-2 is a cutter constituting the chain cutter 3; 4 is a rail on which the bottom and side of the wall 1 or the pile 2 are provided with the chain cutter 3; 5 is a chain cutter driving device, which is driven by the driving power device 5-1 and spoil The device 5-2 and the frame 5-3 are composed; 5-1 is the driving power device; 5-2 is the spoil handling device; 5-3 is the frame; 6 is the mud pipeline device; 6-1 is the wall 1 or Mud nozzle on the bottom of pile 2; 6-2 is the mud line inside wall 1 or pile 2; 7 is the wall 1 or the side cover of the pile 2 on the outer side of the rail 4 with a beveled edge; t is the thickness of the joint between the end of the boss and the wall 1.
  • the prefabricated underground building comprises a wall 1 and a pile 2, and the adjacent wall 1 is integrally connected by the pile 2.
  • the structure of the connection between the wall 1 and the pile 2 adopts a concave-convex embedded structure, and the connection of the wall 1 is convex.
  • the joint of the pile 2 is a concave portion, each concave portion is a groove having an opening in the middle of the pile, the convex portion of the wall 1 is embedded in the concave portion of the pile 2, and the end portion of the convex portion of the wall 1 is at the interface with the wall 1
  • the thickness is greater than or equal to the thickness of the wall 1
  • the width of the groove portion of the pile 2 is greater than or equal to the thickness of the joint between the tail end of the wall 1 and the wall 1, and is smaller than the maximum thickness of the convex portion at the interface of the wall 1
  • the wall 1 includes a word Wall 1-1, T-wall 1-2 and cross wall 1-3
  • Pile 2 is divided into two wall interface, three-wall interface and four-wall interface; during construction, first construct the pile 2 to the set depth, then re-construction
  • the wall 1; the bottom and the side of the wall 1 are provided with a track 4 for the operation of the chain cutter 3, and the track 4 is provided with a chain cutter 3 at the
  • the bottom and the side of the pile 2 are provided with a track 4 on which the chain cutter 3 is operated.
  • the track 4 is provided with a chain cutter 3, and the chain cutter 3 is composed of a chain 3-1 and a cutter 3-2 mounted on the chain 3-1.
  • the chain cutter 3 only excavates the rock and soil at the bottom of the pile 2, and the excavated geotechnical soil at the bottom of the pile 2 is brought upward by the chain cutter 3 running downward and upward, and the pile 2 and the bottom chain cutter 3 are simultaneously operated downward.
  • the T-wall 1-2 and the cross wall 1-3 are both composed of a wall 1-1.
  • the two wall interface is applied to the connection with two walls 1 at the interface.
  • the three-wall interface is applied to the connection with three walls 1 at the interface.
  • the four-wall interface is applied to the connection with four walls 1 at the interface.
  • the underground building is an underground continuous wall.
  • the underground building is a revetment.
  • the assembled underground building includes a wall 1 and a pile 2, and adjacent walls 1 are integrally connected by a pile 2.
  • the structure of the connection between the wall 1 and the pile 2 is embedded in a concave-convex type.
  • the structure, the joint of the wall 1 is a convex part
  • the joint of the pile 2 is a concave part
  • each concave part is a groove with an opening in the middle of the cavity
  • the convex part of the wall 1 is embedded in the concave part of the pile 2
  • the wall 1 is convex
  • the thickness of the joint between the tail end and the wall 1 is greater than or equal to the thickness of the wall 1.
  • the width of the groove portion of the pile 2 is greater than or equal to the thickness of the joint between the end of the convex portion of the wall 1 and the wall 1, and is smaller than the convex portion at the interface of the wall 1.
  • the maximum thickness of the construction first, after the construction of the pile 2 to the set depth, the construction wall 1; the bottom and the side of the wall 1 are provided with the track 4 running the chain knife 3, and the track 4 is equipped with a chain knife 3 and a chain knife during construction.
  • the width of 3 is smaller than the width of the groove of the pile 2, and the chain cutter 3 is composed of a chain 3-1 and a cutter 3-2 mounted on the chain 3-1. When the chain cutter 3 is working, only the rock at the bottom of the wall 1 is excavated.
  • the excavated geotechnical soil at the bottom of the wall 1 is brought up to the top by the chain cutter 3 running downwards, and the wall 1 and the bottom chain cutter 3 are simultaneously operated downward; the mud pipeline device 6 is on the bottom of the wall 1 or the pile 2 6-1 and mud nozzles pile wall 1 or inside the line 6-2 2 composition.
  • the wall 1 includes three structures: a wall 1-1, a typographic wall 1-2, and a cross wall 1-3. Both the T-shaped wall 1-2 and the cross wall 1-3 are It consists of a wall 1-1, and the bottom and side of the wall 1 are provided with a track 4 on which the chain cutter 3 operates.
  • the bottom and the side of the pile 2 are provided with a rail 4 for the operation of the chain cutter 3.
  • a chain cutter 3 is mounted, and the chain cutter 3 is attached by the chain 3-1 and mounted on the chain 3-1.
  • the upper cutter 3-2 is composed.
  • the chain cutter 3 works, only the rock soil at the bottom of the pile 2 is excavated, and the excavated rock soil at the bottom of the pile 2 is brought to the top by the chain cutter 3 running downward and upward, and the pile 2 and the bottom chain cutter 3 At the same time running down; there are three structural forms: two-wall interface pile 2A, three-wall interface pile 2B and four-wall interface pile 2C.
  • the concrete construction method in which the wall 1-1 and the pile 2B are integrally connected to form a fabricated underground building has the following steps:
  • Pile 2B at the bottom of the pile 2B excavates the rock and soil, and the side of the chain knife 3 running from the bottom up to bring the excavated rock soil to the top;
  • the wall-type 1-1 and the pile 2B are integrally connected to form a prefabricated underground building which is an underground continuous wall. First, the earth and earth are excavated in the underground continuous wall, and then other construction of the basement is carried out.
  • the assembled underground structure is integrally formed by the wall 1-2 and the pile 2A.
  • the assembled underground structure formed by a plurality of walls 1-2 is a revetment.

Landscapes

  • Engineering & Computer Science (AREA)
  • Environmental & Geological Engineering (AREA)
  • Life Sciences & Earth Sciences (AREA)
  • General Life Sciences & Earth Sciences (AREA)
  • Mining & Mineral Resources (AREA)
  • Paleontology (AREA)
  • Civil Engineering (AREA)
  • General Engineering & Computer Science (AREA)
  • Structural Engineering (AREA)
  • Bulkheads Adapted To Foundation Construction (AREA)

Abstract

A fabricated underground building, comprising walls (1) and piles (2). Adjacent walls (1) are connected into a whole by means of piles (2); a concave-convex embedded structure is provided at each joint between the walls (1) and the piles (2); a convex portion is provided at the joint of the wall (1) and a concave portion is provided at the joint of a pile (2); the convex portion of the wall (1) is embedded into the concave portion of the pile (2); the bottom and side surfaces of the walls (1) are provided with tracks (4) where chain cutters (3) can operate therein; the chain cutter (3) is mounted on the track (4) during construction; the width of the chain cutter (3) is smaller than that of a recess opening of the pile (2); the chain cutter (3) is composed of a chain (3-1) and a cutter (3-2) mounted on the chain (3-1); during construction, the chain cutter (3) merely excavates rock at the bottom of the wall (1); the chain cutter (3) running from bottom to top brings the excavated rock upward from the bottom of the wall (1); and the wall (1) and the bottom chain cutter (3) move downwards simultaneously. Also disclosed is a construction method of the fabricated underground building. The wall (1) and the pile (2) are prefabricated by a factory and are provided with the chain cutter (3) for excavating rock at the bottom; after the pile (2) is constructed to a set depth, the wall (1) is then constructed. The construction is simple, the construction period is short, and the costs are low.

Description

一种装配式地下建筑及其施工法Assembled underground building and construction method thereof 技术领域Technical field

本发明涉及的是一种装配式地下建筑及其施工法,属于土木工程基础施工技术领域。The invention relates to a prefabricated underground building and a construction method thereof, and belongs to the technical field of civil engineering foundation construction.

背景技术Background technique

现有大型基础技术采用整体开挖施工方式,施工周期长,劳动强度大,工作环境安全度差。The existing large-scale basic technology adopts the overall excavation construction method, with long construction period, high labor intensity and poor working environment safety.

发明内容Summary of the invention

本发明提出的是一种装配式地下建筑及其施工法,其目的旨在克服现有技术存在的缺陷,其主要优点:装配式地下建筑由墙和桩组成,墙和桩自身带有挖掘其底部岩土的链刀,工厂预制墙和桩,现场分块或者整体下降,施工简单,施工周期短,成本低。The invention provides a fabricated underground building and a construction method thereof, the purpose of which is to overcome the defects of the prior art, and the main advantages thereof: the assembled underground building is composed of walls and piles, and the wall and the pile itself are excavated. Chain cutters at the bottom of the rock, prefabricated walls and piles of the factory, on-site block or overall drop, simple construction, short construction period and low cost.

本发明的技术解决方案:装配式地下建筑包括墙1和桩2,相邻的墙1之间是通过桩2连接成一体的,墙1与桩2连接处的结构采用凹凸型嵌入式结构,墙1的连接处为凸部,桩2的连接处为凹部,每个凹部都是中间设有空腔的开口的凹槽,墙1的凸部嵌入桩2的凹部内,墙1凸部尾端与墙1连接处的厚度大于或等于墙1的厚度,桩2凹槽口部的宽度大于或等于墙1凸部尾端与墙1连接处的厚度,小于墙1接口处凸部的最大厚度;墙1包括一字墙1-1、丁字墙1-2和十字墙1-3;桩2分两墙接口、三墙接口和四墙接口三种结构;施工时,先施工桩2至设定深度后,再施工墙1;墙1的底部和侧面设有链刀3运行的轨道4,施工时轨道4上装有链刀3,链刀3的宽度小于桩2凹槽口部的宽度,链刀3由链条3-1和安装在链条3-1上的刀具3-2组成,链刀3工作时仅挖掘墙1底部的岩土,由下向上运行的链刀3将墙1底部已挖掘的岩土带至上方,墙1和底部链刀3同时向下运行。The technical solution of the invention: the assembled underground building comprises a wall 1 and a pile 2, and the adjacent walls 1 are integrally connected by the pile 2, and the structure of the connection between the wall 1 and the pile 2 adopts a concave-convex embedded structure. The joint of the wall 1 is a convex portion, and the joint of the pile 2 is a concave portion, each concave portion is a groove having an opening in the middle of the cavity, the convex portion of the wall 1 is embedded in the concave portion of the pile 2, and the convex portion of the wall 1 The thickness of the joint between the end and the wall 1 is greater than or equal to the thickness of the wall 1. The width of the groove portion of the pile 2 is greater than or equal to the thickness of the joint between the end of the wall 1 and the wall 1, and is smaller than the maximum of the convex portion at the interface of the wall 1. Thickness; wall 1 includes a wall 1-1, a wall 1-2 and a cross wall 1-3; the pile 2 is divided into two walls, three walls and four walls; during construction, the pile 2 is first After the depth is set, the wall 1 is re-constructed; the bottom and side of the wall 1 are provided with a track 4 running on the chain cutter 3, and the chain 4 is mounted on the track 4 during construction. The width of the chain cutter 3 is smaller than the width of the groove of the pile 2. The chain cutter 3 is composed of a chain 3-1 and a cutter 3-2 mounted on the chain 3-1. When the chain cutter 3 works, only the rock at the bottom of the wall 1 is excavated, and the chain cutter 3 runs from the bottom to the top. A bottom wall with excavated rock and soil to the top, and a bottom wall of a chain cutter 3 run down.

桩2的底部和侧面设有链刀3运行的轨道4,施工时轨道4上装有链刀3,链刀3由链条3-1和安装在链条3-1上的刀具3-2组成,链刀3工作时仅挖掘桩2底部的岩土,由下向上运行的链刀3将桩2底部已挖掘的岩土带至上方,桩2和底部链刀3同时向下运行。The bottom and the side of the pile 2 are provided with a track 4 on which the chain cutter 3 is operated. During the construction, the track 4 is provided with a chain cutter 3, and the chain cutter 3 is composed of a chain 3-1 and a cutter 3-2 mounted on the chain 3-1. When the knife 3 is working, only the rock soil at the bottom of the pile 2 is excavated, and the excavated rock soil at the bottom of the pile 2 is brought to the top by the chain knife 3 running downward and upward, and the pile 2 and the bottom chain knife 3 are simultaneously operated downward.

本发明的优点:墙和桩自身带有挖掘其底部岩土的链刀,采用工厂预制, 现场分块或者整体下降的施工方法,施工简单,施工周期短,成本低。The invention has the advantages that the wall and the pile itself have a chain cutter for excavating the bottom rock, and the factory prefabrication, on-site block or overall descending construction method, the construction is simple, the construction period is short, and the cost is low.

附图说明DRAWINGS

图1是墙1与桩2连接成一体形成的装配式地下建筑的局部示意图,也是墙1与桩2连接处的结构采用凹凸型嵌入式结构的结构示意图,也是墙1侧面链刀3运行的轨道的结构示意图,也是凸台尾端与墙1连接处厚度t的结构示意图;1 is a partial schematic view of a prefabricated underground building integrally formed by connecting the wall 1 and the pile 2, and is also a structural schematic view of the structure of the joint between the wall 1 and the pile 2 adopting a concave-convex embedded structure, and is also operated by the side chain cutter 3 of the wall 1 The schematic diagram of the structure of the track is also a structural diagram of the thickness t of the joint between the end of the boss and the wall 1;

图2是图1的A向示意图,也是施工桩2至设定深度后,施工墙1的结构示意图,也是由驱动动力装置5-1、弃土处理装置5-2和机架5-3组成的链刀驱动装置5的结构示意图;2 is a schematic view of the A direction of FIG. 1 , and is a structural schematic view of the construction wall 1 after the construction pile 2 is set to a depth, and is also composed of a driving power unit 5-1, a spoil processing unit 5-2 and a frame 5-3. Schematic diagram of the chain cutter driving device 5;

图3是图2的B-B视图(去除链刀3),也是墙1-1的底部链刀3运行的轨道4的结构示意图,也是泥浆管路装置6在墙1-1上的泥浆喷嘴6-1和泥浆管路6-2的结构示意图;Figure 3 is a BB view of Figure 2 (with the chain cutter 3 removed), also a schematic view of the structure of the rail 4 running on the bottom chain cutter 3 of the wall 1-1, and also the mud nozzle 6 of the mud pipeline device 6 on the wall 1-1. 1 and a schematic view of the structure of the mud pipeline 6-2;

图4是链刀3的结构示意图,也是链条3-1和刀具3-2的结构示意图;4 is a schematic structural view of the chain cutter 3, and is also a schematic structural view of the chain 3-1 and the cutter 3-2;

图5是可实现空间弯曲的链刀3的结构示意图,也是链条3-1和刀具3-2的结构示意图;FIG. 5 is a schematic structural view of a chain cutter 3 capable of realizing space bending, and is also a schematic structural view of the chain 3-1 and the cutter 3-2;

图6是丁字墙1-2的结构示意图,也是墙1-2的三处端部连接处为凸部的结构示意图,也是墙1-2凸部尾端与墙1-2连接处的厚度t大于墙1-2中间的厚度的结构示意图;6 is a schematic structural view of the T-shaped wall 1-2, and is also a structural schematic view of the junction of the three end portions of the wall 1-2 being a convex portion, and is also a thickness t of the junction of the end of the wall 1-2 convex portion and the wall 1-2. a structural schematic view of the thickness greater than the middle of the wall 1-2;

图7是十字墙1-3的结构示意图,也是墙1-3的连接处为凸部的结构示意图,也是墙1-3凸部尾端与墙1-3连接处的厚度t大于墙1-3中间的厚度的结构示意图;7 is a schematic structural view of the cross wall 1-3, and is also a structural schematic view of the joint of the wall 1-3 being a convex portion, and the thickness t of the connection between the end of the wall 1-3 and the wall 1-3 is greater than the wall 1- 3 structural schematic diagram of the thickness of the middle;

图8是由驱动动力装置5-1、弃土处理装置5-2和机架5-3组成链刀驱动装置5的结构示意图,也是链刀驱动装置5驱动链刀3挖掘桩2A底部的岩土,并一起下降的施工结构示意图;8 is a schematic structural view of the chain cutter driving device 5 composed of the driving power device 5-1, the spoil processing device 5-2, and the frame 5-3, and is also a rocker driving the chain knife 3 to excavate the bottom of the pile 2A. Schematic diagram of the construction structure of the soil, and descending together;

图9是图8的A-A视图,也是Ⅰ型工装2-1在桩2A内的施工状态结构示意图;Figure 9 is a view of the A-A of Figure 8, and is also a schematic structural view of the construction state of the I-type tooling 2-1 in the pile 2A;

图10是桩2A有两个墙1接口,连口处为凹部的结构示意图,也是设有链刀运行轨道4的Ⅰ型工装2-1的结构示意图;Figure 10 is a schematic view showing the structure of the pile 2A having two wall 1 interfaces, the joint being a concave portion, and the structure of the I-type tooling 2-1 provided with the chain cutter running track 4;

图11是Ⅰ型工装2-1和Ⅱ型工装2-2在桩2B内的施工状态结构示意图;Figure 11 is a schematic structural view showing the construction state of the Type I tooling 2-1 and the Type II tooling 2-2 in the pile 2B;

图12是桩2B有三个凹部接口的结构示意图,也是Ⅱ型工装2-2的结构示意图, 也是桩2B的侧面链刀3运行的轨道4的结构示意图,也是轨道4外侧的底部带刃角的侧面罩7的结构示意图;12 is a structural schematic view of the pile 2B having three recessed interfaces, and is also a schematic structural view of the type II tooling 2-2, which is also a structural schematic view of the rail 4 of the side chain cutter 3 of the pile 2B, and also the bottom edge of the rail 4. Schematic diagram of the side cover 7;

图13是Ⅰ型工装2-1和Ⅱ型工装2-2在桩2C内的施工状态结构示意图;Figure 13 is a schematic structural view showing the construction state of the Type I tooling 2-1 and the Type II tooling 2-2 in the pile 2C;

图14是桩2C有四个凹部接口的结构示意图;Figure 14 is a schematic view showing the structure of the pile 2C having four recessed interfaces;

图15是墙1与桩2A连接处的结构采用凹凸型嵌入式结构的结构示意图;15 is a schematic structural view showing a structure in which a joint between a wall 1 and a pile 2A adopts a concave-convex embedded structure;

图16是将桩2B运至安装处,在桩2B上安装链刀3及链刀驱动装置5的结构示意图;Figure 16 is a schematic view showing the structure in which the pile 2B is transported to the installation place, and the chain cutter 3 and the chain cutter driving device 5 are attached to the pile 2B;

图17是链刀驱动装置5驱动链刀3挖掘桩2B底部岩土,桩2B和链刀3下降到位的结构示意图;Figure 17 is a structural schematic view showing that the chain cutter driving device 5 drives the chain cutter 3 to excavate the bottom of the pile 2B, and the pile 2B and the chain cutter 3 are lowered into position;

图18是桩2B下降到设定的深度后拆除链刀驱动装置5和链刀3后的结构示意图;Figure 18 is a schematic view showing the structure after the pile 2B is lowered to a set depth and the chain cutter driving device 5 and the chain cutter 3 are removed;

图19是两个桩2B按设定要求施工完的结构示意图;Figure 19 is a schematic view showing the construction of two piles 2B according to the set requirements;

图20是Ⅰ型工装2-1从桩2B抽出后的结构示意图;Figure 20 is a schematic view showing the structure of the I-type tooling 2-1 after being taken out from the pile 2B;

图21是在墙1-1上安装链刀3和链刀驱动装置5,将墙1-1的凸部嵌入桩2B的凹部槽内的结构示意图;Figure 21 is a structural view showing the attachment of the chain cutter 3 and the chain cutter driving device 5 to the wall 1-1, and embedding the convex portion of the wall 1-1 into the recessed groove of the pile 2B;

图22是墙1-1底部链刀3挖掘岩土,侧面由下向上运行的链刀3将已挖掘的岩土带至上方,墙1-1和底部的链刀3一起下降到位的结构示意图;Figure 22 is a schematic view of the bottom of the wall 1-1 with the chain cutter 3 excavating the earth and soil, the side of the chain knife 3 running from the bottom up, the excavated geotechnical belt is brought to the top, and the wall 1-1 and the bottom chain knife 3 are lowered together. ;

图23是清除墙1-1和桩2B接口部凹槽空腔内的岩土,并灌注混凝土的结构示意图,也是由墙1-1和桩2B组成的地下连续墙的结构示意图;Figure 23 is a schematic view showing the structure of the concrete in the cavity of the groove of the wall 1-1 and the pile 2B, and the concrete is poured; and the structure of the underground continuous wall composed of the wall 1-1 and the pile 2B;

图24是图23的A-A视图,也是在由墙1-1和桩2B组成的地下连续墙内挖掘岩土,进行地下室的施工的结构示意图;Figure 24 is a view of the A-A of Figure 23, and is a structural schematic view of excavating the rock in the underground continuous wall composed of the wall 1-1 and the pile 2B for the construction of the basement;

图25是由墙1-1和桩2A组成的地下建筑是驳岸的结构示意图;Figure 25 is a schematic view showing the structure of the underground structure composed of the wall 1-1 and the pile 2A;

图26是图25的A-A视图;Figure 26 is a view taken along line A-A of Figure 25;

图27是由丁字墙1-2组成的地下建筑是驳岸的结构示意图。Figure 27 is a schematic view showing the structure of the underground structure composed of the T-shaped wall 1-2.

图中的1是装配式地下建筑的墙,包括一字墙1-1、丁字墙1-2和十字墙1-3;1-1是一字墙;1-2是丁字墙;1-3是十字墙;2是装配式地下建筑的桩,有三种结构形式:两墙接口桩2A、三墙接口桩2B和四墙接口桩2C;2A是两墙接口的桩;2B是三墙接口的桩;2C是四墙接口的桩;2-1是桩2施工时,装有链刀3运行轨道4的Ⅰ型工装,桩2施工完成后需抽出;2-2是桩2施工时的Ⅱ型工装, 桩2施工完成后需抽出;3是挖掘岩土的链刀,由链条3-1和安装在链条3-1上的刀具3-2组成;3-1是组成链刀3的链条;3-2是组成链刀3的刀具;4是墙1或者桩2的底部和侧面设有链刀3运行的轨道;5是链刀驱动装置,由驱动动力装置5-1、弃土处理装置5-2和机架5-3组成;5-1是驱动动力装置;5-2是弃土处理装置;5-3是机架;6是泥浆管路装置;6-1是墙1或桩2底部上的泥浆喷嘴;6-2是墙1或桩2内部的泥浆管路;7是墙1或者桩2上轨道4外侧的底部带刃角的侧面罩;t是凸台尾端与墙1连接处的厚度。1 in the figure is the wall of the assembled underground building, including a wall 1-1, a T-shaped wall 1-2 and a cross wall 1-3; 1-1 is a wall; 1-2 is a T-wall; 1-3 It is a cross wall; 2 is a pile of prefabricated underground building. There are three structural forms: two-wall interface pile 2A, three-wall interface pile 2B and four-wall interface pile 2C; 2A is a two-wall interface pile; 2B is a three-wall interface Pile; 2C is the pile of four-wall interface; 2-1 is the type I tooling with the chain knife 3 running track 4 when the pile 2 is constructed, the pile 2 needs to be extracted after the construction is completed; 2-2 is the pile II construction II Type tooling, pile 2 needs to be taken out after construction; 3 is a chain cutter for excavating rock and soil, consisting of chain 3-1 and cutter 3-2 installed on chain 3-1; 3-1 is chain constituting chain cutter 3. 3-2 is a cutter constituting the chain cutter 3; 4 is a rail on which the bottom and side of the wall 1 or the pile 2 are provided with the chain cutter 3; 5 is a chain cutter driving device, which is driven by the driving power device 5-1 and spoil The device 5-2 and the frame 5-3 are composed; 5-1 is the driving power device; 5-2 is the spoil handling device; 5-3 is the frame; 6 is the mud pipeline device; 6-1 is the wall 1 or Mud nozzle on the bottom of pile 2; 6-2 is the mud line inside wall 1 or pile 2; 7 is the wall 1 or the side cover of the pile 2 on the outer side of the rail 4 with a beveled edge; t is the thickness of the joint between the end of the boss and the wall 1.

具体实施方式detailed description

装配式地下建筑包括墙1和桩2,相邻的墙1之间是通过桩2连接成一体的,墙1与桩2连接处的结构采用凹凸型嵌入式结构,墙1的连接处为凸部,桩2的连接处为凹部,每个凹部都是中间设有空腔的开口的凹槽,墙1的凸部嵌入桩2的凹部内,墙1凸部尾端与墙1接口处的厚度大于或等于墙1的厚度,桩2凹槽口部的宽度大于或等于墙1凸部尾端与墙1连接处的厚度,小于墙1接口处凸部的最大厚度;墙1包括一字墙1-1、丁字墙1-2和十字墙1-3;桩2分两墙接口、三墙接口和四墙接口三种结构;施工时,先施工桩2至设定深度后,再施工墙1;墙1的底部和侧面设有链刀3运行的轨道4,施工时轨道4上装有链刀3,链刀3的宽度小于桩2凹槽口部的宽度,链刀3由链条3-1和安装在链条3-1上的刀具3-2组成,链刀3工作时仅挖掘墙1底部的岩土,由下向上运行的链刀3将墙1底部已挖掘的岩土带至上方,墙1和底部链刀3同时向下运行。The prefabricated underground building comprises a wall 1 and a pile 2, and the adjacent wall 1 is integrally connected by the pile 2. The structure of the connection between the wall 1 and the pile 2 adopts a concave-convex embedded structure, and the connection of the wall 1 is convex. The joint of the pile 2 is a concave portion, each concave portion is a groove having an opening in the middle of the pile, the convex portion of the wall 1 is embedded in the concave portion of the pile 2, and the end portion of the convex portion of the wall 1 is at the interface with the wall 1 The thickness is greater than or equal to the thickness of the wall 1, and the width of the groove portion of the pile 2 is greater than or equal to the thickness of the joint between the tail end of the wall 1 and the wall 1, and is smaller than the maximum thickness of the convex portion at the interface of the wall 1; the wall 1 includes a word Wall 1-1, T-wall 1-2 and cross wall 1-3; Pile 2 is divided into two wall interface, three-wall interface and four-wall interface; during construction, first construct the pile 2 to the set depth, then re-construction The wall 1; the bottom and the side of the wall 1 are provided with a track 4 for the operation of the chain cutter 3, and the track 4 is provided with a chain cutter 3 at the time of construction, the width of the chain cutter 3 is smaller than the width of the groove portion of the pile 2, and the chain cutter 3 is made of the chain 3 -1 and the cutter 3-2 installed on the chain 3-1, the chain cutter 3 only excavates the rock at the bottom of the wall 1 when working, and the excavated geotechnical strip at the bottom of the wall 1 is driven by the chain knife 3 running downwards and upwards. The top wall and a bottom chain cutter 3 1 run down.

所述的桩2的底部和侧面设有链刀3运行的轨道4,施工时轨道4上装有链刀3,链刀3由链条3-1和安装在链条3-1上的刀具3-2组成,链刀3工作时仅挖掘桩2底部的岩土,由下向上运行的链刀3将桩2底部已挖掘的岩土带至上方,桩2和底部链刀3同时向下运行。The bottom and the side of the pile 2 are provided with a track 4 on which the chain cutter 3 is operated. During the construction, the track 4 is provided with a chain cutter 3, and the chain cutter 3 is composed of a chain 3-1 and a cutter 3-2 mounted on the chain 3-1. In the composition, the chain cutter 3 only excavates the rock and soil at the bottom of the pile 2, and the excavated geotechnical soil at the bottom of the pile 2 is brought upward by the chain cutter 3 running downward and upward, and the pile 2 and the bottom chain cutter 3 are simultaneously operated downward.

所述的丁字墙1-2和十字墙1-3均是由一字墙1-1组成的。The T-wall 1-2 and the cross wall 1-3 are both composed of a wall 1-1.

所述的两墙接口是应用于接口处有两个墙1的连接。The two wall interface is applied to the connection with two walls 1 at the interface.

所述的三墙接口是应用于接口处有三个墙1的连接。The three-wall interface is applied to the connection with three walls 1 at the interface.

所述的四墙接口是应用于接口处有四个墙1的连接。The four-wall interface is applied to the connection with four walls 1 at the interface.

所述的地下建筑是地下连续墙。The underground building is an underground continuous wall.

所述的地下建筑是驳岸。The underground building is a revetment.

所述的具体施工法有如下步骤:The specific construction method described has the following steps:

1)预制墙1和桩2;1) Prefabricated wall 1 and pile 2;

2)将墙1和桩2运至安装处;2) transport wall 1 and pile 2 to the installation;

3)在桩2上安装链刀3及链刀驱动装置等;3) Mounting the chain cutter 3 and the chain cutter driving device on the pile 2;

4)桩2底部链刀3挖掘岩土,侧面由下向上运行的链刀3将已挖掘的岩土带至上方;4) The bottom chain knife 3 of the pile 2 excavates the rock and soil, and the side of the chain knife 3 running from the bottom up brings the excavated rock soil to the top;

5)桩2和底部的链刀3一起下降;5) the pile 2 and the chain cutter 3 at the bottom are lowered together;

6)桩2下降到设定的深度,拆除链刀驱动装置和链刀3;6) The pile 2 is lowered to the set depth, and the chain cutter driving device and the chain cutter 3 are removed;

7)在墙1上安装链刀3及链刀驱动装置等;7) Install the chain cutter 3 and the chain cutter driving device on the wall 1;

8)将墙1的凸部嵌入桩2的凹部槽内;8) embedding the convex portion of the wall 1 into the recessed groove of the pile 2;

9)墙1底部链刀3挖掘岩土,侧面由下向上运行的链刀3将已挖掘的岩土带至上方;9) The bottom chain knife 3 of the wall 1 excavates the rock and soil, and the side of the chain knife 3 running from the bottom up brings the excavated rock soil to the top;

10)墙1和底部的链刀3一起下降;10) Wall 1 and the chain cutter 3 at the bottom are lowered together;

11)墙1下降到设定的深度,拆除链刀驱动装置和链刀3;11) The wall 1 is lowered to the set depth, and the chain cutter driving device and the chain cutter 3 are removed;

12)清除墙1和桩2接口部凹槽空腔内的岩土,并灌注混凝土;12) removing the rock and soil in the groove cavity of the interface part of the wall 1 and the pile 2, and pouring the concrete;

重复上述2)至12)的施工,直至完成全部墙1和桩2的施工。The construction of the above 2) to 12) is repeated until the construction of all the walls 1 and 2 is completed.

所述的地下建筑完成墙1和桩2的施工后,再挖掘四周墙内的岩土,进行地下室的施工。After the underground building completes the construction of the wall 1 and the pile 2, the rock and soil in the surrounding wall are excavated to carry out the construction of the basement.

下面结合附图进一步描述本发明:The invention is further described below in conjunction with the drawings:

如图1~图5所示,装配式地下建筑包括墙1和桩2,相邻的墙1之间是通过桩2连接成一体的,墙1与桩2连接处的结构采用凹凸型嵌入式结构,墙1的连接处为凸部,桩2的连接处为凹部,每个凹部都是中间设有空腔的开口的凹槽,墙1的凸部嵌入桩2的凹部内,墙1凸部尾端与墙1连接处的厚度大于或等于墙1的厚度,桩2凹槽口部的宽度大于或等于墙1凸部尾端与墙1连接处的厚度,小于墙1接口处凸部的最大厚度;施工时,先施工桩2至设定深度后,再施工墙1;墙1的底部和侧面设有链刀3运行的轨道4,施工时轨道4上装有链刀3,链刀3的宽度小于桩2凹槽口部的宽度,链刀3由链条3-1和安装在链条3-1上的刀具3-2组成,链刀3工作时仅挖掘墙1底部的岩土,由下向上运行的链刀3将墙1底部已挖掘的岩土带至上方,墙1和底部链刀3同时向下运行;泥浆管路装置 6由墙1或桩2底部上的泥浆喷嘴6-1和墙1或桩2内部的管路6-2组成。As shown in FIG. 1 to FIG. 5, the assembled underground building includes a wall 1 and a pile 2, and adjacent walls 1 are integrally connected by a pile 2. The structure of the connection between the wall 1 and the pile 2 is embedded in a concave-convex type. The structure, the joint of the wall 1 is a convex part, the joint of the pile 2 is a concave part, each concave part is a groove with an opening in the middle of the cavity, the convex part of the wall 1 is embedded in the concave part of the pile 2, the wall 1 is convex The thickness of the joint between the tail end and the wall 1 is greater than or equal to the thickness of the wall 1. The width of the groove portion of the pile 2 is greater than or equal to the thickness of the joint between the end of the convex portion of the wall 1 and the wall 1, and is smaller than the convex portion at the interface of the wall 1. The maximum thickness of the construction; first, after the construction of the pile 2 to the set depth, the construction wall 1; the bottom and the side of the wall 1 are provided with the track 4 running the chain knife 3, and the track 4 is equipped with a chain knife 3 and a chain knife during construction. The width of 3 is smaller than the width of the groove of the pile 2, and the chain cutter 3 is composed of a chain 3-1 and a cutter 3-2 mounted on the chain 3-1. When the chain cutter 3 is working, only the rock at the bottom of the wall 1 is excavated. The excavated geotechnical soil at the bottom of the wall 1 is brought up to the top by the chain cutter 3 running downwards, and the wall 1 and the bottom chain cutter 3 are simultaneously operated downward; the mud pipeline device 6 is on the bottom of the wall 1 or the pile 2 6-1 and mud nozzles pile wall 1 or inside the line 6-2 2 composition.

如图1、图6和图7所示,墙1包括一字墙1-1、丁字墙1-2和十字墙1-3三种结构,丁字墙1-2和十字墙1-3均是由一字墙1-1组成,墙1的底部和侧面设有有链刀3运行的轨道4。As shown in FIG. 1, FIG. 6, and FIG. 7, the wall 1 includes three structures: a wall 1-1, a typographic wall 1-2, and a cross wall 1-3. Both the T-shaped wall 1-2 and the cross wall 1-3 are It consists of a wall 1-1, and the bottom and side of the wall 1 are provided with a track 4 on which the chain cutter 3 operates.

如图8~图15所示,桩2的底部和侧面设有链刀3运行的轨道4,施工时轨道4上装有链刀3,链刀3由链条3-1和安装在链条3-1上的刀具3-2组成,链刀3工作时仅挖掘桩2底部的岩土,由下向上运行的链刀3将桩2底部已挖掘的岩土带至上方,桩2和底部链刀3同时向下运行;有三种结构形式:两墙接口桩2A、三墙接口桩2B和四墙接口桩2C。As shown in Fig. 8 to Fig. 15, the bottom and the side of the pile 2 are provided with a rail 4 for the operation of the chain cutter 3. When the rail 4 is installed, a chain cutter 3 is mounted, and the chain cutter 3 is attached by the chain 3-1 and mounted on the chain 3-1. The upper cutter 3-2 is composed. When the chain cutter 3 works, only the rock soil at the bottom of the pile 2 is excavated, and the excavated rock soil at the bottom of the pile 2 is brought to the top by the chain cutter 3 running downward and upward, and the pile 2 and the bottom chain cutter 3 At the same time running down; there are three structural forms: two-wall interface pile 2A, three-wall interface pile 2B and four-wall interface pile 2C.

如图16~图24所示,由墙1-1与桩2B连接成一体形成装配式地下建筑的具体施工法有如下步骤:As shown in FIG. 16 to FIG. 24, the concrete construction method in which the wall 1-1 and the pile 2B are integrally connected to form a fabricated underground building has the following steps:

1)预制墙1-1和桩2B;1) Prefabricated wall 1-1 and pile 2B;

2)将墙1-1和桩2B运至安装处;2) transport wall 1-1 and pile 2B to the installation;

3)在桩2B上安装链刀3及链刀驱动装置等;3) attaching the chain cutter 3 and the chain cutter driving device to the pile 2B;

4)桩2B底部链刀3挖掘岩土,侧面由下向上运行的链刀3将已挖掘的岩土带至上方;4) Pile 2B at the bottom of the pile 2B excavates the rock and soil, and the side of the chain knife 3 running from the bottom up to bring the excavated rock soil to the top;

5)桩2B和底部的链刀3一起下降;5) the pile 2B and the chain cutter 3 at the bottom are lowered together;

6)桩2B下降到设定的深度,拆除链刀驱动装置5和链刀3;6) The pile 2B is lowered to a set depth, and the chain cutter driving device 5 and the chain cutter 3 are removed;

7)在墙1-1上安装链刀3及链刀驱动装置5等;7) mounting the chain cutter 3 and the chain cutter driving device 5 on the wall 1-1;

8)将墙1-1的凸部嵌入桩2B的凹部槽内;8) embedding the convex portion of the wall 1-1 into the recessed groove of the pile 2B;

9)墙1-1底部链刀3挖掘岩土,侧面由下向上运行的链刀3将已挖掘的岩土带至上方;9) The bottom chain knife 3 of the wall 1-1 excavates the rock and soil, and the side of the chain knife 3 running from the bottom up brings the excavated rock soil to the top;

10)墙1-1和底部的链刀3一起下降;10) Wall 1-1 and the chain knife 3 at the bottom are lowered together;

11)墙1-1下降到设定的深度,拆除链刀驱动装置5和链刀3;11) The wall 1-1 is lowered to the set depth, and the chain cutter driving device 5 and the chain knife 3 are removed;

12)清除墙1-1和桩2B接口部凹槽空腔内的岩土,并灌注混凝土;12) Clear the rock in the cavity of the groove of the wall 1-1 and the pile 2B interface, and inject the concrete;

重复上述2)至12)的施工,直至完成全部墙1-1和桩2B的施工;Repeat the above construction of 2) to 12) until the completion of the construction of all the walls 1-1 and 2B;

由墙1-1和桩2B连接成一体形成装配式地下建筑是地下连续墙,先在地下连续墙内挖掘岩土,再进行地下室的其他施工。The wall-type 1-1 and the pile 2B are integrally connected to form a prefabricated underground building which is an underground continuous wall. First, the earth and earth are excavated in the underground continuous wall, and then other construction of the basement is carried out.

如图25和图26所示,由墙1-2和桩2A连接成一体形成装配式地下建筑 是驳岸。As shown in Figs. 25 and 26, the assembled underground structure is integrally formed by the wall 1-2 and the pile 2A.

如图27所示,由若干个墙1-2形成装配式地下建筑是驳岸。As shown in Fig. 27, the assembled underground structure formed by a plurality of walls 1-2 is a revetment.

Claims (10)

一种装配式地下建筑,其特征是装配式地下建筑包括墙(1)和桩(2),相邻的墙(1)之间是通过桩(2)连接成一体的,墙(1)与桩(2)连接处的结构采用凹凸型嵌入式结构,墙(1)的连接处为凸部,桩(2)的连接处为凹部,每个凹部都是中间设有空腔的开口的凹槽,墙(1)的凸部嵌入桩(2)的凹部内,墙(1)凸部尾端与墙(1)连接处的厚度大于或等于墙(1)的厚度,桩(2)凹槽口部的宽度大于或等于墙(1)凸部尾端与墙(1)连接处的厚度,小于墙(1)接口处凸部的最大厚度;墙(1)包括一字墙(1-1)、丁字墙(1-2)和十字墙(1-3);桩(2)分两墙接口、三墙接口和四墙接口三种结构;施工时,先施工桩(2)至设定深度后,再施工墙(1);墙(1)的底部和侧面设有链刀(3)运行的轨道(4),施工时轨道(4)上装有链刀(3),链刀(3)的宽度小于桩(2)凹槽口部的宽度,链刀(3)由链条(3-1)和安装在链条(3-1)上的刀具(3-2)组成,链刀(3)工作时仅挖掘墙(1)底部的岩土,由下向上运行的链刀(3)将墙(1)底部已挖掘的岩土带至上方,墙(1)和底部链刀(3)同时向下运行。A prefabricated underground building characterized in that the assembled underground building comprises a wall (1) and a pile (2), and the adjacent walls (1) are integrally connected by a pile (2), the wall (1) and The structure of the joint of the pile (2) adopts a concave-convex embedded structure, the joint of the wall (1) is a convex part, and the joint of the pile (2) is a concave part, and each concave part is a concave with an opening in the middle of the cavity. The groove of the groove and the wall (1) is embedded in the recess of the pile (2), and the thickness of the joint between the end of the wall (1) and the wall (1) is greater than or equal to the thickness of the wall (1), and the pile (2) is concave. The width of the notch portion is greater than or equal to the thickness of the joint between the end of the wall (1) and the wall (1), which is smaller than the maximum thickness of the protrusion at the interface of the wall (1); the wall (1) includes a wall (1- 1), T-wall (1-2) and cross wall (1-3); pile (2) is divided into two walls, three-wall interface and four-wall interface; during construction, first construction pile (2) to set After the depth is fixed, the construction wall (1); the bottom and side of the wall (1) are provided with a chain knife (3) running track (4), and the rail (4) is equipped with a chain knife (3) and a chain knife ( 3) The width is smaller than the width of the groove of the pile (2), and the chain cutter (3) is composed of a chain (3-1) and a cutter (3-2) mounted on the chain (3-1). When the chain cutter (3) works, it only excavates the rock at the bottom of the wall (1). The chain cutter (3) running from the bottom up brings the excavated rock at the bottom of the wall (1) to the top, the wall (1) and the bottom chain. The knife (3) runs down at the same time. 根据权利要求1所述的一种装配式地下建筑,其特征是所述的桩(2)的底部和侧面设有链刀(3)运行的轨道(4),施工时轨道(4)上装有链刀(3),链刀(3)由链条(3-1)和安装在链条(3-1)上的刀具(3-2)组成,链刀(3)工作时仅挖掘桩(2)底部的岩土,由下向上运行的链刀(3)将桩(2)底部已挖掘的岩土带至上方,桩(2)和底部链刀(3)同时向下运行。A prefabricated underground building according to claim 1, characterized in that the bottom and sides of the pile (2) are provided with a track (4) running by a chain cutter (3), and the rail (4) is mounted during construction. The chain cutter (3), the chain cutter (3) consists of a chain (3-1) and a cutter (3-2) mounted on the chain (3-1), and the chain cutter (3) only excavates the pile when working (2) At the bottom of the rock, the excavated rock at the bottom of the pile (2) is brought up to the top by the chain knife (3) running up and down, and the pile (2) and the bottom chain knife (3) run downward simultaneously. 根据权利要求2所述的一种装配式地下建筑,其特征是所述的丁字墙(1-2)和十字墙(1-3)均是由一字墙(1-1)组成的。A fabricated underground building according to claim 2, wherein said T-shaped wall (1-2) and cross wall (1-3) are each composed of a wall (1-1). 根据权利要求1所述的一种装配式地下建筑,其特征是所述的两墙接口是应用于接口处有两个墙(1)的连接。A fabricated underground building according to claim 1, wherein said two wall interface is applied to a connection having two walls (1) at the interface. 根据权利要求1所述的一种装配式地下建筑,其特征是所述的三墙接口是应用于接口处有三个墙(1)的连接。A fabricated underground building according to claim 1, wherein said three-wall interface is applied to a connection having three walls (1) at the interface. 根据权利要求1所述的一种装配式地下建筑,其特征是所述的四墙接口是应用于接口处有四个墙(1)的连接。A fabricated underground building according to claim 1, wherein said four-wall interface is a connection applied to four walls (1) at the interface. 根据权利要求1所述的一种装配式地下建筑,其特征是所述的地下建筑是地下连续墙。A fabricated underground building according to claim 1 wherein said underground structure is an underground continuous wall. 根据权利要求1所述的一种装配式地下建筑,其特征是所述的地下建筑是驳 岸。A fabricated underground building according to claim 1 wherein said underground structure is a bank. 根据权利要求1所述的一种装配式地下建筑,其特征是所述的具体施工法有如下步骤:A fabricated underground building according to claim 1, wherein said specific construction method has the following steps: 1)预制墙(1)和桩(2);1) Prefabricated walls (1) and piles (2); 2)将墙(1)和桩(2)运至安装处;2) transport the wall (1) and the pile (2) to the installation; 3)在桩(2)上安装链刀(3)及链刀驱动装置等;3) Install a chain cutter (3) and a chain cutter drive device on the pile (2); 4)桩(2)底部链刀(3)挖掘岩土,侧面由下向上运行的链刀(3)将已挖掘的岩土带至上方;4) Pile (2) bottom chain knife (3) excavate the rock and soil, and the side of the chain knife (3) running from the bottom up to bring the excavated rock to the top; 5)桩(2)和底部的链刀(3)一起下降;5) the pile (2) and the chain knife (3) at the bottom are lowered together; 6)桩(2)下降到设定的深度,拆除链刀驱动装置和链刀(3);6) The pile (2) is lowered to the set depth, and the chain cutter driving device and the chain cutter (3) are removed; 7)在墙(1)上安装链刀(3)及链刀驱动装置等;7) Install a chain knife (3) and a chain cutter drive device on the wall (1); 8)将墙(1)的凸部嵌入桩(2)的凹部槽内;8) embedding the convex portion of the wall (1) into the recessed groove of the pile (2); 9)墙(1)底部链刀(3)挖掘岩土,侧面由下向上运行的链刀(3)将已挖掘的岩土带至上方;9) The wall (1) bottom chain knife (3) excavates the rock and soil, and the side of the chain knife (3) running from the bottom up to bring the excavated rock to the top; 10)墙(1)和底部的链刀(3)一起下降;10) The wall (1) and the chain knife (3) at the bottom are lowered together; 11)墙(1)下降到设定的深度,拆除链刀驱动装置和链刀(3);11) The wall (1) is lowered to the set depth, and the chain cutter drive and the chain cutter (3) are removed; 12)清除墙(1)和桩(2)接口部凹槽空腔内的岩土,并灌注混凝土;12) Clear the rock in the cavity of the groove of the wall (1) and the pile (2) and inject the concrete; 重复上述2)至12)的施工,直至完成全部墙(1)和桩(2)的施工。Repeat the construction of 2) to 12) above until the construction of all walls (1) and piles (2) is completed. 根据权利要求9所述的一种装配式地下建筑,其特征是所述的地下建筑完成墙(1)和桩(2)的施工后,再挖掘四周墙内的岩土,进行地下室的施工。A prefabricated underground building according to claim 9, characterized in that after the underground building completes the construction of the wall (1) and the pile (2), the rock in the surrounding wall is excavated to carry out the construction of the basement.
PCT/CN2018/080791 2017-03-29 2018-03-28 Fabricated underground building and construction method thereof Ceased WO2018177307A1 (en)

Applications Claiming Priority (2)

Application Number Priority Date Filing Date Title
CN201710195882.5A CN106812156A (en) 2017-03-29 2017-03-29 A kind of assembled hypogee and its construction method
CN201710195882.5 2017-03-29

Publications (1)

Publication Number Publication Date
WO2018177307A1 true WO2018177307A1 (en) 2018-10-04

Family

ID=59116406

Family Applications (1)

Application Number Title Priority Date Filing Date
PCT/CN2018/080791 Ceased WO2018177307A1 (en) 2017-03-29 2018-03-28 Fabricated underground building and construction method thereof

Country Status (2)

Country Link
CN (1) CN106812156A (en)
WO (1) WO2018177307A1 (en)

Families Citing this family (5)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN106812156A (en) * 2017-03-29 2017-06-09 王燏斌 A kind of assembled hypogee and its construction method
CN107386295A (en) * 2017-07-24 2017-11-24 能诚集团有限公司 A kind of sedimentation constructing device of underground structure
CN113818495B (en) * 2021-09-16 2022-07-26 中南大学 Periodic pile-wall structure aiming at low-frequency surface wave vibration isolation and construction method
CN114164881A (en) * 2021-10-21 2022-03-11 王树生 Main and auxiliary double excavation device for subsidence construction of grid-like underground buildings
CN114164861A (en) * 2021-10-21 2022-03-11 王树生 Construction method for underground building composed of wall-sinking foundation

Citations (7)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JPS5985021A (en) * 1982-11-05 1984-05-16 Kajima Corp Method and apparatus for construction of underground continuous wall
JPS62233328A (en) * 1986-04-01 1987-10-13 Fusao Sakano Method and apparatus for setting retaining wall by excavator
JPH04179726A (en) * 1990-11-13 1992-06-26 Kazutoshi Isachi Wall member in simplified underground continuous wall construction method and simplified underground continuous wall construction method using the same
CN2260103Y (en) * 1996-08-05 1997-08-20 郭同元 Pile
CN103334422A (en) * 2013-06-26 2013-10-02 中国建筑股份有限公司 Assembled embedded type prefabricated hollow underground continuous wall and construction method thereof
CN105887806A (en) * 2016-06-13 2016-08-24 上海强劲地基工程股份有限公司 Prefabricated underground diaphragm wall and its construction method
CN106812156A (en) * 2017-03-29 2017-06-09 王燏斌 A kind of assembled hypogee and its construction method

Patent Citations (7)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JPS5985021A (en) * 1982-11-05 1984-05-16 Kajima Corp Method and apparatus for construction of underground continuous wall
JPS62233328A (en) * 1986-04-01 1987-10-13 Fusao Sakano Method and apparatus for setting retaining wall by excavator
JPH04179726A (en) * 1990-11-13 1992-06-26 Kazutoshi Isachi Wall member in simplified underground continuous wall construction method and simplified underground continuous wall construction method using the same
CN2260103Y (en) * 1996-08-05 1997-08-20 郭同元 Pile
CN103334422A (en) * 2013-06-26 2013-10-02 中国建筑股份有限公司 Assembled embedded type prefabricated hollow underground continuous wall and construction method thereof
CN105887806A (en) * 2016-06-13 2016-08-24 上海强劲地基工程股份有限公司 Prefabricated underground diaphragm wall and its construction method
CN106812156A (en) * 2017-03-29 2017-06-09 王燏斌 A kind of assembled hypogee and its construction method

Also Published As

Publication number Publication date
CN106812156A (en) 2017-06-09

Similar Documents

Publication Publication Date Title
WO2018177307A1 (en) Fabricated underground building and construction method thereof
CN110043264B (en) Construction method for jacking prefabricated rectangular vertical shaft structural type
CN101736749B (en) Method for constructing soft soil foundation continuous caisson
CN109555540B (en) Tunnel form prestressed pipe curtain structure and construction method
CN107119711B (en) Connecting structure for large-range adjacent existing transfer station and construction method
CN110700841B (en) Double side wall guide pit excavation method for tunnel excavation
AU2019439324A1 (en) Wall sinking construction method
CN102587922A (en) Oblique-crossing inclined shaft upper arc guide top brushing construction method for soft crushed rock layer
CN102410031B (en) Underground space structure constructed by pile wall construction method
WO2018133739A1 (en) Foundation having chain cutter at base during construction and construction method of same
WO2018133740A1 (en) Underground building and construction method for same
CN109555535B (en) Structure and construction method of prestressed pipe curtain in the form of lower road truss
WO2018133746A1 (en) Underground building formed of piles and walls, and method for constructing same
CN207261017U (en) Tunnel form prestressed pipe curtain system
CN110056003A (en) A kind of integral sinking construction method and its constructing device for basement
WO2018177304A1 (en) Fabricated underground building and construction method thereof
CN103866787B (en) A kind of spacious reverse masonry method concrete cut that digs builds construction technology
WO2018177306A1 (en) Fabricated underground wall and construction method thereof
CN210712922U (en) An integral subsidence construction device for basement
WO2018177305A1 (en) Groove pile for fabricated underground building and construction method thereof
CN108571010B (en) Method for integrating open cut method engineering prefabricated main structure and supporting structure
CN106759593A (en) A kind of groover and its construction method for hypogee
CN207714369U (en) A kind of assembled hypogee
CN113202106B (en) Deep foundation pit excavation method
CN109972634A (en) A soil retaining method for the side wall of the open excavation foundation pit of the pipe gallery crossing the branch pipe trench

Legal Events

Date Code Title Description
121 Ep: the epo has been informed by wipo that ep was designated in this application

Ref document number: 18777047

Country of ref document: EP

Kind code of ref document: A1

NENP Non-entry into the national phase

Ref country code: DE

122 Ep: pct application non-entry in european phase

Ref document number: 18777047

Country of ref document: EP

Kind code of ref document: A1